EPS

CIVIL ENGINEERING WORKS SECTION A: ROADWORKS & STORMWATER DRAINAGE

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT


SITE CLEARANCE
Allow for the clearing of all the bushes,
A1 undergrowth and small trees with girth 3,000.0 m2 1.10 3,300.00
n.e 1000 mm along roads
Provisional allowance for use as
A2 requested by Engineer for site Sum 2,000.00 2,000.00
preparation & Supervision
A3 Rip off tarmac specified areas 0.0 m2 20.00 0.00

Removal of trees, stumps and roots in


areas for roadworks and along route for
A4 2.0 No 40.00 80.00
stormwater, of girth more than 1000 mm
measured at 1m above ground level.

Remove overburden/topsoil to a depth


A5 of 200 mm and stockpile for later use 660.0 m3 3.00 1,980.00
along roads and walkways
Spread topsoil and level in specified
A6 660.0 m3 2.80 1,848.00
areas
Excavate excess or unsuitable material
A7 below formation level to spoil within 0.5 330.0 m3 3.35 1,105.50
km in roads
Source and supply fill material and use
for fill sections in roads spreading in
A8 layers n.e 150mm (measured 330.0 m3 5.10 1,683.00
compacted ) to 91% HCE (free haulage
0.5 km)
A9 Excavation in
A9.1 hard material 49.5 m3 10.50 519.75
A9.2 rock material 5.0 m3 25.00 123.75
Excavate anthills as to spoil within
A10 50.0 m3 15.00 750.00
0.5km (prov)
A11 Treat antihills as specified (prov) 60.0 m2 3.50 210.00
Extra over D3, D4, D5, D6, D7, D8 & D9
A12 2,640.0 m3km 0.35 924.00
for overhaul exceeding 0.5km.
Form, scarify and compact subgrade as
A13 specified 91% HCE along roads and 3,000.0 m2 1.50 4,500.00
walkways.
Source, supply, spread trim and
A14 compact 150mm base layers (free 450.0 m3 30.00 13,500.00
overhaul 0.5 km)
A15 Extra over item D14 for overhaul 9,000.0 m3km 0.10 900.00
TOTAL CARRIED FORWARD 33,424.00

Enhanced Power Solutions Pvt Ltd 9


EPS

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT


TOTAL BROUGHT FORWARD 33,424.00
Supply and spray Bitumen Prime
including preapation and watering of
A16 1,500.0 m2 2.20 3,300.00
base 1 (cut back Bitumen to be applied
at a rate of 1.001/m2
13.2/6.7 DOUBLE SEAL
Supply all materials for and apply
double seal. Seal spray and cheap
surfacing including over shoulders if
A18
required by the Engineer using the
following materials and application
rates.
tack coat of penetration grade Bitumen
A18.1 1,500.0 m2 3.60 5,400.00
150/200 0.9 to 1.21/m2
13 mm stone chips 60 to 80 sq.m per
A18.2 1,500.0 m2 4.50 6,750.00
cu.m
seal coat of penetration grade Bitumen
A18.3 1,500.0 m2 1.25 1,875.00
150/200 0.8 to 1.01/sq.m
6.7 mm stone chips 115 to 130 sq.m per
A18.4 1,500.0 m2 3.10 4,650.00
cu.m
Extra over for cement stabilization of
A19
base

A19.1 Supply of cement to point of application 50.0 m2 25.00 1,250.00

Allow for spreading, firm, mixing and


A19.2 compacting as specified by the 50.0 m2 15.00 750.00
Engineer.
WALKWAYS
None
KERBING, SIGNAGE AND PAINTING
Supply, lay and bed precast concrete
A20 municipal kerb type H7 (Fort Concrete 10.0 m 11.90 119.00
or similar)
Supply, lay and bed precast concrete
A21 rollover kerbing kerb type H9 (Fort 10.0 m 13.50 135.00
Concrete or similar)
TOTAL CARRIED FORWARD 57,653.00

Enhanced Power Solutions Pvt Ltd 10


EPS

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT


TOTAL BROUGHT FORWARD 57,653.00
Supply and erect stop signs complete
A22 1.0 No 225.50 225.50
with post
Supply and erect street name signs as
directed. (Standard MS plate or other
A23 approved bolted to 3mx50mm GMS 1.0 No 192.85 192.85
pipe).

A24 Grade 10 haunching to kerbing 0.4 m3 150.00 56.63


STORMWATER
A25 Excavate for trapezoidal drains
A25.1 soft material 108.8 m3 7.10 772.13
A25.2 hard material 16.3 m3 10.50 171.28
A25.3 rock material 8.2 m3 25.00 203.91
CULVERTS & STORMWATER PIPES
Excavate for culverts and stormwater
A26
pipes
A26.1 soft material 5.3 m3 7.10 37.49
A26.2 hard material 0.5 m3 10.50 5.54
A26.3 rock material 0.3 m3 25.00 6.60
Excavate, backfill and compact pipe
A27 12.0 m 3.70 44.40
trenches for concrete stormwater pipes
Supply, lay and backfill concrete 525
A28 mm nb stormwater pipes with 12.0 m 230.76 2,769.12
interlocking ogee joints
TOTAL CARRIED FORWARD 62,138.44

Enhanced Power Solutions Pvt Ltd 11


EPS

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT


TOTAL BROUGHT FORWARD 62,138.44
Grade concrete 10 bed and
A29 haunch/surround to culverts and 0.4 m3 150.00 60.00
stormwater pipes
Supply all materials and construct 20
A30 1.0 m3 210.00 210.00
Mpa concrete headwalls
Allow a provisional sum for testing by
A31 Sum 800.00 800.00
appointed laboratory
Apply for and make a permanent
connection into municipality stormwater
catchpit/drain on behalf of Client.
A32 1 No 500.00 500.00
Include for excavation, all materials and
making good and testing etc as required
by Municipality.
TOTAL FOR SECTION 'A' CARRIED TO SUMMARY 63,708.44

Enhanced Power Solutions Pvt Ltd 12


SUMMARY OF CIVIL ENGINEERING WORKS BILL OF QUANTITIES

CIVIL ENGINEERING
DESCRIPTION CLAIMED AMOUNT (USD)
WORKS SECTION
(Karuch CE)

ROADWORKS AND STORMWATER


A 63,708.44
DRAINAGE

SUB-TOTAL 1 63,708.44

ADD 10 % CONTINGENCIES (RIGHT RESERVED FOR CLIENT TO


6,370.84
RECLAIM FUNDS)

SUB-TOTAL 2 70,079.28

ADD 15 % VAT (For ZIMRA) 10,511.89


TOTAL FOR CIVIL ENGINEERING WORKS CARRIED TO FORM
80,591.18
OF QOUTE

CIVIL ENGINEERING WORKS SECTION A: ROADWORKS & STORMWATER DRAINAGE

ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT


SITE CLEARANCE
Allow for the clearing of all the bushes,
A1 undergrowth and small trees with girth 3,000.0 m2 1.10 3,300.00
n.e 1000 mm along roads
Provisional allowance for use as
A2 requested by Engineer for site Sum 2,000.00 2,000.00
preparation & Supervision
A3 Rip off tarmac specified areas 0.0 m2 20.00 0.00
Removal of trees, stumps and roots in
areas for roadworks and along route
A4 for stormwater, of girth more than 1000 2.0 No 40.00 80.00
mm measured at 1m above ground
level.
Remove overburden/topsoil to a depth
A5 of 200 mm and stockpile for later use 660.0 m3 3.00 1,980.00
along roads and walkways
Spread topsoil and level in specified
A6 660.0 m3 2.80 1,848.00
areas
Excavate excess or unsuitable material
A7 below formation level to spoil within 0.5 330.0 m3 3.35 1,105.50
km in roads
Source and supply fill material and use
for fill sections in roads spreading in
A8 layers n.e 150mm (measured 330.0 m3 5.10 1,683.00
compacted ) to 91% HCE (free
haulage 0.5 km)
A9 Excavation in
A9.1 hard material 49.5 m3 10.50 519.75
A9.2 rock material 5.0 m3 25.00 123.75
Excavate anthills as to spoil within
A10 50.0 m3 15.00 750.00
0.5km (prov)
A11 Treat antihills as specified (prov) 60.0 m2 3.50 210.00
Extra over D3, D4, D5, D6, D7, D8 &
A12 2,640.0 m3km 0.35 924.00
D9 for overhaul exceeding 0.5km.
Form, scarify and compact subgrade
A13 as specified 91% HCE along roads 3,000.0 m2 1.50 4,500.00
and walkways.
Source, supply, spread trim and
A14 compact 150mm base layers (free 450.0 m3 30.00 13,500.00
overhaul 0.5 km)
A15 Extra over item D14 for overhaul 9,000.0 m3km 0.10 900.00
Supply and spray Bitumen Prime
including preapation and watering of
A16 1,500.0 m2 2.20 3,300.00
base 1 (cut back Bitumen to be applied
at a rate of 1.001/m2

13.2/6.7 DOUBLE SEAL SURFACING


Supply all materials for and apply
double seal. Seal spray and cheap
surfacing including over shoulders if
A18
required by the Engineer using the
following materials and application
rates.
tack coat of penetration grade Bitumen
A18.1 1,500.0 m2 3.60 5,400.00
150/200 0.9 to 1.21/m2
13 mm stone chips 60 to 80 sq.m per
A18.2 1,500.0 m2 4.50 6,750.00
cu.m
seal coat of penetration grade Bitumen
A18.3 1,500.0 m2 1.25 1,875.00
150/200 0.8 to 1.01/sq.m
6.7 mm stone chips 115 to 130 sq.m
A18.4 1,500.0 m2 3.10 4,650.00
per cu.m
Extra over for cement stabilization of
A19
base
Supply of cement to point of
A19.1 50.0 m2 25.00 1,250.00
application
Allow for spreading, firm, mixing and
A19.2 compacting as specified by the 50.0 m2 15.00 750.00
Engineer.
WALKWAYS
None
KERBING, SIGNAGE AND PAINTING
Supply, lay and bed precast concrete
A20 municipal kerb type H7 (Fort Concrete 10.0 m 11.90 119.00
or similar)
Supply, lay and bed precast concrete
A21 rollover kerbing kerb type H9 (Fort 10.0 m 13.50 135.00
Concrete or similar)
Supply and erect stop signs complete
A22 1.0 No 225.50 225.50
with post
Supply and erect street name signs as
directed. (Standard MS plate or other
A23 approved bolted to 3mx50mm GMS 1.0 No 192.85 192.85
pipe).
A24 Grade 10 haunching to kerbing 0.4 m3 150.00 56.63
STORMWATER DRAINAGE
A25 Excavate for trapezoidal drains
A25.1 soft material 108.8 m3 7.10 772.13
A25.2 hard material 16.3 m3 10.50 171.28
A25.3 rock material 8.2 m3 25.00 203.91
CULVERTS & STORMWATER PIPES ACROSS ROAD
Excavate for culverts and stormwater
A26
pipes
A26.1 soft material 5.3 m3 7.10 37.49
A26.2 hard material 0.5 m3 10.50 5.54
A26.3 rock material 0.3 m3 25.00 6.60
Excavate, backfill and compact pipe
A27 12.0 m 3.70 44.40
trenches for concrete stormwater pipes

Supply, lay and backfill concrete 1 X


A28 525 mm nb stormwater pipes with 12.0 m 230.76 2,769.12
interlocking ogee joints
Grade concrete 10 bed and
A29 haunch/surround to culverts and 0.4 m3 150.00 60.00
stormwater pipes
Supply all materials and construct 20
A30 1.0 m3 210.00 210.00
Mpa concrete headwalls
Allow a provisional sum for testing by
A31 Sum 800.00 800.00
appointed laboratory

Apply for and make a permanent


connection into municipality
stormwater catchpit/drain on behalf of
A32 1 No 500.00 500.00
Client. Include for excavation, all
materials and making good and testing
etc as required by Municipality.

TOTAL FOR SECTION 'A' CARRIED TO SUMMARY 63,708.44


SUMMARY OF CIVIL ENGINEERING WORKS BILL OF QUANTITIES

CIVIL ENGINEERING
DESCRIPTION CLAIMED AMOUNT (USD)
WORKS SECTION

A WATER RETICULATION 0.00

B TRUNK SEWER 0.00

C SEWER RETICULATION 0.00

D ROADWORKS AND STORMWATER DRAINAGE 63,708.44

SUB-TOTAL 1 63,708.44

ADD 10 % CONTINGENCIES 6,370.84

SUB-TOTAL 2 70,079.28

ADD 15 % VAT (Zimra) 10,511.89

TOTAL FOR CIVIL ENGINEERING WORKS CARRIED TO FORM OF


80,591.18
QOUTE