Professional Documents
Culture Documents
Engineering
Engineering
Building Overview
1 2
3 4
5 6
5 6
1
1/25/2019
7 8
7 8
9 10
9 10
Cladding Cladding
- the application of one material over another to provide
skin or layer intended to control the infiltration of weather
elements, or for aesthetic purposes
- does not necessarily have to provide a waterproof
condition but is instead a control element
11 12
11 12
2
1/25/2019
Cladding Plant/Equipment
- are semi-permanent building features that supports the
operation of a facility
- examples are escalators and elevators, HVAC, generators
and substations, MEPF system
13 14
13 14
The Building Site is where the building structure is being The site-based management can make significant
built. It should be a well-planned area that considers improvements in the cost and time savings during the
mobility and function of the construction process. construction process without involving a mass of additional
work.
The project manager decides the allocation of areas in a The role of site managers is to control and maintain work
performance and then taking actions to rectify situations
construction site.
where performance is unsatisfactory.
Site planning in particular, has been the most neglected
aspect in the construction industry and the attitude of the
engineers has been that it will be done as the project
progress.
15 16
15 16
17 18
3
1/25/2019
Common Problems
Material stacks wrongly placed
Plant and equipment wrongly located
Inadequate space allowed
Temfacil wrongly located
19 20
19 20
21 22
23 24
23 24
4
1/25/2019
Substructure Foundation
Building component that rests on earth Part of the building that transfers all the load of the
building to the earth underneath
Foundation
Shallow foundation
Slab-on-grade
Isolated footing
Earth-retaining structures Combined footing
Superstructure Spread/Mat footing
25 26
27 28
29 30
29 30
5
1/25/2019
31 32
31 32
33 34
33 34
35 36
35 36
6
1/25/2019
Method of Installation 5
Superstructure (Girders, Beams and Slab)
Scaffolds are installed to support the formworks 6
Bottom forms are installed (including slab)
4
Conventional formworks 3
Table forms
37 38
Formworks Formworks
Plywood Phenolic board
Used for small construction where reuse of forms is
cannot significantly affect the total cost
Phenolic board
Special type of engineered wood with smooth surface
(coated with phenolic) to maximize reuse of forms
39 40
39 40
Formworks Formworks
Conventional Scaffolding Conventional Scaffolding
Scaffoldings are used to support the assembly of
phenolic boards to serve as formworks for cast-in-place
concrete
Table Forms
A pre-assembled platform, complete with forms, will
serve as formworks assembly for the entire project Table Forms
41 42
41 42
7
1/25/2019
Concrete Concrete
Concrete = water + cement + FA + CA Cast-in-place concrete
Mortar = water + cement + FA Fresh concrete is delivered at site and poured in pre-
assembled formworks
Grout = water + cement
Pre-cast concrete
Hardened concrete is delivered at site to act as building
Ready-mix concrete = concrete mixed at the batching plant
components (e.g. pre-cast wall, pre-cast girder)
Job-mix concrete = concrete mixed on-site
43 44
43 44
Concrete Concrete
Cast-in-place concrete Direct pouring
used if concrete can flow using gravity
Pumpcrete
used to pump concrete to reach higher levels and hard
to reach areas
Pre-cast concrete
45 46
45 46
Reinforcing bars
Ribbed steel bars of varying sizes and strength
Grade 40, Grade 60
10mm, 12mm, 16mm,
20mm, 25mm, 32mm, 36mm
47
47