MOM.SV.GBK.001

HO Project : Central Java 2x1000 MW Coal Fired Power Plant Project No : 1607.SD/1607.C

DESCRIPTION : Implementation Storage Area

VENUE : Laboratory PT. SSP Site Batang


DATE : 28 October 2018
TIME : 08:15 – 09:30 hrs

ATTACHMENT : N/A

NO Items Discussed Action By Remarks

Meeting start at 08:15am as all parties are reached the office earlier.

1 All Parties (Workers)

 All parties must care for the work environment All parties

 Prohibited from placing material in any place All parties


 Please be able to properly store all construction materials in the
storage area, so as not to damage of the material quality. All parties

 The error in this case is rebar materials storage around the work
area and there is no protection for the rebar materials which is under
the stairs for access to mobilization. All parties
Danger and obstruction for something unwanted must be avoided.