Professional Documents
Culture Documents
Electricity Review Japan: The Federation of Electric Power Companies of Japan
Electricity Review Japan: The Federation of Electric Power Companies of Japan
Electricity Review Japan: The Federation of Electric Power Companies of Japan
R E V I E W J A PA N
The Federation of
Electric Power Companies
of Japan
2018
History of Japan’s Electric Utility Industry The Ten Electric Power Companies by Main Service Area
(North latitude)
National Trunk Line
Connections
45゜ (As of December 2012)
Transmission Line(500kV)
Electricity was first used in Japan on March 25, 1878 at demand for electricity remained very tight in Japan. A HOKKAIDO Electric Power Co. Transmission Line(154kV~275kV)
the Institute of Technology in Toranomon, Tokyo when series of intense discussions were held on restructuring DC Transmission Line
an arc lamp was switched on in commemoration of the the electric utility industry as one of the measures for HOKURIKU Electric Power Co. Switching Station or Substation
opening of the Central Telegraph Office. In those days, democratizing the economy. As a result, nine regional 40゜ Frequency Converter Facility(F.C.)
TOHOKU Electric Power Co. AC-DC Converter Facility
electricity was still unfamiliar and uncommon not only in privately owned and managed General Electricity CHUBU Electric Power Co.
The CHUGOKU
Japan but also in Europe and the United States. In 1886, Utilities— Hokkaido, Tohoku, Tokyo, Chubu, Hokuriku, Electric Power Co.
TOKYO Electric Power Company Holdings
Tokyo Electric Lighting, a private company, commenced Kansai, Chugoku, Shikoku and Kyushu Electric Power The OKINAWA
Electric Power Co.
operations as the nation’s first electric power company, Companies — were established in 1951 and assumed the 35゜
and began supplying electricity to the public in the responsibility of supplying electricity to each region.
following year. The Okinawa Electric Power Co. was established with The KANSAI Electric Power Co. Shin-
Shinano
In the early days, use of electricity grew primarily for the return of Okinawa to Japan in 1972. SHIKOKU F.C.
Electric Power Co.
KYUSHU
lighting because of its safety and cleanness, and gradually At the end of the 20th century, a trend toward Electric Power Co.
found broader applications as a power source to replace deregulation and competition took hold throughout 130゜ 135゜ 140゜ 145゜
(East longitude)
the steam engine. By 1896, the number of electric utilities society, and the electric utility industry started to be Sakuma Higashi-Shimizu
F.C. F.C.
established throughout the nation reached a total of 33. liberalized. In December 1995, organizations such as
60Hz 50Hz
The early 20th century marked the establishment of independent power producers (IPP) were allowed to Column
long-distance transmission technology. As larger thermal provide electricity wholesale services, and in March 2000,
The Linchpins of East-West Grid Connection-
and hydro-power plants were introduced, generation costs electricity retail supply for extra-high voltage users Frequency Converter Facilities
fell and electricity came into wider use throughout the (demand exceeding 2MW) was liberalized. The scope of The frequency of grid power differs between eastern and western Japan, namely 50 Hz
country. Consequently, electricity became an indispensable retail liberalization was then expanded in April 2004 to and 60 Hz respectively. This difference has a historical root in that the Tokyo area adopted
German-made generators at the beginning of the electricity business while Osaka chose
energy source for peoples’ lives and industry. users of more than 500kW, and subsequently in April US-made ones. Therefore, Frequency Converter Facilities (FCF) are necessary to connect
In the years that followed, the electricity utility business 2005 to users of more than 50kW. Thus, a Japanese model the eastern and western power grids. Three FCFs, namely Sakuma FCF and Higashi-
Shimizu FCF in Shizuoka Pref. and Shin-Shinano FCF in Nagano Pref., operate to convert
grew in tandem with the modernization of Japan and of liberalization based on fair competition and the frequency.
development of its industry. At the same time, the electric transparency, while maintaining the vertical integration of After the Great East Japan Earthquake, to strengthen the east-west grid connection,
the capacity of FCFs is planned to be expanded to 2,100 MW by FY2020.
utility industry experienced a major restructuring that led generation, transmission and distribution to ensure a Higashi-Shimizu FCF
to the dissolution of 700 electric utilities, which merged to stable supply of electricity, was established.
create five major electric utilities after the First World War. With the Fukushima Daiichi Nuclear Power Station
During the Second World War, the electric utility industry accident and subsequent tight demand and supply brought Power Demand for Ten Companies
(TWh)
was completely state-controlled and utilities were about by the Great East Japan Earthquake in March 2011 1,000
Japan’s Energy Supply Situation & Development of
906.4 2030 Energy Mix 2
integrated into Nihon Hatsusoden Co. (a nationwide power as a turning point, numerous discussions were held to 900 859.8 851.6 848.5
837.9 823.0
generating and transmitting state-owned company) and maintain a stable supply and reduce energy costs, and in 800
797.1 Nuclear Safety & Market Liberalization 4
nine distribution companies. November 2013, the policy to implement three-phase Electric Power Sources 6
700
After the end of World War II in 1945, supply and reforms of the electric power system was adopted.
600 Nuclear Fuel Cycle 8
521.9
500 Environmental Conservation 10
2 1
Japan’s Energy Supply Situation & Development of 2030 Energy Mix
Securing safety
Only 6% at 2014
Target:
About 25%, surpassing the pre-earthquake level of about 20%
Electricity cost:
Dependence on Imported Energy Sources by Japan’ s Reliance on Middle East Crude Oil of
Electricity rates have risen since the earthquake. Target:
Major Countries (2015) Total Imports Bring it down from
The surcharge for purchasing renewable energy in FY 2017 is 2.1 trillion yen.
the present level*
100
Major premise
97
100 9394 (%) Greenhouse gas emissions: * (FY 2013 9.7 trillion yen ⇒ FY 2030 9.5 trillion yen)
(%) 90
81 76 Nuclear Energy not included in
Due to NPP shutdowns and the increase of thermal power generation, Target:
80 76 domestic energy A reduction comparable with
the CO2 emissions (from energy sources) in FY2013 were the worst ever.
69 Nuclear Energy included in
those of western nations
61 domestic energy
89.1
60 90 Electric power demand Power source mix
44 44 87.1 87.2 Thorough energy efficiency
36 88.3 and conservation (Total power generation)
40 86.6 Geothermal power:
34 35
196.1 billion kWh 1,278 billion kWh
17% lower than before the 1.0 to 1.1%
implementation of the energy
18 18 84.6 conservation measures Power conservation: (Total power generation) Biomass power:
(Power transmission/
20 16 Economic growth 17% 3.7 to 4.6%
Russia 82.5 1.7%/year
distribution loss, etc.) 1,065 billion kWh
8 Energy efficiency
8 6 Federation 80 and conservation Wind power: 1.7%
+ renewable
Canada 78.6
0 energy account Renewable energy: Renewable energy:
Japan Italy France India China for 40%
19 to 20% 22 to 24% Solar power: 7.0%
78.2
South Germany U.K. U.S.A. Brazil
Korea
-20 Nuclear power: Nuclear power:
17 to 18% 20 to 22%
71.4
70 71.5 Hydroelectric power:
-40 Electric power Electric power 8.8 to 9.2%
68.8 966.6 billion 980.8 billion
LNG: 22% LNG: 27%
kWh kWh
-60
- 65
-80 -74
Coal: 22% Coal: 26%
-81 0
-88 '65 '70 '75 '80 '85 '90 '95 '00 '05 '10 '16 (FY)
Source: IEA "World Energy Balances 2017 Edition” Oil: 2% Oil: 3%
Source: Petroleum Association of Japan FY2013 FY2030 FY2030
*Values are approximate.
(Actual value)
Source: METI "Long-term Energy Supply and Demand Outlook”
2 3
Nuclear Safety & Market Liberalization
evaluates the safety improvement activities of electric power regulatory requirements for 27 units out of their 16 power trend of liberalization by increasing their business efficiency Overview of the Reforms of the Electric Power System
companies and gives them technical advice, and the Nuclear stations. Thirteen units have passed the review and nine of while lowering electricity prices and offering a variety of The following revisions to the Electricity Business Act related to
Risk Research Center(NRRC), which uses Probabilistic Risk them have restarted commercial operation. pricing plans. the reforms of the electric power system were passed into law in
November 2013.
Assessment(PRA) and proposes solutions based on R&D,
were established. The electric power companies take to heart Column Phase 1: Enforced in April 2015
(1) Establishment of the “Organization for Cross-regional
Start of full operation of Mihama Nuclear Emergency Coordination of Transmission Operators, JAPAN”
Natural disasters Installation within 5 years Assistance Center in December 2016 (Enhancement of nationwide grid operation)
The New Electricity Supply System (from April 2016) Phase 2: Enforced in April 2016
Plane crash, etc. • When an nuclear accident occurs, the center swiftly assembles an
(2) Full deregulation of entry into the electricity retail sector
emergency dispatch team, transports personnel and equipment
Surveillance Abolishment of wholesale regulations
to the operator struck by disaster, and cooperates with the Competition in Wholesale Market
Phase 3: Should be implemented in April 2020
Volcano Tornado Wildfire operator to deal with the nuclear accident at high radiation dose.
(3) Implementation of the legal unbundling of the electricity
Duplicating external
power supplies
• During normal times, the center intensively deploys and manages transmission and distribution department (for ensuring
ration controlled robots, etc., and implements operating training further neutrality)
Japan Electric Power Exchange
Emergency for nuclear operator personnel. (4) Abolishment of the retail price regulations
response office Specified safety facility
Fire engine/
Reservoir
pump vehicle
Power source
vehicle Utilities
Generation
Freshwater
souce Power Generation Power Generation Power Generation
(ex-IPP, J-power etc.) (Newcomers) Minister of
Economy, Trade and
Industry
4 5
Electric Power Sources
Oil
Mid-range
Load
Supply LNG and Other Gas
Coal
Okumino Hydroelectric Power Station (Pumped-storage) Kawasaki Thermal Power Station (LNG Combined-cycle) Ohi Nuclear Power Station (PWR)
Nuclear
Base
Load
Hydroelectric (Inflow type) and Geothermal
Supply
0 2 4 6 8 10 12 14 16 18 20 22 24
Hydroelectric and nuclear power provides base load supply, while coal and LNG
are major power sources for mid-range load supply. Oil-fired and pumped-storage
hydroelectric power respond to peak demand fluctuation and contribute to the
consistent, stable supply of electricity.
Takami Hydroelectric Power Station Yoshinoura Thermal Power Station (LNG-fired) Ohma Nuclear Power Station (ABWR, Under Construction)
6 7
Nuclear Fuel Cycle
Outline of JNFL’s Nuclear Fuel Cycle Facilities (as of October 2018) The Safeguards Program
Facility Reprocessing MOX fuel fabrication Vitrified waste Uranium enrichment Low-level radioactive
Plant plant storage center plant waste disposal center
Site
Iyasakatai, Rokkasho-mura, Oishitai, Rokkasho-mura, Assessment Column
Kamikita-gun, Aomori Prefecture Kamikita-gun, Aomori Prefecture
Report
Maximum capacity: Maximum capacity: Storage capacity for Design capacity Planned to be expanded
800 ton-U/year 130 ton-HM/year (*) wastes returned from 1,500 ton-SWU/year (*) to 600,000m3 (equivalent
Nuclear
Enactment of the Spent Nuclear Fuel Reprocessing Fund Act
Capacity overseas plants: to 3 million 200 liter drums) IAEA Regulation
Storage capacity 2,880 canisters of (*) "ton-HM" stands for "tons of heavy In May 11, 2016, the Spent Nuclear Fuel Reprocessing Fund Act was passed in the
for spent fuel: vitrified waste metal" which indicates the weight of Material Authority
3,000 ton-U Diet. The objective of the legislation is to provide a framework for pursuing the national
plutonium and uranium metallic Accounting
Current Cumulative number of Running capacity: Cumulative number of content in MOX. Report/ policy of reprocessing spent fuel in a most reliable and efficient manner even under
Under construction Under construction "SWU" stands for "Separative Work Unit" a new business environment characterized by the liberalized electricity market and
Status received canisters: 1,830 1,050 ton-SWU/year received drums: about 302,000 Activities
which is a measure of the work
Start of construction: Start of construction: Start of construction: Start of construction: Start of construction: expended during an enrichment
Report reduced dependence on nuclear energy.
1993 2010 1992 1988 1990
Schedule
Completion of construction: Completion of construction: Start of storage: Start of operation: Start of operation:
process of uranium The new bill is to implement a series of institutional measures, which include
2021(planned) 2022(planned) 1995 1992 1992 Sources: JNFL’s website and others creating a new funding system aimed at securing adequate funds, organizing a
government-authorized corporation (the spent fuel reprocessing organization) which,
as a principal business entity, conducts the reprocessing business both appropriately
Nuclear Fuel Cycle and efficiently, and establishing an authorized corporation acting as a decision-making
Conversion UF6 UF6
Plant Uranium Inspection Inspection organization (a management committee) from a proper governance viewpoint. The law
Enrichment Plant
Uranium ore
Yellow cake also ensures a certain level of involvement of the National Government.
(U3O8) Reconversion
Plant Furthermore, the supplemental resolution to the legislation reaffirms the policy of
Uranium Mine Refining Plant possessing no plutonium reserves without specified purposes. Also, according to the
UO2
(Depleted Uranium) bill, the Governmental instructs the nuclear operators to conduct reprocessing business
Recovered MOX Fuel
UO2 while upholding this policy, and if an implementing body should make reprocessing
Uranium Fabrication Plant
Reprocessing Recovered
plans that go against this policy, the Minister of Economy, Trade and Industry can
Vitrified Waste
Storage Center Plant Uranium, withhold approval of such plans.
Plutonium
MOX Fuel
Assemblies Uranium Material
Fuel Fabrication
JNFL Nuclear Accounting Status of MOX Fuel Utilization
High-level Plant Facilities Report
(Rokkasho-mura) The electric power industry in Japan intends to introduce MOX fuel in 16 to 18
radioactive waste Uranium Aomori
Spent fuel Fuel
Spent fuel nuclear reactors.
Low-level So far 27 units have applied for a review of conformance with the new regulatory
Nuclear Power Plant radioactive waste requirements, out of which 8 units have received permission to introduce MOX fuel
Activities
Spent fuel Non-nuclear Report
and have gained the understanding of the local municipalities. 4 units have restarted
Facilities operation using MOX fuel thus far.
Spent-fuel Storage Center or
Final disposal of high-level Interim Storage Facility
radioactive waste Low-level Radioactive
Waste Disposal Center
Tokyo
8 9
Environmental Conservation
Measures by the Electric Utility Industry to Suppress CO2 Emissions Decarbonization of Energy on the Supply-side
Promoting nuclear power generation while assuring safety, and improving the thermal
Regarding global warming measures, the “Paris constructed a voluntary framework for a low carbon society
Agreement” was adopted in December 2015 at the 21st and prepared an “Action Plan for a Low-Carbon Society”
efficiency of thermal power plants further
Session of the Conference of the Parties to the United that laid out specific efforts to be made. In February 2016, Nuclear power emits no carbon dioxide (CO2) in the maintenance of the existing plants.
Nations Framework Convention on Climate Change “the Electric Power Council for a Low-Carbon Society process of power generation, and even considering CO2 Currently operating state-of -the-art gas turbine combined
(COP21), and it entered into force in November 2016, (ELCS)” was founded to facilitate efforts toward this goal emissions over the entire life cycle of various energy cycle power plants have achieved the world’s highest level of
building a framework that all countries and regions of the (a membership of 43 companies as of the end of October sources, those from nuclear power are lower than those 62% (LHV) in thermal efficiency by, for example, raising the
world participate for global warming measures. In July 2018). from thermal power, and are even lower than those from combustion temperature at the gas turbines. (Chubu Electric
2015, the Japanese Government announced its “Intended According to the Action Plan, an end-user CO2 emission solar or wind power. However, because of the extended Power Co.’s Nishi-Nagoya Thermal Power Station Unit 7-1
Nationally Determined Contributions(INDC)”, with the factor of about 0.37kg- CO2/kWh will be targeted in light of shutdown of nuclear power plants following the Great East has achieved the world’s highest thermal efficiency of 63.08%
objective of reducing greenhouse gas emissions in 2030 the Government’s 2030 energy supply and demand outlook. Japan Earthquake, and subsequent increase in thermal (LHV) (as of March 2018))
by 26% from 2013 levels. In May 2016, in accordance with Moreover, as the maximum reduction potential, a reduction power generation, the CO2 emission factor has remained As to the conventional coal-fired power plants, the
INDC, the plan for Global Warming Countermeasures was of about 11 million t- CO 2 will be expected by using higher than that before the earthquake. adoption of enhanced steam conditions (temperature
adopted. Emissions of carbon dioxide(CO2), a major cause economically achievable best available technologies(BATs) in Considering that nuclear power generation will and pressure) is being promoted to improve thermal
of global warming, are closely related to energy utilization light of the construction of new thermal power plants, etc. continuously play a key role in combating global warming, efficiency. Presently, ultra-supercritical (USC) thermal
in economic activities and daily life, and so the reduction of The member companies will make efforts towards a the industry is committed to making the utmost effort power generation with the main steam temperature of
CO2 emissions is a major challenge for the industry. low carbon society by utilizing nuclear power generation to improve the safety of nuclear power generation and to 600°C is commercially available. Moreover, research and
The electric power companies are trying to reduce CO2 premised on ensuring safety or renewable energy, raising restore the trust of citizens. development of the Integrated coal Gasification Combined
emissions mainly through attaining the optimal energy the efficiency of thermal power plants and optimizing The electric power companies are also striving to Cycle (IGCC) are being conducted, in which gasified coal
mix, seeking to simultaneously achieve Energy security, their appropriate maintenance and control, and promoting maintain and improve the efficiency of thermal power will be used in combination with gas turbines and steam
Economic efficiency and Environmental conservation, energy-conservation or CO2 reduction services on both the plants through the introduction of highly efficient plants turbines to generate electricity.
under the major premises of Safety (S+3Es). supply and demand sides. of the latest design or through appropriate operation and
In July 2015, 35 electricity utility companies jointly
CO2 Emissions Intensity over the Entire Lifecycle Historical Trends in CO2 Emissions from Power Generation
by Source Electricity Consumption (TWh) CO2 Emissions Factor CO2 Emissions
(g-CO2/kWh) Nuclear Power Generation (TWh) (kg-CO2/kWh) Volume
International efforts- Assisting developing countries to reduce carbon emissions through participation and 1,000
(million metric
tons-CO2)
cooperation with overseas ventures 943
Fuel Combustion 1,000 0.6 1,000
Using nuclear power with safety as a major premise Facilites/Operations 834.0
Expanding the use of non-fossil CO2 Emissions
900 Factor 900
energy sources 800
Efforts in Using renewable energies 0.6
738
domestic Improving the efficiency of power 800 800
business Improving the efficiency of thermal power 0.518
facilities
operations 0.5
599 700 700
Provide energy conservation and Provide energy conservation and CO2 emission reduction services 600
CO2 emission reduction services in electricity retail field 864 0.516 *
600 600
Promoting high-efficiency electrical devices to enhance the efficient 474 0.4
use of electricity 695 432
Sterngthened Energy saving PR activities and providing information on energy-saving and CO2 500 500
400 476
cooperation reduction Electricity Consumption
376 0.3
with other Introducing smart meters for the efficient use of electricity 400 400
interested
groups Efforts by electric power industry Efforts in office-use energy saving and the use of company-owned
CO2 Emissions Volume
430 *
as users vehicles 300
200 300 0.2
123
98 200 200
79
Contributions Assisting developing countries to reduce carbon emissions through 43 38
at the International efforts participation and cooperation with overseas ventures 26 19 13 Nuclear Power Generation 0.1
11
international Low carbonization on a global scale through development and 0 100 100
level Coal Oil LNG LNG Wind Geothermal
introduction of electric technology combined 15.3
0 0.0 0
R&D for use of nuclear power Solar Nuclear Hydro 1970 1975 1980 1985 1990 1995 2000 2005 2010 2016 (FY)
Note: (1) Based on total CO2 emissions from all energy consumed in energy Note: Data up until 2007 is reported by FEPC.
Development Thermal power technology to reduce the environmental load extraction, transportation, refining, plant operation and maintenance, etc. Data from 2007 to 2014 is reported by FEPC and some PPSs.
of innovative Research and development in addition to burning of the fuel. Data from 2014 onward is reported by ELCS.
technologies Countermeasures for large amount introduction of renewable energy (2) The figure of nuclear power generation is calculated including the Up until 2014, the figures for nuclear power generation are on a gross-output basis as
reprocessing of spent fuel, use of MOX fuel, and the disposal of reported by FEPC, whereas the figures from 2015 onward are on a net-output basis as
high-level radioactive waste. reported by ELCS.
Development of technologies on the efficient use of energy Source: Report of the Central Research Institute of Electric Power Industry, etc.
The figures with an asterisk are adjusted values taking into account CO2 credits and other
adjustments.
10 11
Environmental Conservation
Decarbonization of Energy on the Supply-side Sharing Japan’s Top-level Power Generation Technologies
Development and expansion of the use of renewable energy sources with the World
The feed-in tariff system for renewable energy began in storage batteries will be actively conducted to help stabilize Japan has achieved the world’s top-level in energy improvement of operation and maintenance technologies,
July 2012, whereupon the electric power companies are the system, when introducing large amounts of wind and efficiency by introducing various technologies for higher coal-fired plants’ CO 2 reduction potential in OECD
obliged to buy such electricity at a fixed price for a certain photovoltaic power, which are susceptible to the weather. energy efficiency to thermal power plants. Based on this countries and developing countries in Asia in FY 2030 is
period. The cost of purchasing this electricity is finally borne Electric utilities will keep striving to develop and improve achievement, the electric utility industry in Japan has been estimated to be a maximum of 900 million t- CO2/year.
by customers in the form of a surcharge, which in principle renewable energy sources. making efforts to establish a mechanism for sharing such The electric utility industry of Japan will contribute to the
is proportional to the amount of electricity consumed. In March 2017, the Organization for Cross-regional advanced technologies with electric power industries in reduction of global CO2 emissions with Japan’s expertise
The Revised FIT Act was enacted in April 2017, Coordination of Transmission Operators, JAPAN (OCCTO) other countries. and advanced technologies.
making changes to the FIT system including creating a significantly shifted the approach taken toward electricity With high-efficiency plants to be introduced and the
new authorization system, revising the method of setting network operation and facility configuration by presenting
purchase prices, and revising businesses obliged to purchase a direction where “maximum use would be made of existing
FIT electricity, under the policy of “maximizing the amount electricity networks to comprehensively minimize long-term
of renewable energy to be introduced while suppressing the electricity source and distribution costs while continuing to
burden on the public”. meet electric source connection needs through expanded
However, renewable energy such as solar power has adoption of renewable energies and other measures”. Given
problems involving efficiency, cost of power generation and this new policy, discussions are being held on flexibly
stability of output. R&D on the latest power system control utilizing existing transmission lines’ capacity to enable
technologies for combining existing power plants and connection under certain conditions.
Introduction amount of Generating Capacity Comparison of Thermal Power Plant Efficiency in Japan and Other Countries
(Renewable energy) *
50
6,000 (%) U.K./lreland
(Ten thousand kW) Solar
Wind 48 France
Small and medium sized hydro
Geothermal
5,000 46
Biomass
T herma l E ffi cie nc y
Northern
Europe
40
Germany
3,000
38 China
India
36
2,000 Mikuni Solar Power Station
Australia
34
1,000 32
30
0
'10 '11 '12 '13 '14 '15 '16 28
'90 '92 '94 '96 '98 '00 '02 '04 '06 '08 '10 '12 '14 '16(Year)
Note: Values listed for heat efficiency are gross thermal efficiency values: a weighted average of the heat efficiency of coal, oil, and gas (lower heating value standard).
Feed-in tariff system Subject facilities are those of operators whose main business is selling electricity to third parties.
Japan’s values are fiscal year values.
* Excludes large-scale hydroelectric power generation Source: ECOFYS "INTERNATIONAL COMPARISON OF FOSSIL POWER EFFICIENCY AND CO2 INTENSITY(2018)”
Source: METI Wind Power
12 13
Environmental Conservation International Exchanges
Demand-side Efforts for CO2 Reduction Strengthening International Communication and Cooperation
Along with working to promote further use of hot Trends in EcoCute Unites Shipped Japan’s electric power companies remain active on a control. The industry’s top executives actively participate in
water supply systems (EcoCute) with CO 2 refrigerant (Thousands of units) worldwide basis. In order to cope with global warming international meetings such as the International Electricity
heat pumps, which significantly reduce CO2 emissions 6,000 5,912 and to ensure the safety of nuclear power generation, Summit and the World Association of Nuclear Operators
compared to conventional water heaters, the industry is Cumulative Units Shipped 447 international cooperation is indispensable. Each of (WANO) to exchange views, while we also accept trainees
5,466
actively working to promote more widespread use of high- Units Shipped in fiscal year
the electric power companies in Japan has individual from overseas. We import most of our fuel such as oil and
424
efficiency commercial air conditioners and other appliances 5,041 agreements with overseas utilities in order to facilitate coal from overseas countries and also keep our doors open
5,000
that utilize heat pump technology. 408 exchanges on a wide range of information such as power to foreign companies for the purchase of equipment such as
4,634
EcoCute heats water by transferring the thermal energy 415 generation, customer relations, distribution and quality generators.
4,219
in air, which is freely available, to water by means of
4,000 459
refrigerants. With a single unit of electric energy for heat 3,759 Overseas Offices
pump operation and two units of thermal energy from air, it 447
3,312 Please feel free to contact your nearest office.
produces three units of thermal energy.
If the heat demand for the consumer division (households 497
3,000 2,816 WASHINGTON, D.C. PARIS
and commercial divisions) and industrial division currently ●The Federation of Electric Power Companies of Japan, ●The Kansai Electric Power Co., Inc., Paris Office
566
being fulfilled through boilers can be met with heat pumps, Washington Office 13-15 Boulevard de la Madeleine 75001 Paris, FRANCE
2,249 Tel: (01) 43 12 81 40 Fax: (01) 43 12 81 44
CO2 emissions in 2030 are estimated to be reduced by 21.74 The Federation’s Washington Office was established in January 1994. Its Established in 2008
2,000 508
million t-CO2/year compared to 2015 levels. 1,741 principal objectives are to study U.S. energy policies and to exchange
DOHA
information with U.S. energy opinion leaders in order to promote a greater
500 understanding of the Japanese electric power industry. ●Chubu Elecric Power Co., Inc., Doha Office
1,241 4th Floor, Salam Tower, Al Corniche P.O.Box 22470,
1707 L Street, N.W., Suite 670, Washington, D.C. 20036, U.S.A.
413 Tel: (202) 466-6781 Fax: (202) 466-6758 Doha-QATAR
1,000 828 Tel: (974) 4483-6680 Fax: (974) 4483-4841
350 Established in 1994
Established in 2007
478 ●Tokyo Electric Power Company Holdings, Inc., Washington Office
252 226 2121 K Street, N.W., Suite 910, Washington, D.C. 20037, U.S.A. BEIJING
41 121 131
3 37 81 Tel: (202) 457-0790 Fax: (202) 457-0810
0 ●Tokyo Electric Power Company Holdings, Inc., Beijing Office
Established in 1978
2001 03 05 07 09 11 13 15 17 (FY) Unit 4, Level 8, Tower E3, Oriental Plaza,
●Chubu Electric Power Co., Inc., Washington Office No.1 East Chang An Avenue, Dong Cheng District, Beijing 100738, CHINA
Source: The Japan Refrigeration and Air Conditioning Industry Association
900 17th Street, N.W., Suite 1220, Washington, D.C. 20006, U.S.A. Tel: (10) 8518-7771 Fax: (10) 8518-7770
Tel: (202) 775-1960 Fax: (202) 331-9256 Established in 2011
Established in 1982
BANGKOK
NEW YORK
●The Kansai Electric Power Co., Inc., Bangkok Office
EcoCute Hot Water Supply Structure: CO2 Refrigerant Heat Pump Hot Water Heater ●The Kansai Electric Power Co., Inc., New York Office 23rd Floor, BHIRAJ TOWER AT EMQUARTIER, 689 Sukhumvit Rd,
1 Rockefeller Plaza, Suite 1410, New York, NY 10020 U.S.A. Kholng Tan Nuea, Vadhana, Bangkok, 10110, THAILAND
Tel: (917)265 - 8612 Fax: (917) 265-8614 Tel: (02)014-2520 Fax: (02)014-2521
Established in 2017 Established in 2016
Temperature Control Knob
Compressor LONDON JAKARTA
Electricity 1 Kitchen
●Tokyo Electric Power Company Holdings, Inc., London Office ●The Kansai Electric Power Co., Inc., Jakarta Office
Tank Hot 4th Floor, Marlborough Court, 14-18 Holborn, London, EC1N 2LE U.K. 18th Floor Summitmas I Jl Jend Sudirman Kav 61-62 Jakarta 12190 INDONESIA
Water Tel: (020) 7405-5299 Fax: (020) 7831-3065 Tel: (021)2751-0048 Fax: (021)2751-0047
Water Heat Energy Obtained Supply Bathtub Established in 1982 Established in 2016
Air Heat Exchanger
Heat Shower
Water
2
Cycle =3
Floor London
Paris
heating
New York Beijing
Washington, D.C.
JAPAN
Expansion Pump Cold
Valve Doha
Water
Supply Bangkok
1 Electricity Energy +2 Atmospheric Heat =3 Energy Obtained for Hot Water Supply EcoCute Heat Pump Unit (left) and
Hot Water Storage Tank
14 15
Location of Power Stations
8 Chiba Tokyo 4,380 LNG 3 1,100 BWR 1993.8 12 Okutataragi Kansai 1,932 Pumped Storage
9 Anegasaki Tokyo 3,600 Heavy, crude oil, LNG, LPG, NGL 4 1,100 BWR 1994.8 13 Okawachi Kansai 1,280 Pumped Storage
5 1,100 BWR 1990.4 14 Okuyoshino Kansai 1,206 Pumped Storage
10 Sodegaura Tokyo 3,600 LNG
ABWR
6 1,356 1996.11 15 Kisenyama Kansai 466 Pumped Storage
11 Yokohama Tokyo 3,460 Heavy, crude oil, LNG
7 1,356 ABWR 1997.7 16 Matanogawa Chugoku 1,200 Pumped Storage
12 Kawasaki Tokyo 3,370 LNG 6 Hamaoka Chubu
3 1,100 BWR 1987.8
1 1 17 Nabara Chugoku 620 Pumped Storage
13 Hitachinaka Tokyo 2,000 Coal 4 1,137 BWR 1993.9
5 1,380 ABWR 2005.1
18 Hongawa Shikoku 615 Pumped Storage
14 Higashi Ogishima Tokyo 2,000 LNG 1
7 Shika Hokuriku
1 540 BWR 1993.7 19 Omarugawa Kyushu 1,200 Pumped Storage
15 Goi Tokyo 1,886 LNG
2 1,206 ABWR 2006.3 20 Tenzan Kyushu 600 Pumped Storage
16 Kawagoe Chubu 4,802 LNG
8 Mihama Kansai
3 826 PWR 1976.12 21 Ohira Kyushu 500 Pumped Storage
17 Hekinan Chubu 4,100 Coal
9 Takahama Kansai
1 826 PWR 1974.11 22 Shin Toyone J-Power 1,125 Pumped Storage
18 Chita Chubu 3,966 Heavy, crude oil, LNG 2 826 PWR 1975.11
2 23 Shimogo J-Power 1,000 Pumped Storage
19 Shin Nagoya Chubu 3,058 LNG 3 870 PWR 1985.1
PWR
24 Okukiyotsu J-Power 1,000 Pumped Storage
20 Joetsu Chubu 2,380 LNG 4 870 1985.6
10 Ohi Kansai
3 1,180 PWR 1991.12
25 Numappara J-Power 675 Pumped Storage
21 Atsumi Chubu 1,900 Heavy, crude oil
4 1,180 PWR 1993.2 26 Okukiyotsu Daini J-Power 600 Pumped Storage
22 Chita Daini Chubu 1,708 LNG 4
29 9
16 11 Shimane Chugoku
2 820 BWR 1989.2 27 Okutadami J-Power 560
23 Toyama Shinko Hokuriku 1,500 Heavy, crude oil, coal 8
12 Ikata Shikoku
3 890 PWR 1994.12
10 =Thermal Power Plant 28 Tagokura J-Power 400
24 Himeji Daini Kansai 4,091.5 LNG (1,500MW or greater) 13 Genkai Kyushu
2 559 PWR 1981.3
25 Kainan Kansai 2,100 Heavy, crude oil =Hydroelectric Power Plant
(400MW or greater)
3 1,180 PWR 1994.3
26 Sakaiko Kansai 2,000 LNG 3 =Nuclear Power Plant 4 1,180 PWR 1997.7
14 Sendai Kyushu
1 890 PWR 1984.7
27 Gobo Kansai 1,800 Heavy, crude oil 2 35
2 890 PWR 1985.11 End of Operation (End)
3
7 28 2 23 15 Tokai Daini Japan Atomic Power Co. 1,100 BWR 1978.11
5 Fukushima 1 Tokyo 460 BWR 2012.4
20 27 4 16 Tsuruga 2 Japan Atomic Power Co. 1,160 PWR 1987.2
23 24 8
25 Daiichi 2 784 BWR 2012.4
6 7 Total 39 Units 38,566MW
3
26 5 36 3 784 BWR 2012.4
15 Under Construction (Estimated start) 4 784 BWR 2012.4
11
7 13 Higashi-Dori 1 Tokyo 1,385 ABWR U.D 5 784 BWR 2014.1
16 9
13 10 5 12 8 Shimane 3 Chugoku 1,373 ABWR U.D 6 1,100 BWR 2014.1
12 11 15
17 14 Ohma J-Power 1,383 ABWR U.D Hamaoka 1 Chubu 540 BWR 2009.1
30 24 4 11 9
22 10 Total 3 Units 4,141MW 2 840 BWR 2009.1
32 15
6 Preparing for Construction (Estimated start) Mihama 1 Kansai 340 PWR 2015.4
34 13 20 6
14 Higashi-Dori 2 Tohoku 1,385 ABWR U.D 2 500 PWR 2015.4
12 33
31
18 Kaminoseki 1 Chugoku 1,373 ABWR U.D Ohi 1 1,175 PWR 2018.3
2 1,373 ABWR U.D 2 1,175 PWR 2018.3
Shimane 1 Chugoku 460 BWR 2015.4
21 Sendai 3 Kyushu 1,590 APWR U.D
28 Ikata 1 Shikoku 566 PWR 2016.5
19 Tsuruga 3 Japan Atomic Power Co. 1,538 APWR U.D
19 26 22 2 566 PWR 2018.5
14 16 4 1,538 APWR U.D
18 Genkai 1 Kyushu 559 PWR 2015.4
17 Total 6 Units 8,797MW
25 Tokai Japan Atomic Power Co. 166 GCR 1998.3
21 Others Tsuruga 1 Japan Atomic Power Co. 357 BWR 2015.4
27
Name Company Installed Type of Reactor Total 18 Units 11,940MW
of Plant Capacity (MW)
Fugen Japan Atomic Energy Agency 165 ATR(Prototype) End of Operation Note: PWR=Pressurized Water Reactor, BWR=Boiling Water Reactor, APWR=Advanced Pressurized
Water Reactor, ABWR=Advanced Boiling Water Reactor, GCR=Gas Cooled Reactor,
Monju Japan Atomic Energy Agency 280 FBR(Prototype) End of Operation ATR=Advanced Thermal Reactor, FBR=Fast Breeder Reactor
16 17
FEPC
History of Japan’s
The Federation Electric Power
of Electric UtilityCompanies
Industry Business Addresses
Tokyo Electric Lighting, a private company, commenced Kansai, Chugoku, Shikoku and Kyushu Electric Power Tokyo Electric Power Company Holdings, Inc.
1-1-3 Uchisaiwai-cho, Chiyoda-ku, Tokyo 100-8560, Japan
operations as the nation’s first electric power company, Companies — were established in 1951 and assumed the Tel: (03) 6373-1111 URL http://www.tepco.co.jp
Board of Directors
and began supplying electricity to the public in the responsibility of supplying electricity to each region. Chubu Electric Power Co., Inc.
1, Higashi-shincho, Higashi-ku, Nagoya, Aichi 461-8680, Japan
following year. The Okinawa Electric Power Co. was established with
Tel: (052) 951-8211 URL http://www.chuden.co.jp
In the early days, use of electricity grew primarily for the return of Okinawa to Japan in 1972. Hokuriku Electric Power Co., Inc.
lighting because of its safety and cleanness, and gradually At the end of the 20th century, a trend toward 15-1, Ushijima-cho, Toyama-shi, 930-8686, Japan
Tel: (076) 441-2511 URL http://www.rikuden.co.jp
found broader applications as a power source to replace deregulation and competition took hold throughout
The Kansai Electric Power Co., Inc.
the steam engine. By 1896, the number of electric utilities society, and the electric utility industry started to be 3-6-16, Nakanoshima , Kita-ku, Osaka, 530-8270, Japan
established throughout the nation reached a total of 33. liberalized. In December 1995, organizations such as Tel: (06) 6441-8821 URL http://www.kepco.co.jp
Chairman Vice Chairman Vice Chairman Vice Chairman
The early 20th century
Satoru marked the Akihiko
Katsuno establishment
Mayumiof independent
Hayato Saeki power producers Head of Nuclear(IPP)
Waste were allowed to The Chugoku Electric Power Co., Inc.
Final Repository Promotion 4-33, Komachi, Naka-ku, Hiroshima-shi, Hiroshima 730-8701, Japan
long-distance transmission technology. As larger thermal provide electricity wholesale services, and in March 2000,
Headquarters
Tel: (082) 241-0211 URL http://www.energia.co.jp
Yuzuru Hiroe
and hydro-power plants were introduced, generation costs electricity retail supply for extra-high voltage users Shikoku Electric Power Co., Inc.
fell and electricity came into wider use throughout the (demand exceeding 2MW) was liberalized. The scope of 2-5, Marunouchi, Takamatsu-shi, Kagawa 760-8573, Japan
Tel: (087) 821-5061 URL http://www.yonden.co.jp
country. Consequently, electricity became an indispensable retail liberalization was then expanded in April 2004 to
Kyushu Electric Power Co., Inc.
energy source for peoples’ lives and industry. users of more than 500kW, and subsequently in April 1-82, Watanabe-dori 2-chome, Chuo-ku, Fukuoka-shi, Fukuoka 810-8720, Japan
Tel: (092) 761-3031 URL https://www.kyuden.co.jp
In the years that followed, the electricity utility business 2005 to users of more than 50kW. Thus, a Japanese model
The Okinawa Electric Power Co., Inc.
grew in tandem with the modernization of Japan and of liberalization based on fair competition and 2-1, Makiminato 5-chome, Urasoe, Okinawa 901-2602, Japan
development of its industry.Head At ofthe sameSupport
time, the electric
Senior Managing Director
Fukushima
Director
Secretary General transparency, while
Director
Deputy maintaining
Secretary General the vertical integration of Tel: (098) 877-2341 URL https://www.oki d en.co.jp
Headquarters
utility industry experiencedShigenobu
a major restructuring Satoshi
that led Ohmori Yoshihiro Tomioka
generation, transmission and distribution to ensure a Electric Power Development Co., Ltd. (J-Power)
Shimizu
6-15-1, Ginza, Chuo-ku, Tokyo 104-8165, Japan
to the dissolution of 700 electric utilities, which merged to stable supply of electricity, was established.
Organization of FEPC Tel: (03) 3546-2211 URL http://www.jpower.co.jp
create five major electric utilities after the First World War. With the Fukushima Daiichi Nuclear Power Station The Japan Atomic Power Company (JAPC)
During the Second World War, the electric utility industry accident and subsequent tight demand and supply brought 1-1,Kanda-Mitoshiro-cho, Chiyoda-ku, Tokyo 101-0053, Japan
General Affairs Tel: (03) 6371-7400 URL http://www.japc.co.jp
was completely
Chairman state-controlled and utilities were about by the Great East Japan Earthquake in March 2011
Japan Nuclear Fuel Limited (JNFL)
integrated into Nihon Hatsusoden Co. (a nationwide power as a turning point, numerous discussions were held to
General Planning 4-108 Aza Okitsuke, Oaza Obuchi, Rokkasho, Kamikita-gun, Aomori Prefecture 039-3212, Japan
Tel: (0175) 71-2000 URL https://www.jnfl. co.jp
generating and transmitting state-owned company) and
Vice Chairman
maintain a stable supply and reduce energy costs, and in
Public Relations
Japan Atomic Energy Agency (JAEA)
nine distribution companies. Nuclear Waste November 2013, the policy to implement three-phase 765-1, Funaishikawa, Tokai-mura, Naka-gun, Ibaraki 319-1184, Japan
After the end of World War II in Final1945,
Repository
supply and reforms of the electric power Business
system was adopted. Tel: (029) 282-1122 URL https://www.jaea.go.jp
Promotion Headquarters
Senior Managing Central Research Institute of Electric Power Industry (CRIEPI)
Director Siting & Environment Otemachi Bldg., 7F, 1-6-1 Otemachi, Chiyoda-ku, Tokyo 100-8126, Japan
Nuclear Fuel Cycle Tel: (03) 3201-6601 URL https://cri epi .denken.or.jp/
Promotion Headquarters Nuclear Power
Japan Electric Power Information Center, Inc. (JEPIC)
15-33, Shibaura 4-chome, Minato-ku, Tokyo 108-0023, Japan
Secretary General Power System Planning and Operations
Fukushima Tel: (03) 6361-8210 URL https://www.jepic.or.jp
Support Headquarters World Association of Nuclear Operators Tokyo Centre (WANO-TC)
Engineering 6F Igarashi Bldg., 2-11-5 Shibaura, Minato, Tokyo 108-0023, Japan
Deputy Secretary Tel: (03) 6722-5900 URL https://www.wano.info
General Information Systems and Telecommunications
Atomic Energy Association (ATENA)
Washington Office Keidanren-kaikan, 1-3-2, Otemachi, Chiyoda-ku, Tokyo 100-8118, Japan
Research & Development Tel: (03) 5877-3880 URL http://www.atena-j.jp
18 19
The Federation of
Electric Power Companies of Japan
Keidanren-kaikan,
1-3-2, Otemachi, Chiyoda-ku,
Tokyo 100-8118, Japan
http://www.fepc.or.jp/english/index.html