PROJECT : PARSONS REGIONAL HEADQUARTERS

MEP ROOMS HANDOVER TRACKER 3-Nov-18


Actual/
SL MEP Works Plan Finish based
ROOM DESCRIPTION ROOM NO FLOOR Forecast* Hand Over reference Delay Remarks
NO Status Duration on Access
Handover
1 ELECTRICAL ROOM B03.16 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
2 ELECTRICAL ROOM B03.04 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
3 TELECOMS B03.05 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
4 TELECOMS B03.15 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
5 DOMESTIC WATER TANK B03.19 B03 17-Sep-18 BM-AD-SUBCONLET-001273 In progress 60 16-Nov-18 13
6 PUMP ROOM B03.20 B03 17-Sep-18 BM-AD-SUBCONLET-001273 In progress 60 16-Nov-18 13
7 ELECTRICAL ROOM B02.04 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
8 TELECOMS B02.05 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
9 TELECOMS B02.15 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
10 ELECTRICAL ROOM B02.16 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
11 WATER TANK B01.08 B01 28-Oct-18 60 27-Dec-18 54
12 ELECTRICAL ROOM B01.04 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
13 TELECOMS B01.05 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
14 TELECOMS B01.15 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
15 ELECTRICAL ROOM B01.16 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
16 L.V ROOM-1 GF.72 GRD 08-Oct-18 BM-AD-SUBCONLET-001359 In progress 60 07-Dec-18 34
17 ELECTRICAL ROOM GF.04 GRD 06-Nov-18 BM-AD-SUBCONLET-001541 60 05-Jan-19 63
18 TELECOMS GF.05 GRD 06-Nov-18 BM-AD-SUBCONLET-001541 60 05-Jan-19 63
19 TELECOMS GF.15 GRD 24-Oct-18 60 23-Dec-18 50
20 ELECTRICAL ROOM GF.16 GRD 05-Nov-18 BM-AD-SUBCONLET-001536 60 04-Jan-19 62
21 ELECTRICAL ROOM GF.48 GRD 28-Oct-18 BM-AD-SUBCONLET-001487 60 27-Dec-18 54
22 GENERATOR ROOM GF.70 GRD 20-Oct-18 BM-AD-SUBCONLET-001433 In progress 60 19-Dec-18 46
23 TRANSFORMER ROOM GF.71 GRD 20-Oct-18 BM-AD-SUBCONLET-001433 In progress 60 19-Dec-18 46
24 L.V ROOM GF.19 GRD 20-Oct-18 BM-AD-SUBCONLET-001433 In progress 60 19-Dec-18 46
25 ELECTRICAL ROOM GF.40 GRD 28-Oct-18 BM-AD-SUBCONLET-001487 60 27-Dec-18 54
26 SECURITY CONTROL & BMS ROOM GF.56 GRD 25-Oct-18 60 24-Dec-18 51
27 ODF ETISALAT GF.74 GRD 25-Oct-18 60 24-Dec-18 51
28 FIRE COMMAND CENTRE GF.81 GRD 10-Nov-18 60 09-Jan-19 67
29 H.V ROOM GF.88 GRD 10-Nov-18 60 09-Jan-19 67
30 ELECTRICAL ROOM P01.04 P01 05-Nov-18 60 04-Jan-19 62
31 TELECOMS P01.05 P01 05-Nov-18 60 04-Jan-19 62
32 TELECOMS P01.15 P01 05-Nov-18 60 04-Jan-19 62
33 ELECTRICAL ROOM P01.16 P01 05-Nov-18 60 04-Jan-19 62
34 ELECTRICAL ROOM P02.04 P02 12-Nov-18 60 11-Jan-19 69
35 TELECOMS P02.05 P02 12-Nov-18 60 11-Jan-19 69
36 MEP P02.08 P02 08-Dec-18 60 06-Feb-19 95
37 MEP P02.12 P02 12-Dec-18 60 10-Feb-19 99
38 TELECOMS P02.15 P02 12-Nov-18 60 11-Jan-19 69
39 ELECTRICAL ROOM P02.16 P02 12-Nov-18 60 11-Jan-19 69
40 ELECTRICAL ROOM L01.04 L01 07-Nov-18 BM-AD-SUBCONLET-001545 60 06-Jan-19 64
41 TELECOMS L01.05 L01 07-Nov-18 BM-AD-SUBCONLET-001545 60 06-Jan-19 64
41A WATER METER ROOM L01.06 L01 07-Nov-18 BM-AD-SUBCONLET-001545
41B WASTE ROOM L01.07 L01
42 TELECOMS L01.32 L01 01-Dec-18 60 30-Jan-19 88
43 ELECTRICAL ROOM L01.33 L01 05-Dec-18 60 03-Feb-19 92
43A WATER METER ROOM L01.31 L01
43B WASTE ROOM L01.30 L01
44 ELECTRICAL ROOM L02.04 L02 09-Dec-18 60 07-Feb-19 96
45 TELECOMS L02.05 L02 13-Dec-18 60 11-Feb-19 100
46 TELECOMS L02.33 L02 17-Dec-18 60 15-Feb-19 104
47 ELECTRICAL ROOM L02.34 L02 21-Dec-18 60 19-Feb-19 108
48 ELECTRICAL ROOM L03.09 L03 25-Dec-18 60 23-Feb-19 112
49 TELECOMS L03.10 L03 29-Dec-18 60 27-Feb-19 116
50 TELECOMS L03.20 L03 02-Jan-19 60 03-Mar-19 120
51 ELECTRICAL ROOM L03.21 L03 06-Jan-19 60 07-Mar-19 124
52 ELECTRICAL ROOM L04.09 L04 02-Jan-19 60 03-Mar-19 120
53 TELECOMS L04.10 L04 05-Jan-19 60 06-Mar-19 123
54 TELECOMS L04.20 L04 09-Jan-19 60 10-Mar-19 127
55 ELECTRICAL ROOM L04.21 L04 13-Jan-19 60 14-Mar-19 131
56 ELECTRICAL ROOM L05.09 L05 09-Jan-19 60 10-Mar-19 127
57 TELECOMS L05.10 L05 12-Jan-19 60 13-Mar-19 130
58 TELECOMS L05.20 L05 16-Jan-19 60 17-Mar-19 134
59 ELECTRICAL ROOM L05.21 L05 20-Jan-19 60 21-Mar-19 138
60 ELECTRICAL ROOM L06.09 L06 16-Jan-19 60 17-Mar-19 134
61 TELECOMS L06.10 L06 16-Jan-19 60 17-Mar-19 134
62 TELECOMS L06.20 L06 16-Jan-19 60 17-Mar-19 134
63 ELECTRICAL ROOM L06.21 L06 16-Jan-19 60 17-Mar-19 134
64 ELECTRICAL ROOM L07.05 L07 23-Jan-19 60 24-Mar-19 141
65 TELECOMS L07.07 L07 23-Jan-19 60 24-Mar-19 141
66 TELECOMS L07.21 L07 23-Jan-19 60 24-Mar-19 141
67 ELECTRICAL ROOM L07.22 L07 23-Jan-19 60 24-Mar-19 141
68 ELECTRICAL ROOM L08.04 L08 30-Jan-19 60 31-Mar-19 148
69 TELECOMS L08.05 L08 30-Jan-19 60 31-Mar-19 148
70 TELECOMS L08.21 L08 30-Jan-19 60 31-Mar-19 148
71 ELECTRICAL ROOM L08.22 L08 30-Jan-19 60 31-Mar-19 148
72 CHILLED WATER PUMP ROOM RF.06 RF 06-Feb-19 60 07-Apr-19 155
73 PUMP ROOM FOR DOMESTIC WATER PUMPS RF.03 RF 06-Feb-19 60 07-Apr-19 155
74 CALORIFIER ROOM RF.05 RF 06-Feb-19 60 07-Apr-19 155
75 PUMP ROOM FOR DOMESTIC WATER PUMPS RF.11 RF 06-Feb-19 60 07-Apr-19 155
76 CHILLED WATER PUMP ROOM RF.13 RF 06-Feb-19 60 07-Apr-19 155
77 CALORIFIER ROOM RF.08 RF 06-Feb-19 60 07-Apr-19
78 MCC Room RF.04 RF 06-Feb-19 60 07-Apr-19
79 MCC Room RF.12 RF 06-Feb-19 60 07-Apr-19 155