Conclusion: Due To A Good Work Planning and Work Coordination We Succeeded To Finish This Job Within 4 Hours in A Very Safe Way
Conclusion: Due To A Good Work Planning and Work Coordination We Succeeded To Finish This Job Within 4 Hours in A Very Safe Way
Observations :
Fresh Air supply : Forced ( Ventilation was very good ; 1 high performance airmover and 1 airblower)
Confined space entry form : you had to sign in before entering and sign out after coming out of the tank.
Work Coordination : Very Good ; Irem was working on the tank and we were working in the tank.
Cleaning : We got help from the painting crew (who were busy with outside of the tank) do clean
the tank from all the rust-flakes that had fallen from the roof on the tank bottom , in a very high tempo .
Fresh Air Break : we took a 10-15 min. break after 40-45 min. of working in the tank , because the tank
was ventilated very good.
Conclusion:
Due to a good work planning and work coordination we succeeded to finish this job within 4 hours in a very safe way.
Technicians busy with Floor Scanning Taking UT measurements & Pitting depth with pith gauge