This document outlines the items of work for a construction project including site preparation, excavation, foundation work, RCC and brickwork up to the third floor, and finishing works like plumbing, electrical, and plastering. Key stages include soil and PCC for the foundation, RCC column and tie beam installation, brickwork, RCC slab and staircase works for three floors, and final plumbing, electrical, and plastering works.
This document outlines the items of work for a construction project including site preparation, excavation, foundation work, RCC and brickwork up to the third floor, and finishing works like plumbing, electrical, and plastering. Key stages include soil and PCC for the foundation, RCC column and tie beam installation, brickwork, RCC slab and staircase works for three floors, and final plumbing, electrical, and plastering works.
This document outlines the items of work for a construction project including site preparation, excavation, foundation work, RCC and brickwork up to the third floor, and finishing works like plumbing, electrical, and plastering. Key stages include soil and PCC for the foundation, RCC column and tie beam installation, brickwork, RCC slab and staircase works for three floors, and final plumbing, electrical, and plastering works.
This document outlines the items of work for a construction project including site preparation, excavation, foundation work, RCC and brickwork up to the third floor, and finishing works like plumbing, electrical, and plastering. Key stages include soil and PCC for the foundation, RCC column and tie beam installation, brickwork, RCC slab and staircase works for three floors, and final plumbing, electrical, and plastering works.
Items of Works Site Preparation and Layout Excavation Works
Soiling and PCC for Foundation
Bar Bending Schedule Centering and Installation of Column RCC Work below plinth level Lower Tie Beam RCC Works Brickwork below plinth level Upper Tie Beam RCC Works RCC Works at Column Backfilling of soil and compaction Works Soiling and PCC (Rough Surface) at Ground level
Bar Bending Schedule for staircase slab and beam
Formwork for Beam Slab and Staircase RCC works for beam, slab and staircase Curing Works Brickwork, sill and lintel works at and upto 1st floor slab
Bar bending schedule for column
Column Installation and RCC Works Bar bending schedule for slab beam and staircase Formwork for beam, slab and staircase RCC works at slab, beam and staircase Curing Brickwork, sill and lintel works at and upto 2nd floor slab
Bar bending schedule for column
Column Installation and RCC Works Bar bending schedule for slab beam and staircase Formwork for beam, slab and staircase RCC works at slab, beam and staircase Curing Brickwork, sill and lintel works at and upto 3rd floor slab