Professional Documents
Culture Documents
Chien1993 PDF
Chien1993 PDF
Chien1993 PDF
ABSTRACT
107
J. Construct. Steel Research 0143-974X/93/$06-00 © 1993 Elsevier Science Publishers Ltd,
England. Printed in Malta
108 E. Y. L Chien & J. K. Ritchie
INTRODUCTION
using joists with the top chord replaced by concrete through embedment
of web members in a concrete slab were also developed. For example, a
shop manufactured composite slab and joist system (Trusscrete) was
produced during the late 1950s and early 1960s. It had physical limitations
such as a maximum width of 1.22 m, length of 9.76 m and the inherent
shipping and handling limitations. This development may have overlap-
ped American developments such as the Laclede system, well known for
its use in large preassembled panels (complete deck and joists with
concrete slab placed after erection) on the World Trade Center, and the
Macomber system. In both systems, web members extended up into the
cover slab. But the most significant development of this type was the
Hambro system, a patented composite system developed in Canada. This
system utilizes high strength steel joists with a unique top chord. The cold
formed top chord is partially embedded in the concrete floor slab to
achieve composite action, while the non-embedded portion provides
connection slots for removable formwork supporting members (roll-bars),
which not only carry the removable formwork and construction loads but
also space and stabilize the joists during construction. Custom designed,
non-proprietary composite trusses built from standard steel components
also now see widespread use and will be discussed in greater detail.
TABLE 1
Major Buildings with Long Span Steel Floors (Recent Construction)
DECK-SLAB SYSTEMS
Since deck slabs are common to all systems, we will begin with them. Deck
steel profiles and shear connection considerations have been adequately
covered in the evolutionary discussion. Several other topics relating to
composite deck-slab systems are provided below.
i T
Fig. 1. Bar and mesh reinforcementat beam-to-girderjoint.
Under static load conditions, two primary failure modes are found for
composite deck-slab systems, i.e. flexural failure and shear-bond failure.
Important composite deck-slab design considerations are summarized in
a recent publication.t2 In addition, a standard for composite steel deck has
been prepared by the Canadian Sheet Steel Building Institute ~3 and this
publication includes guidance on statically loaded decks.
repeated load at the level of the first slip load, while another product may
be susceptible to fatigue failure of the sheet steel. Some manufacturers are
able to provide quantitative information on the performance of their deck
products in this regard.
and 415 O,¢A,c is the factored tensile capacity of the stud material, by
taking the strength of commonly available stud steel as 415 MPa. To
Composite floor systems 115
When steel deck flutes (or ribs) are oriented parallel with a steel girder, the
studs may be field-welded through the deck steel if a deck flute coincides
with the girder top flange. When a deck flute does not coincide with the
flange, the deck must be discontinued above the girder top flange, allowing
stud connectors to be applied directly to the flange in the shop, or in the
field. When the deck rib is wide enough or when the deck is split at the
girder, such that the ratio w,~/hd>~1.5, a solid-slab stud value is usually
appropriate. The shear value assigned for each stud is,
formula. Hence, design expressions are given in the Canadian steel design
standard -S16-M89 as:
- Apkx
IoH "T\I
Fig. 2. Pyramidal puillOUt cone area of a single stud connection in a steel deck.
118 E. Y. L C h i e n & J. K . R i t c h i e
Tr
I
W/ 2 Nemnd Ax~ ln Sleb '
i
. . . . . . . . . . 'H.n'e:
W12 i
d
ix~l~.:pn.~l:~p,&l,:i.,,Z.~.,,.,~,dt,.,pp_dr.~,i.,a~.~.~tf: •
| i Tr
I
F i g . 4. F o r c e e q u i l i b r i u m in a u n i f o r m l y - l o a d e d composite member.
Composite floor systems 119
m I
11'. , , , , r . . 3 . . . . . . . . 3. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A BI CI
- - Va/q, or
Eq~ ar Un~luml
n
_ Vet ~
,_ _L
~.n'.s [- --~--~.. v,lq, o, i
BC=n" ,L: - -"I Va/( N ' q , o ~ )
Composite floor framing, and therefore studs, are now used on vir-
tually every multi-storey steel building in Canada. Although most shear
studs are installed with the special welding guns described earlier, a
highly recommended technique, some may be installed using stick elec-
trode welding on small or remotely located buildings. The structural
effectiveness of studs, applied with both installation methods, was con-
firmed in a recent Canadian test.11 With the advent of limit states design,
the recent change to a minimum of 40% connection, and the use of
wide-rib profile decks, fewer studs are used and they must carry large
shear loads. Consequently, a designer must specify appropriate instal-
lation and inspection procedures, such as using CSA W59.1, on plans
and in specifications to ensure stud weld quality for ultimate shear
resistance.
steel shape is used primarily to resist tension and shear while the concrete
slab acts as a compression element.
Assessment of the properties of the T-beam includes an evaluation of
effective depth and width of the concrete flange. When deck flutes and
therefore the concrete ribs formed are perpendicular to a steel member,
only the slab thickness above the tops of the steel deck flutes is considered
effective for composite action. When concrete ribs are parallel with a steel
member, the entire depth of the concrete slab is effective, although
concrete below the top of deck is often neglected to facilitate computation,
except for stub-girder designs.
The effective width rules provided by current design standards are
formulated on the basis of elastic conditions and cannot be viewed as
precise rules due to simplification to account for shear lag effects within
slabs. Elkelish and Robinson a8 found that the effective width at ultimate
load is at least equal to or greater than the effective width in the elastic
range. However, an evaluation using typical ultimate strength composite
beam tables 7 shows that the bending capacity of a composite beam is
largely insensitive to the effective width of the slab used, because only a
portion of the slab depth is effective in contributing to member property.
Thus, for composite beam, truss or stub-girder design, ultimate flexural
strength and elastic composite beam deflections can be calculated using
the same empirical effective slab width rules as described below.
A recent paper by Vallenilla and Bjorhovde 39 lead to the elimination of
the '16t+b' rule (an inappropriate empirical rule) for Canadian and US
design standards. 4,4° Hence, the effective slab width for interior beams is
given as the lesser of L/4 and the actual slab width. For exterior beams, the
effective width extending from each side of a member is the lesser of L/IO,
and one half of the clear distance between steel top flanges supporting an
interior slab or the clear cantilever for an exterior slab.
The ultimate flexural strength of the composite member, with the plastic
neutral axis (PNA) in either the concrete slab or in the steel, is a well
documented concept. 50t2 At ultimate, it is assumed that the strains across
the composite section are large enough that the steel stresses are at yield
and the concrete compressive stress is at its ultimate design strength. The
tensile strength of the concrete is ignored. With either full or partial shear
connection, the stress blocks in the composite section are rectangular and
not linear as in elastic design. Large plastic rotation (as in plastic design) in
the maximum moment region is not considered essential for composite
members of normal span to steel depth ratios (>~ 18) to reach ultimate
moment capacity. Hence, when the PNA is in the steel, class 1 or 2 rules
are generally used to limit local buckling. It is hoped to illustrate in an
upcoming Canadian research project that when the PNA falls within a
thin (class 3) steel flange, local buckling will not occur, due to restraint
from deck-slab attachments. Thus the section class limitation of 1 and 2
could be further relaxed.
The procedure for arriving at factored moment resistance, Mrc, of a
composite section, using full or partial shear connection, has been illus-
trated in detail. ~2 Composite beam design using full shear connection is
rare. Partial shear connection, rather than full shear connection, is
preferred for the following reasons: (1) Typically, composite beams using
40% shear connection can usually attain about 85% of the flexural
capacity achieved with full shear connection. 7 (2) Selection of steel beam
sizes in composite design is often governed by constroction and deflection
considerations rather than by ultimate moment capacity. Thus a section
selected to meet these criteria, particularly in the case of unshored designs,
will usually provide sufficient moment capacity with partial shear connec-
tion. And partial shear connection minimizes the required number of
studs. (3) Since flute geometry and layout of deck units on a composite
floor restricts the distribution of studs and since double or triple-stud
shear connection reduces per-stud efficiency, partial shear connection
using a single stud per flute is most desirable.
Today, most composite floor beams are constructed with shear con-
nection in the range of 40-70% of the theoretical connection required
for full composite action. Recent comprehensive surveys of Canadian
122 E. Y. L Chien & J. K. Ritchie
,.
A~ M IfI~L 2 . y ~ ~ A f L 2 n . ~e~b~or~m
8Elf 8nit n*,,o~.~n~
Briefly, longitudinal slab shear arises from the transfer of axial stresses in
the slab to the steel member through stud shear connectors, as illustrated
in Fig. 7. If we examine the shear transfer mechanism from a steel 'girder'
(where deck flutes run parallel with the steel member) to studs, and hence
to a deck-slab, we will find a tendency for the concrete slab to shear above
J'I'IIn$~BClIQ
L ~ ~ ~Dr~.~-~_ •
(*~KSee*,H~ [ ~ j ~ < ~ _ _ ~ - - ~ . - - -
and adjacent to the girder at ultimate load, with the highest slab shear
stresses concentrating at the first deck flute off the girder due to an abrupt
reduction in slab area, see Fig. 7. In this case, the contributipn of steel deck
to the longitudinal shear capacity of the deck-slab is negligible, especially
where the decks are 'cut and spead' over a girder to accommodate a
particular structural module, to permit fitting of beam flanges (i.e. uncoped
beams) under the girder flanges, or to permit studs to be shop or field
welded directly to the girder top flange.
End rotation due to superimposed-load induced deflection of beams
meeting at a girder and concrete shrinkage accumulations at areas of least
restraint also contribute to a tendency for slab cracking along the girder.
This adverse effect is considered to be more acute, thus special reinforcing
as previously shown in Fig. 1 is needed, when long, shallow beams are
connected to opposite sides of a girder.
Research work by Johnson, '*70ehlers, 4s Davies, 49 E1-Ghazzi, 5° Azmi 51
and Robinson 52 have provided a satisfactory explanation of longi-
tudinal shear resistance of composite floor members, as follows: The
longitudinal shear strength of a concrete slab is affected by internal and
external forces, and by the amount of transverse reinforcement. Longi-
tudinal cracks should theoretically initiate at the base when using a
solid concrete slab. In a transversely reinforced solid slab composite
beam, there is only a minimal increase in composite beam capacity
when the amount of this reinforcement is in excess of 1% of slab area.
Also, the reduction in beam capacity is small when 0.5% is used.
Longitudinal shear cracking in deck-slabs has not been observed in
hollow composite 'beams' (where deck flutes run perpendicular to beam
span). However, flexural and shrinkage cracks may occur, depending on
concrete placing and curing techniques and concrete quality. Hollow
composite 'beam' capacity is nominally increased when transverse rein-
forcing increases from 0.1 to 0-25% due to deck acting as transverse
reinforcement.
Doubling the 152x 152-MW13.3xMW13.3 mesh and adding trans-
verse reinforcing at concentrated load points over a hollow composite
girder can improve ductile behaviour and longitudinal crack distribution
at ultimate loads, nonetheless it may not enhance its overall member
capacity. 52 Most research testing has ignored the three-dimensional aspect
of real structures. Therefore, the longitudinal slab cracking found in Ref.
52 and the precise influence of extra transverse reinforcing in the deck-slab
as noted in Ref. 42 may not be fully identified. Research on shear capacity
in reinforced deck-slabs by Buckner et al., sa and calibration of Canadian
stub-girder sub-assemblage component tests 54-56 have resulted in a CSA-
126 E. Y. L Chien & J. K. Ritchie
STUB--GIRDER F L O O R C O N S T R U C T I O N
............ ~,:.-:.-,:~.:..
"'::"~" ""- 8 /
Stub-girders
full-scale testing. Since the late 1970s, Canadian research and construction
has concentrated on a 310mm deep bottom chord with some applications
using a 250 mm girder, while most US projects have used 360 mm sections.
Unlike conventional systems, the girder steel depth is not particularly span
dependent since tension and shear govern its required properties. Main goals
such as simplifying stub stiffening, minimizing stub-to-girder welding and
improving slab reinforcing criteria have been accomplished through full-
scale lab-tests, leading to several notable changes to the original stub-girder
configuration. These changes include reduction in girder depth, use of partial
height end plate stiffeners rather than full-height fitted stiffeners, or
elimination of stub stiffening by using them only when required, reduction in
stub welding, increased emphasis on slab reinforcement, and the truncation
of girder bottom chord to accommodate services near supports.
Rigid-ended stub-girders
Low rise buildings may be built with rigid framed stub-girders to provide
lateral load resistance. When used in a rigid framework, see Ref. 5, the
deep out-to-out depth of stub-girders produces a large moment of inertia
in the girders as well as rigidity and flexural strength at the girder ends for
. . . . . . . . . . . . . . . . . . :. . . . . . .
efficient resistance of wind and seismic loads and for good inter-storey
drift control.
Floor beams, ranging from about 310 to 460 mm in depth, are placed over
steel stub-girders on about 2.5-3.5 m centres, depending upon the struc-
tural module and the spanning capability of the selected deck-slab system.
A typical deck-slab system usually incorporates a 75 mm deep composite
wide-rib profile deck, covered by about 75 mm of ND concrete or 85 mm
of SLD concrete.
Considerations when selecting the depth of cantilever beams should
include span, strength of stub-girder (i.e. effective composite depth), depth
of duct openings, storey height, total floor steel mass, etc. Beam sizes are
chosen based on loading and geometric requirements. For example,
mechanical ducts through a stub-girder may dictate selection of a beam
size deeper than that required for strength. Beams of an appropriate depth
should be used instead. Since the tensile component of a stub-girder is
separated from its top chord by the depth of the floor beams, the chosen
beam depth directly affects the girder capacity and the governing forces for
the deck-slab top chord as well as the steel bottom chord at the critical
design locations. Designers are cautioned against introducing complexity
such as the use of shallow beams supported on high plinthes on the girder
top flange to increase overall depth of opening through girder and effective
depth of girder assembly.
The floor beams are designed based on cantilever and suspended span
(or Gerber) construction where the cantilever spans are continuous over
girders for an appropriate length, with the suspended spans or drop-in
segments picked up at the ends of the cantilevers. The cantilever spans are
field bolted to the top flange of the steel bottom chord of the stub-girder;
while at each cantilever beam to girder joint, two shear studs are usually
specified for anchorage to the deck-slab system. The positive moment
Composite floor systems 131
regions of the cantilever beams are often designed compositely with the
deck-slab system to produce savings in structural steel as well as to provide
stiffness. The simply supported suspended spans may be much shallower in
depth than the cantilever beams, and even more so when designed
compositely, permitting additional plenum service depth in those areas for
main ducts feeding from the core. For details of design, see Refs 5 and 12.
The following is a list of the state-of-the-art design considerations for floor
beam members: Check positive moment at mid-span using zero live load on
both cantilever arms and suspended spans. Design as conventional compos-
ite beams when applicable. Span/depth ratios should be about ~<30 and 24
for bare steel and composite section depth respectively. The ratio of
cantilever arm length to depth of steel section should be ~<5. A larger
cantilever arm length would be established by evaluating Mr of the steel
section with appropriate structural restraints. Check deflections at mid-span
and at the ends of the cantilever arms. Determine whether camber is required
for concrete placing. Knowledge gleaned from recent cantilever (Gerber)
beam tests 7t'72 in Canada can enable designers to accurately assess
cantilever beam lateral-torsional buckling strengths under construction,
although this aspect would rarely be critical if the above criteria are followed.
Long span Gerber beams and stub-girders often require shop cambering
to avoid use of excessive concrete quantities (and dead load) and to ensure
a 'flat' floor after shore removal. In general, floor beams are cambered
when the estimated deflection during slab placing approaches 20 mm. It
must be remembered that, at certain stages of floor construction, the
stub--girder deflection may be slightly negative, but when shores supported
by the girders are removed there can be significant elastic recovery. Also,
on the projects checked, actual deflections have never reached theoretical
values. Stub-girders only require a small amount of positive camber and
may be cambered during installation of the shores rather than in the shop.
The elastic self-weight deflection of girders should be removed during
placement of shoring jacks. Also, the girder should be shop or field
cambered to allow for a small amount of instantaneous elastic deflection
during slab placing and after shore removal.
at critical girder locations can affect overall girder strength and stiffness.
Therefore, screeding concrete to actual steel elevations is critical. Screed
discs attached to the top of the stub flanges, or some other positive means,
indicating the desired depth of concrete cover slab, may be used to ensure
that the cover slabs are screeded to the design thickness. Laser screeding of
any cambered and shored system to a horizontal plane would obviously
present some risk of incorrect slab thicknesses.
COST I M P L I C A T I O N S O F C O M P O S I T E C O N S T R U C T I O N
fire protection have been omitted from the tabulated data. The savings to
be achieved using composite design are clearly visible. Steel tonnages are
significantly reduced using compositely designed floor framing. Note that
the mass of composite beam framing is normalized as 1.00 in the ratios,
with non-composite showing as a higher ratio, i.e. more tonnes. Composite
truss schemes, when shown, are ratioed against composite beam scheme
weights, and therefore show ratios less than 1 indicating lower steel mass,
and on longer spans, lower costs. Stub-girders were included in one
evaluation (project 4) to show its ranking cost wise. This is an interesting
case, not easily visualized from cost data alone but illustrated in Fig. 10.
The framing is turned 90 ° compared with other schemes, placing large
stub-girder reactions either directly on columns or on the building core.
Therefore no large reactions are carried in bending, each member is
optimized for its application and overall efficiency is increased, when
compared with the beam and truss schemes for this project.
Steel framing costs are comprised of material, and shop and field labour.
Although a reduction in materials will save costs, savings will not be
proportional to steel reduction. In many cases, the number of pieces to be
handled is not changed by switching from non-composite design to
composite design for a frame with the same bay size, and shear stud costs,
and possibly camber costs must be included. A comparison of the steel
mass ratios with the cost ratios will illustrate this point. Such a compari-
son demonstrates that inclusion of shear stud and cambering costs narrow
the gap between composite and non-composite designs but still show cost
penalties of at least 15% on non-composite beam schemes, and at least
30% on larger span truss to beam comparisons. It can be clearly seen that
in order to meet the demands of modern building criteria, such as long,
clear spans, composite design must be used. Other conclusions and
obvious benefits of composite design can also be drawn from the table.
CLOSURE
TABLE 2
Composite versus Non-composite Design--Cost Comparisons
Project no. No. of Gravity Live load Bras Total Steel Steel No. of Steel Steel
Lateral floors flaming (kPa) (t) (t) wt cost studs + stud + stud
system Area Bay size Deck span Trus. Total ratio (/m 2) COSt COSt COSt
(m z) (m × m) (m) (t) ( ~g/m ~) (/m 2) (/m 2) ratio
26 Comp. tr. 2.4 710 1600 0-74 $36-89 61464 $39"19 0-82
73543 13.75x9.15 3050 890 21-76 $2.30
4 26 Stub-girder 2.4 2036 2036 0-94 $44.57 68952 $47.15 0-99
73 543 13.75x9.15 3438 27-68 $2-58
Office tower
26 Comp. bm. 2.4 2174 2174 57600
cone. eor 1.00 $45.52 $47-68 1-00
73 543 13.75 x 9.15 3050 29-56 $2-15
26 N.c. bm. 2.4 2626 2626
1-21 $54.99 $54-99 1-15
73 543 13-75x 9-15 3050 35.71
Note: Structural steel costed using the CISC Metric Steel Cost Index of 1400 as per Appendix of GFD3. s
n.r. = not reduced (client requirement); N.c. bin. = non-composite beams.
136 E. Y. L Chien & J. K. Ritchie
Canlm ~
REFERENCES
I. MacKay, H. M., Gillespie, P. & Leluau, C., Report on the strength of steel
I-beams Munched with concrete. The Enoineerino Journal, 6(8) (1923) 365-9.
2. Manning, R. C., Canadian Steel Construction, Part II Composite Construction.
Canadian Institute of Steel Construction, Toronto, 1947, 114.
3. David, R., and Meyerhof, G. G., Composite construction of bridges using
steel and concrete. The Engineering Journal, (May 1958) 2-8.
4. Steel Structures for Buildings--Limit States Design. CAN3-SI6.1-M89, Cana-
dian Standards Association, Rexdale, ON.
5. Chien, E. Y. L. & Ritchie, J. K., Design and Construction of Composite Floor
Systems, CISC, Toronto, August, 1984.
6. Chien, E. Y. L., CISC Low Rise Building Design Aid. CISC, Toronto, May,
1991.
7. CISC Handbook of Steel Construction, 5th edn. CISC, Toronto, 1991.
8. Gravity Frame Design 3, User's Guide & Technical Manual. CISC, Toronto,
Jan., 1992.
9. Bergmann, R., The 72 storey office tower of the King/Bay Project, Toronto--
its structural concept and analysis. Canadian Steel Construction Council
(CSCC) Canadian Structural Engineering Conference, 1974.
10. Ritchie, J. K. & Chien, E. Y. L., Innovative designs in structural systems for
buildings. CSCC, Canadian Structural Engineering Conference, 1978.
11. 3ent, K. A., Effects of shrinkage, creep and applied loads on continuous
deck-slab composite beams. Masters Thesis, Department of Civil Engineering,
Queen's University, Kingston, Ontario, Canada, Sept., 1989.
12. Constructional Steel Design: An International Guide. Elsevier, London (in
press).
13. Standard for Composite Steel Deck. Canadian Sheet Steel Building Institute,
Dec., 1988.
Composite floor systems 137