Contract Comparison Windturbines: Enercon Ge Vestas General
Contract Comparison Windturbines: Enercon Ge Vestas General
Enercon GE Vestas
General
Contract duration 15 yrs
Total Value € 2,600,000.00
Total Value/yr € 200,000.00
No. of WEC's 13
Cost per WEC/yr (Morotin= 12x 900kW)) € 16,000.00
Cost per WEC/yr (Sorobon 1x 300kW) € 8,000.00
Total Output (MW) 11.1 MW
Cost per MW/hr
Guaranties
Availability N.A.
Fuel Saving
Output N.A.
Execution
Contractor Maintenance
Owner Maintenance
Scheduled Maintenance
Unscheduled Maintenance
Offline Maintenance/yr 30Hrs
On-site support
Response times (notifications) 12Hrs
Response times (repair plans) 48Hrs
Spare Parts Consignment stock
Special tools Provided
Reporting
Additional Services
Additional Equipment (1) SCADA
Additional Equipment (2) PMS