General Specification for Painting

QAP No. TSL / New Fabrication-


QAP FOR SURFACE PREPARATIOPN & PAINT APPLICATION
001/Rev.0 Date:

Name of the Applicator: M/S .


Name of the Item to coated: Steel Plates, Bulb Bars etc. Name of Paint Manufacturer: M/S
Type of
Witnessed Record
Standards of Check(visu
Sr. Parameters to be Acceptance Qty/ Performed & & No./
Compliances/Work al/ Hold Points Remarks if Any
No. checked Criteria Frequency documented by Recorded Inspection
instruction instrument
By format
al/ Both)
After satisfactory Paint material to be
Time of Primer Within 4 hours after Blasting & Cli
Coating Manufacturer surface Paint Inspection mixed properly with
C10 application after blast Dry blast cleaning Visual 100% painting ent
guidelines preparation prior to Mfg. Records the mechanical
cleaning preparation preparation. Contractor QC
paint application agitator
Wet Film Thickness Randomly
ISO 2808 :1997, Clause To achieve the Blasting & Cli
to be checked during After Satisfactory in every Paint Inspection
C11 No. 6.2.2 Determination of adequate Dry Film Instrumental painting ent
application of each WFT shift for Mfg. Records
Film Thickness Thickness. Contractor QC
coat. each coat
Follow the
As per ISO 2808 ,SSPC Standard
Dry film thickness to As per relevant Blasting & Cli
PA-2 ,ASTM-D-1186 After drying of guideline Paint Inspection
C12 be checked after Specification or Instrumental painting ent
(Ferrous metal surface) on shop primer coat. as per Mfg. Records
drying of each coat Manufacturer TDS. Contractor QC
smooth panels SSPC PA-
2
Over coating interval
Prior to Blasting & Cli
Time of Subsequent Follow Manufacturer TDS period to be Paint Inspection
C13 Visual subsequent coat 100% painting ent
coat application. & AG maintained as per Mfg. Records
application Contractor QC
Manufacturer TDS
Visual defects (like
No defects is
Visual check after sagging, runs, unwanted
acceptable which Blasting & Cli
completion of paint paint droplets, pin holes, Prior to handing Paint Inspection
C14 affects the Visual 100% painting ent
system for any contamination, craters, over the project. Mfg. Records
performance of Contractor QC
coating defect orange peel etc. shall be
coating system
rectified
Prepared & Proposed By. TATA STEEL Ltd. Agreed & Approved By: M/s Committed By:

GSP-01-00-00-14-000-001-R2 43 44
Confidential. ©2016 TATA Steel Limited, All rights reserved