Bandar Sri Sendayan : Progress Certificate Check List

Suriaman 2 Block Unit F'tion RC Wall Roof Plast. Sewer.


Dec 2018 DT A1-1* 2
DT A2-1* 2
DT A1-1 7
DT A1-2 8
DT A1-3 7
DT A1-4 6
DT A1-5 6
DT A1-6 6
DT A1-7 6
DT A1-8 6 24-Oct
DT A1-9 8
DT A1-10 8
DT A1-11 8
DT A1-12 8
DT A1-13 8
DT A2-1 9
DT A2-2a 8
DT A2-2b 6 21-Oct
DT A2-3 8 23-Oct
DT A2-4 12 14-Nov
DT A2-5 11 29-Nov
DT A2-6 6 13-Nov
DT A2-7 8
DT A2-8 8
DT A2-9 8
DT A2-10 8
DT A2-11 8
DT A2-12 3 9-Nov
DT A2-13 9 1-Nov
DT A2-14 9 26-Oct
DT A2-15 9 5-Nov
DT A2-16 9 28-Oct
DT A2-17 9 20-Oct
DT A2-18 9 12-Oct
Block Unit F'tion RC Wall Roof Plast. Sewer.
253

Legend: Date Works in progress


Works completed for certification
Previous work done
11/10/2018

Drainage Road VP
*Show Unit PT11934, 11935
*Show Unit PT11944, 11945

Drainage Road VP
Block DT-5 Raft Foundation completed.

Block DT-6 Raft Foundation completed.

Block DT-7 Raft Foundation completed.

Block DT-8 Raft Foundation completed.


Block ST-1 Raft Foundation completed.

Block ST-18 Raft Foundation completed.

Sewerage Work Done