Professional Documents
Culture Documents
De 2013
De 2013
Abstract— The objective of protective relay coordination in power system. This will increase the fault current levels
a distribution system is to achieve selectivity without which results in damage of the electrical equipment and also
sacrificing sensitivity and fast fault clearance time. When a DG affect the existing coordination between relays and may
is installed in a distribution system, they change the original prevent this relays from detecting a fault, which is supposed
steady-state and fault current magnitudes, on which the to be within its protection zone [1]. In [2], a new approach is
original relay settings were set. The severity is based on DG’s proposed to solve the directional over-current relay
capacity and its location. Usually disconnection of all DGs coordination problems, which arises from installing DG in
from distribution system is the current local distribution looped Power Delivery Systems (PDS) by implementing
company’s practise during fault, in order to maintain the
fault current limiters to locally limit the DG fault current,
original relay coordination. However, instead of removing DG
and thus restore the original relay coordination. The basic
it is better to limit the fault current from the DG. In this paper
hybrid super conducting fault current limiter which gives a
idea was to limit the fault current so it does not matter if the
promising solution to limit fault current without much loss in system is disconnected from supply. Many other methods
electrical energy is considered, modelled and simulated in were used to limit the current, like air core reactors, basically
PSCAD as a countermeasure to limit fault current from DG, it was a good approach but the only disadvantage was very
in order to improve the disrupted original relay coordination. high voltage drop in normal operation, for which VAR
compensation is required. The increase in the size of the
Keywords— Distributed Generation (DG), OCR (Over system is the other disadvantage of this approach. Hence the
Current Relay), FCL (Fault Current Limiter), WTGS (Wind approach of FCL was taken up to overcome the issue
Turbine Generator System), SFCL (Super Conducting Fault mentioned in the case of large reactor The general operation
Current Limiter), CTI (Coordination Time Interval). of a FCL as a circuit element and, more specifically, the
operation of superconducting SFCL, its designing, HTSC
I. INTRODUCTION (High Temperature Super Conducting) element characteristic
Power system protection deals with the protection of resistance equations and its recovery characteristics after
electrical power systems from faults, through the isolation of current limitation are reported in [3-7]. To overcome the
faulted parts from the rest of the electrical network. The problems of large volume of superconducting components
objective of a protection scheme is to keep the power system required for conventional SFCL (resistive and flux-lock
stable by isolating only the components that are under fault, type) and their slow recovery time after the current
while leaving as much of the network as possible still in limitation, development of hybrid SFCL using HTSC
operation. In that without having any mal-operation of element as an alternate solution is discussed in [8].
protective devices is very essential. Thus, the protection
When a wind-turbine generator system (WTGS) is
coordination between the primary and the secondary
installed in a radial distribution system as a DG, the
protective devices plays an important role in minimizing an
increased fault current reduces the Coordination Time
outage to the greatest extent possible. A failure of primary
Interval (CTI) between the multiple relays therefore disrupts
protection will usually result in the operation of back-up
their coordination [9]. In [10], investigations were carried out
protection. Back-up protection will generally remove both
to assess the effectiveness of the resistive SFCL for fault
the affected and unaffected items of system to clear the fault.
level management in wind power system. In this paper,
To coordinate this back-up protection with the primary relay,
PSCAD modelling of hybrid type SFCL and its effectiveness
the relay characteristic should ensure that the back-up relay
in improving the CTI between protective devices so as to
has sufficient time delay to allow the primary relay (and its
retain the original relay coordination when WTGS is added
breaker) to clear the fault.
to a distribution system are reported.
When electric power systems expand and become
complex due to improvement in the grid connections with
the incorporation of Distributed Generator (DG) into the
1
⎡ ⎛ t − t o ⎞⎤ 2
R SFCL (t) = R n ⎢1 − exp⎜⎜ − ⎟⎟⎥ (t o < t < t 1 ) (1)
⎣ ⎝ TF ⎠⎦
current (kA)
0.10 0.20
0.00
0.00
-0.10
-0.20
-0.20
-0.30 -0.40
-0.40
-0.60
sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50 4.60 sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50
(a) (b)
INSTANTANEOUS CURRENT IN LINE-45
<Untitled>
0.50 Fig.5. Instantaneous current in line 4-5 (a) when OCR-4 senses the fault
0.40 (b) when OCR-3 senses the fault
0.30
0.20
C. Fault analysis with WTGS of 1 MVA and with hybrid
current (kA)
0.10
0.00 SFCL
-0.10 With WTGS of 1 MVA rating and hybrid SFCL
-0.20
integrated together, the operating time for OCR-4 has
-0.30
-0.40
increased to 0.2595 s and OCR-3 to 0.4715 s, thus
sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50 4.60 improving the CTI to 0.2120 s when compared with 0.2066
s without hybrid SFCL. Response of line current in bus 4-5
(b) is shown in Fig.6.
Fig.4. Instantaneous current in line 4-5 (a) when OCR-4 senses the fault INSTANTANEOUS CURRENT IN LINE-45
(b) when OCR-3 senses the fault
0.60
applied with WTGS of 1 MVA rating, the operating time for -0.20
without hybrid SFCL. Response of line current in bus 4-5 is sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50
shown in Fig.5.
(a)
INSTANTANEOUS CURRENT IN LINE-45
INSTANTANEOUS CURRENT IN LINE-45
0.60
0.80
0.40
0.60
0.20
0.40
current (kA)
0.00
current (kA)
0.20
-0.20
0.00
-0.20 -0.40
-0.40 -0.60
sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50
-0.60
sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50
(b)
(a) Fig.6. Instantaneous current in line 4-5 (a) when OCR-4 senses the fault
(b) when OCR-3 senses the fault
20.0
15.0
Resistane(ohm)
10.0
5.0
0.0
-5.0
Time 3.990 4.000 4.010 4.020 4.030 4.040 4.050 4.060
0.050
0.000
After the two switches (BRK1a, BRK2a) are operated as
-0.050
described above, the breaking switch (BRK3a) in the current
-0.100 limiting part is opened and the fault current can be finally
-0.150 limited by the CLR. With the hybrid SFCL realized by the
sec 3.970 3.980 3.990 4.000 4.010 4.020 4.030 4.040 4.050
breakers which act as fast switches, as described above, the
protection coordination experiments of the OCRs in the
(b) Current through HTSC element, breaking switch, CLR
simulated power distribution system with the hybrid SFCL
was performed. Fig. 8 shows the improved CTI with the
Right after the switch BRK1a is closed, the switch BRK2a is
application of hybrid SFCL in the system.
ready for opening. Though the current flowing into the ROTAR SPEED
driving coil decreases, its root-mean-square (RMS) value 1.0200
rotar speed
1.0100
1.0080
SFCL CURRENT CHARACTERISTIC WAVEFORMS
1.0060
current in HTSC element current in driving coil RMS current in driving coil
0.150 1.0040
1.0020
0.100
1.0000
sec 0.0 1.0 2.0 3.0 4.0 5.0
0.050
current (kA)
0.000
(a)
-0.050 ROTOR SPEED
rotor speed
1.0250
-0.100
1.0200
-0.150
sec 3.970 3.980 3.990 4.000 4.010 4.020 4.030 4.040 1.0150
speed (pu)
1.0100
1.0000
Fig.7. Characteristic waveforms of Hybrid SFCL
0.9950
sec 0.0 1.0 2.0 3.0 4.0 5.0
(b)
Fig.9. Rotor speed of WTGS of 1 MVA rating (a) without Hybrid SFCL
(b) with Hybrid SFCL
INSTANTANEOUS CURRENT FROM INDUCTION GENERATOR Improvement in the CTI gives the opportunity to install
0.40 larger rating of WTGS integrated with HSFCL securing
0.30
back the protective coordination. This study also showed
0.20
how the HSFCL could improve the dynamic performance of
0.10
the WTGS under the fault condition. In practice, this study
curent (kA)
0.00
-0.10
could be used as a decision making guide for setting up a
-0.20 Hybrid SFCL to power grid with distributed generation.
-0.30
-0.40 VI. CONCLUSION
sec 3.90 4.00 4.10 4.20 4.30 4.40 4.50
This paper made a study to analyse the effect of Hybrid
SFCL on the electric power grid integrated with the WTGS.
(a)
INSTANANTANEOUS LINE CURRENT OF INDUCTION GENERATOR
It describes the effects of a Hybrid SFCL in improving the
0.250
CTI between the primary and back-up OCRs. The
0.200 simulation results shows that the Hybrid SFCL could
0.150 provide an effective solution in installing a large WTGS
0.100
0.050
under the tightly constrained conditions resulting from the
current (kA)