NESPAK designed and supervised construction of a sewage treatment plant and sewerage system in Misfat Al Abrean, Oman from 2003 to 2010. The project included a 250 cu.m/day sewage treatment plant based on extended aeration process, as well as 3 km of main sewers, 2 km of lateral sewers, 5 lift stations, and 2.5 km of pumping main to serve the area through 2028. NESPAK's services included surveys, design, drawings, documents and cost estimation for the $33 million project.
NESPAK designed and supervised construction of a sewage treatment plant and sewerage system in Misfat Al Abrean, Oman from 2003 to 2010. The project included a 250 cu.m/day sewage treatment plant based on extended aeration process, as well as 3 km of main sewers, 2 km of lateral sewers, 5 lift stations, and 2.5 km of pumping main to serve the area through 2028. NESPAK's services included surveys, design, drawings, documents and cost estimation for the $33 million project.
NESPAK designed and supervised construction of a sewage treatment plant and sewerage system in Misfat Al Abrean, Oman from 2003 to 2010. The project included a 250 cu.m/day sewage treatment plant based on extended aeration process, as well as 3 km of main sewers, 2 km of lateral sewers, 5 lift stations, and 2.5 km of pumping main to serve the area through 2028. NESPAK's services included surveys, design, drawings, documents and cost estimation for the $33 million project.
NESPAK designed and supervised construction of a sewage treatment plant and sewerage system in Misfat Al Abrean, Oman from 2003 to 2010. The project included a 250 cu.m/day sewage treatment plant based on extended aeration process, as well as 3 km of main sewers, 2 km of lateral sewers, 5 lift stations, and 2.5 km of pumping main to serve the area through 2028. NESPAK's services included surveys, design, drawings, documents and cost estimation for the $33 million project.
Name of Project: Design and Construction Supervision Country: Sultanate of Oman
of Sewage Treatment Plant and Sewerage System for Misfat Al Abrean Wilayat Al Hamra
Project Location within Country: Misfat Al Abreen Professional Staff provided
by Our Company: - Name of Client: Ministry of Regional Municipalities No. of Man-Months: 13 Environment & Water Resources (MRM, E&WR) Name of Financing Agency: -
Starting Date: Completion Date: Project Cost:
Rs. 158.47 Million 15.7.2003 2010 Approx. Value of Services: Rs. 33.064 Million Name of Associated Firm(s) if any: - No. of Man-Months of Professional Staff provided by Associated Firm(s): -
Senior Staff involved and Functions Performed:
1. M.P. Aftab Project Advisor
2. Muhammad Sajid Team Leader 3. Muhammad Arif Katal Sanitary Drainage Design Engineer 4. Muhammad Zubair Sewage Treatment Engineer
Detailed Narrative Description of the Project:
The objective of this Project was to construct a Sewage Treatment Plant (STP) and Sewage Collection System. The design horizon of the project is 2028. The 250 cu.m/day capacity STP (package plant) was based on extended aeration process which would treat the sewage carried through the collection system comprising 3 km main & 2 km lateral sewers, 5 lift stations and 2.5 km pumping main.
Detailed Description of Actual Services provided by NESPAK:
The services provided by NESPAK included assessment of existing sewage treatment plant and sewage collection system. It included data collection, topographic surveys, study report, preliminary engineering design, detailed design, BOQs, tender drawings, tender documents and cost estimate.