Date Prepared: February 7, 2019

Republic of the Philippines


Department of Agriculture
Regional Field Office 3
Philippine Rural Development Project
Regional Project Coordination Office
City of San Fernando, Pampanga

AGT CERTIFICATE
in Support to the Validated Statement
of Work Accomplished (VSWA) of 59.71%
as of January 27, 2019

This is to confirm that the geotagged photographs of progress


at stations 0+000 to 15+031 of the subproject in support of
this fund transfer has been submitted by the Contractor to
the Procuring Entity on January 25, 2019. The photographs are
dated February 1, 2019 as shown in the screen shot. This is
also to certify that the geotagged photos have satisfactorily
complied with the GGU requirements.

Prepared by: Comformed by:

Subproject Title: New Construction of San Antonio-Parang-Saysain Farm-to-Market Road


Province: Bataan RONALD PATRICK J. SOCORRO Engr. ALEXANDER BALUYOT
Municipality: Bagac RPCO3 GGU PPMIU Head
Contract Amount: Php 172,874,866.02 (Original: Php 157,521,347.90) + (V.O.: Php 15,353,518.12)
Status of the sub-project: On-going
% Accomplishment to date: 59.71% (Costshared: 51.85%) + (V.O.: 7.86%) Approved by:
Date Started / NTP: July 27, 2017
Target Completion Date: September 30, 2018
Revised Target Completion Date: April 15, 2019 DR. EDUARDO L. LAPUZ, JR.
Name of Contractor: 4B CONSTRUCTION CORPORATION OIC-RTD for Regulations, Research and ILD/
Regional Project Director, RPCO3

Remarks: “Stated billable request for fund transfer will comply with COA Circular No. 2012-001
dated June 14, 2012, Section 9.1.1 (pictures/geotag, before, during and after construction of items
of work especially the embedded items.”