Professional Documents
Culture Documents
Cost Type Amount: Planned Costs 600k Actual Costs 500k Earned Value 460k
Cost Type Amount: Planned Costs 600k Actual Costs 500k Earned Value 460k
Question 1
Consider a project with a budget of £1m (BAC). It has a planned duration of 18 months. After 10 months the
reported figures are:
Cost Type Amount
Planned Costs £600k
Actual Costs £500k
Earned Value £460k
Calculate CPI, CV, SPI, SV, Final Coat, Final Planned Duration and % Complete. Comment on the figures you have
calculated.
Formulae
CPI = EV/AC
SPI = EV/PC
CV = EV – AC
SV = EV – PC
CPI 0.92
SPI 0.77
CV -40
SV -140
% complete 46%
Session 7B – Control costs
A CPI value less than 1, or a negative CV indicates that the project will be over budget. This is supported by the Final
Cost calculation indicating a budget overrun of just under 9%.
A SPI value less than 1, or a negative SV, indicates that the project will be late. This is supported by the Final Planned
Duration figure of 23 months.
The project is less than half finished (%complete = 46%) and is going to be late by 5 months in a 18 month project.
This is perhaps more worrying than the cost overrun as this is less than a potentially acceptable 10% overall.
I would investigate the reasons for the delay and see if it can be corrected.