S.N.

Items of Works
Site Preparation and Layout
Excavation Works

Soiling and PCC for Foundation


Bar Bending Schedule
Centering and Installation of Column
RCC Work below plinth level
Lower Tie Beam RCC Works
Brickwork below plinth level
Upper Tie Beam RCC Works
RCC Works at Column
Backfilling of soil and compaction Works
Soiling and PCC (Rough Surface) at Ground level

Bar Bending Schedule for staircase slab and beam


Formwork for Beam Slab and Staircase
RCC works for beam, slab and staircase
Curing Works
Brickwork, sill and lintel works at and upto 1st floor slab

Bar bending schedule for column


Column Installation and RCC Works
Bar bending schedule for slab beam and staircase
Formwork for beam, slab and staircase
RCC works at slab, beam and staircase
Curing
Brickwork, sill and lintel works at and upto 2nd floor slab

Bar bending schedule for column


Column Installation and RCC Works
Bar bending schedule for slab beam and staircase
Formwork for beam, slab and staircase
RCC works at slab, beam and staircase
Curing
Brickwork, sill and lintel works at and upto 3rd floor slab

Plumbing Works
Electrical Works
Plastering Works