Professional Documents
Culture Documents
TRNG Handouts For Project PLNG & MGMT Wkshop 27 Nov 1dec 201 248
TRNG Handouts For Project PLNG & MGMT Wkshop 27 Nov 1dec 201 248
22 At the project review meeting your team member tells you the project’s EV is €800, PV
is €850 and the AC is €800.
What would best describe the health of your project?
a. Behind schedule and over budget
b. Behind schedule and on budget
c. Ahead of schedule and under budget
d. Behind schedule and under budget
24 If Estimate at completion is more than Budget at completion at some point in time, then
CPI at that time must be
a. Greater than 1
b. Equal to 1
c. Less than 1
d. Less than zero
26 Project ABC has a total budget of $9 Million and was planned to be completed in 8
months. While reviewing the progress at the end of 3 months, the following data was
presented: PV = $3 Million; EV = $2.5 Million and AC = $3 Million. What is the EAC if
the efficiency will change to 100% from now onwards?
a. $9 Million
b. $8.5 Million
c. $9.5 Million
d. $10.8 Million
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 197
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 5
(Cost & Finance / EVM)
29 You have a project where the total budget of $100,000 is evenly allocated throughout
the 5-month life of the project. You have just completed the second month of the
project and have finished only half of the Planned work. What is the Schedule
Performance Index and what conclusion can you draw about the project from this
data?
30 The initial budget of your project was $200,000. During the Earned Value Management
review, you calculate that the Estimate at Completion is $150,000. You also find that
your project duration which was originally estimated to take 24 months is now going to
be 36 months. At the time of the review if the Actual Cost is $75,000, then the Earned
Value was:
a. 100,000
b. 120,000
c. 175,000
d. 150,000
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 198
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 6
(Quality)
1 Name a Quality tool that lists out defects in the order of the frequency of occurrence is:
a. Crawford slip
b. Pareto chart
c. Histogram
d. Cause-and-effect analysis
8 A Pareto diagram:
a. Is an S curve based on the cumulative frequency of occurrence
b. Is a histogram depicting the magnitude of frequencies
c. Is a histogram based on the order of frequency of occurrence
d. Shows that 80 percent of the causes produce 20 percent of the problems
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 199
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 6
(Quality)
11 In a control chart the upper and lower control limits are generally set:
a Two standard deviations from the mean
b. Three standard deviations from the mean
c. At same level as the specification limits
d. It is changed every time
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 200
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 7
(Risk)
4 If the probability that an event A will occur is 60% and that the event B will occur is
50% then what is the probability of both A and B occurring when they are independent
events?
a. 55%
b. 40%
c. 30%
d. 36%
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 201
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 7
(Risk)
9 Assumption analysis:
a. Undertakes a stability analysis
b. Is done to identify risks
c. Undertakes a sensitivity analysis
d. All of the above
a. The sum total of the probability times the impact of all the identified risks
b. The total number of identified risks in the project
c. Probability of successful completion of the project
d. The product of the probability of a risk event times its impact
13 A negative risk has a 70% probability of occurrence with a financial impact of $50K and
a positive risk has a 50% probability of occurrence with a financial impact of $100K.
Your project budget should be:
a. Increased by $15K
b. Decreased by $15K
c. Increased by $ 50K
d. Decreased by $ 50K
14 After prioritizing the most important risks through Qualitative Risk Analysis, you have
updated the Risk Register with the top 20 risks. What should you do with the risks
which are at the bottom of the list?
a. Discard them as they are having a low risk score
b. Carryout a quantitative risk analysis
c. Ask the Sponsor and follow their instructions
d. Monitor these risks in future review meetings to check if the risk score has
changed
15. You have implemented a risk response measure due to which the probability of
occurrence of a significant risk has reduced from 80 % to 20 % although it’s impact has
not reduced. This action of yours may be termed as:
a. Avoidance
b. Transfer
c. Mitigation
d. Acceptance
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 202
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 8
(HR)
7 All of the following are true about the Responsibility Matrix except:
a. Shows when the tasks will be performed
b. Is made using the WBS and the OBS
c. Rows generally indicate the activities
d. Shows the responsibilities or functions
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 203
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 8
(HR)
9 The project manager believes in keeping tight control over the team working and
dictating what should be done by the team members. This style of management is
……………. and more suitable for ……………. projects:
a. Bureaucratic, government
b. Directive, low level
c. Autocratic, low risk
d. Laissez Faire, R&D
10 Which of the following conflict resolution method results in a long lasting solution?
a. Forcing
b. Confrontation
c. Withdrawal
d. Smoothing
11 In case of a conflict, who will decide the importance between the project’s cost,
schedule and quality?
a. Project manager
b. Sponsor
c. Both the project manager and sponsor
d. None of above
12 When a conflict arises in the project team between two team members the project
manager’s preferred approach should be:
a. Let the persons involved be responsible to resolve their conflict
b. Try to resolve the conflict as soon as possible
c. Try to resolve it when he has some spare time
d. Avoid getting involved
13 If your boss supervises your work throughout the day to see what you are doing, then
your boss believes in:
a. Theory X management
b. Theory Y management
c. Kaizen
d. Quality circles
15 Herzberg’s Two Factor theory looks at the two aspects of ……… and …….:
a. Motivators, de-motivators
b. Motivators, hygiene factors
c. Salary, recognition
d. Hygiene factors, social needs
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 204
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises - Set 9
(Communication / Change)
1 Communicating has many dimensions that includes all of the following Except:
a. Written and oral, listening and speaking
b. Internal and external
c. Definitive and clear
d. Formal and informal
2 You decide to go to the library and read about project Management best practices.
This is an example of:
a. Push communication
b. Pull communication
c. Interactive communication
d. Lateral communication
3 The performance of one of your subordinates is not up to the mark and you are in the
process of providing positive feedback to him. However, you find that he is not paying
full attention to your words. What kind of communication barrier is exhibited through his
behaviour?
a. Ignoring
b. Perception
c. Selective listening
d. Cultural differences
4 If the number of communication channels in your project is 45, then the number of
persons communicating in your project is:
a. 9
b. 10
c. 45
d. 90
6 As part of making the communication management plan, you should consider all the
following points except:
a. Who needs what information
b. When they will need the information
c. What format will be used to send the information
d. How to suppress unpleasant facts
7 You had 10 people in your project team till last month including you. Two of your team
members have been transferred to another project. Percentage change in your
communication channels with respect to last month is:
a. 20%
b. 37.7%
c. 60.7%
d. Not possible to determine
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 205
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises - Set 9
(Communication / Change)
8 You believe that your boss does not like you and always finds faults with you. As a
result, you do not feel comfortable in discussing work related issues with your boss.
This in turn piles up the unresolved issues which make your work more difficult. Your
inability to communicate with your boss is due to what kind of communication barrier?
a. Message competition
b. Hidden agenda
c. Project Jargon
d. Perception
9 Communication about Liquidation Damages under a contract between buyer and Seller
should be:
a. Formal written communication
b. Formal verbal communication
c. Informal written communication
d. Informal verbal communication
10 If there is a scope change in the project during implementation the change should be
monitored against?
a. Project goals that were set out in the project charter
b. The project network schedule
c. The impact of the change on the resource usage
d. The communication plan
11 The project is progressing on schedule when the client asks for a change that is likely
to upset the schedule. As the project manager what should you do first?
a. Tell the client the change cannot be implemented as the time is too short
b. Analyze the impact of the change and follow the change management
process
c. Start implementing the change as the time is too short
d. Inform the sponsor of the change request
12 Which one of the following communication methods has more message impact on the
receiver?
a. Verbal
b. Written
c. Non-verbal
d. Diagram
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 206
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises - Set 9
(Communication / Change)
14 You are the Project Manager having a team of 25 people distributed in 3 geographic
locations. Each location is headed by a Assistant PM. No. of communication channels
possible in your project is:
a. 406
b. 378
c. 392
d. 350
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 207
© Centre for Excellence in Project Management (P) Ltd
CIPM Class Exercise – Set 10
(Procurement)
3 You want to outsource some of the work packages, but are not very sure of the exact
nature of the work involved. The most suitable contract in this case is a:
a. Fixed plus incentive fee contract
b. Cost reimbursable contract
c. Time & Material contract
d. Any type is equally suitable
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 208
© Centre for Excellence in Project Management (P) Ltd
CIPM Class Exercise – Set 10
(Procurement)
9 The amount of monitoring of contractor's cost by the PM will vary based on:
a. The value of the contract
b. The type of contract being used
c. The reputation of the contractor
d. The nature of the work being done
10 The business risks in a Firm Fixed Price contract will be borne by:
a. Buyers
b. Sellers
c. Buyer or seller
d. Not possible to know this
13 In your contract you are using a Maximum Fee and a Minimum Fee. This means you
are using a _________ contract.
a. FPIF
b. CPIF
c. CPPC
d. CPFF
14 In a CPFF contract, the estimated cost of the contract is Rs.1,00,000 and the contractor
fee is 10% of the estimated cost. However, the actual costs incurred by the to complete
the work was Rs.1,50,000. What is the final amount payable for the contract?
a. 1,00,000
b. 1,10,000
c. 1,50,000
d. 1,60,000
15 In a CPPC contract signed by your company, the estimated cost of the contract was
Rs. 2,00,000 and a 20% fee was to be paid to the contractor for doing the work. The
actual costs incurred by the contractor to complete the contract went up by 25%. What
is the final amount you need to pay to the contractor?
a. 2,00,000
b. 2,50,000
c. 3,00,000
d. 3,50,000
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 209
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 11
(Integration and Closeout)
4 The work packages should be checked against the approved specification to ensure
the deliverables ________________:
a. Have been completed as per schedule
b. Have met the planned cost
c. Have not used extra resources
d. Conform to the plan
7 The project manager is responsible to integrate the project. Integration of the project
work involves:
a. Efficient use of network schedules
b. Effective coordination and control
c. Making the responsibility matrix
d. Meetings of all the stakeholders regularly
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 210
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises – Set 11
(Integration and Closeout)
13 The project has been completed and the contract is in process of being closed. A
common dispute that arises at this time between the contractor and the owner could be
regarding all of the following except:
a. Is the work part of the original contract or not?
b. The additional time taken to complete project due to delays from owner side
c. The monetary compensation that should be awarded to the contractor for
contract changes
d. When owner is required to release the final payment to contractor
15 To ensure that the project’s scope has been fully met a scope verification process for
acceptance of deliverables before delivery will be conducted by the:
a. Client
b. Contractor
c. Contractor in presence of Client
d. Contractor in presence of Directors
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 211
© Centre for Excellence in Project Management (P) Ltd
Mock Test
A EAC
B BAC
C ACWP
D EV
3 You are part of the team developing the project’s responsibility matrix. Which statement is not
true of a responsibility matrix?
A Projects have a finite time duration with start and end dates
B Every project has a definite beginning
C The project results are temporary
D Projects have no significance to the permanent sustainability of a corporation
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 212
© Centre for Excellence in Project Management (P) Ltd
Mock Test
8 A risk has a 35% chance of happening in any given month. If the project is expected to last for 8
months, the probability that this risk event will occur during the project’s sixth month is:
A 25%
B 35%
C 75%
D 100%
9 In the arrow diagramming method (ADM), __________ do not consume time or resources:
A Events
B Activities
C Float
D Arrows
10 In a three time estimate using PERT, if the optimistic estimate for a task is 6 days and
pessimistic estimate is 18 days, what is the most likely estimate if the mean is 10 days:
A 7 days
B 8 days
C 9 days
D 12 days
A The late start date is earlier than the early start date
B The critical path supports the imposed end date
C The early finish date is equal to the late finish date
D The late start date is later than early start date
12 Task B cannot begin until 10 days after task A begins is best described as a:
13 Which of the following is most important to plan and control the project?
A Project charter
B Project schedule
C Work breakdown structure
D Work assignments
14 Your project manager has asked you to show the relationships between the different activities.
To do this you should use a:
A Bar chart
B Network diagram
C Histogram
D Work breakdown structure
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 213
© Centre for Excellence in Project Management (P) Ltd
Mock Test
15 ROM cost estimates are meaningful during the _______ phase of the project:
A Conceptual
B Planning
C Control
D Execution
16 Your project work requires that you must wait for 3 days before you can begin the successor
activity. What is this relationship called?
A Lead
B External dependency
C Lag
D Discretionary dependency
17 If you are a project team member how could you make use of floats?
A Not possible
B If the activity is not completed by it’s Late Finish date
C When the project progress shows the activity has a negative float
D B and C
A The predecessor activity can start once it’s successor has started
B The successor activity can start once it’s predecessor has started
C The successor activity can finish once it’s predecessor has started
D A lead in the successor activity
22 When developing the WBS at which level will you place the work package?
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 214
© Centre for Excellence in Project Management (P) Ltd
Mock Test
23 You notice that your client has made a calculation mistake and made an excess payment to you.
What should you do?
24 Activity C is part of an on-going project. The activity has a total duration of 15 days, the early
start is day 25 and the late start is day 30. Two activities D and F both have a finish to start
dependency with activity C. Activity D is the critical activity. This implies that activity C:
25 Complex projects that require a multi disciplinary approach will be most suited to which of the
following structures:
26 You are required to examine the consequences of a scope change. To do this you should view
its impact on the project’s:
A Schedule
B Cost
C Quality
D All of the above
27 When you are contemplating how to recover a delay in the project schedule, the last thing you
should consider is to _______:
29 If the project manager does not allow the team members to provide extra items as an add-on to
please the customer during the execution phase, is she/he following the principles of good
scope management to complete the required work?
A May be yes or no
B No
C Yes
D It depends
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 215
© Centre for Excellence in Project Management (P) Ltd
Mock Test
A Change control
B Project control
C Time control
D Scope control
31 You are involved in identifying risks using the Delphi technique. Which statement is not true
about this technique?
32 Your sponsor has asked you to prepare a report showing the start and end dates of critical path
activities. To do this you would use:
A Bar charts
B PDM network
C Milestone charts
D Pert networks
A Control chart
B Attribute variable
C Pareto chart
D Run chart
36 During the execution of a project two team members disagree about how to proceed with a task
that they are working on. This disagreement is seriously affecting the work on the project. The
project manager holds a meeting with both of them to discuss the alternative options and decide
on the best approach. This method of settling differences can be described as:
A Compromising
B Forcing
C Smoothing
D Confronting/problem solving
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 216
© Centre for Excellence in Project Management (P) Ltd
Mock Test
A CEO
B Functional managers
C Project manager with involvement of the project team
D Project team alone
A Reporting
B Exchanging information
C On the phone
D Solving problems
43 Each project is divided into several project phases. Project management follows this approach
in order to:
A Improve management control of the project
B Understand the specific deliverable to be produced at the end of a phase
C Have better control on resource deployment as resource requirements may vary from
phase to phase
D All of the above
44 In the beginning of a project, the probability of successfully completing the project is ______ ,
risk is _____ and uncertainty is _______:
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 217
© Centre for Excellence in Project Management (P) Ltd
Mock Test
A Involved in the project and /or have positive or negative influence on project
execution
B Are only involved in project execution
C Have influence only in investment decisions
D Are a member of the Board of the corporation
A Payback period
B Discounted cash flow
C Net present value
D Internal rate of return
49 Lessons learned is an important part of project management. These are documented by the
project team in order to:
50 Project A has a probability of scope change of .70, and a .20 probability that the project will be
terminated. What is the probability the project will have scope changes and will not be
terminated?
A 0.24
B 0.56
C 0.14
D 0.06
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 218
© Centre for Excellence in Project Management (P) Ltd
Mock Test
51 Your project is an important one for the company and it was a feather in your cap to be selected
as the project manager. Unfortunately, the project is not progressing as well as planned and it
will be reviewed in the next board meeting. Which of the following is not a common format for
performance reporting and should not be used by you for management reporting?
A Bar charts
B S-curves
C Histograms
D Precedence diagrams
A Project manager
B Finance manager
C Sponsor
D Customer
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 219
© Centre for Excellence in Project Management (P) Ltd
Mock Test
A Balanced matrix
B Functional
C Projectised
D Strong matrix
A Resource availability
B Indirect costs
C Technical competence
D All of above
A Sponsor
B Customer
C Project manager
D A and C
65 A project is a:
A Repetitive process
B Unique and temporary endeavour
C Has a definite beginning and end
D B and C
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 220
© Centre for Excellence in Project Management (P) Ltd
Mock Test
A Technocrat
B Communicator
C Integrator
D Risk manager
Type 2 Questions
72 _____________defines why the project is required and what the project will do:
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 221
© Centre for Excellence in Project Management (P) Ltd
Mock Test
75 An “S” curve:
78 “I cannot test the software until I code the software”. This expression describes which of the
following dependencies?
A Discretionary
B Soft
C Mandatory or hard
D Regulated
E External
A Project Manager
B Project Manager and sponsor
C Project Manager and customer
D Sponsor and customer
E Project manager, sponsor and the project team
81 You are evaluating five projects. Project A has an NPV of 10,000, Project B has an NPV of Zero,
Project C has an NPV of 11,000, Project D has a NPV of 9,000 and Project E has a NPV of
-11,000. You should select:
A Project A
B Project B
C Project C
D Project D
E Project E
83 During the project’s implementation phase an unidentified risk arises. What should you do first?
A Project’s justification
B Customer requirements and expectations
C Network schedule
D Milestone schedule
E Summary budget
85 As the Project Manager you are attempting to solve a complex problem. Which communication
method will be most suitable?
A Informal verbal
B Formal verbal
C Informal written
D Formal written
E It will vary with the project manager
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 223
© Centre for Excellence in Project Management (P) Ltd
Mock Test
Type 3 Questions
87 The activities of a small project are given below with the activity duration and activity
interrelationships.
Select the critical path and the activity/ies that have free float.
Activity Duration in weeks Predecessor Type of
Activities Dependency
A 1 - FS
B 3 A FS
C 6 B FS
D 5 A FS
E 2 D FS
F 1 C&E FS
G 6 E FS
H 4 F&G FS
88 The following table shows the initial investment, cash flows and Discount Factor associated with a
particular project option.
Calculate the Payback period and the Net Present Value for this project .
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 224
© Centre for Excellence in Project Management (P) Ltd
Mock Test
89 A project has a budget of Rs.1,50,000 and a planned duration of 24 months. The following table
shows progress information for the first four months. Figures are cumulative:
What is the cost variance and schedule variance at the end of the third month and the
Estimate at completion based on the latest progress information?
Month 1 2 3 4
Planned (Rs)
10,000 20,000 30,000 45,000
Actual Spend (Rs)
6000 14,000 25,000 38,000
Earned Value (Rs) 32,000
5000 12,000 21,000
90 The probability and impact grid shown below depicts the relative positions of different
risks to the project following a risk assessment. The risk identification numbers are
entered in the grid.
High (.75) 12
Probability
Medium (.5) 8 9
Low (.35) 2 1
Impact
A 4, 6, 12, 9, 1
B 6, 12, 4, 9, 3
C 11, 5, 2, 7, 3
D 6, 12, 9, 10, 4
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 225
© Centre for Excellence in Project Management (P) Ltd
EXERCISES
q Numerical Exercises
n Investment Appraisal
n Networks & Resource Histograms
n PERT & Standard Deviation
n Crashing
n EVMS
n Contracts
q Objective Exercises
n Set 1 - Set 11
q Mock Test
Numerical Practice Exercises - Answers
(NPV/IRR)
NPV - 1
------------------------------------------------------------------------------------------------------------------------------------
Year Discount Cash Flow A PV A Cash Flow B PV B
Factor (Rev.-Exp.) (Cash Flow x DCF) (Rev.-Exp.) (Cash Flow x DCF)
(RS) (Rs) (Rs) (Rs)
------------------------------------------------------------------------------------------------------------------------------------
Note: (A higher NPV is better. If NPV negative then one should not go ahead with project.)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 227
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(NPV/IRR)
NPV – 2
Ans. 2.1
-------------------------------------------------------------------------------------------------
Year Discount Cash Flow in £ PV £
Factor (Anticipated annual return) (Cash Flow x Discount Factor)
or cash flow
-------------------------------------------------------------------------------------------------
1 .925 1500 1387.5
2 .857 1500 1285.5
3 .793 1500 1189.5
4 .735 1500 1102.5
--------- -------
4965
Less Initial investment 5000
--------
- 35
NPV = - 35
IRR
Discount Factor
Year Cash Flow Present Value
@ 8%
0 (149,500) 1.0 (149,500)
1 39,995 .926 37,035
2 40,000 .857 34,280
3 40,000 .794 31,760
4 40,000 .735 29,400
5 25,000 .681 17,025
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 228
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
Network 1
N1.1
4 2d 6 6 3d 9 9 5d 14
B E F
5 1 7 7 1 10 10 1 15
0 4d 4
A
0 0 4 4 3d 7 7 8d 15
C D
4 0 7 7 0 15 15 1d 16
H
15 0 16
7 5d 12
G
10 3 15
Legend:
ES - Early Start EF - Early Finish
ES DUR EF
(d, w, m) DUR - Duration of an activity (d = days, w = weeks, m = months)
Activity A - Name of an activity
LS - Late start LF - Late Finish
LS F LF F - Total Float
Note: .Figures in a box are in the same time units as the unit of the duration i.e. in days (d), week (w) or month (m).
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 229
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
NETWORK 1
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 230
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
Network 2
4 6w 10 12 9w 21 21 12w 33
B E F
6 2 12 12 0 21 21 0 33
0 4w 4 4 8w 12 12 14w 26 26 3w 29 33 7w 40
A D G H J
0 0 4 4 0 12 16 4 30 30 4 33 33 0 40
4 4w 8
C
12 8 16
Legend:
ES - Early Start EF - Early Finish
ES DUR EF
(d, w, m) DUR - Duration of an activity (d = days, w = weeks, m = months)
Activity A - Name of an activity
LS - Late start LF - Late Finish
LS F LF F - Total Float
Note: .Figures in a box are in the same time units as the unit of the duration i.e. in days (d), week (w) or month (m).
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 231
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercies - Answers
NETWORK -2
Activity
A 3 3 3 3
G 3 3 3 3 3 3 3 3 3 3 3 3 3 3
6
H 5 5 5
3 3 3 3 3 3 3 4
J 2
0
Wkly Res. Eng. 3 3 3 3 8 8 8 8 7 7 5 5 7 7 7 7 7 7 7 7 7 12 12 12 12 12 14 14 14 9 9 9 9 3 3 3 3 3 3 3
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
232
Numerical Practice Exercises - Answers
Network 3
16 3 19
G
0 2 2 17 1 20 20 1 21
A (Subt. 5 from H
ES of D)
2 2 4 20 0 21
4 8 12 7 9 16 17 3 20
C D F
4 0 12 8 1 17 17 0 20
0 4 4 (Add 5 to 8 for C)
B
12 5 17
0 0 4
E
12 0 17
NOTE:
Activity D has a lead of 5 days and it has a S-F relationship with activity C.
• In the Forward Pass the lead amount of 5 days is subtracted from the EF of activity C to get the
ES of activity D.
• In the Backward Pass the lead of 5 days is re-adjusted by adding the lead amount (5 days) to the
LS of activity D when deciding what duration we should take for LF for activity C – it’s
predecessor i.e. 5 is added to 8, the LS of D making it 13 when deciding the LF for C. Since
activity E has a LS of 12 we then take 12 as the LF of C.
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 233
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
Network 4
26 3 29
G
0 2 2 26 0 29 29 1 30
A (Add 5 to H
ES of D)
2 2 4 29 0 30
4 8 12 17 9 26 26 3 29
C D F
4 0 12 17 0 26 26 0 29
0 4 4 (Subt. 5 from
17 for C)
B
12 5 17
0 4
E
21 9 26
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 234
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(Standard Deviation/Crashing)
Standard Deviation
Activity
Activity Duration range
PERT Duration Variance
S.D. at 68%
Activity O ML P (Mean)
confidence
O+(4xML) + P {(P-O)/6}2
(P-O)/6 level
6
20.83
30 6.250 20.83 +/- 2.50
A 15 20 2.50
15+80+30 2.50 x 2.50) 18.33 to 23.33
6
20.00+/- 3.33
B 10 20 30 20.0 3.33 11.088
16.67 to 23.33
5.034
25.346
(Sq. Rt of 60.99 +/-5.034
For the (Total
60.99 25.346
Path Activity
which is 55.965 to
A+B+C Variance for
Variances 66.024
A+B+C)
of A+B+C
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 235
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(Crashing)
Crashing
Normal Crash
Crash Cost Y/N
time Normal
Activity Predecessor time in after Crash cost
required cost
weeks Crashing
in weeks
C A 3 2 8,000 9,500 N
D B 2 1 11,000 16,000 N
Q.C1.1 You can crash activities A, B E and F as they are in the critical path.
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 236
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(EVMS)
A 160 90 150
B 200 50 140
C 100 60 50
D 300 75 225
------- -------
760 565
EV1.1 What is the earned value for each activity and the project at review point?
EV1.2 What is the overall % complete of the project?
EV1.3 What is the current CPI?
EV1.4 What are the man-hours the project is likely to take to be completed based on the
current cost efficiency.
EV for B = 100
EV for C = 60
EV for D = 225
1.2 Overall % complete of the project is: 69.6% (Total EV / Total PV) = (529/760) = 69.6%
1.3 Current cost efficiency of the project is: 93.6% (Total EV/Total AC) = 529/565 = 0.936
1.4 Expected man-hours (EAC) based on current performance = 812 Man-hours (BAC/CPI)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 237
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(EVMS)
Earned Value – 2
Actual Cost
Month PV (BCWS) EV (BCWP)
(ACWP)
1 7000 2000 2500
2 14000 6000 9000
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 238
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(EVMS)
Earned Value - 3
Month PV in Rs AC in Rs EV
1 100 100 50
2 200 250 150
3 300 400 201
4 400 550 300
6 Forecast the expected cost of the project based on the current performance.
Expected cost of project as per current performance is Rs. 1833.
BAC / CPI = 1000/.545
7 Forecast the expected cost of the project if the efficiency becomes 50% from 5th month.
Expected cost of project if efficiency is 50% from month 5 is Rs. 1950
AC + BAC-EV = 550+ (700 /.5) = 1950
.5
8 Forecast the expected cost of project if efficiency becomes 100% from 5th month.
Expected cost of project if efficiency is 100% from month 5 is Rs. 1250
AC + BAC-EV = 550 + 700 = 1250
1
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 239
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(Contracts)
Contractor’s Fee =
2,10,000 – 2,00,000 (Target Cost minus Actual cost)
Contractor’s Fee =
2,10,000 – 2,50,000 (Target cost minus Actual cost)
-40,000 x 20% = -8000 (20% of extra cost)
25,000 - 8000 = 17,000 (Target fee less share of cost overrun)
Contractor fee = 20,000/- (Minimum Fee assured is 20,000)
Final Price of contract = Actual cost + Contractor’s fee
= 2,50,000 + 20,000 = 2,70,000/-
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 240
© Centre for Excellence in Project Management (P) Ltd
Numerical Practice Exercises - Answers
(Contracts)
Final Price
= 90,000 + 12,500 (Actual cost + contractor Fee)
= 1,02,500
---------------------------------------------------------------------------
Q. What is the contractor fee and total contract price for the following FPIF contract:
Target Cost 1,50,000
Target Fee 10,000
Contractor’s Fee
[(150,000 – 170,000) (.20) = -4000 Fee reduction
= 10,000 - 4000 (10,000 less 4000) Target fee after adjusting for 20% excess cost
= 6000 less any excess cost above Ceiling price
Final Price
1,70,000 + 5000 (6000 less excess cost)
= 1,75,000 (Limited to ceiling)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 241
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises - Answers
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 242
© Centre for Excellence in Project Management (P) Ltd
Objective Practice Exercises - Answers
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 243
© Centre for Excellence in Project Management (P) Ltd
DŽĐŬTest - Answers
Test
Ques. Ans. Ques. Ans. Ques. Ans.
1 B,C,D,A 31 A 61 B
2 A 32 A 62 D
3 A 33 C 63 B
4 C 34 A 64 C
5 C 35 D 65 D
6 A 36 D 66 A
7 D 37 D 67 C
8 B 38 C 68 A
9 A 39 C 69 A
10 C 40 B 70 D
11 A 41 C 71 E
12 C 42 C 72 D
13 C 43 D 73 C
14 B 44 C 74 C
15 A 45 A 75 A
16 C 46 A 76 E
17 B 47 B 77 E
18 D 48 B 78 C
19 C 49 C 79 C
20 C 50 B 80 E
21 B 51 D 81 C
22 C 52 A 82 A
23 B 53 D 83 C
24 C 54 C 84 C
25 C 55 A 85 D
26 D 56 C 86 B
27 D 57 C 87 B
28 C 58 D 88 C
29 C 59 B 89 C
30 A 60 C 90 BMoc
------------------------------------------------------------------------------------------------------------------------------------------------------------------------- 244
© Centre for Excellence in Project Management (P) Ltd