v0-umrdkif;-vHkcif;-zm;uefUvrf;rdkif(5^6-6^0 ) Mum;&Sd eefaumif;acsm

(900)ay t&Snf oHuluGefu&pfwHwm; wnfaqmufjcif;vkyfief; NyD;pD;rI ta

vkyfief;wpfckcsif;pDt
pOf taMumif;t&m NyD;pD;rI &mcdkifEIef;
vdkuf &mcdkifEIef;

1 2m ϕ Caisson Wells of Abutment A1 = 3 Nos 3% 3.0%

2 2m ϕ Caisson Wells of Abutment A2 = 3 Nos 3% 3.0%

3 Pier Caps of Abutment A1 1% 1.0%

4 Pier Caps of Abutment A2 1% 1.0%

5 Abutment,Wing Wall & Back Wall of A1 5% 5.0%

6 Abutment,Wing Wall & Back Wall of A2 5% 5.0%

7 2m ϕ Caisson Wells of Piers(P1-P12)=24 Nos 30.00% 30.0%

8 Pier Caps of Piers(P1-P12) =12 Nos 12.00% 12.0%

9 Pier Shaft & Cross Beams of Piers (P1-P12)=12 Nos 10.00% 10.0%

10 70' Span Girder & Diaphragm (11 spans) 19.00% 22.0%

11 65' Span Girder & Diaphragm (2 spans) 3.00% 3.0%

12 Overlay Slab (70'x30' Span)=11nos 2.86% 3.5%

13 Overlay Slab (65'x30' Span)=2nos 0.50% 0.5%

14 Road Curb & Hand Rail (For 900' Span) 0.09% 1.0%

Overall Progress 95.5% 100%


MYANMAR MAKER HOME CONSTRUCTION CO.,LTD
PROGRESS SCHEDULE
v0-umrdkif;-vHkcif;-zm;uefUvrf;rdkif(5^6-6^0 ) Mum;&Sd 900ay t&Snf eefhaumif;acsmif;wHwm;
8.3.2016

2015 2016
No Particular Nov Dec Jan Feb March April May June Remark
12341234123412341234123412341234
Overall Progress 95.50%
2
1 Pre-Engineering Work 100%

2 Caisson Well Foundation A1 100%


3 Caisson Well Foundation A2 100%
Caisson Well Foundation
4 100.0%
P1,P2,P3,P4,P5,P6,P7,P8,P9,P10,P11,P12
5 Construction of Pile Cap A1 100%
6 Construction of Pile Cap A2 100%
Construction of Pile Cap
7 100.00%
P1,P2,P3,P4,P5,P6,P7,P8,P9,P10,P11,P12
8 Construction of Abutment & Wing Wall A1 100%
9 Construction of Abutment & Wing Wall A2 100%
Construction of Pier Shaft & Cross Beam
10 100.0%
P1,P2,P3,P4,P5,P6,P7,P8,P9,P10,P11,P12
11 Construction of 70' Long R.C.C Girder :11 Span 86.30%

12 Construction of 65' Long R.C.C Girder: 2 Span 100%

13 Construction of 70' Long 30' wide R.C.C Slab:11 span 81.70%


14 Construction of 65' Long 30' wide R.C.C Slab:2 span 100%

15 Construction of R.C.C Hand Rail,Road Curbs and finishing works 9%

PLAN ACTUAL