ID Task Task Name Duration Start Finish Tue Jan 29

Mode 5 AM 6 AM 7 AM 8 AM 9 AM 10 AM 11 AM 12 PM 1 PM 2 PM 3 PM 4 PM 5 PM 6 PM 7 PM 8 PM 9 PM 10 PM 11 PM 12 AM 1 AM 2 AM 3 AM
1 Parada de Planta C2 Molinos 05/02/2019 15 hrs 7:30 AM 10:30 PM
2 INICIO DE PARADA 15 hrs 7:30 AM 10:30 PM
3 ZARANDAS 15 hrs 7:30 AM 10:30 PM
4 Cambio de Mallas Zaranda 1 (Deck 1) 2.5 hrs 7:30 AM 10:00 AM Manuel,Ricardo,Edith,Adrián
5 Cambio de Mallas Zaranda 2 (Deck 1) 2.5 hrs 10:00 AM 12:30 PM Manuel,Ricardo,Edith,Adrián
6 Cambio de Mallas Zaranda 3 (Deck 1 y Deck 2) 7 hrs 12:00 PM 7:00 PM Manuel,Ricardo,Edith,Adrián
7 Cambio de Mallas Zaranda 4 (Deck 1) 3.5 hrs 7:00 PM 10:30 PM Manuel,Ricardo,Edith,Adrián
8 Instalar Lifter faldón Zaranda 2 4.5 hrs 7:30 AM 12:00 PM Jesús,Francis,Diego
9 Cambiar Aspersores Zaranda 1 1 hr 7:30 AM 8:30 AM Manuel,Ricardo,Edith,Adrián
10 Cambiar Aspersores Zaranda 2 1 hr 10:00 AM 11:00 AM Manuel,Ricardo,Edith,Adrián
11 Cambiar Aspersores Zaranda 3 1 hr 12:00 PM 1:00 PM Manuel,Ricardo,Edith,Adrián
12 Cambiar Aspersores Zaranda 4 1 hr 7:00 PM 8:00 PM Manuel,Ricardo,Edith,Adrián
13 Engrase cardán excitadores Zaranda 3 3 hrs 3:00 PM 6:00 PM Ronald,Juan
14 Engrase cardán excitadores Zaranda 4 3 hrs 6:00 PM 9:00 PM Ronald,Juan
15 CHUTES ALIMENTACIÓN ZARANDAS 10 hrs 7:30 AM 5:30 PM
16 Cortar Mesa Zaranda 1 3 hrs 7:30 AM 10:30 AM Miguel,Jordan,Blas
17 Cortar Mesa Zaranda 3 3 hrs 11:30 AM 2:30 PM Miguel,Jordan,Blas
18 Sellado de Compuertas Laterales (8 lifters) Z1,Z2,Z3,Z4 3 hrs 2:30 PM 5:30 PM Miguel,Jordan,Blas
19 CHUTES DESCARGA ZARANDAS 4.5 hrs 7:30 AM 12:00 PM
20 Colocar Lifters chute de descarga Zaranda 1 1.5 hrs 7:30 AM 9:00 AM Ronald,Juan
21 Colocar Lifters chute de descarga Zaranda 2 1.5 hrs 9:00 AM 10:30 AM Ronald,Juan
22 Colocar Lifters chute de descarga Zaranda 4 1.5 hrs 10:30 AM 12:00 PM Ronald,Juan
23 NIDOS DE HIDROCICLONES 2 hrs 1:00 PM 3:00 PM
24 Inspeccion Tina Nido 1 1 hr 1:00 PM 2:00 PM Ronald,Juan
25 Inspeccion Tina Nido 2 1 hr 2:00 PM 3:00 PM Ronald,Juan
26 BOMBAS WARMAN 9 hrs 7:30 AM 4:30 PM
27 Cambio Elastomero Bomba Warman 1 (Valvula de Agua) 2 hrs 7:30 AM 9:30 AM Jordy,Jorshy

28 Cambio de Empaque Bomba Warman 1 2 hrs 9:30 AM 11:30 AM Jordy,Jorshy


29 Inspección Buje Bomba 1 1 hr 11:30 AM 12:30 PM Jordy,Jorshy
30 Cambio de Empaque Bomba Warman 2 2 hrs 1:30 PM 3:30 PM Jordy,Jorshy
31 Inspección Buje Bomba 2 1 hr 3:30 PM 4:30 PM Jordy,Jorshy
32 FAJAS 4 hrs 2:30 PM 6:30 PM
33 Inspección de Equipo Lanzas Belt Feeder 4 hrs 2:30 PM 6:30 PM Miguel,Jordan
34 MOLINOS 8 hrs 1:00 PM 9:00 PM
35 Retiro del Cajón de Alimentación Molino GMD 1 4 hrs 1:00 PM 5:00 PM Jesús,Francis,Diego
36 Retiro del Cajón de Alimentación Molino GMD 2 4 hrs 5:00 PM 9:00 PM Jesús,Francis,Diego
37 FLOTACIÓN 3 hrs 4:30 PM 7:30 PM
38 Montaje de línea de 6" feed box 2 3 hrs 4:30 PM 7:30 PM Blas,Jordy,Jorshy
39 FIN DE PARADA 0 hrs 10:30 PM 10:30 PM 1/28

Task Project Summary Manual Task Start-only Deadline

Project: Diagrama Gantt Parada Split Inactive Task Duration-only Finish-only Progress
Date: 3:49 PM Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone