Prepare estimation cost for fixing one 1 piece 250mm x 250mm heavy duty car porch tile
with 15mm thick of cement and total cost for 800 pieces of the proposed car porch tiles
project abiding on data below. The project duration is expected to be 2 days and requires
2 skilled workers and 3 unskilled workers.
Given
(i) White horse heavy duty tile (250mmx250mm) = RM1.60/piece
(ii) Cement = RM 14.00/bag
(iii) Skilled worker = RM 90.00/day
(iv) Unskilled worker = RM 50.00/day
(v) Profit = 15%
Solution
Material cost:
1. Tile;
a) Tiles = 800 pieces
b) Waste (5%) = 40 pieces
Cost of tiles = 840 pieces x RM1.60/ piece = RM 1344.00
2. Cement;
a) vol. of cement = 0.25 x 0.25 x 0.015 = 0.0009375 m3/piece
Total vol. of cement = 800 pieces x 0.0009375 m3/piece= 0.75 m3
Cost of cement = (0.75 m3x28bag/m3) x RM14.00/bag = RM 294.00
Labour cost:
1. Workers;
a) Skilled workers = 2 x RM 90.00 = RM 180.00
b) Unskilled workers = 3 x RM 50.00 = RM 150.00
Total labour cost = RM 330.00