STRUCTURES
P . Suresh B .Tech.,
BASIC CONCEPT OF REINFORCED EARTH
The soils which have little tensile strength can be
strengthened by the inclusion of materials with high
tensile strength . The principle is same as adopted in
reinforced concrete.
This mobilization of tensile strength is obtained by
surface interaction between the soil and the
reinforcement elements through friction and
adhesion.
If the soil is cohesion less like sand the resistance will
be friction and if the soil is cohesive the bond stress
will be adhesive.
The reinforced earth technique is useful in urban
locations where availability of land is minimum and
construction is required with min disturbance to
traffic.
It is very important to note that the total horizontal earth
pressure is resisted by the frictional force between the soil
and reinforcing element and the design will be made with
required no. of layers vertically at adequate spacing
Hence there will not be any horizontal thrust on facia
panels/blocks and these elements are non structural and are
provided only to prevent erosion, loss of material at the face
of re wall. The foundation provided for facia panels is only to
take the self weight of panels, kerb over wall etc., but not for
resisting the horizontal thrust.
The facia wall facilitates to keep the reinforcing elements at
desired level and to retain fill material.
Compaction of fill material is not compulsory for walls
without any vertical loads like gardens etc. For roads the
compaction of fill shall be done as usual. But care must be
taken that the compaction equipment like rollers etc should
go not closer than 2m to wall facing
Generally the size of square panels shall be 1500 x
1500mm. The thickness of panels shall be 180 mm
and concrete grade of M35 shall be adopted.
Nominal reinforcement consisting of 8mm Hysd
bars shall be provided both ways at center
SOIL FORMATION
EXISTING G.L.
1) REINFORCING ELEMENT
3) FACING ELEMENT
TYPES OF REINFORCING ELEMENTS
P. SURESH.
Deputy Executive Engineer
(R&B) sub division, Udayagiri.
CELL NO: 9440818349