Nepal Electricity Authority

( An Undertraking of Nepal Government)


Distribution And Cosumer Service Directorate
Butwal Regional Office
Lamahi-Jaluke 33KV Transmission line Project
Site : Rapti River Crossing
Calculation of Quantity of Tower No. One

AS PER ACTUAL As per Different


S.N Description Unit No. length Breadth height Quantity BOQ Quantity
A Construction of tower foundation in
different types of tower includining
supply of construction of materials
1.1 Excavation of foundation (pit in good
fair types soil including site clearing
disposal as directed by the employer
tower staking tower orientation pit
making shoring dewatrering etc. all
complete before and after the work)
( hard soil / Gravel / BMS ) cu.m. 4 2.4 2.4 3.5 80.64 78.09 2.55
1.2 Hard rock cu.m. 4 2.5 2.5 2.5 62.5 62.5
2 Rubble Masonry filling work in
foundation cu.m. 4 3 3 3.5 126
3 PCC 1:3:6 for foundation
for tower foundation cu.m. 4 2.8 2.8 0.075 2.352 1.57 0.782
4 foundation concrete M20 in
foundation footing pad and chmney
including cube testiing and stub etc
all complete as per drawing and
specification
Raft Portion 1st Pad cu.m. 4 2.4 2.4 0.3 6.912
Raft Portion 2nd Pad cu.m. 4 1.45 1.45 0.2 1.682
Inclined Portion cu.m. 4 0.5 0.5 3.75 3.75
coping cu.m. 4 2.4 2.4 0.03 0.691
total concreting cu.m. 13.49 13.49
5 Preparation of wooden form collection
of matrials, nailing, removing and
placing as per drawing as including
transportation
raft portion sq.m
Inclined Portion sq.m 4*4 0.5 3.25 26 26

6 Tor Steel Reinforcement bar


including bending & binding Kg 1375.96
10 % Wastage Kg 137.59
Total kg 1513.56 1218 295.56
7 Gabbion wall cu.m 3 layer 25 1 1 75