Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

502

TECHNICAL BROCHURE
WG
High-Voltage On-Site Testing with D1.33
Partial Discharge Measurement

Members
Groupe d’Action 05
R. Pietsch, Convenor (DE): 2007-2010,
W. Hauschild, Convenor (DE): 2004-2007,
J. Blackett (AU), R. Bodega (NL), A. Claudi (DE), M. Gamlin (CH),
B. Finlay (AU), E. Gockenbach (DE), E. Gulski (NL), R.A. Jongen (CH),
Th. Leibfried (DE), E. Lemke (DE), S. Meijer (NL), P. Mohaupt (AT),
M. Muhr (AT), F. Petzold (DE), E. Pultrum (NL), G. Rizzi (IT),
Th. Strehl (DE), C. Sumereder (AT),
S. Tenbohlen (DE), P. Werle (DE)

During the life cycle of high voltage (HV) apparatus • the expectations from testing depend on the
or systems (Fig. 1), many tests and measurements are test procedure as selected for the particular
performed to characterize the insulation condition. component;
The results of these tests and measurements should • some degradation and breakdown risks may be
be compiled in a “life data record”, which supplies related to the level and the duration of withstand
information on trends of diagnostic indicator values. voltage stresses as applied during on-site testing;
The HV on-site test with PD measurement has an • voltage withstand testing at the selected voltage
intermediate position between routine tests and level gives go/no-go information for this test
in-service monitoring measurements (on-line or voltage level and requires confirmation by
off-line): methods such as PD measurement of possible
field strength effects on the insulation system.
In addition to type and routine testing, HV on-site
testing is an important part of quality assurance. The different aims of HV testing on the one hand
On-site tests are applied: and insulation diagnostics/monitoring on the other
• as a part of commissioning of equipment on hand may have caused the sometimes quite different
site to demonstrate that the transport from philosophies (Table 1). But the common physical
manufacture to site and erection on-site have background of the measured phenomena is the
not caused any critical defects, which lower the behaviour of dielectrics in the electric field. Therefore,
dielectric withstand voltage of the insulation the tests and measurements in the factory and on-site
below coordination withstand level Ucw ; (off-line or in-service) should be harmonized. This
• after repair on site to demonstrate that the offers an improvement of on-site test procedures
equipment has been successfully repaired; supported by PD measurement.
• for diagnostic purposes in the framework of
the asset management program by providing PD measurements play an important role in both
reference values of diagnostic indicators quality assurance tests and monitoring for condition
(e.g. partial discharge values and dielectric assessment. In contrast to diagnostics of integral
parameters) for later trending of test results. On dielectric parameters, such as tan δ, εr and dielectric
site tests are normally applied after a warning response, which are characteristics of the whole dielectric
is received from the condition monitoring volume, partial discharges are related to local insulation
program. defects. Such “weak-points”, are a part of the insulation
system, where under certain stress circumstances of e.g.
Furthermore it has to be considered that depending mechanical, chemical, thermal or electrical character a
on the particular condition of the HV component: severe PD activity prior breakdown may occur. 

No. 262 - June 2012 ELECTRA 83


502
TECHNICAL BROCHURE
WG
D1.33

Fig. 1: Data sampling and recording during the life cycle of HV


apparatus

In case of new insulation, critical defects are the result period – the previous mentioned “weak point”. In other
of assembling failures which can be found by a routine words, partial discharges indicate the non-reversible
test consisting of the HV withstand test combined destruction of solid or mixed insulation. This is
with PD measurement. In case of the insulation of HV important for both the detection of production faults
equipment in service (which has been tested successfully by means of quality assurance test and the recognition
and which operates for years) a critical defect might be of weak points/defects caused by aging during service
caused by high electrical, thermal or mechanical stresses by means of diagnostic tests. Consequently, all HV
or by the “aging” of the insulation itself. This means the withstand tests, also if performed on site, should be
partial discharges are symptoms and sometimes also combined with PD measurement.
the results of this “integral” process in the volume of
the insulation, which causes – over a more or less long During the HV dielectric withstand test, the 

No. 262 - June 2012 ELECTRA 85


502
TECHNICAL BROCHURE
WG
D1.33

Figure 2: Figure 3:
Life time characteristic of a solid insulation Test cycle for withstand test with PD measurement

insulation is stressed with the specified test voltage (ut)


for a specified time duration (tt), see Figure 1. This test For non-self-restoring insulation it should be noted
is successful if the insulation withstands the applied that insulation with defects may pass the withstand test
stress. If a disruptive discharge occurs, the insulation with the test stress triggering defects which in time lead
fails the withstand test, which means the result delivers to a failure in service. To check the presence of insulation
a clear answer which does not require any further defects, the withstand test should be combined with a
interpretation. Therefore the withstand test is a direct sensitive PD measurement (Fig. 3). The voltage should
test, which is intended to destroy a defective insulation be increased to the highest test voltage value in steps
whereas healthy insulation should pass the test. and then decreased in identical steps. The voltage step
During an indirect test other parameters, such as the levels and the time of voltage application on each step
apparent PD is measured. The insulation passes the test can differ when applied to power cables, GIS or power
when the measured parameter value remains below transformers. The PD magnitude at each step (ut)
a predefined limit during the test. The limit value is should not exceed a defined limit and the PD inception
derived from laboratory and field experience, computer and extinction voltages should be above the maximum
simulation based on physical models or simply from operation voltage. It is recommended that the PD
an agreement between the utility and manufacturer. measurement be performed on all voltage steps prior
The certainty of the interpretation of the on-site test to, during and following the withstand test levels as this
results is very much dependent on how the limit value is may provide an indication of possible damage of the
originally determined. On-site voltage levels and the test insulation.
duration should also to be taken into account. In most
cases, the certainty of the interpretation from indirect The combination of withstand testing and PD
tests is very much lower than those of direct tests. measurement is strongly recommended. The test voltage
sequence as given in Fig. 3 has been a recommended
Additionally it is necessary to consider the life time procedure for quality testing during routine tests for
consumption of a withstand test. Each electrical stress many years (this method cannot be applied to all HV
consumes life time, depending on parameters such as equipment with non-self-restoring insulation however).
voltage level, test duration and test frequency. A healthy It is expected that the combination of withstand testing
insulation has a higher withstand voltage than insulation and PD measurement will become mandatory for both
with critical defects. A withstand voltage test must be routine and on-site tests in future. Additionally, the
designed in such a way that the life time consumption condition-assessment of insulation should take into
of healthy insulation is negligible whereas the voltage is account different methods of periodic inspection or
high enough to cause breakdown in defective insulation monitoring. As a general principle periodic inspections
(Figure 2). or monitoring should deliver a warning which 

No. 262 - June 2012 ELECTRA 87


502
TECHNICAL BROCHURE
WG
D1.33

Table 2: Test voltages used on-site for various HV apparatus / systems

Abbreviations:

W - withstand voltage test (e.g. 60 s, AC) ACRF - frequency-tuned resonant circuit for AC voltage generation
PD - voltage test with PD measurement MV - medium voltage
DM - voltage test with dielectric measurement (mainly tan δ), HV - high-voltage
no withstand test
ACTC - transformer circuit for AC voltage generation 1) applied in the past and no longer recommended
ACRL - inductance-tuned resonant circuit for AC voltage generation 2) mainly for PD diagnostics

might be followed by a diagnostic off-line test. This test for in-service insulation is not currently available.
should apply the same procedure of withstand testing
and PD measurement as described above. The PD Furthermore, it is important to coordinate the
values of that test shall be compared with the reference quality assurance tests (routine tests in factory,
values (“fingerprints”) of the initial on-site test. commissioning tests on-site, and tests after repair) and
the diagnostic tests (off-line or on-line). The results of
There are many different types of HV apparatus and measurements of partial discharges, dissipation factor
systems. To be able to test them all requires a wide variety and other quantities of quality tests are used as the
of well adapted mobile HV test facilities including references (“fingerprints”) for later diagnostic tests
PD measuring equipment. Fig. 4 shows examples of and measurements. Records of repeated measurements
a selection of the HV test facilities outlining the type may be used to show trends (e.g. PD magnitudes,
of test object, the purpose of the on-site test, methods pulse rate/s, etc.) which present the most important
of handling and the cost requirements. A main aspect information for condition assessment. All this enables
should be that the test voltage should represent stresses the establishment of the “life cycle record” (Fig. 1) for
in service. Related aspects are given in chapters 4 and 5. important HV equipment as the reference for condition
based maintenance (CBM).
Clear guidelines for the requirements of the test
voltages to be applied are given in IEC 60060-1 and The brochure is organized in six chapters. In chapter
60060-2 for routine testing and in IEC 60060-3 for 2, titled “High Voltage Sources and Accessories for
on-site testing. For installations which have been in On-Site Applications” the general requirements for
service, lower voltages and/or shorter durations may on-site test voltages as published by CIGRE WG 33.03/
be used. These test values should be fixed, taking into TF 04 and published in ELECTRA No. 195 (2000) are
account the age, environment, history of breakdowns, up-dated with the state of the art of test voltages, used
and the purpose of carrying out this test, as there is not a for PD measurements (continuous alternating voltage
general principle for the value of the on-site test voltage (AC); damped alternating voltage (DAC), very-low
levels for all type of HV apparatus. The test voltage frequency voltage (VLF)). A survey on the application
levels required for insulation coordination are only of these test voltages for various HV apparatus is given
related to new insulation, and any similar coordination in Table 2. 

No. 262 - June 2012 ELECTRA 89


502
TECHNICAL BROCHURE
WG
Chapter 3, “On-site PD Measurements”, presents
actual aspects of PD detection, measurement, noise
three parts referring to the characteristics of the HV
component under test and its installation, the aim and
D1.33
reduction and PD evaluation including identification requirements of the test as well as the characteristics of
and localisation of defects in the insulation. In this the HV test system to be applied.
context it should be noted, that recently an application
guide on PD measurements in compliance with IEC Various examples of HV on-site tests in
60270 was published as TB No. 366. Moreover, another combination with PD measurements are given
TB by CIGRE WG D1.33, which deals with so-called in chapter 5, “Examples of Test and Measuring
non-conventional PD detection methods, should be Techniques for Apparatus and Systems”. Each example
mentioned here. Therefore, the fundamentals of both includes the description of the HV test sources, the
conventional and non-conventional PD detection PD measurement methods and the test procedures
techniques are only briefly presented, whereas practical for on-site PD tests on GIS, power cables, rotating
experiences gained from on-site PD tests are discussed machines and power transformers.
more in detail in this brochure.
Chapter 6, “Conclusions”, summarizes the most
Chapter 4, “Preconditions for On-Site Testing important aspects of on-site testing with PD
Including PD Measurement”, gives a short list of measurement as follows:
information with the aim to help in the selection of
optimised HV test systems and test procedures for 1. HV withstand testing plays an important role
any kind of on-site test. The list is subdivided into in quality assurance of HV apparatus. 

a b

c d

Figure 1.4: Examples for HV tests with PD measurement

(a) 400 kV GIS by ACRF (frequency tuned resonant circuit) test system of modular reactors via bushing
(b) 400 kV GIS by ACRF test system with directly flanged reactor
(c) 150 kV HV cable system by DAC test system
(d) 400 kV/433 MVA power transformer by static frequency converter

No. 262 - June 2012 ELECTRA 91


502
TECHNICAL BROCHURE
WG
However, additional measurements of the
dielectric properties, such as significant
volume, partial discharges are “weak point
phenomena” as it is also the electric breakdown.
D1.33
PD quantities and the loss factor tan In case of the new insulation, the critical
δ may enhance the reliability and defects/weak points are e.g. the result of an
remaining life time of electrical insulation. assembling failure which can be found by
a routine test consisting of the HV withstand
2. As there are several methods of voltage test including PD measurement. In case of
generation on site which can be applied the insulation of HV equipment in service
for withstand testing combined with PD (which has been tested successfully and
measurements, the brochure discusses which operates for years) a critical defect
and presents those various and commonly might be caused by high electrical, thermal
used HV sources and PD measurement or mechanical stresses and by
techniques developed for on-site tests. the “aging” of the insulation itself.

3. In this context PD measurements play an 4. It is expected that HV on-site testing with


important role in both quality testing and PD measurement will play an increasing role
monitoring for condition assessment. As for the improvement of the reliability of
opposed to most dielectric measurements (tan equipment for electric power generation,
δ, εr, dielectric response parameters) which transmission and distribution. 
are characteristics of the whole dielectric

BROCHURE N° 502
Copie papier / Hardcopy
(en anglais seulement)
(in English only)

En vente au Bureau Central


On sale at the Central Offi ce

Prix Membres / Members Price:


58 €
Prix non-Membres / Non-Member Price:
116 €

Contact
Fax +33 (1) 53 89 12 99
e-mail : publication@cigre.org
ou téléchargerà http://www.e.cigre.org
or download at http://www.e.cigre.org
(Membres uniquement /Members only)

No. 262 - June 2012 ELECTRA 93

You might also like