23rd August 2016
PROJECT OVER VIEW
Key Milestones
Aug 2016 Sep 2016 Oct 2016 Nov 2016 Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 2017
PLANNED
1 2 3 4 5 6 7 8 9
Sept Oct Nov Nov Dec Dec Dec Feb Mar
6 3 14 30 7 11 27 14 30
ACTUAL/FORECASTED
1 2 5 3 4 6 7 8 9
Oct Nov Dec Dec Jan Jan Jan Feb Mar
8 1 7 15 1 10 26 14 30
OVERALL 27/08/2014 16/07/2016 690 29/06/2017 ‐348 30/03/2017 0 100% 57.95% ‐42.05%
Building A 27/08/2014 17/04/2016 600 06/06/2017 ‐415 26/01/2017 ‐30 100% 51.84% ‐48.16%
Building BD 27/08/2014 17/04/2016 600 26/04/2017 ‐374 01/01/2016 ‐32 100% 56.45% ‐43.55%
Building C 27/08/2014 16/07/2016 690 29/06/2017 ‐348 30/03/2017 0 100% 43.42% ‐56.58%
Key Milestone Legend: Gray Originally planned or completed activity Green On track; will complete as planned Yellow Planned delivery at risk Red Will miss planned delivery
MEP PROJECT SUMMARY
Recent Accomplishments Upcoming Key Activities
FAHU Installation in Building A & BD Chiller Installation in Building C
VRF Outdoor Installations in Building A Generator Installation.
GRP Tank Installation in Building A MDB & SMDB Installation
VRF Outdoor Installation Building BD FAHU Installation in Building C
Fire Pump Room Piping and Valve Packages. GRP Water Tank Installation in Building C
HVAC Risers installation on going in 5th & 6th Floors. Ventilation Fan Installation in Basements
LPG Tank Installation.
VRF Outdoor Unit Installation.
Electrical Room Mockup.
PROJECT STATUS
Building : C – 1st & 2nd Fix High‐level Works
PROJECT STATUS
Building : C ‐ 1st & 2nd Fix High‐level Works
• Fire Fighting : 2nd Fix Installation Completed up to 5th floor, 6th, 7th, & 8th floor in
progress.
• Plumbing : 1st and 2nd floor Completed, 3rd floor to 8th floor in progress,
water meter room mockup installation in progress.
• HVAC : 1st floor and 2nd floor ducting completed, 3rd to 4th floor in
progress,
1st and 2nd floor refrigerant piping completed, 3rd to 5th floor in
progress.
• Shafts : 2 HVAC duct riser completed up to 9th floor.
• Roof : FAHU installation, VRF outdoor units & GRP tanks
installations ongoing
PROJECT STATUS
Building : BD ‐ 1st & 2nd Fix High‐level Works
PROJECT STATUS
Building : BD ‐ 1st & 2nd Fix High‐level Works
• Fire Fighting : 2nd Fix Installation Completed up to 5th floor, 6th, 7th, & 8th floor in
progress
• Electrical : 1st floor completed 2nd floor to 8th floor in progress.
• Plumbing : 1st floor Completed, 2nd floor to 7th floor in progress.
• HVAC : 1st floor ducting completed, 2nd to 5th floor in progress,
1st and 2nd floor refrigerant piping completed, 3rd to 5th floor in
progress.
• Shafts : Duct ‐ 2 risers completed up to 8th floor,
Garbage chute – 2 risers completed up to 6th floor
• Roof : FAHU installation, VRF outdoor units & GRP tanks installation ongoing
MEP DASHBOARD