Concreting Works TSP1

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

PROJECT: TIARA SENDAYAN PRECINCT 1

RE: CONCRETING WORKS


SUBCON: SP SIVA CONSTRUCTION

ITEM DESCRIPTION UNIT QTY Crane (Hr) Labour (Head x Hr)

A. DOUBLE STOREY
A.1 Polysheet m2 123.55

A.2 Concreting
Raft Foundation m3 5.97
Ground Slab m3 10.17
Carporch & Driveway (By Others) m3 -
Column ( GF - 1F/RF ) m3 1.86
1F Beam m3 6.07
1F Slab m3 13.28
Column ( 1F - 2F/ RF ) m3 1.28
RF Beam m3 2.81
RF Slab m3 0.95
Column (Above Roof Beam) m3 0.32
Staircase m3 1.80
Sub total: 44.51

A.3 Lintel & Copping


R.C. Lintel < 1.80m no 12.00

A.4 Compactor, Petrol & Etc. L/S 1.00

A.5 Clearing L/S 1.00

A.6 Mark level & Slab Curing

B. SINGLE STOREY
B.1 Polysheet m2 125.10

B.2 Concreting
Raft Foundation m3 3.54
Ground Slab m3 8.40
Carporch & Driveway (By Others) m3 -
Column ( GF - 1F/RF ) m3 1.81
RF Beam m3 5.39
RF Slab m3 5.46
Column (Above Roof Beam) m3 0.31
Sub total: 24.91

B.3 Lintel & Copping


R.C. Lintel < 1.80m no 10.00

B.4 Compactor, Petrol & Etc. L/S 1.00

B.5 Clearing L/S 1.00

A.6 Mark level & Slab Curing