This document summarizes the daily work activities of PHAL Pisey in April 2018. It includes revising forms and drawings for bridge projects, revising bills of quantities for 7 bridges and box culverts, making drawings showing pile depths for bridges, marking locations for a concrete plant and temporary yard, and preparing documents for a company. Some activities were completed while others included additional tasks or meetings.
This document summarizes the daily work activities of PHAL Pisey in April 2018. It includes revising forms and drawings for bridge projects, revising bills of quantities for 7 bridges and box culverts, making drawings showing pile depths for bridges, marking locations for a concrete plant and temporary yard, and preparing documents for a company. Some activities were completed while others included additional tasks or meetings.
This document summarizes the daily work activities of PHAL Pisey in April 2018. It includes revising forms and drawings for bridge projects, revising bills of quantities for 7 bridges and box culverts, making drawings showing pile depths for bridges, marking locations for a concrete plant and temporary yard, and preparing documents for a company. Some activities were completed while others included additional tasks or meetings.
Date Contents Achievement Remark -Revise total quantity form for Bridge 21 Sat -Complete. Project. 22 Sun -Revise total quantity form for Bridge 23 Mon Project. -Complete. -Add some items more. -Revise BOQ for 7 Bridges. -Revise total quantity form for Bridge Project. 24 Tue -Revise BOQ for 7 Bridges. -Complete. -Revise Excavation ane Backfill for Box culvert. -Make drawing of Depth of pile for 25 Wed Anlong khle, Prek chhloung and Peam -Complete. Te. -Mark location for Concrete plant. -Revise drawing of Depth of pile for 26 Thu -Complete. Anlong khle, Prek chhloung and Peam Te. -Make location of Temporary yard. -Meeting at Pisnoka office 27 Fri -Complete. -Revise Concrete Plant location. in the mornig. -Preparing document for OMURA company. 28 Sat -Revise BOQ for BP comparing with SAITA.