SHOP DRAWING

CPL BUILDING
ROLL SHOP

FCPT BUILDING
CRC BUILDING

MCPL1 BUILDING

A 05 OCT 2018 CHANGE SECTION LOCATION

0 10 APR 2018 FOR CONSTRUCTION

REV. DATE DESCRIPTION

PROJECT NAME:

PROJECT RUBY

SECTION DRAWING CLIENT NAME:

DRAWING TILTE DRAWING NO.


JFE MERANTI MYANMAR CO.,LTD.
LAYOUT PLAN M-SEC-01
SECTION OF PIPING AT G.L 1 @ B to T; G.L B @ 5 to 1; G.L 5 @ B to F; G.L 5 @ F to I; G.L 5 @ I to L; G.L 5 @ L to P M-SEC-02 CONTRACTOR:

SECTION OF PIPING AT G.L 5 @ B to Q; G.L Q @ 5 to 9A; G.L 9A @ Q to T ; G.L T @ 1 to 9A; G.L I @ 21 to 6 M-SEC-03
2-2-8, KORAKU, BUNKYO-KU TOKYO (112-8576) JAPAN
SECTION OF PIPING AT G.L I @ 33a to 22; G.L L @ 7 to 6; G.L L @ 21 to 9; G.L 22 @ L1 to L3 & G.L 25@ L3 to L1 M-SEC-04 TEL: +81-338177182 FAX: +81-338177642

SECTION OF PIPING AT G.L L3 @ 25 to 22; G.L L3 @ 30 to 25 M-SEC-05 PREPARED BY CHECKED BY APPROVED BY

SECTION OF PIPING AT G.L L @ 33 to 32; G.L 60 @ M to Q1 M-SEC-06


SECTION OF PIPING AT G.L 34@B1 to I, L to R1; G.L 37@B1 to R1;G.L 40@B1 to N; G.L 40 @ O to R1; G.L A @ 36 to 35; G.L B1 @ 39 to 38 M-SEC-07
DRAWING TITLE:
SECTION OF PIPING AT G.L S1 @ 64 to 50; G.L S1 @ 40 to 34 M-SEC-08
SECTION OF PIPING AT G.L 40 @ W1 to S1; G.L W1 @ 40 to 35 M-SEC-09 SECTION DRAWING
SECTION OF PIPING AT G.L W1 @ 34 to 51; G.L 50 @ S1 to W1 LAYOUT PLAN
M-SEC-10
SECTION OF PIPING AT PIPERACK @ R.1' to R.24 M-SEC-11 DWG No: M-SEC-01
SIZE: A-3 SCALE: 1/1000 REV: A