VENTURINA, JOHN LUIS L.

BSCE 5B

Duration
Activity Description Precedence Mean/te Variance
O M P
A Location Survey ­ 0.5 1 2 1.083 0.063
B Renting of Equipment ­ 1 1.5 2 1.5 0.028
C Preparation of Materials ­ 1 2 2.5 1.916 0.063
D Clearing of the Area A 1 2 2.5 1.916 0.063
E Excavation B 3 4 6 4.166 0.25
F Piling B 4 5 7 5.166 0.25
G Electrical Installation C 2 3 5 3.166 0.25
H Formwork Installation F 3 4 6 4.166 0.25
I Installation of Steel Reinforcement D, E 4 5 7 5.166 0.25
J Concreting F 2 3 5 3.166 0.25
K Plumbing Installation G, H 1 1.5 3 1.666 0.112
L Administrative Closure J, K 0.5 1 1.5 1 0.028
M Project Sign Off I, L 1 1.5 2 1.5 0.028
N Furniture and Finish J, K 1 2 3 2 0.112