Professional Documents
Culture Documents
Risk Qualification
Risk Qualification
Evaporator
Refrigeration
unit
Racking
Control
Racking System
Conditioned Space
Level 1
Equipment
Racking
CPP
monitoring
system
Instruments directly associated with these attributes as part of the SPP FAN, SUPPLY
Monitoring System shall be classified as level 1. INSTRUMENT – Level 1
• Relational Model
Engineering Design
Change Automation
Review
Management Project Delivery
Commissioning
Planning and
Execution
Engineering
Quality Systems
Engineering Walk
Vendor Data Vendor CMMS Instrument Receipt Down and
Requirements Assessment Data Calibration Verification Punch
listing
Verification
tests, SAT
Development
Validation Plan Design Reviews Testing
Quality Pre and Post Approval Quality Review Quality Approval
Amgen Relational Model for Qualification
SME’s
Process
Product
System User
Regulatory Requirements
Quality
Vendors
Traceability
System Qualification
Risk Commissioning Performance
Specifications report
Assessment / Testing Qualification
• Strategic:
• Commissioning, Qualification, and
Validation are processes
• Tactical
• Verification is an activity within any of
these processes
Risk Assessments
Requirement
• Provide an environment to maintain product in
pre-defined conditions – temperature – not
usually but potentially light levels, RH.
Procedures required to
Occurrence
Detection
Source or cause of the control the likelihood of the risk controls are in What mechanisms would
Severity
Effect / consequence of control the likelihood of Risk Impacted
SQA Potential hazard to SQA hazard (how can the hazard occurrence place working as specified detect the result if the risk Comments
the hazard hazard occurrence (SOPs, Level Systems
hazard occur?) (Instrumentation, (development testing, IV, occurred?
training manuals)
alarms and interlocks). OV)
Compliance with the
Compliance with the
specifications for the
Breakdown of the product PM's will include the specifications for the
Specification of system materials of
contact materials of requirement to inspect system materials of
Particulate Potential contamination appropriate materials construction will be
1 Purity construction (metallic) - the equipment during construction will be None N/A
contamination (metallic) of the system product for system construction confirmed through the
due to the system maintenance and report confirmed through the
and filters Commissioning Test
product. any degradation or commissioning test
Protocol (CTP).
corrosion found. protocol (CTP).
7 1 1 Low
The report from
The operational SOP will The commissioning test operations that the
The specification will
require a visual inspection protocol (CTP) will confirm system is not clean, or
call for the system to be
2 N/A N/A N/A N/A of the system to ensure that the system was from maintenance that None N/A
cleaned and flushed
that it is clean and cleaned and flushed prior the system is damaged or
prior to use.
undamaged. to use. degradation / corrosion
has been found.
Score the results: Severity - score based on – if the hazard occurs
(i.e. no system based prevention or detection in place but considering
the impact of additional processing/testing that will occur)
SEVERITY of the effect of failure Scoring Guidance – if appropriate this may be used
Rating
(System/Equipment ) to help assess the severity rating
Scoring Guidance – if
appropriate this may be used
Score QRAES definitions
to help assess the Detection
score
Absolutely uncertain – Existing controls cannot detect the
9 failure. No controls are in place. N/A
3 High – Very likely that the control will detect the failure. Procedural controls in place
Almost certain – The control will detect the failure in almost Monitored by automation system
every instance. using automated alarm for
1 the parameter.
Independent check, e.g. product
release test
Severity of Risk
Likelihood of 1 3 5 7 9
Occurrence Insignificant Minor Moderate Major Severe
9 – Frequent Medium Medium High High High
7 – Likely Low Medium High High High
5 – Occasional Low Medium Medium High High
3 – Unlikely Low Low Medium Medium High
1 – Remote Low Low Low Low Medium
NOTE: Utilize the output from the table above for a risk classification in the table below
Detection
Detectability
Probability
mitigate this source? How do site What mechanisms
Severity
Source of hazard (how (instrumentation, procedures mitigate would detect the
can the hazard alarms and this source? (Quality result if the hazard
RPN
Hazard happen?) interlocks) Systems) occurred?
Breakdown of Pipework, valve,
Particulate or chemical pipework/instrumentation gasket & Instrument Water Quality
contamination material 9 Specification IV 1 Monitoring 9 81
Alarm on high
Calibration of the on conductivity, with SOP
Provision of an on line line conductivity defining action in the
conductivity meter instrument event of an alarm 0
Provision of sample Off line quality
points Sampling procedures monitoring. 0
Input from
procurement
procedures &
Provide an approved maintenance Water Quality
spare parts list procedures Monitoring 0
Reverse flow of air into Pumps design to
the system through a drop maintain system Low loop return
valve. 9 pressure IV/ACO 1 pressure alarm 1 9
Drop valve orifices,
used to restrict outlet Low loop return
SME sub
flow. IV pressure alarm 0
Alarm on low loop Calibration of the SOP - action in the
return pressure pressure detector, event of an alarm 0
team
Design to maintain pressures of the WFI
WFI at a higher and utility supplying the
pressure than the control valve as it is Water Quality
heating/cooling media. tested during ACO Monitoring 0
Scope, CPPs,
sanitized after any recipe with alarms /
System can be steam shutdown exceeding 8 timers, + other
sanitized. hours (per SOP). thermocouples.) 0
Reverse flow of air into Pumps design to
the system through a drop maintain system Low loop return
valve. 9 pressure IV/ACO 1 pressure alarm 1 9
Drop valve orifices,
used to restrict outlet Low loop return
flow. IV pressure alarm 0
CQAs
Alarm on low loop Calibration of the SOP - action in the
return pressure pressure detector, event of an alarm 0
IV,ACO,FT, IOQ
Qualification
Summary
Report
Verification Traceability
Qualification Summary Reports
Cross-functional Review
Program Deliverables
Based
Corporate
Based
Proof
Program of
Theory Concept
Feedback
The Proof-of-Concept (POC) Methodology
Reinforces our Partnership Approach
Roles
• Corporate provide overall strategy for program
framework
• Functions provide technical perspective
• Sites provide execution perspective (i.e. will this work?)
Procedures
Records
Changes to Key Processes Have Resulted in
Measurable Value
Historical Approach New Approach Benefit
by applying...
Qualification protocols at Qualification process Efficient use of
project-end with testing integrated into resources and
redundant to engineering Good engineering project reduced pressure
project lifecycle Engineering without unnecessary on project schedule
Practices redundant testing
Qualification testing Testing also considers Focuses
based on equipment critical controls, qualification efforts
specifications and Risk detection mechanisms & on defined critical
capabilities Management all quality systems aspects
Design review applied Design review well- Enables appropriate
inconsistently with directed with defined and defendable
Systematic
unstructured Quality Quality involvement Quality oversight
Design Review
involvement
Changes are not well- All changes are Prevents need to
controlled until a system Engineering effectively managed perform redundant
is qualified and released Change throughout the testing at project-
for use Management engineering project end
The POC Projects Validate the Value of the
Concepts and Amgen Approach
Validation Projected
Project Cost Avoidance
23% Savings
Purification Train
Capacity Increase
20% savings
Fill Finish Facility
We Tested More During FAT and Less on Site
39
We Reduced Redundancy in Testing and
Documentation
• Process Equipment Example
500
• 75% reduction in total pages
18
• Eliminated redundant testing
across protocols
Quality Summary
400 Report • Eliminated redundant
attachment of vendor documents
CQP Document Pages
Commissioning Test
229 • Reduced un-necessary testing
Protocol
by benchmarking best in class
300 System Test
protocols across network
Qualification Matrix
Operational • 50% reduction in documents
Qualification
200 • Combined IV,RV, FAT, and
Factory Acceptance OQ into one protocol (CTP)
122 Testing
Installation
100 20 Verification
79 Receipt Verification
93
31
0 8
Project E Project F
Project Scope
Operate &
Plan Design Build Test
Maintain
Adopted Practices
SME’s
Process Additional Value???
Product
System
Regulatory
User • Change Control
Quality
Requirements
Vendors
Assessments
Process
Characterization
data
• Failure Event Impact
Risk Assessments
Assessment Additional
Benefits • Preventive
Maintenance
• Process
Characterization
• Others?
Lessons Learned and Next Steps
Energy Efficient!
Starting
Point
Goal –
Integrated
Processes
Lessons Learned: Effective Partnerships
have been Key to our Success
• Joint sponsorship demonstrated shared
leadership and accountability.
• Breaking down barriers between Functions
improved process and equipment knowledge.
• Different groups understand and appreciate
roles and interactions more clearly
Maturity? – Engineering:
49
Questions?
Thanks
haycocks@amgen.com