MS - Inspection of Penstock
MS - Inspection of Penstock
DRAINAGE AFFAIRS
CONTRACTOR
SUB CONTRACTOR
TABLE OF CONTENTS
CONTENT
1. PURPOSE
2. SCOPE
4. PROCEDURE
5. HSE
6. APPENDIX
DOHA WEST SEWAGE TREATMENT WORKS EXT#5
Doc No: GE-SUEZ-MS-032
Method Statement – Inspection of Penstock Rev. 0
471E_VZ403_
Page 3 of 4 Date:23-01-2019
:
1. PURPOSE
The purpose of this method statement is to detail the general steps of works involved in the
inspection of defective Penstock at Distribution Chamber 471B.
2. SCOPE
This method statement outlines the procedure to safely access the distribution chamber
and conduct the inspection of penstock 471E_VZ403_.
Access
opening
4. HSE
• Permit to Work: Permit to work, work in confined space permit shall be
obtained before starting activities. Workers involved shall be trained for
Confined Space Entry.
• LOTO shall be arranged and managed by O&M during the works.
• Tool Box Talks and Risk Assessments: Prior to the commencement of the
task a Vigiminute shall be conducted and recorded by the concerned
supervisor.
• Signage: the work area shall be adequately barricaded off and be
appropriately warned by signboards posted at the work area.
• PPE: Helmet, safety harness, safety shoes, goggles and reflective vest shall
be worn during site activities. Gum Boots shall be worn by the personnel
entering confined space.
• Housekeeping: Ensure to keep the area neat and tidy during and after the
work.
8. ATTACHMENTS
• Risk Assessment.
• Training and Equipment Certificates
• P&ID
• Assembly Drawing
RISK ASSESSMENT
Sl. Description of Hazard Potential and S P Risk Precautionary Measures and Safeguards S P Risk
No Activity Consequences Rating to control the risk Rating
2. Lifting of Man- Failure of lifting equipment, 4 3 12 ➢ Erect adequate barriers or hoardings are around 2 2 4
basket Collision , Property damage, the work site to prevent unauthorized access.
Trapping/Crushing, ➢ Ensure the correct type of lifting equipment is
Overturning, Walking under selected for the lift.
load, Fail of lifting slings, ➢ Ensure the load does not exceed the SWL of the
Plant and Vehicle equipment.
movement, ➢ Do not lift outside of the cranes safe working
Wind and dust radius
➢ Ensure that all equipment certification is in date.
➢ Inspect equipment before use to ensure it is free
from damage.
➢ Do not lift if wind speed exceeds permissible
limits
➢ Report any damage to your supervisor and take
it out of use.
➢ Only allow competent operatives to carry out
lifting activities.
3. Entering to the Entry to the confined space, 4 5 20 ➢ Obtain confined space entry permit 2 2 4
chamber Narrow access to the ➢ Job specific TBT to be conducted for working in
(confined chamber, Access by confined space
space) manbasket, Oxygen ➢ Area shall be barricaded
deficiency, presence of toxic ➢ All confined space interveners shall be third
and flammable gases LEL, party trained and certified
Fumes, Vapour, Excessive ➢ Use 24 volts lighting inside the chamber
heat and humid atmosphere ➢ Man-basket shall be tested and certified.
in the chamber, Biological ➢ At least one forced ventilation and one forced
Hazards, Sudden discharge exhaust shall be provided with duct
of water to the tank, Fall into ➢ Atmospheric checking shall be done prior to
the tank, Falling materials, enter inside the chamber using five gas
Injury, Fire, Intoxication, detectors.
Asphyxia, Death ➢ Enter inside the chamber if atmosphere is safe
to occupy inside the chamber
➢ All interveners shall wear safety harness
attached to rails in manbasket
➢ Atmosphere shall be monitored during full
course of work
➢ A Hole watch shall be appointed to keep records
of atmospheric inspection, keep communication
with workers and keep records of entry / exit of
the workers
➢ All required LOTO shall be done by O&M