Professional Documents
Culture Documents
Abutment A1: Excavation
Abutment A1: Excavation
Abutment A1
1 Excavation 1 14.700 8.400 3.697 456.506
Pier
1 Excavation 1 14.700 8.400 3.260 402.545
1 of 22
SL NO Particulars No's L B D QTY-M3
2 of 22
SL NO Particulars No's L B D QTY-M3
TOTAL 13108.637
TOTAL MT 13.109
Annular Filling (M15)
Abutment A2
Footing all around 1 15.700 9.600 1.650 248.688
Less-PCC 1 14.700 8.400 0.150 18.522
RCC M30 FDD
Less-1st Footing 1 14.500 8.200 1.000 118.900
Less-2nd footing 1 10.200 3.900 0.500 19.890
Total 91.376
Net Total 271.909
3 of 22
SCHEDULE 2007 -2008
Sl.No Description of Work Unit Qty of ROB at Qty of ROB at Qty of ROB at Rate Total Amount
Ch 31+500 Km Ch 68+073 Km Ch 83+500 Km
Providing and fixing strip seal type expansion joint complete as per
drawing specification and technical specification Clause 2607
11 m. 108.780 0.000 #REF! #REF!
Providing and fixing drainage spouts for bridges as per drawing and
12 technical specification clause 2705 Nr. 36.000 0.000 #REF! #REF!
Providing 500x500x75 high sleet for drainage water from crash barrier
15 Nr. 60.000 0.000 1,922 115,320
16 M15 annular filling around foundation Cu.m 543.818 562.464 562.464 3,579 1,946,318
Painting of concrete hand rails/Parapets Crash barriers with two coats
of cement based paint as per technical specification and the
17 directions of the Engineer Sqm 1800.000 0.000 #REF! #REF!
Total Amount #REF!
SI No Description No Length Breadth Depth Qty
1 Excavation
Abutment 4 6 6 2.5 360
Pier 4 7.9 7.9 2.5 624.1
984.1
2 P.C.C
Pier P1 2 4 1.2 5 48
2 4 1.2 3.08 29.568
Footing Top Level = 176.749, Pier Cap Top Level
= 186.079, Pier Top Level = 184.829
Semi Circular Portion 4 0.5652 5 11.304
4 0.5652 3.08 6.963264
Pier P2 2 4 1.2 5 48
2 4 1.2 3.077 29.5392
445.0291
122.4525
6 RCC Pedestral & Bearing (M 30)
Abutment 16 0.75 0.75 0.4 3.6
Pier 12 0.75 0.75 0.475 3.20625
6.80625
7 Dirt Wall
Abutment
L = (7+10.25)/2 , D = (1.803+1.547)/2 4 8.625 0.3 1.45 15.0075
4 10.25 0.3 0.225 2.7675
Pier Dirt Wall for supprting bearing 4 7 0.8 1.65 36.96
54.735
8 PSC Girder (Cast In Situ) (M40)
8.230625
4 7.505 6 1.15 207.138
4 7.505 3.9 0.275 32.19645
4 7.505 0.35 0.7375 7.748913
Section BB
Length = 4.95
1.975 x 2 x 0.4 , 0.15 (0.4 to 1.15) x 2, (6 x 1.15)
4 2 6 1.15 55.2
8.7125 4 2 3.95 0.3375 10.665
4 2 0.3 0.75625 1.815
16 Drainage Spout 8 8
Abutment A1
1 Excavation 1 14.700 8.400 3.697 456.506
Pier
1 Excavation 1 14.700 8.400 3.260 402.545
9 of 22
SL NO Particulars No's L B D QTY-M3
10 of 22
SL NO Particulars No's L B D QTY-M3
TOTAL 13108.637
TOTAL MT 13.109
Annular Filling (M15)
Abutment A2
Footing all around 1 15.700 9.600 1.650 248.688
Less-PCC 1 14.700 8.400 0.150 18.522
RCC M30 FDD
Less-1st Footing 1 14.500 8.200 1.000 118.900
Less-2nd footing 1 10.200 3.900 0.500 19.890
Total 91.376
Net Total 271.909
11 of 22
Sl.No Particulars No Qty Total Qty
1 Earth work Excavation in Soil
Abutment -1 2 456.506 913.011
Abutment -2 2 297.957 595.914
Pier -1 2 402.545 805.090
Total 2314.015 M3
7
M40 grade parapet wall 4 45 RM 180 RM
M40 grade Crash barrier cum Parapet
Wall 4 45 RM 180 RM
M40 grade Crash barrier 4 45 RM 180 RM
12 of 22
Sl.No Particulars No Qty Total Qty
High tensile steel strands including
9 straight strands
19T13 Strands 4 13.109 52.435 MT
Providing bricating and fixing in position
10 pot cum PTFE bearing 250 T 4 2 No's 8 No's
Providing bricating and fixing in position
pot cum PTFE bearing 300 T 4 4 No's 16 No's
Providing and fixing strip seal type
11 Expansion joint 4 27.20 108.780 RM
12 Providing and fixing drainage spont 4 9 No's 36 No's
13 of 22
Sl.No Description of work Unit Quantity Rate Rs Cost Rs
1 Earth Work Excavation for foundation in ordinary soil including dewatering
Unit: cum
Depth 3m to 6m
Taking output 210 cum
a Labour
male Nos 0.32 105 33.6
Mazdoor Nos 8 100 800
b Machinery
Hydraulic Excavation Hours 6.000 1100.00 6600.00
b Material
40mm cum 64.8 662 42897.6
20mm cum 32.4 857 27766.8
10mm cum 10.8 637 6879.6
sand cum 54 696 37584
cement cum 33.04 4990 164869.6
c Machinery
Batching Plant 20cum/Hr Hrs 6 1563 9378
Generator 100KVA Hrs 6 587 3522
Loader 1 Hrs 6 677 4062
Transit Mixer Hrs 15 782 11730
Concrete Pump Hrs 6 215 1290
14 of 22
Sl.No Description of work Unit Quantity Rate Rs Cost Rs
40 mm Aggregate cum 43.2 662 28598.4
20 mm Aggregate cum 43.2 857 37022.4
10 mm Aggregate cum 21.6 637 13759.2
b b) Labour
Mate day 0.84 105 88.2
Mason day 3 160 480
Mazdoor day 18 100 1800
c c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1563 9378
Generator 100 KVA hour 6.00 587 3522
Loader 1 cum capacity hour 6 677 4062
Transit Mixer 4 cum capacity for lead
upto 1 km. hour 15.00 782 11730
Transit Mixer 4 cum capacity lead
beyond 1 Km, L - lead in Kilometer tonne.km 300L
Concrete Pump hour 6 215 1290
Per Cum Basic Cost of Labour, Material
& Machinery (a+b+c) 2961
d) Formwork @ 3.75 per cent of
cost of concrete i.e. cost of material,
labour and machinery 13323.8025
e) Overhead charges @ 25 % on
(a+b+c+d) 92156.3006
f) Contractor's profit @ 10 % on
(a+b+c+d+e) 46078.1503
cost of 120 cum = a+b+c+d+e+f 506859.653
Rate per cum = (a+b+c+d+e+f)/120 4223.83045
say
4 B RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for
formwork which shall be 10 per cent instead of 4 per
cent of cost of material, labour and machinery.
Per Cum Basic Cost of Labour, Material & 2977.00
Machinery (a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 297.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 25 % on (a+b+c+d) 818.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 409.34
Rate perm (a+b+c+d+e+f) 4502.71
say
5 HYSD/TMT bar reinforcement completed as per drawing and technical specification in 1600
ii For Substructure
Unit MT
Tacking output = 1MT
a Labour
Male nos 0.34 105 35.7
Blacksmith nos 2 125 250
Mazdoor nos 6.5 100 650
15 of 22
Sl.No Description of work Unit Quantity Rate Rs Cost Rs
b Material
HYSD T 1.05 51030 53581.5
Binding Wire kg 6 43.2 259.2
Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in head walls
and parapets .
Unit = metre
Taking output = 12.5 metres ( 5
pipes of 2.5 m length each )
A 1000 mm dia
a) Labour
Mate day 0.18 105 18.9
Mason day 0.5 160 80
Mazdoor day 4 100 400
b) Material
Sand at site cum 0.07 696 48.72
Cement at site tonne 0.05 4990 249.5
c) Overhead charges @ 0.1 on
(a+b) 79.712
d) Contractor's profit @ 0.1 on
(a+b+c) 87.6832
Cost for 12.5 metres = a+b+c+d 964.5152
Rate per metre = (a+b+c+d)/12.5 77.161216
Supply of Pipe RM 2700
Say
7 Dry Rubble Flooring
16 of 22
Sl.No Description of work Unit Quantity Rate Rs Cost Rs
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
17 of 22
Net cost
Excavation for foundation in ordinary soil including dewatering
cum
833.60
6600.00
7991.12
1997.78
998.89
10987.79
52.32
Course
2368.20
279997.60
29982.00
78086.95
39043.48
429478.23
3578.99
18 of 22
Net cost
4224.00
4503.00
75317.55
935.70
19 of 22
Net cost
53840.70
13694.10
6847.05
75317.55
cement concrete pipe NP4/prestressed concrete pipe for culverts on first class
ular material in single row including fixing collar with cement mortar 1:2 but
tion, protection works, backfilling, concrete and masonry works in head walls
and parapets .
2777.16
20 of 22
Net cost
802
M-012
L-12
L-15
L-13
1014
21 of 22
SCHEDULE 2007 -2008
Providing and fixing strip seal type expansion joint complete as per
drawing specification and technical specification Clause 2607
11 m. 108.780 #REF! #REF!
Providing and fixing drainage spouts for bridges as per drawing and
12 technical specification clause 2705 Nr. 36.000 #REF! #REF!
Providing 500x500x75 high sleet for drainage water from crash barrier
15 Nr. 60.000 1,922 115,320
16 M15 annular filling around foundation Cu.m 543.818 3,579 1,946,318
Painting of concrete hand rails/Parapets Crash barriers with two coats
of cement based paint as per technical specification and the
17 directions of the Engineer Sqm 1800.000 #REF! #REF!
Total Amount #REF!