Professional Documents
Culture Documents
Construction Site Name Location Introduction To Site
Construction Site Name Location Introduction To Site
Construction
Manpower Machinery
Materials
Mason Sand Concrete mixer
Manpower Diesel
Activities
Excavation
At the ground floor, I observed a room in which the activity of excavation was performed. The
purpose of activity was to maintain the level of floor
Brickwork in super structure
At the topmost floor, I observed brickwork was carried to construct the walls
Plastering
In the lower stories, masons were busy in plastering
Preparation of mortar
Some masons were preparing mortar for plastering
Preparation of concrete
P.C.C & R.C.C were prepared on the construction site for the construction of columns &
flooring purposes etc.
Steel fixing
Steel fixers were cutting, bending & fixing the steel
Watering
Watermen were watering the freshly constructed parts of the structure
Material dumping
Some laborers were dumping the materials like cement, sand etc
Formation & placing of brick ballast
Some laborers were making the brick ballast from the weird bricks & other were placing that
brick ballast
Flooring
Flooring activity was carried on the upper stories of the construction site
Electricity works
Electricians were carrying out their relevant work on the construction site
Removal of the formwork
Some laborers were removing the formwork of the roof
Removal of defeats due to poor form working
Some laborers were removing different effects caused by the poor formwork
Part 2
Situation
We have to establish the water sewerages system in a sub division of Karachi, & we need to tell
about the projects as well as the activities involved in this program. Moreover we need to tell
about the hurdles faced in a particular situation which includes
A motorway on the right side
A river flowing on the left side
A sub Division
Industrial area
Projects involved in the program are
Construction of a water reservoir in ground
Construction of Water storing tanks
Lying of the water line under the ground
Activities
For the construction of ground water reservoir, we need to do the following activities
Investigate the soil type present at the site
1. Excavation of the soil
2. Determination of ground water table
3. Providence of resistance to the walls of the reservoir
For the construction of storage tanks
1. Preparation of P.C.C for the its use in Foundation
2. Brickwork in sub & super structure
3. Cutting, bending & fixing of steel
4. Formation of beams & columns
For the lying of water supply line
1. Excavation of the soil
2. Lying of water supply line
3. Leveling the water supply line
4. Joining of the water supply line
5. Back filling of the soil
Constraints
Due to the river, the ground water table will be increased in the area so the lying of the
supply line will be quite difficult
There will be a lot of hindrance due to the people passing through the construction site