(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul

- All Levels 809 809 0% 19-Jun-16 05-Sep-18 -262

AL.KD.010 Construction Date (Demarcation\Site Clear From Obstacle)


0 0 100% 19-Jun-16 2 Construction Date (De
AL.KD.030 Completion Date 0 0 0% 05-Sep-18 -272
AL.MO.120 Install Tower Crane 7 7 0% 28-Nov-16 05-Dec-16 22
AL.MO.300 Desmantling Tower Crane 7 7 0% 10-Jun-18 17-Jun-18 -260
AL.LO.020 Internal\External Plaster 8 8 0% 02-Jul-18 09-Jul-18 -260
AL.LO.030 Flooring Tiles 8 8 0% 09-Jul-18 17-Jul-18 -260
AL.LO.040 Painting Work 8 8 0% 17-Jul-18 24-Jul-18 -260
AL.LO.010 Block Work 16 16 0% 17-Jun-18 02-Jul-18 -260
AL.MO.010 Mobilization Work 30 30 0% 19-Jun-16 18-Jul-16 32
AL.KD.020 Project Time Elapse\Remaining 809 809 0% 19-Jun-16 05-Sep-18 -262

- Authority Schedule 736 736 0% 10-Jul-16 16-Jul-18 -243

HO.AU.EL.S70 Last date For Transformer Delivery 0 0 0% 06-Mar-18 -115


HO.AU.EL.S30 DEWA Inspection\Comments 3 3 0% 31-Dec-17 03-Jan-18 -115
HO.AU.EL.E50 Application For Estimate 4 4 0% 15-Jan-17 18-Jan-17 19
HO.AU.W30 Application For Estimation 4 4 0% 17-Jul-17 20-Jul-17 7
HO.AU.EL.S50 DEWA Re-Inspection\Approval 5 5 0% 17-Jan-18 23-Jan-18 -115
HO.AU.EL.S10 Application For DEWA Inspection 5 5 0% 24-Dec-17 28-Dec-17 -115
AL.AU.EL.L20 Submit LV Design\S.L Diagram to DEWA 7 7 0% 15-Sep-16 25-Sep-16 19
AL.AU.EL.L60 DEWA Review\Approval (Obtain Construction NOC) 7 7 0% 14-Dec-16 22-Dec-16 19
AL.AU.EL.S10 Sub-Station Location Approval 7 7 0% 29-Sep-16 09-Oct-16 33
AL.AU.EL.S20 Sub-Station Detail Approved Drawing-Trench Layout 7 7 0% 10-Oct-16 18-Oct-16 33
HO.AU.EL.S80 Install Transformer 7 7 0% 07-Mar-18 15-Mar-18 -115
AL.AU.SH.010 Shoring Work Review\Approval 7 7 0% 10-Jul-16 19-Jul-16 1
AL.AU.EL.L40 Incorporating Comments From DEWA 14 14 0% 03-Nov-16 22-Nov-16 19
AL.AU.EL.L50 Re-Submit LV Design\S.L Diagram to DEWA 14 14 0% 23-Nov-16 13-Dec-16 19
HO.AU.EL.S40 Incorporating Comments From DEWA 14 14 0% 03-Jan-18 17-Jan-18 -169
HO.AU.EL.S90 Temp. Electric Connection 21 21 0% 18-Jun-18 16-Jul-18 -178
HO.AU.EL.E70 Reciept Of Estimate 21 21 0% 28-Feb-17 28-Mar-17 19
HO.AU.W50 Reciept Of Estimate 21 21 0% 30-Aug-17 28-Sep-17 7
AL.AU.EL.L30 DEWA Review\Comments 28 28 0% 26-Sep-16 02-Nov-16 19
HO.AU.EL.E60 Estimation Approval By DEWA 28 28 0% 19-Jan-17 27-Feb-17 19
HO.AU.W40 Estimation Approval By DEWA 28 28 0% 23-Jul-17 29-Aug-17 7

Actual Level of Effort Remaining Work Page 1 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Construction Date (Demarcation\Site Clear From Obstacle), 19-Jun-16

Install Tower Crane

Mobilization Work

Last date For Transformer Delivery,


DEWA Inspection\Comments
Application For Estimate
Application For Estimation
DEWA Re-Inspection\Approval
Application For DEWA Inspection
Submit LV Design\S.L Diagram to DEWA
DEWA Review\Approval (Obtain Construction NOC)
Sub-Station Location Approval
Sub-Station Detail Approved Drawing-Trench Layout
Install Transformer
Shoring Work Review\Approval
Incorporating Comments From DEWA
Re-Submit LV Design\S.L Diagram to DEWA
Incorporating Comments From DEWA

Reciept Of Estimate
Reciept Of Estimate
DEWA Review\Comments
Estimation Approval By DEWA
Estimation Approval By DEWA

Actual Level of Effort Remaining Work Page 2 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
HO.AU.W60 Payment Of Estimation (By Client) 28 28 0% 30-Sep-17 06-Nov-17 7
HO.AU.EL.E80 Payment Of Estimate (By Client) 45 45 0% 28-Mar-17 10-May-17 29
AL.AU.WS.010 Approval Of Shop Drawing From DEWA 75 75 0% 29-Mar-17 16-Jul-17 7
HO.AU.EL.S60 Period Required for Installation Of Transformer 112 112 0% 15-Nov-17 06-Mar-18 -161
AL.AU.ET.010 Submit\Approved Drawing By Etisalat 120 120 0% 29-Mar-17 18-Sep-17 41
AL.AU.CD.020 Submit\Approved Drawing (Fire Protection\LPG System)
120By CD 120 0% 29-Mar-17 18-Sep-17 34

- Sub-Contractor\Suppliers Approvals 506 506 0% 19-Jun-16 16-Oct-17 25

PC.PN.310 Road Marking- First Delivery 0 0 0% 16-Oct-17 25


SC.SH.010 Shoring Work (Prequalification Submission) 0 0 100% 19-Jun-16 2 Shoring Work (Prequa
PC.PN.330 Thermoplastic Paint- First Delivery 0 0 0% 03-Oct-17 32
SC.ME.A10 A.C Sub-Contractor (Actual Nomination Date) 0 0 0% 15-May-17* -271
SC.WP.010 Waterproofing Work (Prequalification Submission) 3 3 0% 02-Jul-16 04-Jul-16 7
SC.DW.010 Dewatering (Prequalification Submission) 3 3 0% 02-Jul-16 04-Jul-16 12
SC.ME.G10 Garbage Chute (Prequalification & Submission) 7 7 0% 12-Jan-17 18-Jan-17 27
SC.PG.010 LPG System (Prequalification & Submission) 7 7 0% 23-Feb-17 01-Mar-17 3
SC.CO.010 Concrete Supplier (Prequalification Submission) 7 7 0% 29-Aug-16 04-Sep-16 31
SC.SS.100 Anti-Termite (Prequalification Submission) 7 7 0% 15-Aug-16 21-Aug-16 31
SC.FC.010 False Ceiling (Prequalification Submission) 7 7 0% 09-Feb-17 15-Feb-17 3
SC.CL.010 Wall Tiles Supplier (Prequalification Submission) 7 7 0% 08-Dec-16 15-Dec-16 26
SC.FL.100 Floor Tiles Supplier (Prequalification Submission) 7 7 0% 05-Feb-17 11-Feb-17 3
SC.FL.200 Epoxy Coating (Prequalification Submission) 7 7 0% 23-Mar-17 29-Mar-17 30
SC.FO.010 Wardrobes (Prequalification & Submission) 7 7 0% 20-May-17 25-May-17 29
SC.FO.100 Kitchen Kabinet (Prequalification & Submission) 7 7 0% 20-Apr-17 27-Apr-17 20
SC.FO.200 Vanity Counter (Prequalification & Submission) 7 7 0% 20-Apr-17 27-Apr-17 20
SC.FO.300 Mirrors For Bath (Prequalification & Submission) 7 7 0% 15-May-17 21-May-17 31
SC.FO.500 Remote Control Gate Barrier (Prequalification & Submission)
7 7 0% 12-Jun-17 18-Jun-17 32
SC.FO.980 Biycle Rack (Prequalification & Submission) 7 7 0% 21-Jun-17 29-Jun-17 32
SC.PN.100 Internal Paint Applicator (Prequalification & Submission) 7 7 0% 06-Nov-16 12-Nov-16 28
SC.PN.200 External Paint Applicator (Prequalification & Submission) 7 7 0% 20-Apr-17 27-Apr-17 33
SC.PN.300 Road Marking\Thermoplastic Paint (Prequalification Submission)
7 7 0% 17-Jun-17 22-Jun-17 25
SC.SH.015 Shoring Work (Engineer Review\Approval) 7 7 0% 19-Jun-16 25-Jun-16 2 Shoring Work (Engin
SC.WD.010 Wooden Doors (Prequalification & Submission) 7 7 0% 05-Mar-17 11-Mar-17 27
SC.WD.100 Ironmongery and Accessories (Prequalification & Submission)
7 7 0% 05-Mar-17 11-Mar-17 33

Actual Level of Effort Remaining Work Page 3 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Payment Of Estimation (By Client)
Payment Of Estimate (By Client)
Approval Of Shop Drawing From DEWA
Period Required for Installation Of Transformer
Submit\Approved Drawing By Etisalat
Submit\Approved Drawing (Fire Protection\LPG System) By CD
16-Oct-17, - Sub-Contractor\Suppliers Approvals

Road Marking- First Delivery, 16-Oct-17


Shoring Work (Prequalification Submission),
Thermoplastic Paint- First Delivery, 03-Oct-17
A.C Sub-Contractor (Actual Nomination Date),
Waterproofing Work (Prequalification Submission)
Dewatering (Prequalification Submission)
Garbage Chute (Prequalification & Submission)
LPG System (Prequalification & Submission)
Concrete Supplier (Prequalification Submission)
Anti-Termite (Prequalification Submission)
False Ceiling (Prequalification Submission)
Wall Tiles Supplier (Prequalification Submission)
Floor Tiles Supplier (Prequalification Submission)
Epoxy Coating (Prequalification Submission)
Wardrobes (Prequalification & Submission)
Kitchen Kabinet (Prequalification & Submission)
Vanity Counter (Prequalification & Submission)
Mirrors For Bath (Prequalification & Submission)
Remote Control Gate Barrier (Prequalification & Submission)
Biycle Rack (Prequalification & Submission)
Internal Paint Applicator (Prequalification & Submission)
External Paint Applicator (Prequalification & Submission)
Road Marking\Thermoplastic Paint (Prequalification Submission)
Shoring Work (Engineer Review\Approval)
Wooden Doors (Prequalification & Submission)
Ironmongery and Accessories (Prequalification & Submission)

Actual Level of Effort Remaining Work Page 4 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SC.FO.250 Vanity Counter (Prequalification & Submission) 7 7 0% 26-Jun-17 04-Jul-17 27
SC.FO.800 Signage (Prequalification & Submission) 7 7 0% 03-Jun-17 08-Jun-17 32
SC.ME.L10 Elevator (Prequalification & Submission) 7 7 0% 20-Nov-16 26-Nov-16 27
SC.ME.010 MEP Sub-Contractor (Prequalification Submission) 7 7 0% 06-Aug-16 11-Aug-16 4
SC.FO.400 GRC Work (Prequalification & Submission) 7 7 0% 28-Mar-17 03-Apr-17 32
SC.ME.L20 Elevator (Engineer Review\Approval) 14 14 0% 26-Nov-16 08-Dec-16 27
SC.WD.020 Wooden Doors (Engineer Review\Approval) 14 14 0% 11-Mar-17 23-Mar-17 27
SC.WD.110 Ironmongery and Accessories (Engineer Review\Approval)
14 14 0% 11-Mar-17 23-Mar-17 33
SC.ME.015 MEP Sub-Contractor (Engineer Review\Approval) 14 14 0% 11-Aug-16 24-Aug-16 4
SC.FO.810 Signage Engineer Review\Approval) 14 14 0% 08-Jun-17 21-Jun-17 32
SC.ME.G20 Garbage Chute (Engineer Review\Approval) 14 14 0% 18-Jan-17 31-Jan-17 27
SC.ME.125 Switches & Sockets (Engineer Review\Approval) 14 14 0% 22-Apr-17 06-May-17 27
SC.ME.115 Light Fittings- Buildings\Boundary Wall (Engineer Review\Approval)
14 14 0% 22-Apr-17 06-May-17 20
SC.ME.150 Sanitary Ware (Engineer Review\Approval) 14 14 0% 03-Apr-17 16-Apr-17 14
SC.PG.10 LPG System (Engineer Review\Approval) 14 14 0% 01-Mar-17 14-Mar-17 3
SC.WP.020 Waterproofing Work (Engineer Review\Approval) 14 14 0% 04-Jul-16 18-Jul-16 7
SC.CO.020 Concrete Supplier (Engineer Review\Approval) 14 14 0% 04-Sep-16 20-Sep-16 31
SC.SS.110 Anti-Termite (Engineer Review\Approval) 14 14 0% 21-Aug-16 03-Sep-16 31
SC.FC.020 False Ceiling (Engineer Review\Approval) 14 14 0% 15-Feb-17 28-Feb-17 3
SC.CL.020 Wall Tiles Supplier (Engineer Review\Approval) 14 14 0% 15-Dec-16 28-Dec-16 26
SC.FL.110 Floor Tiles Supplier (Engineer Review\Approval) 14 14 0% 11-Feb-17 23-Feb-17 3
SC.FL.210 Epoxy Coating (Engineer Review\Approval) 14 14 0% 29-Mar-17 11-Apr-17 30
SC.FO.020 Wardrobes (Engineer Review\Approval) 14 14 0% 25-May-17 07-Jun-17 29
SC.FO.110 Kitchen Kabinet (Engineer Review\Approval) 14 14 0% 27-Apr-17 10-May-17 20
SC.FO.210 Vanity Counter (Engineer Review\Approval) 14 14 0% 27-Apr-17 10-May-17 20
SC.FO.310 Mirrors For Bath (Engineer Review\Approval) 14 14 0% 21-May-17 03-Jun-17 31
SC.FO.510 Remote Control Gate Barrier (Engineer Review\Approval)
14 14 0% 18-Jun-17 03-Jul-17 32
SC.FO.990 Biycle Rack (Engineer Review\Approval) 14 14 0% 29-Jun-17 12-Jul-17 32
SC.PN.110 Internal Paint Applicator (Engineer Review\Approval) 14 14 0% 12-Nov-16 24-Nov-16 28
SC.PN.210 External Paint Applicator (Engineer Review\Approval) 14 14 0% 27-Apr-17 10-May-17 33
SC.PN.310 Road Marking\Thermoplastic Paint (Engineer Review\Approval)
14 14 0% 22-Jun-17 08-Jul-17 25
SC.AL.020 Metal Doors (Prequalification Submission) 14 14 0% 14-Mar-17 27-Mar-17 37
SC.AL.025 Metal Doors (Engineer Review\Approval) 14 14 0% 27-Mar-17 09-Apr-17 37
SD.PN.310 Road Marking (Engineer Review\Approval) 14 14 0% 03-Oct-17 16-Oct-17 25

Actual Level of Effort Remaining Work Page 5 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Vanity Counter (Prequalification & Submission)
Signage (Prequalification & Submission)
Elevator (Prequalification & Submission)
MEP Sub-Contractor (Prequalification Submission)
GRC Work (Prequalification & Submission)
Elevator (Engineer Review\Approval)
Wooden Doors (Engineer Review\Approval)
Ironmongery and Accessories (Engineer Review\Approval)
MEP Sub-Contractor (Engineer Review\Approval)
Signage Engineer Review\Approval)
Garbage Chute (Engineer Review\Approval)
Switches & Sockets (Engineer Review\Approval)
Light Fittings- Buildings\Boundary Wall (Engineer Review\Approval)
Sanitary Ware (Engineer Review\Approval)
LPG System (Engineer Review\Approval)
Waterproofing Work (Engineer Review\Approval)
Concrete Supplier (Engineer Review\Approval)
Anti-Termite (Engineer Review\Approval)
False Ceiling (Engineer Review\Approval)
Wall Tiles Supplier (Engineer Review\Approval)
Floor Tiles Supplier (Engineer Review\Approval)
Epoxy Coating (Engineer Review\Approval)
Wardrobes (Engineer Review\Approval)
Kitchen Kabinet (Engineer Review\Approval)
Vanity Counter (Engineer Review\Approval)
Mirrors For Bath (Engineer Review\Approval)
Remote Control Gate Barrier (Engineer Review\Approval)
Biycle Rack (Engineer Review\Approval)
Internal Paint Applicator (Engineer Review\Approval)
External Paint Applicator (Engineer Review\Approval)
Road Marking\Thermoplastic Paint (Engineer Review\Approval)
Metal Doors (Prequalification Submission)
Metal Doors (Engineer Review\Approval)
Road Marking (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 6 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.PN.310 Road Marking (Engineer Review\Approval) 14 14 0% 09-Aug-17 23-Aug-17 25
SC.AL.010 Aluminium Work (Prequalification Submission) 14 14 0% 12-Jan-17 25-Jan-17 16
SC.AL.015 Aluminium Work (Engineer Review\Approval) 14 14 0% 25-Jan-17 07-Feb-17 16
SC.DW.015 Dewatering (Engineer Review\Approval) 14 14 0% 04-Jul-16 18-Jul-16 12
SC.AL.25 Tension Fabric (Prequalification Submission) 14 14 0% 14-Mar-17 27-Mar-17 33
SC.AL.35 Tension Fabric (Engineer Review\Approval) 14 14 0% 27-Mar-17 09-Apr-17 33
SC.FO.260 Vanity Counter (Engineer Review\Approval) 14 14 0% 04-Jul-17 17-Jul-17 27
MC.PN.330 Thermoplastic Paint (Engineer Review\Approval) 14 14 0% 27-Jul-17 09-Aug-17 32
SD.PN.330 Thermoplastic Paint (Engineer Review\Approval) 14 14 0% 20-Sep-17 03-Oct-17 32
SC.FO.410 GRC Work (Engineer Review\Approval) 14 14 0% 03-Apr-17 16-Apr-17 32
SC.ME.120 Switches & Sockets (Prequalification Submission) 21 21 0% 02-Apr-17 22-Apr-17 27
SC.ME.110 Light Fittings- Buildings\Boundary Wall (Prequalification 21
Submission) 21 0% 02-Apr-17 22-Apr-17 20
SC.ME.100 Sanitary Ware (Prequalification & Submission) 21 21 0% 14-Mar-17 03-Apr-17 14
SD.PN.300 Road Marking (Preparation & Submission) 21 21 0% 13-Sep-17 03-Oct-17 25
PC.PN.300 Road Marking (Procurement\Placing Order) 21 21 0% 23-Aug-17 13-Sep-17 25
MC.PN.300 Road Marking (Preparation & Submission) 21 21 0% 22-Jul-17 09-Aug-17 25
MC.PN.320 Thermoplastic Paint (Preparation & Submission) 21 21 0% 08-Jul-17 27-Jul-17 32
PC.PN.320 Thermoplastic Paint (Procurement\Placing Order) 21 21 0% 09-Aug-17 29-Aug-17 32
SD.PN.320 Thermoplastic Paint (Preparation & Submission) 21 21 0% 29-Aug-17 20-Sep-17 32

Material Approvals Through Sub-Contractor 664 664 0% 18-Jul-16 15-Apr-18 -215

MC.EL.L10 Earthing System (Preparation & Submission) 7 7 0% 24-Sep-16 29-Sep-16 32


MC.WP.F10 Bitumen Coating to Foundation (Preparation & Submission)
7 7 0% 18-Jul-16 25-Jul-16 31
MC.AL.310 Aluminium Canopy (Engineer Review\Approval) 14 14 0% 20-Apr-17 06-May-17 27
MC.AL.410 Cat Ladder (Engineer Review\Approval) 14 14 0% 17-Jun-17 03-Jul-17 36
MC.AL.110 Aluminium Windows\Doors (Engineer Review\Approval)14 14 0% 20-Apr-17 06-May-17 20
MC.AL.B20 Balcony Handrails (Engineer Review\Approval) 14 14 0% 03-Jul-17 17-Jul-17 29
MC.AL.T20 Steps Handrail (Engineer Review\Approval) 14 14 0% 26-Jun-17 12-Jul-17 26
MC.AL.S20 Aluminium Louver Doors\Windows (Engineer Review\Approval)
14 14 0% 05-Mar-17 19-Mar-17 32
MC.AL.510 Powder Coat Aluminium Fence- Roof (Engineer Review\Approval)
14 14 0% 21-Jun-17 08-Jul-17 30
MC.AL.160 Aluminium Aluminium Glazing (Engineer Review\Approval)
14 14 0% 10-May-17 24-May-17 16
MC.WD.410 Wooden Doors Sample\material to Staircase (Engineer 14
Review\Approval) 14 0% 11-Jul-17 24-Jul-17 27
MC.WD.310 Wooden Doors Sample\material (Engineer Review\Approval)
14 14 0% 19-Apr-17 03-May-17 33
MC.WD.460 Ironmongery and Accessories to Staircase (Engineer Review\Approval)
14 14 0% 02-Jul-17 15-Jul-17 37

Actual Level of Effort Remaining Work Page 7 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Road Marking (Engineer Review\Approval)
Aluminium Work (Prequalification Submission)
Aluminium Work (Engineer Review\Approval)
Dewatering (Engineer Review\Approval)
Tension Fabric (Prequalification Submission)
Tension Fabric (Engineer Review\Approval)
Vanity Counter (Engineer Review\Approval)
Thermoplastic Paint (Engineer Review\Approval)
Thermoplastic Paint (Engineer Review\Approval)
GRC Work (Engineer Review\Approval)
Switches & Sockets (Prequalification Submission)
Light Fittings- Buildings\Boundary Wall (Prequalification Submission)
Sanitary Ware (Prequalification & Submission)
Road Marking (Preparation & Submission)
Road Marking (Procurement\Placing Order)
Road Marking (Preparation & Submission)
Thermoplastic Paint (Preparation & Submission)
Thermoplastic Paint (Procurement\Placing Order)
Thermoplastic Paint (Preparation & Submission)
15-Apr-18, Material Approvals Throu

Earthing System (Preparation & Submission)


Bitumen Coating to Foundation (Preparation & Submission)
Aluminium Canopy (Engineer Review\Approval)
Cat Ladder (Engineer Review\Approval)
Aluminium Windows\Doors (Engineer Review\Approval)
Balcony Handrails (Engineer Review\Approval)
Steps Handrail (Engineer Review\Approval)
Aluminium Louver Doors\Windows (Engineer Review\Approval)
Powder Coat Aluminium Fence- Roof (Engineer Review\Approval)
Aluminium Aluminium Glazing (Engineer Review\Approval)
Wooden Doors Sample\material to Staircase (Engineer Review\Approval)
Wooden Doors Sample\material (Engineer Review\Approval)
Ironmongery and Accessories to Staircase (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 8 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.WD.360 Ironmongery and Accessories (Engineer Review\Approval)
14 14 0% 19-Apr-17 03-May-17 33
MC.ME.L20 Lift Work (Engineer Review\Approval) 14 14 0% 07-Jan-17 19-Jan-17 27
MC.ME.L50 Marble Jamb (Engineer Review\Approval) 14 14 0% 08-May-17 21-May-17 31
MC.DR.105 Riser Drainge Pipes\Fittings (Engineer Review\Approval)14 14 0% 08-Dec-16 22-Dec-16 30
MC.DR.100 Riser Drainge Pipes\Fittings (Preparation & Submission)14 14 0% 24-Nov-16 08-Dec-16 30
MC.DR.R15 Outlet Body (Engineer Review\Approval) 14 14 0% 15-Apr-17 29-Apr-17 31
MC.DR.R25 Domical Grate (Engineer Review\Approval) 14 14 0% 03-Aug-17 16-Aug-17 19
MC.DR.025 Floor Trap (Engineer Review\Approval) 14 14 0% 26-Jan-17 08-Feb-17 32
MC.DR.035 Bath-Tub (Engineer Review\Approval) 14 14 0% 04-Mar-17 16-Mar-17 28
MC.DR.015 Drainge Pipes \ Fittings (Engineer Review\Approval) 14 14 0% 07-Sep-16 24-Sep-16 39
MC.DR.020 Floor Trap (Preparation & Submission) 14 14 0% 12-Jan-17 26-Jan-17 32
MC.DR.010 Drainge Pipes \ Fittings (Preparation & Submission) 14 14 0% 24-Aug-16 07-Sep-16 39
MC.DR.205 Sanitary Ware (Engineer Review\Approval) 14 14 0% 25-Jun-17 10-Jul-17 14
MC.FF.145 Fire Fighting Riser Pipes (Engineer Review\Approval) 14 14 0% 06-Jun-17 19-Jun-17 28
MC.FF.015 G.I Fire Fighting Pipes, Valves,etc.. (Engineer Review\Approval)
14 14 0% 13-Dec-16 26-Dec-16 27
MC.FF.025 Sprinklers (Engineer Review\Approval) 14 14 0% 15-Jun-17 01-Jul-17 27
MC.FF.035 Hose Reel\Fire Extinguisher (Engineer Review\Approval)14 14 0% 23-May-17 05-Jun-17 27
MC.FF.115 Preaction System (Engineer Review\Approval) 14 14 0% 23-May-17 05-Jun-17 29
MC.FF.125 Foam System (Engineer Review\Approval) 14 14 0% 15-Jun-17 01-Jul-17 32
MC.FF.155 Fire Pump (Engineer Review\Approval) 14 14 0% 19-Apr-17 03-May-17 32
MC.WS.045 Mixers, Valves, etc (Engineer Review\Approval) 14 14 0% 25-Jun-17 10-Jul-17 30
MC.WS.015 Hot and Cold Water Pipes (Engineer Review\Approval) 14 14 0% 16-Nov-16 29-Nov-16 32
MC.WS.025 Water Supply Pipes\Fittings (Engineer Review\Approval)14 14 0% 23-Nov-16 06-Dec-16 30
MC.WS.075 Transfer Pump (Engineer Review\Approval) 14 14 0% 09-Mar-17 23-Mar-17 30
MC.WS.065 Booster Pump (Engineer Review\Approval) 14 14 0% 19-Mar-17 02-Apr-17 30
MC.WS.055 GRP Water Tank (Engineer Review\Approval) 14 14 0% 04-May-17 17-May-17 29
MC.WS.035 Water Heaters (Engineer Review\Approval) 14 14 0% 30-Jan-17 12-Feb-17 25
MC.AC.015 FCU (Engineer Review\Approval) 14 14 0% 17-Jun-17 03-Jul-17 -271
MC.AC.025 Duct (Engineer Review\Approval) 14 14 0% 17-Jun-17 03-Jul-17 -271
MC.AC.035 Mouse Connection\Fire Damper (Engineer Review\Approval)
14 14 0% 22-Aug-17 06-Sep-17 -245
MC.AC.045 Gas Pipes (Engineer Review\Approval) 14 14 0% 17-Jun-17 03-Jul-17 -271
MC.AC.105 Grills,defusers,Isolators,Ext. Fane,etc. (Engineer Review\Approval)
14 14 0% 28-Jan-18 10-Feb-18 -245
MC.AC.010 FCU (Preparation & Submission) 14 14 0% 04-Jun-17 17-Jun-17 -271
MC.AC.020 Duct (Preparation & Submission) 14 14 0% 04-Jun-17 17-Jun-17 -271

Actual Level of Effort Remaining Work Page 9 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Ironmongery and Accessories (Engineer Review\Approval)
Lift Work (Engineer Review\Approval)
Marble Jamb (Engineer Review\Approval)
Riser Drainge Pipes\Fittings (Engineer Review\Approval)
Riser Drainge Pipes\Fittings (Preparation & Submission)
Outlet Body (Engineer Review\Approval)
Domical Grate (Engineer Review\Approval)
Floor Trap (Engineer Review\Approval)
Bath-Tub (Engineer Review\Approval)
Drainge Pipes \ Fittings (Engineer Review\Approval)
Floor Trap (Preparation & Submission)
Drainge Pipes \ Fittings (Preparation & Submission)
Sanitary Ware (Engineer Review\Approval)
Fire Fighting Riser Pipes (Engineer Review\Approval)
G.I Fire Fighting Pipes, Valves,etc.. (Engineer Review\Approval)
Sprinklers (Engineer Review\Approval)
Hose Reel\Fire Extinguisher (Engineer Review\Approval)
Preaction System (Engineer Review\Approval)
Foam System (Engineer Review\Approval)
Fire Pump (Engineer Review\Approval)
Mixers, Valves, etc (Engineer Review\Approval)
Hot and Cold Water Pipes (Engineer Review\Approval)
Water Supply Pipes\Fittings (Engineer Review\Approval)
Transfer Pump (Engineer Review\Approval)
Booster Pump (Engineer Review\Approval)
GRP Water Tank (Engineer Review\Approval)
Water Heaters (Engineer Review\Approval)
FCU (Engineer Review\Approval)
Duct (Engineer Review\Approval)
Mouse Connection\Fire Damper (Engineer Review\Approval)
Gas Pipes (Engineer Review\Approval)
Grills,defusers,Isolators,Ext. Fane,etc. (Engineer Rev
FCU (Preparation & Submission)
Duct (Preparation & Submission)

Actual Level of Effort Remaining Work Page 10 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.AC.040 Gas Pipes (Preparation & Submission) 14 14 0% 04-Jun-17 17-Jun-17 -271
MC.AC.235 Pressurization Unit (Engineer Review\Approval) 14 14 0% 01-Apr-18 15-Apr-18 -243
MC.AC.245 Extact Fan (Engineer Review\Approval) 14 14 0% 17-Dec-17 31-Dec-17 -243
MC.AC.205 FAHU (Engineer Review\Approval) 14 14 0% 07-Dec-17 21-Dec-17 -248
MC.AC.320 Riser Duct (Preparation & Submission) 14 14 0% 19-Aug-17 04-Sep-17 -246
MC.AC.325 Riser Duct (Engineer Review\Approval) 14 14 0% 04-Sep-17 17-Sep-17 -246
MC.EL.L20 Earthing System (Engineer Review\Approval) 14 14 0% 29-Sep-16 13-Oct-16 32
MC.EL.L40 ECC Cables (Engineer Review\Approval) 14 14 0% 15-Jun-17 01-Jul-17 33
MC.EL.L60 Cooper Tape\Accessories (Engineer Review\Approval) 14 14 0% 16-Jul-17 29-Jul-17 25
MC.EL.L80 Air Terminal Rod (Engineer Review\Approval) 14 14 0% 25-Jul-17 07-Aug-17 23
MC.EL.S25 Security System Devices (Engineer Review\Approval) 14 14 0% 14-May-17 27-May-17 31
MC.EL.S15 Security System Control Panels (Engineer Review\Approval)
14 14 0% 23-May-17 05-Jun-17 28
MC.EL.T15 Telephone Cables\Cables Tray (Engineer Review\Approval).
14 14 0% 25-Jan-17 07-Feb-17 30
MC.EL.T25 Telephone Cabinet\ONU (Engineer Review\Approval) 14 14 0% 30-Jan-17 12-Feb-17 29
MC.EL.E96 Riser Cables\Tray (Engineer Review\Approval) 14 14 0% 26-Apr-17 10-May-17 30
MC.EL.E91 Emergency Light Control Panel (Engineer Review\Approval)
14 14 0% 06-Jun-17 19-Jun-17 30
MC.EL.E76 Emergency Light (Engineer Review\Approval) 14 14 0% 01-Jun-17 14-Jun-17 31
MC.EL.E45 LV Panel\Capactor Banks (Engineer Review\Approval) 14 14 0% 28-Mar-17 11-Apr-17 28
MC.EL.E25 Isolators (Engineer Review\Approval) 14 14 0% 16-Jan-17 29-Jan-17 29
MC.EL.E55 Generator\ATS (Engineer Review\Approval) 14 14 0% 14-Feb-17 28-Feb-17 29
MC.EL.E35 Swich Gear (Engineer Review\Approval) 14 14 0% 31-Jan-17 14-Feb-17 12
MC.EL.E15 Power Cables\Cables Tray (Engineer Review\Approval) 14 14 0% 19-Dec-16 03-Jan-17 30
MC.EL.E65 Switches & Sockets (Engineer Review\Approval) 14 14 0% 01-Jun-17 14-Jun-17 27
MC.EL.E86 Light Fittings- Boundary Wall (Engineer Review\Approval)
14 14 0% 30-Jul-17 12-Aug-17 20
MC.EL.E71 Light Fittings- Building (Engineer Review\Approval) 14 14 0% 01-Jun-17 14-Jun-17 27
MC.EL.V25 Desh and Mixer (Engineer Review\Approval) 14 14 0% 15-Jun-17 01-Jul-17 30
MC.EL.V15 Coaxial Cables, Spliter (Engineer Review\Approval) 14 14 0% 25-Jun-17 10-Jul-17 30
MC.EL.F15 Fire Alarm Devices (Engineer Review\Approval) 14 14 0% 04-May-17 17-May-17 31
MC.EL.F35 Fire alarm Control Panel- Sub\App (Engineer Review\Approval)
14 14 0% 06-Jul-17 19-Jul-17 26
MC.EL.025 All Types Of Wires (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 29
MC.EL.015 Conduits,Boxes (Engineer Review\Approval) 14 14 0% 06-Oct-16 19-Oct-16 35
MC.PG.025 Copper Pipes (Engineer Review\Approval) 14 14 0% 10-Apr-17 24-Apr-17 10
MC.PG.035 Switch\Detector\Indicator (Engineer Review\Approval) 14 14 0% 06-Jun-17 19-Jun-17 29
MC.PG.045 Flexible Hose (Engineer Review\Approval) 14 14 0% 06-Jul-17 19-Jul-17 29

Actual Level of Effort Remaining Work Page 11 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Gas Pipes (Preparation & Submission)
Pressurization Unit (Engineer Revie
Extact Fan (Engineer Review\Approval)
FAHU (Engineer Review\Approval)
Riser Duct (Preparation & Submission)
Riser Duct (Engineer Review\Approval)
Earthing System (Engineer Review\Approval)
ECC Cables (Engineer Review\Approval)
Cooper Tape\Accessories (Engineer Review\Approval)
Air Terminal Rod (Engineer Review\Approval)
Security System Devices (Engineer Review\Approval)
Security System Control Panels (Engineer Review\Approval)
Telephone Cables\Cables Tray (Engineer Review\Approval).
Telephone Cabinet\ONU (Engineer Review\Approval)
Riser Cables\Tray (Engineer Review\Approval)
Emergency Light Control Panel (Engineer Review\Approval)
Emergency Light (Engineer Review\Approval)
LV Panel\Capactor Banks (Engineer Review\Approval)
Isolators (Engineer Review\Approval)
Generator\ATS (Engineer Review\Approval)
Swich Gear (Engineer Review\Approval)
Power Cables\Cables Tray (Engineer Review\Approval)
Switches & Sockets (Engineer Review\Approval)
Light Fittings- Boundary Wall (Engineer Review\Approval)
Light Fittings- Building (Engineer Review\Approval)
Desh and Mixer (Engineer Review\Approval)
Coaxial Cables, Spliter (Engineer Review\Approval)
Fire Alarm Devices (Engineer Review\Approval)
Fire alarm Control Panel- Sub\App (Engineer Review\Approval)
All Types Of Wires (Engineer Review\Approval)
Conduits,Boxes (Engineer Review\Approval)
Copper Pipes (Engineer Review\Approval)
Switch\Detector\Indicator (Engineer Review\Approval)
Flexible Hose (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 12 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.PG.105 Gas Alarm Control Panel (Engineer Review\Approval) 14 14 0% 25-Jun-17 10-Jul-17 27
MC.PG.055 Explosion Proof Gas Leak Detector (Engineer Review\Approval)
14 14 0% 01-Jun-17 14-Jun-17 29
MC.PG.075 Pressure Regulating & Dist. Panel (Engineer Review\Approval)
14 14 0% 06-Jun-17 19-Jun-17 28
MC.PG.015 LPG Tank (Engineer Review\Approval) 14 14 0% 18-May-17 31-May-17 32
MC.FO.990 Biycle Rack (Engineer Review\Approval) 14 14 0% 08-Aug-17 21-Aug-17 32
MC.FO.020 Wardrobes Material (Engineer Review\Approval) 14 14 0% 06-Jul-17 19-Jul-17 29
MC.FO.160 Kitchen Cabinet- (Engineer Review\Approval) 14 14 0% 06-Jun-17 19-Jun-17 20
MC.FO.260 Vanity Counter- Typical Floor (Engineer Review\Approval)
14 14 0% 06-Jun-17 19-Jun-17 20
MC.FO.310 Mirrors For Bath (Engineer Review\Approval) 14 14 0% 02-Jul-17 15-Jul-17 31
MC.FO.510 Remote Control Gate Barrier (Engineer Review\Approval)
14 14 0% 30-Jul-17 12-Aug-17 32
MC.AL.710 Tesion Fabric (Engineer Review\Approval) 14 14 0% 06-May-17 20-May-17 33
MC.PN.130 Internal Paint (Engineer Review\Approval) 14 14 0% 10-Apr-17 24-Apr-17 28
MC.PN.110 Primer\Stucco (Engineer Review\Approval) 14 14 0% 22-Dec-16 05-Jan-17 31
MC.PN.160 Internal Paint to Parking Area (Engineer Review\Approval)
14 14 0% 22-Dec-16 05-Jan-17 33
MC.PN.260 External Painting (Engineer Review\Approval) 14 14 0% 06-Jun-17 19-Jun-17 33
MC.WP.R20 Waterproofing to Roof Deck (Engineer Review\Approval)14 14 0% 22-Apr-17 06-May-17 29
MC.WP.G20 Waterproofing to Garbage Chute (Engineer Review\Approval)
14 14 0% 22-Apr-17 06-May-17 7
MC.WP.F20 Bitumen Coating to Foundation (Engineer Review\Approval)
14 14 0% 25-Jul-16 07-Aug-16 31
MC.WP.B20 Waterproofing to Balconies (Engineer Review\Approval)14 14 0% 22-Apr-17 06-May-17 26
MC.WP.W20 Waterproofing to Wet area (Engineer Review\Approval) 14 14 0% 23-Jan-17 05-Feb-17 36
MC.FL.210 Epoxy Coating (Engineer Review\Approval) 14 14 0% 02-May-17 15-May-17 30
MC.AL.610 Metal Doors (Engineer Review\Approval) 14 14 0% 06-May-17 20-May-17 37
MC.CO.110 Anti-Termite (Engineer Review\Approval) 14 14 0% 21-Aug-16 03-Sep-16 31
MC.GC.110 Compactor (Engineer Review\Approval) 14 14 0% 20-Jul-17 02-Aug-17 30
MC.GC.020 Grarbage Shaft (Engineer Review\Approval) 14 14 0% 27-Feb-17 12-Mar-17 30
MC.GC.210 Garbage Chute Trolley (Engineer Review\Approval) 14 14 0% 30-Jul-17 12-Aug-17 27
MC.GC.040 Centerifugal Ext. Fan (Engineer Review\Approval) 14 14 0% 06-Jul-17 19-Jul-17 29
MC.AL.810 Aluminium Louver (Engineer Review\Approval) 14 14 0% 21-Jun-17 08-Jul-17 30
MC.AL.210 Aluminium Element (Engineer Review\Approval) 14 14 0% 10-May-17 24-May-17 28
MC.AL.360 Aluminium Screen (Engineer Review\Approval) 14 14 0% 16-Apr-17 01-May-17 32
MC.AL.840 Aluminium Channel (Engineer Review\Approval) 14 14 0% 02-Apr-17 16-Apr-17 26
MC.AL.860 Aluminium Panels (Engineer Review\Approval) 14 14 0% 12-Jun-17 26-Jun-17 29
MC.FO.280 Reciption Counter- Typical Floor (Engineer Review\Approval)
14 14 0% 13-Aug-17 26-Aug-17 27
MC.DR.055 Catch Basin (Engineer Review\Approval) 14 14 0% 06-Jun-17 19-Jun-17 28

Actual Level of Effort Remaining Work Page 13 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:15
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Gas Alarm Control Panel (Engineer Review\Approval)
Explosion Proof Gas Leak Detector (Engineer Review\Approval)
Pressure Regulating & Dist. Panel (Engineer Review\Approval)
LPG Tank (Engineer Review\Approval)
Biycle Rack (Engineer Review\Approval)
Wardrobes Material (Engineer Review\Approval)
Kitchen Cabinet- (Engineer Review\Approval)
Vanity Counter- Typical Floor (Engineer Review\Approval)
Mirrors For Bath (Engineer Review\Approval)
Remote Control Gate Barrier (Engineer Review\Approval)
Tesion Fabric (Engineer Review\Approval)
Internal Paint (Engineer Review\Approval)
Primer\Stucco (Engineer Review\Approval)
Internal Paint to Parking Area (Engineer Review\Approval)
External Painting (Engineer Review\Approval)
Waterproofing to Roof Deck (Engineer Review\Approval)
Waterproofing to Garbage Chute (Engineer Review\Approval)
Bitumen Coating to Foundation (Engineer Review\Approval)
Waterproofing to Balconies (Engineer Review\Approval)
Waterproofing to Wet area (Engineer Review\Approval)
Epoxy Coating (Engineer Review\Approval)
Metal Doors (Engineer Review\Approval)
Anti-Termite (Engineer Review\Approval)
Compactor (Engineer Review\Approval)
Grarbage Shaft (Engineer Review\Approval)
Garbage Chute Trolley (Engineer Review\Approval)
Centerifugal Ext. Fan (Engineer Review\Approval)
Aluminium Louver (Engineer Review\Approval)
Aluminium Element (Engineer Review\Approval)
Aluminium Screen (Engineer Review\Approval)
Aluminium Channel (Engineer Review\Approval)
Aluminium Panels (Engineer Review\Approval)
Reciption Counter- Typical Floor (Engineer Review\Approval)
Catch Basin (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 14 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.DR.115 Sump Pump (Engineer Review\Approval) 14 14 0% 21-Jun-17 06-Jul-17 27
MC.DR.110 Sump Pump (Preparation & Submission) 14 14 0% 07-Jun-17 21-Jun-17 27
MC.DR.045 Shower Try (Engineer Review\Approval) 14 14 0% 01-Apr-17 13-Apr-17 28
MC.AC.115 Ventilation System Fans. (Engineer Review\Approval) 14 14 0% 19-Oct-17 01-Nov-17 -246
MC.FO.410 GRC Work (Engineer Review\Approval) 14 14 0% 14-May-17 27-May-17 32
MC.WS.010 Hot and Cold Water Pipes (Preparation & Submission) 21 21 0% 27-Oct-16 16-Nov-16 32
MC.EL.010 Conduits,Boxes (Preparation & Submission) 21 21 0% 17-Sep-16 06-Oct-16 35
MC.EL.020 All Types Of Wires (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 29
MC.WP.R10 Waterproofing to Roof Deck (Preparation & Submission)21 21 0% 02-Apr-17 22-Apr-17 29
MC.WP.G10 Waterproofing to Garbage Chute (Preparation & Submission)
21 21 0% 02-Apr-17 22-Apr-17 7
MC.WP.B10 Waterproofing to Balconies\Terrace (Preparation & Submission)
21 21 0% 02-Apr-17 22-Apr-17 26
MC.WP.W10 Waterproofing to Wet area (Preparation & Submission) 21 21 0% 03-Jan-17 23-Jan-17 36
MC.FL.200 Epoxy Coating (Preparation & Submission) 21 21 0% 11-Apr-17 02-May-17 30
MC.AL.300 Aluminium Canopy (Preparation & Submission) 28 28 0% 26-Mar-17 20-Apr-17 27
MC.AL.400 Cat Ladder (Preparation & Submission) 28 28 0% 22-May-17 17-Jun-17 36
MC.AL.100 Aluminium Windows\Doors (Preparation & Submission) 28 28 0% 26-Mar-17 20-Apr-17 20
MC.AL.B10 Balcony Handrails (Preparation & Submission) 28 28 0% 05-Jun-17 03-Jul-17 29
MC.AL.T10 Steps Handrail (Preparation & Submission) 28 28 0% 31-May-17 26-Jun-17 26
MC.AL.S10 Aluminium Louver Doors\Windows (Preparation & Submission)
28 28 0% 07-Feb-17 05-Mar-17 32
MC.AL.500 Powder Coat Aluminium Fence- Roof (Preparation & Submission)
28 28 0% 27-May-17 21-Jun-17 30
MC.AL.150 Aluminium Glazing (Preparation & Submission) 28 28 0% 13-Apr-17 10-May-17 16
MC.WD.400 Wooden Doors Sample\material to Staircase (Preparation
28 & Submission) 28 0% 12-Jun-17 11-Jul-17 27
MC.WD.300 Wooden Doors Sample\material (Preparation & Submission)
28 28 0% 23-Mar-17 19-Apr-17 33
MC.WD.450 Ironmongery and Accessories to Staircase (Preparation28
& Submission) 28 0% 03-Jun-17 02-Jul-17 37
MC.WD.350 Ironmongery and Accessories (Preparation & Submission)
28 28 0% 23-Mar-17 19-Apr-17 33
MC.ME.L10 Lift Work (Preparation & Submission) 28 28 0% 08-Dec-16 07-Jan-17 27
MC.ME.L40 Marble Jamb (Preparation & Submission) 28 28 0% 11-Apr-17 08-May-17 31
MC.DR.R10 Outlet Body (Preparation & Submission) 28 28 0% 19-Mar-17 15-Apr-17 31
MC.DR.R20 Domical Grate (Preparation & Submission) 28 28 0% 08-Jul-17 03-Aug-17 19
MC.DR.030 Bath-Tub (Preparation & Submission) 28 28 0% 05-Feb-17 04-Mar-17 28
MC.DR.200 Sanitary Ware (Preparation & Submission) 28 28 0% 29-May-17 25-Jun-17 14
MC.FF.140 Fire Fighting Riser Pipes (Preparation & Submission) 28 28 0% 10-May-17 06-Jun-17 28
MC.FF.010 G.I Fire Fighting Pipes, Valves,etc... (Preparation & Submission)
28 28 0% 15-Nov-16 13-Dec-16 27
MC.FF.020 Sprinklers (Preparation & Submission) 28 28 0% 20-May-17 15-Jun-17 27

Actual Level of Effort Remaining Work Page 15 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Sump Pump (Engineer Review\Approval)
Sump Pump (Preparation & Submission)
Shower Try (Engineer Review\Approval)
Ventilation System Fans. (Engineer Review\Approval)
GRC Work (Engineer Review\Approval)
Hot and Cold Water Pipes (Preparation & Submission)
Conduits,Boxes (Preparation & Submission)
All Types Of Wires (Preparation & Submission)
Waterproofing to Roof Deck (Preparation & Submission)
Waterproofing to Garbage Chute (Preparation & Submission)
Waterproofing to Balconies\Terrace (Preparation & Submission)
Waterproofing to Wet area (Preparation & Submission)
Epoxy Coating (Preparation & Submission)
Aluminium Canopy (Preparation & Submission)
Cat Ladder (Preparation & Submission)
Aluminium Windows\Doors (Preparation & Submission)
Balcony Handrails (Preparation & Submission)
Steps Handrail (Preparation & Submission)
Aluminium Louver Doors\Windows (Preparation & Submission)
Powder Coat Aluminium Fence- Roof (Preparation & Submission)
Aluminium Glazing (Preparation & Submission)
Wooden Doors Sample\material to Staircase (Preparation & Submission)
Wooden Doors Sample\material (Preparation & Submission)
Ironmongery and Accessories to Staircase (Preparation & Submission)
Ironmongery and Accessories (Preparation & Submission)
Lift Work (Preparation & Submission)
Marble Jamb (Preparation & Submission)
Outlet Body (Preparation & Submission)
Domical Grate (Preparation & Submission)
Bath-Tub (Preparation & Submission)
Sanitary Ware (Preparation & Submission)
Fire Fighting Riser Pipes (Preparation & Submission)
G.I Fire Fighting Pipes, Valves,etc... (Preparation & Submission)
Sprinklers (Preparation & Submission)

Actual Level of Effort Remaining Work Page 16 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.FF.030 Hose Reel\Fire Extinguisher (Preparation & Submission)28 28 0% 26-Apr-17 23-May-17 27
MC.FF.110 Preaction System (Preparation & Submission) 28 28 0% 26-Apr-17 23-May-17 29
MC.FF.120 Foam System (Preparation & Submission) 28 28 0% 20-May-17 15-Jun-17 32
MC.FF.150 Fire Pump (Preparation & Submission) 28 28 0% 23-Mar-17 19-Apr-17 32
MC.WS.040 Mixers, Valves, etc. (Preparation & Submission) 28 28 0% 29-May-17 25-Jun-17 30
MC.WS.020 Water Supply Pipes\Fittings (Preparation & Submission)28 28 0% 27-Oct-16 23-Nov-16 30
MC.WS.050 GRP Water Tank- (Preparation & Submission) 28 28 0% 06-Apr-17 04-May-17 29
MC.WS.030 Water Heaters (Preparation & Submission) 28 28 0% 03-Jan-17 30-Jan-17 25
MC.AC.030 Mouse Connection\Fire Damper (Preparation & Submission)
28 28 0% 26-Jul-17 22-Aug-17 -245
MC.AC.100 Grills,defusers,Isolators,Ext. Fane,etc.. (Preparation & Submission)
28 28 0% 31-Dec-17 28-Jan-18 -245
MC.EL.L30 ECC Cables (Preparation & Submission) 28 28 0% 20-May-17 15-Jun-17 33
MC.EL.L50 Cooper Tape\Accessories (Preparation & Submission) 28 28 0% 17-Jun-17 16-Jul-17 25
MC.EL.L70 Air Terminal Rod (Preparation & Submission) 28 28 0% 26-Jun-17 25-Jul-17 23
MC.EL.S10 Security System Control Panels (Preparation & Submission)
28 28 0% 26-Apr-17 23-May-17 28
MC.EL.S20 Security System Devices (Preparation & Submission) 28 28 0% 16-Apr-17 14-May-17 31
MC.EL.T10 Telephone Cables\Cables Tray (Preparation & Submission)
28 28 0% 28-Dec-16 25-Jan-17 30
MC.EL.T20 Telephone Cabinet\ONU (Preparation & Submission) 28 28 0% 03-Jan-17 30-Jan-17 29
MC.EL.E90 Emergency Light Control Panel (Preparation & Submission)
28 28 0% 10-May-17 06-Jun-17 30
MC.EL.E75 Emergency Light (Preparation & Submission) 28 28 0% 06-May-17 01-Jun-17 31
MC.EL.E20 Isolators (Preparation & Submission) 28 28 0% 19-Dec-16 16-Jan-17 29
MC.EL.E60 Switches & Sockets (Preparation & Submission) 28 28 0% 06-May-17 01-Jun-17 27
MC.EL.E85 Light Fittings- Boundary Wall (Preparation & Submission)
28 28 0% 03-Jul-17 30-Jul-17 20
MC.EL.E70 Light Fittings- Building (Preparation & Submission) 28 28 0% 06-May-17 01-Jun-17 27
MC.EL.V20 Desh and Mixer (Preparation & Submission) 28 28 0% 20-May-17 15-Jun-17 30
MC.EL.V10 Coaxial Cables, Spliter (Preparation & Submission) 28 28 0% 29-May-17 25-Jun-17 30
MC.EL.F10 Fire Alarm Devices (Preparation & Submission) 28 28 0% 06-Apr-17 04-May-17 31
MC.EL.F30 Fire alarm Control Panel (Preparation & Submission) 28 28 0% 07-Jun-17 06-Jul-17 26
MC.PG.020 Copper Pipes (Preparation & Submission) 28 28 0% 14-Mar-17 10-Apr-17 10
MC.PG.030 Switch\Detector\Indicator (Preparation & Submission) 28 28 0% 10-May-17 06-Jun-17 29
MC.PG.040 Flexible Hose (Preparation & Submission) 28 28 0% 07-Jun-17 06-Jul-17 29
MC.PG.100 Gas Alarm Control Panel (Preparation & Submission) 28 28 0% 29-May-17 25-Jun-17 27
MC.PG.050 Explosion Proof Gas Leak Detector (Preparation & Submission)
28 28 0% 06-May-17 01-Jun-17 29
MC.PG.070 Pressure Regulating & Dist. Panel (Preparation & Submission)
28 28 0% 10-May-17 06-Jun-17 28
MC.PG.010 LPG Tank (Preparation & Submission) 28 28 0% 20-Apr-17 18-May-17 32

Actual Level of Effort Remaining Work Page 17 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Hose Reel\Fire Extinguisher (Preparation & Submission)
Preaction System (Preparation & Submission)
Foam System (Preparation & Submission)
Fire Pump (Preparation & Submission)
Mixers, Valves, etc. (Preparation & Submission)
Water Supply Pipes\Fittings (Preparation & Submission)
GRP Water Tank- (Preparation & Submission)
Water Heaters (Preparation & Submission)
Mouse Connection\Fire Damper (Preparation & Submission)
Grills,defusers,Isolators,Ext. Fane,etc.. (Preparation & Su
ECC Cables (Preparation & Submission)
Cooper Tape\Accessories (Preparation & Submission)
Air Terminal Rod (Preparation & Submission)
Security System Control Panels (Preparation & Submission)
Security System Devices (Preparation & Submission)
Telephone Cables\Cables Tray (Preparation & Submission)
Telephone Cabinet\ONU (Preparation & Submission)
Emergency Light Control Panel (Preparation & Submission)
Emergency Light (Preparation & Submission)
Isolators (Preparation & Submission)
Switches & Sockets (Preparation & Submission)
Light Fittings- Boundary Wall (Preparation & Submission)
Light Fittings- Building (Preparation & Submission)
Desh and Mixer (Preparation & Submission)
Coaxial Cables, Spliter (Preparation & Submission)
Fire Alarm Devices (Preparation & Submission)
Fire alarm Control Panel (Preparation & Submission)
Copper Pipes (Preparation & Submission)
Switch\Detector\Indicator (Preparation & Submission)
Flexible Hose (Preparation & Submission)
Gas Alarm Control Panel (Preparation & Submission)
Explosion Proof Gas Leak Detector (Preparation & Submission)
Pressure Regulating & Dist. Panel (Preparation & Submission)
LPG Tank (Preparation & Submission)

Actual Level of Effort Remaining Work Page 18 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.FO.980 Biycle Rack (Preparation & Submission) 28 28 0% 12-Jul-17 08-Aug-17 32
MC.FO.010 Wardrobes Material (Preparation & Submission) 28 28 0% 07-Jun-17 06-Jul-17 29
MC.FO.150 Kitchen Cabinet- (Preparation & Submission) 28 28 0% 10-May-17 06-Jun-17 20
MC.FO.250 Vanity Counter- Typical Floor (Preparation & Submission)
28 28 0% 10-May-17 06-Jun-17 20
MC.FO.300 Mirrors For Bath (Preparation & Submission) 28 28 0% 03-Jun-17 02-Jul-17 31
MC.FO.500 Remote Control Gate Barrier (Preparation & Submission)
28 28 0% 03-Jul-17 30-Jul-17 32
MC.AL.700 Tesion Fabric (Preparation & Submission) 28 28 0% 09-Apr-17 06-May-17 33
MC.PN.120 Internal Paint (Preparation & Submission) 28 28 0% 14-Mar-17 10-Apr-17 28
MC.PN.100 Primer\Stucco (Preparation & Submission) 28 28 0% 24-Nov-16 22-Dec-16 31
MC.PN.150 Internal Paint to Parking Area (Preparation & Submission)
28 28 0% 24-Nov-16 22-Dec-16 33
MC.PN.250 External Painting (Preparation & Submission) 28 28 0% 10-May-17 06-Jun-17 33
MC.AL.600 Metal Doors (Preparation & Submission) 28 28 0% 09-Apr-17 06-May-17 37
MC.CO.010 Concrete Raft Trial Mix 28 28 0% 20-Sep-16 17-Oct-16 32
MC.CO.020 Columns Concrete Trial Mix 28 28 0% 04-Oct-16 30-Oct-16 33
MC.CO.030 Slabs Concrete Trial Mix 28 28 0% 10-Oct-16 06-Nov-16 31
MC.GC.030 Centerifugal Ext. Fan (Preparation & Submission) 28 28 0% 07-Jun-17 06-Jul-17 29
MC.GC.100 Compactor (Preparation & Submission) 28 28 0% 21-Jun-17 20-Jul-17 30
MC.GC.010 Grarbage Shaft (Preparation & Submission) 28 28 0% 31-Jan-17 27-Feb-17 30
MC.GC.200 Garbage Chute Trolley (Preparation & Submission) 28 28 0% 03-Jul-17 30-Jul-17 27
MC.AL.800 Aluminium Louver (Preparation & Submission) 28 28 0% 27-May-17 21-Jun-17 30
MC.AL.200 Aluminium Element (Preparation & Submission) 28 28 0% 13-Apr-17 10-May-17 28
MC.AL.350 Aluminium Screen (Preparation & Submission) 28 28 0% 21-Mar-17 16-Apr-17 32
MC.AL.830 Aluminium Channel (Preparation & Submission) 28 28 0% 07-Mar-17 02-Apr-17 26
MC.AL.850 Aluminium Panels (Preparation & Submission) 28 28 0% 17-May-17 12-Jun-17 29
MC.FO.270 Reciption Counter- Typical Floor (Preparation & Submission)
28 28 0% 17-Jul-17 13-Aug-17 27
MC.DR.050 Catch Basin (Preparation & Submission) 28 28 0% 10-May-17 06-Jun-17 28
MC.DR.040 Shower Try (Preparation & Submission) 28 28 0% 05-Mar-17 01-Apr-17 28
MC.AC.110 Ventilation System Fans. (Preparation & Submission) 28 28 0% 23-Sep-17 19-Oct-17 -246
MC.FO.400 GRC Work (Preparation & Submission) 28 28 0% 16-Apr-17 14-May-17 32
MC.WS.070 Transfer Pump (Preparation & Submission) 45 45 0% 26-Jan-17 09-Mar-17 30
MC.WS.060 Booster Pump (Preparation & Submission) 45 45 0% 05-Feb-17 19-Mar-17 30
MC.AC.230 Pressurization Unit (Preparation & Submission) 45 45 0% 17-Feb-18 01-Apr-18 -243
MC.AC.240 Extact Fan (Preparation & Submission) 45 45 0% 04-Nov-17 17-Dec-17 -243
MC.AC.200 FAHU (Preparation & Submission) 45 45 0% 25-Oct-17 07-Dec-17 -248

Actual Level of Effort Remaining Work Page 19 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Biycle Rack (Preparation & Submission)
Wardrobes Material (Preparation & Submission)
Kitchen Cabinet- (Preparation & Submission)
Vanity Counter- Typical Floor (Preparation & Submission)
Mirrors For Bath (Preparation & Submission)
Remote Control Gate Barrier (Preparation & Submission)
Tesion Fabric (Preparation & Submission)
Internal Paint (Preparation & Submission)
Primer\Stucco (Preparation & Submission)
Internal Paint to Parking Area (Preparation & Submission)
External Painting (Preparation & Submission)
Metal Doors (Preparation & Submission)
Concrete Raft Trial Mix
Columns Concrete Trial Mix
Slabs Concrete Trial Mix
Centerifugal Ext. Fan (Preparation & Submission)
Compactor (Preparation & Submission)
Grarbage Shaft (Preparation & Submission)
Garbage Chute Trolley (Preparation & Submission)
Aluminium Louver (Preparation & Submission)
Aluminium Element (Preparation & Submission)
Aluminium Screen (Preparation & Submission)
Aluminium Channel (Preparation & Submission)
Aluminium Panels (Preparation & Submission)
Reciption Counter- Typical Floor (Preparation & Submission)
Catch Basin (Preparation & Submission)
Shower Try (Preparation & Submission)
Ventilation System Fans. (Preparation & Submission)
GRC Work (Preparation & Submission)
Transfer Pump (Preparation & Submission)
Booster Pump (Preparation & Submission)
Pressurization Unit (Preparation & Subm
Extact Fan (Preparation & Submission)
FAHU (Preparation & Submission)

Actual Level of Effort Remaining Work Page 20 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MC.EL.E95 Riser Cables\Tray (Preparation & Submission) 45 45 0% 14-Mar-17 26-Apr-17 30
MC.EL.E40 LV Panel\Capactor Banks (Preparation & Submission) 45 45 0% 14-Feb-17 28-Mar-17 28
MC.EL.E50 Generator\ATS (Preparation & Submission) 45 45 0% 03-Jan-17 14-Feb-17 29
MC.EL.E30 Swich Gear (Preparation & Submission) 45 45 0% 19-Dec-16 31-Jan-17 12
MC.EL.E10 Power Cables\Cables Tray (Preparation & Submission) 45 45 0% 06-Nov-16 19-Dec-16 30

- Procurement Material Through Sub-Contractor 763 763 0% 07-Aug-16 07-Aug-18 -243

PC.WS.025 Water Supply Pipes\Fittings- First Delivery 0 0 0% 14-Feb-17 30


PC.WS.035 Water Heaters- First Delivery 0 0 0% 20-Apr-17 25
PC.WS.015 Hot and Cold Water Pipes- First Delivery 0 0 0% 08-Feb-17 32
PC.WS.045 Mixers, Valves, etc.- First Delivery 0 0 0% 18-Sep-17 30
PC.WS.075 Transfer Pump- Delivery 0 0 0% 14-Aug-17 30
PC.WS.055 GRP Water Tank- Delivery 0 0 0% 23-Aug-17 29
PC.WS.065 Booster Pump- Delivery 0 0 0% 23-Aug-17 30
PC.AC.015 FCU- First Delivery 0 0 0% 06-Nov-17 -242
PC.AC.105 Grills,defusers,Isolators,Ext. Fane,etc..- First Delivery 0 0 0% 19-Apr-18 -245
PC.AC.025 Duct- First Delivery 0 0 0% 06-Nov-17 -242
PC.AC.035 Mouse Connection\Fire Damper- First Delivery 0 0 0% 13-Nov-17 -245
PC.AC.045 Gas Pipes Pipes- First Delivery 0 0 0% 06-Nov-17 -237
PC.AC.235 Pressurization Unit- First Delivery 0 0 0% 07-Aug-18 -243
PC.AC.245 Extact Fan- First Delivery 0 0 0% 24-Apr-18 -243
PC.AC.205 FAHU- First Delivery 0 0 0% 29-Apr-18 -248
PC.AC.325 Riser Ducts- First Delivery 0 0 0% 09-Nov-17 -246
PC.FF.145 Fire Fighting Riser Pipes- First Delivery 0 0 0% 28-Aug-17 28
PC.FF.015 G.I Fire Fighting Pipes, Valves,etc...- First Delivery 0 0 0% 05-Mar-17 27
PC.FF.025 Sprinklers- First Delivery 0 0 0% 09-Sep-17 27
PC.FF.035 Hose Reel\Fire Extinguisher- First Delivery 0 0 0% 14-Aug-17 27
PC.FF.115 Preaction System- First Delivery 0 0 0% 14-Aug-17 29
PC.FF.125 Foam System- First Delivery 0 0 0% 09-Sep-17 32
PC.FF.155 Fire Pump- Delivery 0 0 0% 09-Sep-17 32
PC.EL.L20 Earthing System- First Delivery 0 0 0% 26-Oct-16 32
PC.EL.L40 ECC Cables- First Delivery 0 0 0% 09-Sep-17 33
PC.EL.L60 Cooper Tape\Accessories- First Delivery 0 0 0% 07-Oct-17 25
PC.EL.L80 Air Terminal Rod- First Delivery 0 0 0% 16-Oct-17 23

Actual Level of Effort Remaining Work Page 21 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Riser Cables\Tray (Preparation & Submission)
LV Panel\Capactor Banks (Preparation & Submission)
Generator\ATS (Preparation & Submission)
Swich Gear (Preparation & Submission)
Power Cables\Cables Tray (Preparation & Submission)

Water Supply Pipes\Fittings- First Delivery, 14-Feb-17


Water Heaters- First Delivery, 20-Apr-17
Hot and Cold Water Pipes- First Delivery, 08-Feb-17
Mixers, Valves, etc.- First Delivery, 18-Sep-17
Transfer Pump- Delivery, 14-Aug-17
GRP Water Tank- Delivery, 23-Aug-17
Booster Pump- Delivery, 23-Aug-17
FCU- First Delivery, 06-Nov-17
Grills,defusers,Isolators,Ext. Fane
Duct- First Delivery, 06-Nov-17
Mouse Connection\Fire Damper- First Delivery, 13-Nov-17
Gas Pipes Pipes- First Delivery, 06-Nov-17

Extact Fan- First Delivery, 24-Apr


FAHU- First Delivery, 29-Apr-18
Riser Ducts- First Delivery, 09-Nov-17
Fire Fighting Riser Pipes- First Delivery, 28-Aug-17
G.I Fire Fighting Pipes, Valves,etc...- First Delivery, 05-Mar-17
Sprinklers- First Delivery, 09-Sep-17
Hose Reel\Fire Extinguisher- First Delivery, 14-Aug-17
Preaction System- First Delivery, 14-Aug-17
Foam System- First Delivery, 09-Sep-17
Fire Pump- Delivery, 09-Sep-17
Earthing System- First Delivery, 26-Oct-16
ECC Cables- First Delivery, 09-Sep-17
Cooper Tape\Accessories- First Delivery, 07-Oct-17
Air Terminal Rod- First Delivery, 16-Oct-17

Actual Level of Effort Remaining Work Page 22 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PC.EL.E96 Riser Cables\Tray- First Delivery 0 0 0% 18-Sep-17 30
PC.EL.E55 Generator\ATS- First Delivery 0 0 0% 05-Aug-17 29
PC.EL.E35 Swich Gear- First Delivery 0 0 0% 07-Jun-17 12
PC.EL.E15 Power Cables\Cables Tray- First Delivery 0 0 0% 11-Apr-17 30
PC.EL.E91 Emergency Light Control Panel- First Delivery 0 0 0% 28-Aug-17 30
PC.EL.E76 Emergency Light- First Delivery 0 0 0% 23-Aug-17 31
PC.EL.E45 LV Panel\Capactor Banks- First Delivery 0 0 0% 19-Aug-17 28
PC.EL.E25 Isolators- First Delivery 0 0 0% 06-Apr-17 29
PC.EL.E65 Sockets, Switchs- First Delivery 0 0 0% 23-Aug-17 27
PC.EL.E86 Light Fittings- Boundary Wall- First Delivery 0 0 0% 21-Oct-17 20
PC.EL.E71 Light Fittings- Building- First Delivery 0 0 0% 23-Aug-17 27
PC.EL.T15 Telephone Cables\Cables Tray- First Delivery 0 0 0% 16-Apr-17 30
PC.EL.T25 Telephone Cabinet\ONU- First Delivery 0 0 0% 20-Apr-17 29
PC.EL.S15 Security System Control Panels- First Delivery 0 0 0% 14-Aug-17 28
PC.EL.S25 Security System Devices- First Delivery 0 0 0% 05-Aug-17 31
PC.EL.F15 Fire Alarm Devices- First Delivery 0 0 0% 26-Jul-17 31
PC.EL.F35 Fire alarm Control Panel- Delivery 0 0 0% 27-Sep-17 26
PC.EL.015 Conduits,Boxes- First Delivery 0 0 0% 01-Nov-16 35
PC.EL.025 All Types Of Wires- First Delivery 0 0 0% 01-Apr-17 29
PC.EL.V25 Desh and Mixer- First Delivery 0 0 0% 09-Sep-17 30
PC.EL.V15 Coaxial Cables, Spliter(SMATV)- First Delivery 0 0 0% 18-Sep-17 30
PC.DR.105 Riser Drainge Pipes \ Fittings- First Delivery 0 0 0% 15-Feb-17 30
PC.DR.R15 Outlet Body- First Delivery 0 0 0% 08-Jul-17 31
PC.DR.R25 Domical Grate- First Delivery 0 0 0% 25-Oct-17 19
PC.DR.015 Drainge Pipes \ Fittings- First Delivery 0 0 0% 19-Oct-16 39
PC.DR.025 Floor Trap- First Delivery 0 0 0% 06-Mar-17 32
PC.DR.035 Bath-Tub- First Delivery 0 0 0% 24-May-17 28
PC.DR.205 Sanitary Wares- First Delivery 0 0 0% 18-Sep-17 14
PC.ME.L20 Lift Work- First Delivery 0 0 0% 08-Jul-17 27
PC.ME.L50 Marble Jamb- First Delivery 0 0 0% 31-Jul-17 31
PC.WD.410 Wooden Doors to Staircase- First Delivery 0 0 0% 02-Oct-17 27
PC.WD.310 Wooden Doors- First Delivery 0 0 0% 12-Jul-17 33
PC.WD.460 Ironmongery and Accessories to Staircase- First Delivery0 0 0% 23-Sep-17 37
PC.WD.360 Ironmongery and Accessories- First Delivery 0 0 0% 12-Jul-17 33

Actual Level of Effort Remaining Work Page 23 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Riser Cables\Tray- First Delivery, 18-Sep-17
Generator\ATS- First Delivery, 05-Aug-17
Swich Gear- First Delivery, 07-Jun-17
Power Cables\Cables Tray- First Delivery, 11-Apr-17
Emergency Light Control Panel- First Delivery, 28-Aug-17
Emergency Light- First Delivery, 23-Aug-17
LV Panel\Capactor Banks- First Delivery, 19-Aug-17
Isolators- First Delivery, 06-Apr-17
Sockets, Switchs- First Delivery, 23-Aug-17
Light Fittings- Boundary Wall- First Delivery, 21-Oct-17
Light Fittings- Building- First Delivery, 23-Aug-17
Telephone Cables\Cables Tray- First Delivery, 16-Apr-17
Telephone Cabinet\ONU- First Delivery, 20-Apr-17
Security System Control Panels- First Delivery, 14-Aug-17
Security System Devices- First Delivery, 05-Aug-17
Fire Alarm Devices- First Delivery, 26-Jul-17
Fire alarm Control Panel- Delivery, 27-Sep-17
Conduits,Boxes- First Delivery, 01-Nov-16
All Types Of Wires- First Delivery, 01-Apr-17
Desh and Mixer- First Delivery, 09-Sep-17
Coaxial Cables, Spliter(SMATV)- First Delivery, 18-Sep-17
Riser Drainge Pipes \ Fittings- First Delivery, 15-Feb-17
Outlet Body- First Delivery, 08-Jul-17
Domical Grate- First Delivery, 25-Oct-17
Drainge Pipes \ Fittings- First Delivery, 19-Oct-16
Floor Trap- First Delivery, 06-Mar-17
Bath-Tub- First Delivery, 24-May-17
Sanitary Wares- First Delivery, 18-Sep-17
Lift Work- First Delivery, 08-Jul-17
Marble Jamb- First Delivery, 31-Jul-17
Wooden Doors to Staircase- First Delivery, 02-Oct-17
Wooden Doors- First Delivery, 12-Jul-17
Ironmongery and Accessories to Staircase- First Delivery, 23-Sep-17
Ironmongery and Accessories- First Delivery, 12-Jul-17

Actual Level of Effort Remaining Work Page 24 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PC.AL.310 Aluminium Canopy- First Delivery 0 0 0% 15-Jul-17 27
PC.AL.410 Cat Ladder- First Delivery 0 0 0% 11-Sep-17 36
PC.AL.510 Powder Coat Aluminium Fence (Roof)- First Delivery 0 0 0% 16-Sep-17 30
PC.AL.S20 Aluminium Louver Doors\Windows- First Delivery 0 0 0% 27-May-17 32
PC.AL.B20 Balcony Handrails- First Delivery 0 0 0% 25-Sep-17 29
PC.AL.T20 Steps Handrail- First Delivery 0 0 0% 20-Sep-17 26
PC.AL.110 Aluminium Windows\Doors- Elevations)- First Delivery 0 0 0% 15-Jul-17 20
PC.AL.160 Aluminium Glazing- Elevations)- First Delivery 0 0 0% 02-Aug-17 16
PC.GC.040 Centerifugal Ext. Fan- Delivery 0 0 0% 27-Sep-17 29
PC.GC.020 Grarbage System- First Delivery 0 0 0% 20-May-17 30
PC.GC.110 Compactor- Delivery 0 0 0% 11-Oct-17 30
PC.GC.210 Garbage Chute Trolley- Delivery 0 0 0% 21-Oct-17 27
PC.PG.025 Copper Pipes- First Delivery 0 0 0% 03-Jul-17 10
PC.PG.035 Switch\Detector\Indicator- First Delivery 0 0 0% 28-Aug-17 29
PC.PG.045 Flexible Hose- First Delivery 0 0 0% 27-Sep-17 29
PC.PG.105 Gas Alarm Control Panel- First Delivery 0 0 0% 18-Sep-17 27
PC.PG.015 LPG Tank- Delivery 0 0 0% 09-Aug-17 32
PC.PG.055 Explosion Proof Gas Leak Detector- Delivery 0 0 0% 23-Aug-17 29
PC.PG.075 Pressure Regulating & Dist. Panel- Delivery 0 0 0% 28-Aug-17 28
PC.FO.020 Wardrobes- First Delivery 0 0 0% 27-Sep-17 29
PC.FO.160 Kitchen Cabinet- First Delivery 0 0 0% 28-Aug-17 20
PC.FO.260 Vanity Counter- Typical Floor- First Delivery 0 0 0% 28-Aug-17 20
PC.FO.310 Mirrors For Bath First Delivery 0 0 0% 23-Sep-17 31
PC.FO.510 Remote Control Gate Barrier-First Delivery 0 0 0% 21-Oct-17 32
PC.FO.990 Biycle Rack- First Delivery 0 0 0% 30-Oct-17 32
PC.AL.710 Tesion Fabric - Delivery 0 0 0% 29-Jul-17 33
PC.FL.210 Epoxy Coating- First Delivery 0 0 0% 18-Jul-17 30
PC.PN.160 Internal Paint to Parking Area- First Delivery 0 0 0% 14-Mar-17 33
PC.PN.110 Primer & Stucco- First Delivery 0 0 0% 14-Mar-17 31
PC.PN.130 Internal Paint to Buildings- First Delivery 0 0 0% 03-Jul-17 28
PC.PN.260 External Painting- First Delivery 0 0 0% 28-Aug-17 33
PC.WP.W20 Waterproofing to Wet area- First Delivery 0 0 0% 15-Apr-17 36
PC.WP.F20 Bitumen Coating to Foundation to Foundation- First Delivery
0 0 0% 08-Sep-16 31
PC.WP.B20 Waterproofing to Balconies\Terrace- First Delivery 0 0 0% 16-Jul-17 26

Actual Level of Effort Remaining Work Page 25 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Aluminium Canopy- First Delivery, 15-Jul-17
Cat Ladder- First Delivery, 11-Sep-17
Powder Coat Aluminium Fence (Roof)- First Delivery, 16-Sep-17
Aluminium Louver Doors\Windows- First Delivery, 27-May-17
Balcony Handrails- First Delivery, 25-Sep-17
Steps Handrail- First Delivery, 20-Sep-17
Aluminium Windows\Doors- Elevations)- First Delivery, 15-Jul-17
Aluminium Glazing- Elevations)- First Delivery, 02-Aug-17
Centerifugal Ext. Fan- Delivery, 27-Sep-17
Grarbage System- First Delivery, 20-May-17
Compactor- Delivery, 11-Oct-17
Garbage Chute Trolley- Delivery, 21-Oct-17
Copper Pipes- First Delivery, 03-Jul-17
Switch\Detector\Indicator- First Delivery, 28-Aug-17
Flexible Hose- First Delivery, 27-Sep-17
Gas Alarm Control Panel- First Delivery, 18-Sep-17
LPG Tank- Delivery, 09-Aug-17
Explosion Proof Gas Leak Detector- Delivery, 23-Aug-17
Pressure Regulating & Dist. Panel- Delivery, 28-Aug-17
Wardrobes- First Delivery, 27-Sep-17
Kitchen Cabinet- First Delivery, 28-Aug-17
Vanity Counter- Typical Floor- First Delivery, 28-Aug-17
Mirrors For Bath First Delivery, 23-Sep-17
Remote Control Gate Barrier-First Delivery, 21-Oct-17
Biycle Rack- First Delivery, 30-Oct-17
Tesion Fabric - Delivery, 29-Jul-17
Epoxy Coating- First Delivery, 18-Jul-17
Internal Paint to Parking Area- First Delivery, 14-Mar-17
Primer & Stucco- First Delivery, 14-Mar-17
Internal Paint to Buildings- First Delivery, 03-Jul-17
External Painting- First Delivery, 28-Aug-17
Waterproofing to Wet area- First Delivery, 15-Apr-17
Bitumen Coating to Foundation to Foundation- First Delivery, 08-Sep-16
Waterproofing to Balconies\Terrace- First Delivery, 16-Jul-17

Actual Level of Effort Remaining Work Page 26 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PC.WP.R20 Waterproofing to Roof Deck- First Delivery 0 0 0% 16-Jul-17 29
PC.WP.G20 Waterproofing to Garbage Chute- First Delivery 0 0 0% 16-Jul-17 7
PC.AL.610 Metal Doors- First Delivery 0 0 0% 29-Jul-17 37
PC.AL.810 Aluminium Louver- First Delivery 0 0 0% 16-Sep-17 30
PC.AL.210 Aluminium Element- First Delivery 0 0 0% 02-Aug-17 28
PC.AL.360 Aluminium Screen- First Delivery 0 0 0% 10-Jul-17 32
PC.AL.840 Aluminium Channel- First Delivery 0 0 0% 24-Jun-17 26
PC.AL.860 Aluminium Panels- First Delivery 0 0 0% 06-Sep-17 29
PC.FO.280 Reciption Counter- Typical Floor- First Delivery 0 0 0% 04-Nov-17 27
PC.DR.055 Catch Basin- First Delivery 0 0 0% 28-Aug-17 28
PC.DR.115 Sump Pump- First Delivery 0 0 0% 29-Aug-17 27
PC.DR.045 Shower Try- First Delivery 0 0 0% 21-Jun-17 28
PC.AC.115 Ventilation System Fans- First Delivery 0 0 0% 10-Jan-18 -246
PC.FO.410 GRC Work First Delivery 0 0 0% 05-Aug-17 32
PC.EL.L10 Earthing System (Procurement\Placing Order) 7 7 0% 13-Oct-16 19-Oct-16 32
PC.EL.010 Conduits,Boxes (Procurement\Placing Order) 7 7 0% 19-Oct-16 26-Oct-16 35
PC.DR.010 Drainge Pipes \ Fittings (Procurement\Placing Order) 14 14 0% 24-Sep-16 06-Oct-16 39
PC.DR.020 Floor Trap (Procurement\Placing Order) 14 14 0% 08-Feb-17 21-Feb-17 32
PC.WP.F10 Bitumen Coating to Foundation to Foundation (Procurement\Placing
14 Order)14 0% 07-Aug-16 20-Aug-16 31
PC.FL.200 Epoxy Coating (Procurement\Placing Order) 21 21 0% 15-May-17 04-Jun-17 30
PC.WS.020 Water Supply Pipes\Fittings (Procurement\Placing Order)
28 28 0% 06-Dec-16 03-Jan-17 30
PC.WS.030 Water Heaters (Procurement\Placing Order) 28 28 0% 12-Feb-17 09-Mar-17 25
PC.WS.010 Hot and Cold Water Pipes (Procurement\Placing Order)28 28 0% 29-Nov-16 27-Dec-16 32
PC.WS.040 Mixers, Valves, etc. (Procurement\Placing Order) 28 28 0% 10-Jul-17 05-Aug-17 30
PC.WS.050 GRP Water Tank (Procurement\Placing Order) 28 28 0% 17-May-17 12-Jun-17 29
PC.AC.030 Mouse Connection\Fire Damper (Procurement\Placing Order)
28 28 0% 06-Sep-17 02-Oct-17 -245
PC.AC.010 FCU (Procurement\Placing Order) 28 28 0% 03-Jul-17 29-Jul-17 -271
PC.AC.100 Grills,defusers,Isolators,Ext. Fane,etc.. (Procurement\Placing
28 Order) 28 0% 10-Feb-18 07-Mar-18 -245
PC.AC.020 Duct (Procurement\Placing Order) 28 28 0% 03-Jul-17 29-Jul-17 -271
PC.AC.040 Gas Pipes Pipes (Procurement\Placing Order) 28 28 0% 03-Jul-17 29-Jul-17 -271
PC.AC.320 Riser Ducts (Procurement\Placing Order) 28 28 0% 17-Sep-17 12-Oct-17 -246
PC.FF.140 Fire Fighting Riser Pipes (Procurement\Placing Order) 28 28 0% 19-Jun-17 17-Jul-17 28
PC.FF.110 Preaction System (Procurement\Placing Order) 28 28 0% 05-Jun-17 03-Jul-17 29
PC.FF.120 Foam System (Procurement\Placing Order) 28 28 0% 01-Jul-17 26-Jul-17 32

Actual Level of Effort Remaining Work Page 27 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Waterproofing to Roof Deck- First Delivery, 16-Jul-17
Waterproofing to Garbage Chute- First Delivery, 16-Jul-17
Metal Doors- First Delivery, 29-Jul-17
Aluminium Louver- First Delivery, 16-Sep-17
Aluminium Element- First Delivery, 02-Aug-17
Aluminium Screen- First Delivery, 10-Jul-17
Aluminium Channel- First Delivery, 24-Jun-17
Aluminium Panels- First Delivery, 06-Sep-17
Reciption Counter- Typical Floor- First Delivery, 04-Nov-17
Catch Basin- First Delivery, 28-Aug-17
Sump Pump- First Delivery, 29-Aug-17
Shower Try- First Delivery, 21-Jun-17
Ventilation System Fans- First Delivery, 10-Jan-18
GRC Work First Delivery, 05-Aug-17
Earthing System (Procurement\Placing Order)
Conduits,Boxes (Procurement\Placing Order)
Drainge Pipes \ Fittings (Procurement\Placing Order)
Floor Trap (Procurement\Placing Order)
Bitumen Coating to Foundation to Foundation (Procurement\Placing Order)
Epoxy Coating (Procurement\Placing Order)
Water Supply Pipes\Fittings (Procurement\Placing Order)
Water Heaters (Procurement\Placing Order)
Hot and Cold Water Pipes (Procurement\Placing Order)
Mixers, Valves, etc. (Procurement\Placing Order)
GRP Water Tank (Procurement\Placing Order)
Mouse Connection\Fire Damper (Procurement\Placing Order)
FCU (Procurement\Placing Order)
Grills,defusers,Isolators,Ext. Fane,etc.. (Procu
Duct (Procurement\Placing Order)
Gas Pipes Pipes (Procurement\Placing Order)
Riser Ducts (Procurement\Placing Order)
Fire Fighting Riser Pipes (Procurement\Placing Order)
Preaction System (Procurement\Placing Order)
Foam System (Procurement\Placing Order)

Actual Level of Effort Remaining Work Page 28 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PC.FF.010 G.I Fire Fighting Pipes, Valves,etc... (Procurement\Placing
28 Order) 28 0% 26-Dec-16 22-Jan-17 27
PC.FF.020 Sprinklers (Procurement\Placing Order) 28 28 0% 01-Jul-17 26-Jul-17 27
PC.FF.030 Hose Reel\Fire Extinguisher (Procurement\Placing Order)
28 28 0% 05-Jun-17 03-Jul-17 27
PC.FF.150 Fire Pump (Procurement\Placing Order) 28 28 0% 03-May-17 29-May-17 32
PC.EL.L30 ECC Cables (Procurement\Placing Order) 28 28 0% 01-Jul-17 26-Jul-17 33
PC.EL.L50 Cooper Tape\Accessories (Procurement\Placing Order)28 28 0% 29-Jul-17 23-Aug-17 25
PC.EL.L70 Air Terminal Rod (Procurement\Placing Order) 28 28 0% 07-Aug-17 04-Sep-17 23
PC.EL.E20 Isolators (Procurement\Placing Order) 28 28 0% 29-Jan-17 23-Feb-17 29
PC.EL.E90 Emergency Light Control Panel (Procurement\Placing Order)
28 28 0% 19-Jun-17 17-Jul-17 30
PC.EL.E75 Emergency Light (Procurement\Placing Order) 28 28 0% 14-Jun-17 12-Jul-17 31
PC.EL.E60 Sockets, Switchs (Procurement\Placing Order) 28 28 0% 14-Jun-17 12-Jul-17 27
PC.EL.E85 Light Fittings- Boundary Wall (Procurement\Placing Order)
28 28 0% 12-Aug-17 09-Sep-17 20
PC.EL.E70 Light Fittings- Building (Procurement\Placing Order) 28 28 0% 14-Jun-17 12-Jul-17 27
PC.EL.T10 Telephone Cables\Cables Tray (Procurement\Placing Order)
28 28 0% 07-Feb-17 05-Mar-17 30
PC.EL.T20 Telephone Cabinet\ONU (Procurement\Placing Order) 28 28 0% 12-Feb-17 09-Mar-17 29
PC.EL.S10 Security System Control Panels (Procurement\Placing Order)
28 28 0% 05-Jun-17 03-Jul-17 28
PC.EL.S20 Security System Devices (Procurement\Placing Order) 28 28 0% 27-May-17 21-Jun-17 31
PC.EL.F10 Fire Alarm Devices (Procurement\Placing Order) 28 28 0% 17-May-17 12-Jun-17 31
PC.EL.F30 Fire alarm Control Panel (Procurement\Placing Order) 28 28 0% 19-Jul-17 14-Aug-17 26
PC.EL.020 All Types Of Wires (Procurement\Placing Order) 28 28 0% 22-Jan-17 18-Feb-17 29
PC.EL.V20 Desh and Mixer (Procurement\Placing Order) 28 28 0% 01-Jul-17 26-Jul-17 30
PC.EL.V10 Coaxial Cables, Spliter (Procurement\Placing Order) 28 28 0% 10-Jul-17 05-Aug-17 30
PC.DR.100 Riser Drainge Pipes \ Fittings (Procurement\Placing Order)
28 28 0% 22-Dec-16 18-Jan-17 30
PC.DR.R10 Outlet Body (Procurement\Placing Order) 28 28 0% 29-Apr-17 24-May-17 31
PC.DR.R20 Domical Grate (Procurement\Placing Order) 28 28 0% 16-Aug-17 13-Sep-17 19
PC.DR.030 Bath-Tub (Procurement\Placing Order) 28 28 0% 16-Mar-17 11-Apr-17 28
PC.DR.200 Sanitary Wares (Procurement\Placing Order) 28 28 0% 10-Jul-17 05-Aug-17 14
PC.ME.L10 Lift Work (Procurement\Placing Order) 28 28 0% 19-Jan-17 14-Feb-17 27
PC.ME.L40 Marble Jamb (Procurement\Placing Order) 28 28 0% 21-May-17 17-Jun-17 31
PC.WD.400 Wooden Doors to Staircase (Procurement\Placing Order)
28 28 0% 24-Jul-17 19-Aug-17 27
PC.WD.300 Wooden Doors (Procurement\Placing Order) 28 28 0% 03-May-17 29-May-17 33
PC.WD.450 Ironmongery and Accessories to Staircase (Procurement\Placing
28 Order) 28 0% 15-Jul-17 09-Aug-17 37
PC.WD.350 Ironmongery and Accessories (Procurement\Placing Order)
28 28 0% 03-May-17 29-May-17 33
PC.AL.300 Aluminium Canopy (Procurement\Placing Order) 28 28 0% 06-May-17 31-May-17 27

Actual Level of Effort Remaining Work Page 29 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
G.I Fire Fighting Pipes, Valves,etc... (Procurement\Placing Order)
Sprinklers (Procurement\Placing Order)
Hose Reel\Fire Extinguisher (Procurement\Placing Order)
Fire Pump (Procurement\Placing Order)
ECC Cables (Procurement\Placing Order)
Cooper Tape\Accessories (Procurement\Placing Order)
Air Terminal Rod (Procurement\Placing Order)
Isolators (Procurement\Placing Order)
Emergency Light Control Panel (Procurement\Placing Order)
Emergency Light (Procurement\Placing Order)
Sockets, Switchs (Procurement\Placing Order)
Light Fittings- Boundary Wall (Procurement\Placing Order)
Light Fittings- Building (Procurement\Placing Order)
Telephone Cables\Cables Tray (Procurement\Placing Order)
Telephone Cabinet\ONU (Procurement\Placing Order)
Security System Control Panels (Procurement\Placing Order)
Security System Devices (Procurement\Placing Order)
Fire Alarm Devices (Procurement\Placing Order)
Fire alarm Control Panel (Procurement\Placing Order)
All Types Of Wires (Procurement\Placing Order)
Desh and Mixer (Procurement\Placing Order)
Coaxial Cables, Spliter (Procurement\Placing Order)
Riser Drainge Pipes \ Fittings (Procurement\Placing Order)
Outlet Body (Procurement\Placing Order)
Domical Grate (Procurement\Placing Order)
Bath-Tub (Procurement\Placing Order)
Sanitary Wares (Procurement\Placing Order)
Lift Work (Procurement\Placing Order)
Marble Jamb (Procurement\Placing Order)
Wooden Doors to Staircase (Procurement\Placing Order)
Wooden Doors (Procurement\Placing Order)
Ironmongery and Accessories to Staircase (Procurement\Placing Order)
Ironmongery and Accessories (Procurement\Placing Order)
Aluminium Canopy (Procurement\Placing Order)

Actual Level of Effort Remaining Work Page 30 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PC.AL.400 Cat Ladder (Procurement\Placing Order) 28 28 0% 03-Jul-17 29-Jul-17 36
PC.AL.500 Powder Coat Aluminium Fence-Roof (Procurement\Placing
28 Order) 28 0% 08-Jul-17 02-Aug-17 30
PC.AL.S10 Aluminium Louver Doors\Windows (Procurement\Placing
28Order) 28 0% 19-Mar-17 13-Apr-17 32
PC.AL.B10 Balcony Handrails (Procurement\Placing Order) 28 28 0% 17-Jul-17 12-Aug-17 29
PC.AL.T10 Steps Handrail (Procurement\Placing Order) 28 28 0% 12-Jul-17 07-Aug-17 26
PC.AL.100 Aluminium Windows\Doors- Elevations (Procurement\Placing
28 Order) 28 0% 06-May-17 31-May-17 20
PC.AL.150 Aluminium Glazing- Elevations (Procurement\Placing Order)
28 28 0% 24-May-17 19-Jun-17 16
PC.GC.030 Centerifugal Ext. Fan (Procurement\Placing Order) 28 28 0% 19-Jul-17 14-Aug-17 29
PC.GC.010 Grarbage System (Procurement\Placing Order) 28 28 0% 12-Mar-17 06-Apr-17 30
PC.GC.100 Compactor (Procurement\Placing Order) 28 28 0% 02-Aug-17 28-Aug-17 30
PC.GC.200 Garbage Chute Trolley (Procurement\Placing Order) 28 28 0% 12-Aug-17 09-Sep-17 27
PC.PG.020 Copper Pipes (Procurement\Placing Order) 28 28 0% 24-Apr-17 20-May-17 10
PC.PG.030 Switch\Detector\Indicator (Procurement\Placing Order) 28 28 0% 19-Jun-17 17-Jul-17 29
PC.PG.040 Flexible Hose (Procurement\Placing Order) 28 28 0% 19-Jul-17 14-Aug-17 29
PC.PG.100 Gas Alarm Control Panel (Procurement\Placing Order) 28 28 0% 10-Jul-17 05-Aug-17 27
PC.PG.010 LPG Tank (Procurement\Placing Order) 28 28 0% 31-May-17 26-Jun-17 32
PC.PG.050 Explosion Proof Gas Leak Detector (Procurement\Placing
28 Order) 28 0% 14-Jun-17 12-Jul-17 29
PC.PG.070 Pressure Regulating & Dist. Panel (Procurement\Placing28Order) 28 0% 19-Jun-17 17-Jul-17 28
PC.FO.010 Wardrobes (Procurement\Placing Order) 28 28 0% 19-Jul-17 14-Aug-17 29
PC.FO.150 Kitchen Cabinet- (Procurement\Placing Order) 28 28 0% 19-Jun-17 17-Jul-17 20
PC.FO.250 Vanity Counter-Typical Floor (Procurement\Placing Order)
28 28 0% 19-Jun-17 17-Jul-17 20
PC.FO.300 Mirrors For Bath (Procurement\Placing Order) 28 28 0% 15-Jul-17 09-Aug-17 31
PC.FO.500 Remote Control Gate Barrier (Procurement\Placing Order)
28 28 0% 12-Aug-17 09-Sep-17 32
PC.FO.980 Biycle Rack (Procurement\Placing Order) 28 28 0% 21-Aug-17 18-Sep-17 32
PC.AL.700 Tesion Fabric (Procurement\Placing Order) 28 28 0% 20-May-17 14-Jun-17 33
PC.PN.150 Internal Paint to Parking Area (Procurement\Placing Order)
28 28 0% 05-Jan-17 31-Jan-17 33
PC.PN.100 Primer & Stucco (Procurement\Placing Order) 28 28 0% 05-Jan-17 31-Jan-17 31
PC.PN.120 Internal Paint to Buildings (Procurement\Placing Order) 28 28 0% 24-Apr-17 20-May-17 28
PC.PN.250 External Painting (Procurement\Placing Order) 28 28 0% 19-Jun-17 17-Jul-17 33
PC.WP.W10 Waterproofing to Wet area (Procurement\Placing Order)28 28 0% 05-Feb-17 04-Mar-17 36
PC.WP.B10 Waterproofing to Balconies\Terrace (Procurement\Placing
28 Order) 28 0% 06-May-17 01-Jun-17 26
PC.WP.R10 Waterproofing to Roof Deck (Procurement\Placing Order)
28 28 0% 06-May-17 01-Jun-17 29
PC.WP.G10 Waterproofing to Garbage Chute (Procurement\Placing28
Order) 28 0% 06-May-17 01-Jun-17 7
PC.AL.600 Metal Doors (Procurement\Placing Order) 28 28 0% 20-May-17 14-Jun-17 37

Actual Level of Effort Remaining Work Page 31 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Cat Ladder (Procurement\Placing Order)
Powder Coat Aluminium Fence-Roof (Procurement\Placing Order)
Aluminium Louver Doors\Windows (Procurement\Placing Order)
Balcony Handrails (Procurement\Placing Order)
Steps Handrail (Procurement\Placing Order)
Aluminium Windows\Doors- Elevations (Procurement\Placing Order)
Aluminium Glazing- Elevations (Procurement\Placing Order)
Centerifugal Ext. Fan (Procurement\Placing Order)
Grarbage System (Procurement\Placing Order)
Compactor (Procurement\Placing Order)
Garbage Chute Trolley (Procurement\Placing Order)
Copper Pipes (Procurement\Placing Order)
Switch\Detector\Indicator (Procurement\Placing Order)
Flexible Hose (Procurement\Placing Order)
Gas Alarm Control Panel (Procurement\Placing Order)
LPG Tank (Procurement\Placing Order)
Explosion Proof Gas Leak Detector (Procurement\Placing Order)
Pressure Regulating & Dist. Panel (Procurement\Placing Order)
Wardrobes (Procurement\Placing Order)
Kitchen Cabinet- (Procurement\Placing Order)
Vanity Counter-Typical Floor (Procurement\Placing Order)
Mirrors For Bath (Procurement\Placing Order)
Remote Control Gate Barrier (Procurement\Placing Order)
Biycle Rack (Procurement\Placing Order)
Tesion Fabric (Procurement\Placing Order)
Internal Paint to Parking Area (Procurement\Placing Order)
Primer & Stucco (Procurement\Placing Order)
Internal Paint to Buildings (Procurement\Placing Order)
External Painting (Procurement\Placing Order)
Waterproofing to Wet area (Procurement\Placing Order)
Waterproofing to Balconies\Terrace (Procurement\Placing Order)
Waterproofing to Roof Deck (Procurement\Placing Order)
Waterproofing to Garbage Chute (Procurement\Placing Order)
Metal Doors (Procurement\Placing Order)

Actual Level of Effort Remaining Work Page 32 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PC.AL.800 Aluminium Louver (Procurement\Placing Order) 28 28 0% 08-Jul-17 02-Aug-17 30
PC.AL.200 Aluminium Element (Procurement\Placing Order) 28 28 0% 24-May-17 19-Jun-17 28
PC.AL.350 Aluminium Screen (Procurement\Placing Order) 28 28 0% 01-May-17 27-May-17 32
PC.AL.830 Aluminium Channel (Procurement\Placing Order) 28 28 0% 16-Apr-17 13-May-17 26
PC.AL.850 Aluminium Panels (Procurement\Placing Order) 28 28 0% 26-Jun-17 24-Jul-17 29
PC.FO.270 Reciption Counter-Typical Floor (Procurement\Placing Order)
28 28 0% 26-Aug-17 23-Sep-17 27
PC.DR.050 Catch Basin (Procurement\Placing Order) 28 28 0% 19-Jun-17 17-Jul-17 28
PC.DR.110 Sump Pump (Procurement\Placing Order) 28 28 0% 06-Jul-17 01-Aug-17 27
PC.DR.040 Shower Try (Procurement\Placing Order) 28 28 0% 13-Apr-17 10-May-17 28
PC.AC.110 Ventilation System Fans. (Procurement\Placing Order) 28 28 0% 01-Nov-17 27-Nov-17 -246
PC.FO.400 GRC Work (Procurement\Placing Order) 28 28 0% 27-May-17 21-Jun-17 32
PC.WS.070 Transfer Pump (Procurement\Placing Order) 45 45 0% 23-Mar-17 06-May-17 30
PC.WS.060 Booster Pump (Procurement\Placing Order) 45 45 0% 02-Apr-17 15-May-17 30
PC.AC.230 Pressurization Unit (Procurement\Placing Order) 45 45 0% 15-Apr-18 29-May-18 -243
PC.AC.240 Extact Fan (Procurement\Placing Order) 45 45 0% 31-Dec-17 12-Feb-18 -243
PC.AC.200 FAHU (Procurement\Placing Order) 45 45 0% 21-Dec-17 03-Feb-18 -248
PC.EL.E95 Riser Cables\Tray (Procurement\Placing Order) 45 45 0% 10-May-17 21-Jun-17 30
PC.EL.E50 Generator\ATS (Procurement\Placing Order) 45 45 0% 28-Feb-17 11-Apr-17 29
PC.EL.E30 Swich Gear (Procurement\Placing Order) 45 45 0% 14-Feb-17 28-Mar-17 12
PC.EL.E10 Power Cables\Cables Tray (Procurement\Placing Order)
45 45 0% 03-Jan-17 14-Feb-17 30
PC.EL.E40 LV Panel\Capactor Banks (Procurement\Placing Order)45 45 0% 11-Apr-17 24-May-17 28

- Material approvals Through Suppliers 431 431 0% 02-Jul-16 19-Aug-17 34

MC.DW.010 Dewatering (Preparation & Submission) 2 2 0% 18-Jul-16 20-Jul-16 12


MS.CO.100 Steel Reinforcement (Preparation & Submission) 7 7 0% 01-Aug-16 07-Aug-16 34
MS.CO.010 Polythene Sheet (Preparation & Submission) 7 7 0% 01-Aug-16 07-Aug-16 32
MS.BL.200 Block Accessories (Preparation & Submission) 7 7 0% 10-Nov-16 16-Nov-16 10
MS.BL.300 D.P.C (Preparation & Submission) 7 7 0% 10-Nov-16 16-Nov-16 10
MS.BL.100 Hollow\Solid Block (Preparation & Submission) 7 7 0% 09-Jul-16 16-Jul-16 30
MS.FL.X10 Curbstone\Interlock Paving (Prequalification Submission)7 7 0% 03-Jun-17 08-Jun-17 32
MS.CL.010 Tile Grout (Preparation & Submission) 7 7 0% 14-Feb-17 20-Feb-17 29
MS.PL.100 Plaster accesories (Preparation & Submission) 7 7 0% 20-Nov-16 26-Nov-16 25
MS.PL.200 Bounding Agent For External Rendring (Preparation & Submission)
7 7 0% 20-Apr-17 27-Apr-17 31
MC.DW.015 Dewatering (Engineer Review\Approval) 7 7 0% 20-Jul-16 27-Jul-16 12

Actual Level of Effort Remaining Work Page 33 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Aluminium Louver (Procurement\Placing Order)
Aluminium Element (Procurement\Placing Order)
Aluminium Screen (Procurement\Placing Order)
Aluminium Channel (Procurement\Placing Order)
Aluminium Panels (Procurement\Placing Order)
Reciption Counter-Typical Floor (Procurement\Placing Order)
Catch Basin (Procurement\Placing Order)
Sump Pump (Procurement\Placing Order)
Shower Try (Procurement\Placing Order)
Ventilation System Fans. (Procurement\Placing Order)
GRC Work (Procurement\Placing Order)
Transfer Pump (Procurement\Placing Order)
Booster Pump (Procurement\Placing Order)
Pressurization Unit (Pro
Extact Fan (Procurement\Placing Order)
FAHU (Procurement\Placing Order)
Riser Cables\Tray (Procurement\Placing Order)
Generator\ATS (Procurement\Placing Order)
Swich Gear (Procurement\Placing Order)
Power Cables\Cables Tray (Procurement\Placing Order)
LV Panel\Capactor Banks (Procurement\Placing Order)
19-Aug-17, - Material approvals Through Suppliers

Dewatering (Preparation & Submission)


Steel Reinforcement (Preparation & Submission)
Polythene Sheet (Preparation & Submission)
Block Accessories (Preparation & Submission)
D.P.C (Preparation & Submission)
Hollow\Solid Block (Preparation & Submission)
Curbstone\Interlock Paving (Prequalification Submission)
Tile Grout (Preparation & Submission)
Plaster accesories (Preparation & Submission)
Bounding Agent For External Rendring (Preparation & Submission)
Dewatering (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 34 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MS.FO.810 Signage (Engineer Review\Approval) 14 14 0% 13-Jul-17 26-Jul-17 32
MC.SH.015 Shoring Piles Concrete Trial Mix 14 14 0% 02-Jul-16 16-Jul-16 6
MS.CO.110 Steel Reinforcement (Engineer Review\Approval) 14 14 0% 07-Aug-16 20-Aug-16 34
MS.CO.020 Polythene Sheet (Engineer Review\Approval) 14 14 0% 07-Aug-16 20-Aug-16 32
MS.BL.110 Hollow\Solid Block (Engineer Review\Approval) 14 14 0% 16-Jul-16 28-Jul-16 30
MS.BL.210 Block Accessories (Engineer Review\Approval) 14 14 0% 16-Nov-16 29-Nov-16 10
MS.BL.310 D.P.C (Engineer Review\Approval) 14 14 0% 16-Nov-16 29-Nov-16 10
MS.FL.10 Marble Threshold (Engineer Review\Approval) 14 14 0% 29-Jun-17 12-Jul-17 30
MS.FL.X20 Curbstone\Interlock Paving (Engineer Review\Approval)14 14 0% 08-Jun-17 21-Jun-17 32
MS.FL.G20 Floor Tiles For Garbage Chute (Engineer Review\Approval)
14 14 0% 11-May-17 24-May-17 35
MS.FL.B20 Floor Tiles For Balcony (Engineer Review\Approval) 14 14 0% 25-Apr-17 08-May-17 31
MS.FL.R25 Mastic Joint (Engineer Review\Approval) 14 14 0% 05-Aug-17 19-Aug-17 34
MS.FL.R10 Roof Cement Tiles (Preparation & Submission) 14 14 0% 15-May-17 28-May-17 31
MS.FL.R15 Roof Cement Tiles (Engineer Review\Approval) 14 14 0% 28-May-17 10-Jun-17 31
MS.FL.D40 Floor Tiles For Dry Area (Engineer Review\Approval) 14 14 0% 17-Apr-17 01-May-17 12
MS.FL.W40 Floor Tiles For Wet Area (Engineer Review\Approval) 14 14 0% 11-Apr-17 25-Apr-17 3
MS.FL.C20 Floor Tiles For Corridors\Lift Lobby (Engineer Review\Approval)
14 14 0% 22-Mar-17 04-Apr-17 26
MS.FL.E20 Floor Tiles For Entrance\Lift Lobby (Engineer Review\Approval)
14 14 0% 10-Apr-17 24-Apr-17 25
MS.CL.020 Tile Grout (Engineer Review\Approval) 14 14 0% 20-Feb-17 05-Mar-17 29
MS.CL.V20 External Cladding (Engineer Review\Approval) 14 14 0% 30-Apr-17 13-May-17 26
MS.CL.W40 Wall Tiles For Wet Area- Typical Floor (Engineer Review\Approval)
14 14 0% 25-Jan-17 07-Feb-17 38
MS.CL.G20 Wall Tiles For Garbage Room (Engineer Review\Approval)
14 14 0% 22-Apr-17 06-May-17 28
MS.CL.E20 Wall Tiles- Entrance\Lift Lobby (Engineer Review\Approval)
14 14 0% 25-Mar-17 06-Apr-17 28
MS.PL.110 Plaster accesories (Engineer Review\Approval) 14 14 0% 26-Nov-16 08-Dec-16 25
MS.PL.210 Bounding Agent For External Rendring (Engineer Review\Approval)
14 14 0% 27-Apr-17 10-May-17 31
MS.FO.830 Convex Mirror (Engineer Review\Approval) 14 14 0% 26-Jul-17 09-Aug-17 33
MS.FO.210 Corner Guard (Engineer Review\Approval) 14 14 0% 08-Jul-17 22-Jul-17 29
MS.FO.310 Parking Stopper (Engineer Review\Approval) 14 14 0% 17-Jul-17 31-Jul-17 26
MC.FC.D20 False Ceiling to Dry Area (Engineer Review\Approval) 14 14 0% 22-Apr-17 06-May-17 16
MC.FC.C20 False Ceiling to Corridors\Lift Lobby (Engineer Review\Approval)
14 14 0% 27-Mar-17 09-Apr-17 26
MC.FC.W20 False Ceiling to Wet Area (Engineer Review\Approval) 14 14 0% 22-Apr-17 06-May-17 3
MS.CL.C20 Wall Tiles- Corridor\Lift Lobby (Engineer Review\Approval)
14 14 0% 18-Jan-17 31-Jan-17 26
MC.FC.E20 False Ceiling to Entrance\Lift Lobby (Engineer Review\Approval)
14 14 0% 19-Apr-17 03-May-17 29
MS.FO.800 Signage (Preparation & Submission) 21 21 0% 21-Jun-17 13-Jul-17 32

Actual Level of Effort Remaining Work Page 35 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Signage (Engineer Review\Approval)
Shoring Piles Concrete Trial Mix
Steel Reinforcement (Engineer Review\Approval)
Polythene Sheet (Engineer Review\Approval)
Hollow\Solid Block (Engineer Review\Approval)
Block Accessories (Engineer Review\Approval)
D.P.C (Engineer Review\Approval)
Marble Threshold (Engineer Review\Approval)
Curbstone\Interlock Paving (Engineer Review\Approval)
Floor Tiles For Garbage Chute (Engineer Review\Approval)
Floor Tiles For Balcony (Engineer Review\Approval)
Mastic Joint (Engineer Review\Approval)
Roof Cement Tiles (Preparation & Submission)
Roof Cement Tiles (Engineer Review\Approval)
Floor Tiles For Dry Area (Engineer Review\Approval)
Floor Tiles For Wet Area (Engineer Review\Approval)
Floor Tiles For Corridors\Lift Lobby (Engineer Review\Approval)
Floor Tiles For Entrance\Lift Lobby (Engineer Review\Approval)
Tile Grout (Engineer Review\Approval)
External Cladding (Engineer Review\Approval)
Wall Tiles For Wet Area- Typical Floor (Engineer Review\Approval)
Wall Tiles For Garbage Room (Engineer Review\Approval)
Wall Tiles- Entrance\Lift Lobby (Engineer Review\Approval)
Plaster accesories (Engineer Review\Approval)
Bounding Agent For External Rendring (Engineer Review\Approval)
Convex Mirror (Engineer Review\Approval)
Corner Guard (Engineer Review\Approval)
Parking Stopper (Engineer Review\Approval)
False Ceiling to Dry Area (Engineer Review\Approval)
False Ceiling to Corridors\Lift Lobby (Engineer Review\Approval)
False Ceiling to Wet Area (Engineer Review\Approval)
Wall Tiles- Corridor\Lift Lobby (Engineer Review\Approval)
False Ceiling to Entrance\Lift Lobby (Engineer Review\Approval)
Signage (Preparation & Submission)

Actual Level of Effort Remaining Work Page 36 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
MS.FL.010 Marble Threshold (Preparation & Submission) 21 21 0% 07-Jun-17 29-Jun-17 30
MS.FL.G10 Floor Tiles For Garbage Chute (Preparation & Submission)
21 21 0% 20-Apr-17 11-May-17 35
MS.FL.R20 Mastic Joint (Preparation & Submission) 21 21 0% 17-Jul-17 05-Aug-17 34
MS.CL.G10 Wall Tiles For Garbage Room (Preparation & Submission)
21 21 0% 02-Apr-17 22-Apr-17 28
MS.CL.E10 Wall Tiles- Entrance\Lift Lobby (Preparation & Submission)
21 21 0% 05-Mar-17 25-Mar-17 28
MS.FO.820 Convex Mirror (Preparation & Submission) 21 21 0% 08-Jul-17 26-Jul-17 33
MS.FO.200 Corner Guard (Preparation & Submission) 21 21 0% 17-Jun-17 08-Jul-17 29
MS.FO.300 Parking Stopper (Preparation & Submission) 21 21 0% 26-Jun-17 17-Jul-17 26
MS.CL.C10 Wall Tiles- Corridor\Lift Lobby (Preparation & Submission)
21 21 0% 28-Dec-16 18-Jan-17 26
MS.FL.B10 Floor Tiles For Balcony (Preparation & Submission) 28 28 0% 28-Mar-17 25-Apr-17 31
MS.FL.D30 Floor Tiles For Dry Area (Preparation & Submission) 28 28 0% 22-Mar-17 17-Apr-17 12
MS.FL.W30 Floor Tiles For Wet Area (Preparation & Submission) 28 28 0% 15-Mar-17 11-Apr-17 3
MS.FL.C10 Floor Tiles For Corridors\Lift Lobby (Preparation & Submission)
28 28 0% 23-Feb-17 22-Mar-17 26
MS.FL.E10 Floor Tiles For Entrance\Lift Lobby (Preparation & Submission)
28 28 0% 14-Mar-17 10-Apr-17 25
MS.CL.V10 External Cladding (Preparation & Submission) 28 28 0% 02-Apr-17 30-Apr-17 26
MS.CL.W30 Wall Tiles For Wet Area- Typical Floor (Preparation & Submission)
28 28 0% 28-Dec-16 25-Jan-17 38
MC.FC.D10 False Ceiling to Dry Area (Preparation & Submission) 28 28 0% 27-Mar-17 22-Apr-17 16
MC.FC.C10 False Ceiling to Corridors\Lift Lobby (Preparation & Submission)
28 28 0% 28-Feb-17 27-Mar-17 26
MC.FC.W10 False Ceiling to Wet Area (Preparation & Submission) 28 28 0% 27-Mar-17 22-Apr-17 3
MC.FC.E10 False Ceiling to Entrance\Lift Lobby (Preparation & Submission)
28 28 0% 23-Mar-17 19-Apr-17 29

- Procurement Material Through Suppliers 461 461 0% 27-Jul-16 11-Oct-17 33

PS.FO.810 Signage- Delivery 0 0 0% 28-Sep-17 32


PS.FO.830 Convex Mirror- First Delivery 0 0 0% 11-Oct-17 33
PS.FO.210 Corner Guard- First Delivery 0 0 0% 23-Sep-17 29
PS.FO.310 Parking Stopper- First Delivery 0 0 0% 02-Oct-17 26
PS.CL.020 Tile Grout- First Delivery 0 0 0% 06-Apr-17 29
PS.CL.G20 Wall Tiles For Garbage Room- First Delivery 0 0 0% 09-Jul-17 28
PS.CL.W40 Wall Tiles For Typical Floor- First Delivery 0 0 0% 03-Apr-17 38
PS.CL.V20 External Cladding- First Delivery 0 0 0% 22-Jul-17 26
PS.CL.E20 Wall Tiles- Entrance\Lift Lobby- G. Floor- First Delivery 0 0 0% 15-Jun-17 28
PS.FL.011 Marble Threshold 2 cm- First Delivery 0 0 0% 21-Sep-17 30
PS.FL.B20 Floor Tiles For Balcony- First Delivery 0 0 0% 17-Jul-17 31
PS.FL.G20 Floor Tiles For Garbage Chute- First Delivery 0 0 0% 12-Jul-17 35

Actual Level of Effort Remaining Work Page 37 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Marble Threshold (Preparation & Submission)
Floor Tiles For Garbage Chute (Preparation & Submission)
Mastic Joint (Preparation & Submission)
Wall Tiles For Garbage Room (Preparation & Submission)
Wall Tiles- Entrance\Lift Lobby (Preparation & Submission)
Convex Mirror (Preparation & Submission)
Corner Guard (Preparation & Submission)
Parking Stopper (Preparation & Submission)
Wall Tiles- Corridor\Lift Lobby (Preparation & Submission)
Floor Tiles For Balcony (Preparation & Submission)
Floor Tiles For Dry Area (Preparation & Submission)
Floor Tiles For Wet Area (Preparation & Submission)
Floor Tiles For Corridors\Lift Lobby (Preparation & Submission)
Floor Tiles For Entrance\Lift Lobby (Preparation & Submission)
External Cladding (Preparation & Submission)
Wall Tiles For Wet Area- Typical Floor (Preparation & Submission)
False Ceiling to Dry Area (Preparation & Submission)
False Ceiling to Corridors\Lift Lobby (Preparation & Submission)
False Ceiling to Wet Area (Preparation & Submission)
False Ceiling to Entrance\Lift Lobby (Preparation & Submission)
11-Oct-17, - Procurement Material Through Suppliers

Signage- Delivery, 28-Sep-17


Convex Mirror- First Delivery, 11-Oct-17
Corner Guard- First Delivery, 23-Sep-17
Parking Stopper- First Delivery, 02-Oct-17
Tile Grout- First Delivery, 06-Apr-17
Wall Tiles For Garbage Room- First Delivery, 09-Jul-17
Wall Tiles For Typical Floor- First Delivery, 03-Apr-17
External Cladding- First Delivery, 22-Jul-17
Wall Tiles- Entrance\Lift Lobby- G. Floor- First Delivery, 15-Jun-17
Marble Threshold 2 cm- First Delivery, 21-Sep-17
Floor Tiles For Balcony- First Delivery, 17-Jul-17
Floor Tiles For Garbage Chute- First Delivery, 12-Jul-17

Actual Level of Effort Remaining Work Page 38 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PS.FL.R25 Mastic Joint- First Delivery 0 0 0% 07-Oct-17 34
PS.FL.R15 Roof Cement Tiles- First Delivery 0 0 0% 27-Jul-17 31
PS.FL.X20 Kerb Stone\Interlock Paving- First Delivery 0 0 0% 24-Aug-17 32
PS.FL.C40 Floor Tiles For Corridor\Lift Labby- First Delivery 0 0 0% 12-Jun-17 26
PS.FL.W40 Floor Tiles For Wet Area- First Delivery 0 0 0% 04-Jul-17 3
PS.FL.D40 Floor Tiles For Dry Area- First Delivery 0 0 0% 11-Jul-17 12
PS.FL.E20 Floor Tiles For Entrance\Lift Labby- First Delivery 0 0 0% 03-Jul-17 25
PS.PL.110 Plaster accesories- First Delivery 0 0 0% 12-Jan-17 25
PS.PL.210 Bounding Agent For External Rendring- First Delivery 0 0 0% 12-Jun-17 31
PS.CO.110 Steel Reinforcement- First Delivery 0 0 0% 08-Sep-16 34
PS.CO.020 Polythene Sheet- First Delivery 0 0 0% 03-Sep-16 32
PS.BL.110 Hollow\Solid Block- First Delivery 0 0 0% 06-Sep-16 30
PS.BL.210 Block Accessories- First Delivery 0 0 0% 10-Jan-17 10
PS.BL.310 D.P.C- First Delivery 0 0 0% 10-Jan-17 10
PC.FC.D20 False Ceiling to Dry Area- First Delivery 0 0 0% 16-Jul-17 16
PC.FC.C20 False Ceiling to Corridors\Lift Lobby- First Delivery 0 0 0% 17-Jun-17 26
PC.FC.W20 False Ceiling to Wet Area- First Delivery 0 0 0% 16-Jul-17 3
PC.DW.015 Dewatering- First Delivery 0 0 0% 18-Aug-16 12
PS.CL.C20 Wall Tiles- Corridor\Lift Lobby-Typical Floor- First Delivery0 0 0% 10-Apr-17 26
PC.FC.E20 False Ceiling toEntrance\Lift Lobby- First Delivery 0 0 0% 12-Jul-17 29
PS.CO.100 Steel Reinforcement (Procurement\Placing Order) 7 7 0% 20-Aug-16 27-Aug-16 34
PS.CO.010 Polythene Sheet (Procurement\Placing Order) 7 7 0% 20-Aug-16 27-Aug-16 32
PC.DW.010 Dewatering (Procurement\Placing Order) 7 7 0% 27-Jul-16 02-Aug-16 12
PS.CL.010 Tile Grout (Procurement\Placing Order) 14 14 0% 05-Mar-17 19-Mar-17 29
PS.PL.100 Plaster accesories (Procurement\Placing Order) 14 14 0% 08-Dec-16 24-Dec-16 25
PS.PL.200 Bounding Agent For External Rendring (Procurement\Placing
14 Order) 14 0% 10-May-17 24-May-17 31
PS.FO.800 Signage (Procurement\Placing Order) 21 21 0% 26-Jul-17 15-Aug-17 32
PS.FO.820 Convex Mirror (Procurement\Placing Order) 21 21 0% 09-Aug-17 28-Aug-17 33
PS.FO.200 Corner Guard (Procurement\Placing Order) 21 21 0% 22-Jul-17 09-Aug-17 29
PS.FO.300 Parking Stopper (Procurement\Placing Order) 21 21 0% 31-Jul-17 19-Aug-17 26
PS.CL.G10 Wall Tiles For Garbage Room (Procurement\Placing Order)
21 21 0% 06-May-17 25-May-17 28
PS.FL.G10 Floor Tiles For Garbage Chute (Procurement\Placing Order)
21 21 0% 24-May-17 13-Jun-17 35
PS.FL.R20 Mastic Joint (Procurement\Placing Order) 21 21 0% 19-Aug-17 09-Sep-17 34
PS.FL.R10 Roof Cement Tiles (Procurement\Placing Order) 21 21 0% 10-Jun-17 02-Jul-17 31

Actual Level of Effort Remaining Work Page 39 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Mastic Joint- First Delivery, 07-Oct-17
Roof Cement Tiles- First Delivery, 27-Jul-17
Kerb Stone\Interlock Paving- First Delivery, 24-Aug-17
Floor Tiles For Corridor\Lift Labby- First Delivery, 12-Jun-17
Floor Tiles For Wet Area- First Delivery, 04-Jul-17
Floor Tiles For Dry Area- First Delivery, 11-Jul-17
Floor Tiles For Entrance\Lift Labby- First Delivery, 03-Jul-17
Plaster accesories- First Delivery, 12-Jan-17
Bounding Agent For External Rendring- First Delivery, 12-Jun-17
Steel Reinforcement- First Delivery, 08-Sep-16
Polythene Sheet- First Delivery, 03-Sep-16
Hollow\Solid Block- First Delivery, 06-Sep-16
Block Accessories- First Delivery, 10-Jan-17
D.P.C- First Delivery, 10-Jan-17
False Ceiling to Dry Area- First Delivery, 16-Jul-17
False Ceiling to Corridors\Lift Lobby- First Delivery, 17-Jun-17
False Ceiling to Wet Area- First Delivery, 16-Jul-17
Dewatering- First Delivery, 18-Aug-16
Wall Tiles- Corridor\Lift Lobby-Typical Floor- First Delivery, 10-Apr-17
False Ceiling toEntrance\Lift Lobby- First Delivery, 12-Jul-17
Steel Reinforcement (Procurement\Placing Order)
Polythene Sheet (Procurement\Placing Order)
Dewatering (Procurement\Placing Order)
Tile Grout (Procurement\Placing Order)
Plaster accesories (Procurement\Placing Order)
Bounding Agent For External Rendring (Procurement\Placing Order)
Signage (Procurement\Placing Order)
Convex Mirror (Procurement\Placing Order)
Corner Guard (Procurement\Placing Order)
Parking Stopper (Procurement\Placing Order)
Wall Tiles For Garbage Room (Procurement\Placing Order)
Floor Tiles For Garbage Chute (Procurement\Placing Order)
Mastic Joint (Procurement\Placing Order)
Roof Cement Tiles (Procurement\Placing Order)

Actual Level of Effort Remaining Work Page 40 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
PS.FL.X10 Kerb Stone\Interlock Paving (Procurement\Placing Order)
21 21 0% 21-Jun-17 13-Jul-17 32
PS.BL.300 D.P.C (Procurement\Placing Order) 21 21 0% 29-Nov-16 20-Dec-16 10
PS.BL.100 Hollow\Solid Block (Procurement\Placing Order) 21 21 0% 28-Jul-16 17-Aug-16 30
PS.BL.200 Block Accessories (Procurement\Placing Order) 21 21 0% 29-Nov-16 20-Dec-16 10
PS.CL.W30 Wall Tiles For Typical Floor (Procurement\Placing Order)
28 28 0% 07-Feb-17 05-Mar-17 38
PS.CL.V10 External Cladding (Procurement\Placing Order) 28 28 0% 13-May-17 07-Jun-17 26
PS.CL.E10 Wall Tiles- Enrance\Lift Lobby- G. Floor (Procurement\Placing
28 Order) 28 0% 06-Apr-17 04-May-17 28
PS.FL.010 Marble Threshold 2 cm (Procurement\Placing Order) 28 28 0% 12-Jul-17 08-Aug-17 30
PS.FL.B10 Floor Tiles For Balcony (Procurement\Placing Order) 28 28 0% 08-May-17 03-Jun-17 31
PS.FL.C30 Floor Tiles For Corridor\Lift Labby (Procurement\Placing28
Order) 28 0% 04-Apr-17 01-May-17 26
PS.FL.W30 Floor Tiles For Wet Area (Procurement\Placing Order) 28 28 0% 25-Apr-17 21-May-17 3
PS.FL.D30 Floor Tiles For Dry Area (Procurement\Placing Order) 28 28 0% 01-May-17 28-May-17 12
PS.FL.E10 Floor Tiles For Entrance\Lift Labby (Procurement\Placing
28Order) 28 0% 24-Apr-17 20-May-17 25
PC.FC.D10 False Ceiling to Dry Area (Procurement\Placing Order) 28 28 0% 06-May-17 01-Jun-17 16
PC.FC.C10 False Ceiling to Corridors\Lift Lobby (Procurement\Placing
28 Order) 28 0% 09-Apr-17 06-May-17 26
PC.FC.W10 False Ceiling to Wet Area (Procurement\Placing Order) 28 28 0% 06-May-17 01-Jun-17 3
PS.CL.C10 Wall Tiles- Corridor\Lift Lobby- Typical Floor (Procurement\Placing
28 Order) 28 0% 31-Jan-17 27-Feb-17 26
PC.FC.E10 False Ceiling to Entrance\Lift Lobby (Procurement\Placing
28 Order) 28 0% 03-May-17 29-May-17 29

- Shop Drawing 609 609 0% 25-Jun-16 29-Jan-18 -63

SD.SH.010 Shoring Work (Preparation & Submission) 1 1 0% 25-Jun-16 26-Jun-16 2 Shoring Work (Prep
SD.DW.010 Dewatering (Preparation & Submission) 3 3 0% 02-Aug-16 06-Aug-16 12
SD.DR.030 Drainage Work Layout Plan- Ground Floor (Preparation &7 Submission) 7 0% 29-Sep-16 06-Oct-16 28
SD.FF.020 Fire Protection Layout Plan- Ground Floor (Preparation &7Submission) 7 0% 29-Sep-16 06-Oct-16 28
SD.BW.040 Builders Work Drawing-Ground Floor (Preparation & Submission)
7 7 0% 09-Jul-17 16-Jul-17 -247
SD.BW.050 Builders Work Drawing- Typical Floor (Preparation & Submission)
7 7 0% 23-Aug-17 30-Aug-17 -271
SD.AC.020 A.C & Ventilation Layout Plan- Ground Floor (Preparation7& Submission) 7 0% 17-Jun-17 24-Jun-17 -247
SD.WS.020 Water Supply Layout Plan- Ground Floor (Preparation & Submission)
7 7 0% 29-Sep-16 06-Oct-16 28
SD.BL.200 Block Layout to G. Floor (Preparation & Submission) 7 7 0% 08-Dec-16 15-Dec-16 30
SD.BL.100 Block Layout to Basement Floor (Preparation & Submission)
7 7 0% 29-Nov-16 05-Dec-16 32
SD.BL.400 Block Layout to Typical Floor (Preparation & Submission)7 7 0% 19-Dec-16 25-Dec-16 32
SD.CO.100 Reinforcement Detail to Foundation (Preparation & Submission)
7 7 0% 29-Sep-16 05-Oct-16 30
SD.CO.900 Reinforcement Detail to Roof Floor Slab (Preparation & Submission)
7 7 0% 11-Apr-17 17-Apr-17 29
SD.CO.400 Reinforcement Detail to G.Floor Slab (Preparation & Submission)
7 7 0% 27-Oct-16 02-Nov-16 20

Actual Level of Effort Remaining Work Page 41 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Kerb Stone\Interlock Paving (Procurement\Placing Order)
D.P.C (Procurement\Placing Order)
Hollow\Solid Block (Procurement\Placing Order)
Block Accessories (Procurement\Placing Order)
Wall Tiles For Typical Floor (Procurement\Placing Order)
External Cladding (Procurement\Placing Order)
Wall Tiles- Enrance\Lift Lobby- G. Floor (Procurement\Placing Order)
Marble Threshold 2 cm (Procurement\Placing Order)
Floor Tiles For Balcony (Procurement\Placing Order)
Floor Tiles For Corridor\Lift Labby (Procurement\Placing Order)
Floor Tiles For Wet Area (Procurement\Placing Order)
Floor Tiles For Dry Area (Procurement\Placing Order)
Floor Tiles For Entrance\Lift Labby (Procurement\Placing Order)
False Ceiling to Dry Area (Procurement\Placing Order)
False Ceiling to Corridors\Lift Lobby (Procurement\Placing Order)
False Ceiling to Wet Area (Procurement\Placing Order)
Wall Tiles- Corridor\Lift Lobby- Typical Floor (Procurement\Placing Order)
False Ceiling to Entrance\Lift Lobby (Procurement\Placing Order)
29-Jan-18, - Shop Drawing

Shoring Work (Preparation & Submission)


Dewatering (Preparation & Submission)
Drainage Work Layout Plan- Ground Floor (Preparation & Submission)
Fire Protection Layout Plan- Ground Floor (Preparation & Submission)
Builders Work Drawing-Ground Floor (Preparation & Submission)
Builders Work Drawing- Typical Floor (Preparation & Submission)
A.C & Ventilation Layout Plan- Ground Floor (Preparation & Submission)
Water Supply Layout Plan- Ground Floor (Preparation & Submission)
Block Layout to G. Floor (Preparation & Submission)
Block Layout to Basement Floor (Preparation & Submission)
Block Layout to Typical Floor (Preparation & Submission)
Reinforcement Detail to Foundation (Preparation & Submission)
Reinforcement Detail to Roof Floor Slab (Preparation & Submission)
Reinforcement Detail to G.Floor Slab (Preparation & Submission)

Actual Level of Effort Remaining Work Page 42 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.CO.800 Reinforcement Detail to Typical Floor Slab (Preparation &7Submission) 7 0% 10-Nov-16 16-Nov-16 30
SD.CO.200 Reinforcement Detail Columns (Preparation & Submission)
7 7 0% 13-Oct-16 19-Oct-16 30
SD.SH.015 Shoring Work (Engineer Review\Approval) 7 7 0% 26-Jun-16 03-Jul-16 2
MC.SH.010 Preparation to Concrete Trial Mix 7 7 0% 25-Jun-16 02-Jul-16 6
SD.EL.L40 Layout Plans & Schematic Layout (Engineer Review\Approval)
14 14 0% 15-Nov-16 28-Nov-16 32
SD.EL.L30 Layout Plans & Schematic Layout (Preparation & Submission)
14 14 0% 01-Nov-16 15-Nov-16 32
SD.EL.T75 Riser Diagram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.EL.T55 Tepehone System Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 15-Mar-17 28-Mar-17 29
SD.EL.T15 Telephone System Layout Plan- Basement Floor (Engineer
14 Review\Approval)
14 0% 27-Oct-16 09-Nov-16 32
SD.EL.T25 Telephone System Layout Plan- Ground Floor (Engineer14
Review\Approval)14 0% 06-Oct-16 19-Oct-16 28
SD.EL.T45 Tepehone System Layout Plan- Typical Floor (Engineer 14
Review\Approval) 14 0% 27-Oct-16 09-Nov-16 31
SD.EL.T10 Telephone System Layout Plan- Basement Floor (Preparation
14 & Submission)
14 0% 13-Oct-16 27-Oct-16 32
SD.EL.T40 Tepehone System Layout Plan- Typical Floor (Preparation
14 & Submission) 14 0% 13-Oct-16 27-Oct-16 31
SD.EL.E15 Lighting\Power Layout Plan- Basement Floor (Engineer 14
Review\Approval) 14 0% 29-Oct-16 10-Nov-16 30
SD.EL.E25 Lighting\Power Layout Plan- G. Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.EL.E45 Lighting\Power Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.EL.E65 Lighting\Power Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 19-Mar-17 01-Apr-17 26
SD.EL.E75 Power Cable Tray Layout (Engineer Review\Approval) 14 14 0% 08-Jan-17 21-Jan-17 30
SD.EL.E20 Lighting\Power Layout Plan- G. Floor (Preparation & Submission)
14 14 0% 24-Sep-16 06-Oct-16 28
SD.EL.E40 Lighting\Power Layout Plan- Typical Floor (Preparation &14Submission) 14 0% 13-Oct-16 27-Oct-16 31
SD.EL.E60 Lighting\Power Layout Plan- Roof Floor (Preparation & Submission)
14 14 0% 05-Mar-17 19-Mar-17 26
SD.EL.E70 Power Cable Tray Layout (Preparation & Submission) 14 14 0% 24-Dec-16 08-Jan-17 30
SD.EL.F75 Riser Diagram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.EL.F55 Fire Alarm Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 15-Mar-17 28-Mar-17 29
SD.EL.F15 Fire Alarm Layout Plan- Basement Floor (Engineer Review\Approval)
14 14 0% 29-Oct-16 10-Nov-16 30
SD.EL.F25 Fire Alarm Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.EL.F45 Fire Alarm Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.EL.F40 Fire Alarm Layout Plan- Typical Floor (Preparation & Submission)
14 14 0% 13-Oct-16 27-Oct-16 31
SD.EL.V15 Layout Plans & Schematic Layout (Engineer Review\Approval)
14 14 0% 24-Aug-17 09-Sep-17 30
SD.EL.S55 Security System Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 15-Mar-17 28-Mar-17 29
SD.EL.S15 Security System Layout Plan- Basement Floor (Engineer14Review\Approval)14 0% 27-Oct-16 09-Nov-16 32
SD.EL.S45 Security System Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.EL.S10 Security System Layout Plan- Basement Floor (Preparation
14 & Submission)14 0% 13-Oct-16 27-Oct-16 32
SD.EL.S40 Security System Layout Plan- Typical Floor (Preparation14
& Submission) 14 0% 13-Oct-16 27-Oct-16 31

Actual Level of Effort Remaining Work Page 43 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Reinforcement Detail to Typical Floor Slab (Preparation & Submission)
Reinforcement Detail Columns (Preparation & Submission)
Shoring Work (Engineer Review\Approval)
Preparation to Concrete Trial Mix
Layout Plans & Schematic Layout (Engineer Review\Approval)
Layout Plans & Schematic Layout (Preparation & Submission)
Riser Diagram (Engineer Review\Approval)
Tepehone System Layout Plan- Roof Floor (Engineer Review\Approval)
Telephone System Layout Plan- Basement Floor (Engineer Review\Approval)
Telephone System Layout Plan- Ground Floor (Engineer Review\Approval)
Tepehone System Layout Plan- Typical Floor (Engineer Review\Approval)
Telephone System Layout Plan- Basement Floor (Preparation & Submission)
Tepehone System Layout Plan- Typical Floor (Preparation & Submission)
Lighting\Power Layout Plan- Basement Floor (Engineer Review\Approval)
Lighting\Power Layout Plan- G. Floor (Engineer Review\Approval)
Lighting\Power Layout Plan- Typical Floor (Engineer Review\Approval)
Lighting\Power Layout Plan- Roof Floor (Engineer Review\Approval)
Power Cable Tray Layout (Engineer Review\Approval)
Lighting\Power Layout Plan- G. Floor (Preparation & Submission)
Lighting\Power Layout Plan- Typical Floor (Preparation & Submission)
Lighting\Power Layout Plan- Roof Floor (Preparation & Submission)
Power Cable Tray Layout (Preparation & Submission)
Riser Diagram (Engineer Review\Approval)
Fire Alarm Layout Plan- Roof Floor (Engineer Review\Approval)
Fire Alarm Layout Plan- Basement Floor (Engineer Review\Approval)
Fire Alarm Layout Plan- Ground Floor (Engineer Review\Approval)
Fire Alarm Layout Plan- Typical Floor (Engineer Review\Approval)
Fire Alarm Layout Plan- Typical Floor (Preparation & Submission)
Layout Plans & Schematic Layout (Engineer Review\Approval)
Security System Layout Plan- Roof Floor (Engineer Review\Approval)
Security System Layout Plan- Basement Floor (Engineer Review\Approval)
Security System Layout Plan- Typical Floor (Engineer Review\Approval)
Security System Layout Plan- Basement Floor (Preparation & Submission)
Security System Layout Plan- Typical Floor (Preparation & Submission)

Actual Level of Effort Remaining Work Page 44 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.EL.S75 Riser Diagram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.EL.S25 Security System Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.EL.S20 Security System Layout Plan- Ground Floor (Preparation14& Submission) 14 0% 24-Sep-16 06-Oct-16 28
SD.EL.C55 Central Battery Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 15-Mar-17 28-Mar-17 29
SD.EL.C15 Central Battery Layout Plan- Basement Floor (Engineer 14
Review\Approval) 14 0% 27-Oct-16 09-Nov-16 32
SD.EL.C45 Central Battery Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.EL.C10 Central Battery Layout Plan- Basement Floor (Preparation
14 & Submission) 14 0% 13-Oct-16 27-Oct-16 32
SD.EL.C40 Central Battery Layout Plan- Typical Floor (Preparation &
14Submission) 14 0% 13-Oct-16 27-Oct-16 31
SD.EL.C75 Riser Diagram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.EL.C25 Central Battery Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.EL.C20 Central Battery Layout Plan- Ground Floor (Preparation 14
& Submission) 14 0% 24-Sep-16 06-Oct-16 28
SD.DR.015 Drainage Work Layout Plan- Foundation (Engineer Review\Approval)
14 14 0% 07-Sep-16 24-Sep-16 29
SD.DR.010 Drainage Work Layout Plan- Foundation (Preparation & 14
Submission) 14 0% 24-Aug-16 07-Sep-16 29
SD.DR.025 Drainage Work Layout Plan- Basement Floor (Engineer 14
Review\Approval) 14 0% 29-Oct-16 10-Nov-16 30
SD.DR.085 Riser Didgram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.DR.035 Drainage Work Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.DR.065 Drainage Work Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.DR.075 Drainage Work Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 01-Mar-17 14-Mar-17 30
SD.DR.060 Drainage Work Layout Plan- Typical Floor (Preparation &
14Submission) 14 0% 13-Oct-16 27-Oct-16 31
SD.FF.015 Fire Protection Layout Plan- Basement Floor (Engineer 14
Review\Approval) 14 0% 27-Oct-16 09-Nov-16 32
SD.FF.055 Fire Protection Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 15-Mar-17 28-Mar-17 29
SD.FF.075 Riser Pipes Diagram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.FF.025 Fire Protection Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.FF.045 Fire Protection Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.FF.010 Fire Protection Layout Plan- Basement Floor (Preparation
14 & Submission) 14 0% 13-Oct-16 27-Oct-16 32
SD.FF.040 Fire Protection Layout Plan- Typical Floor (Preparation &14Submission) 14 0% 13-Oct-16 27-Oct-16 31
SD.BW.015 Builders Work Drawing-Foundation (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 29
SD.BW.010 Builders Work Drawing-Foundation (Preparation & Submission)
14 14 0% 24-Sep-16 06-Oct-16 29
SD.BW.045 Builders Work Drawing-Ground Floor (Engineer Review\Approval)
14 14 0% 16-Jul-17 29-Jul-17 -247
SD.BW.055 Builders Work Drawing- Typical Floor (Engineer Review\Approval)
14 14 0% 30-Aug-17 14-Sep-17 -271
SD.BW.065 Builders Work Drawing- Roof Floor (Engineer Review\Approval)
14 14 0% 10-Jan-18 23-Jan-18 -249
SD.AC.015 A.C & Ventilation Layout Plan- Basement Floor (Engineer14Review\Approval)14 0% 17-Jul-17 30-Jul-17 -243
SD.AC.025 A.C & Ventilation Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 24-Jun-17 09-Jul-17 -247
SD.AC.045 A.C & Ventilation Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 10-Aug-17 23-Aug-17 -271

Actual Level of Effort Remaining Work Page 45 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Riser Diagram (Engineer Review\Approval)
Security System Layout Plan- Ground Floor (Engineer Review\Approval)
Security System Layout Plan- Ground Floor (Preparation & Submission)
Central Battery Layout Plan- Roof Floor (Engineer Review\Approval)
Central Battery Layout Plan- Basement Floor (Engineer Review\Approval)
Central Battery Layout Plan- Typical Floor (Engineer Review\Approval)
Central Battery Layout Plan- Basement Floor (Preparation & Submission)
Central Battery Layout Plan- Typical Floor (Preparation & Submission)
Riser Diagram (Engineer Review\Approval)
Central Battery Layout Plan- Ground Floor (Engineer Review\Approval)
Central Battery Layout Plan- Ground Floor (Preparation & Submission)
Drainage Work Layout Plan- Foundation (Engineer Review\Approval)
Drainage Work Layout Plan- Foundation (Preparation & Submission)
Drainage Work Layout Plan- Basement Floor (Engineer Review\Approval)
Riser Didgram (Engineer Review\Approval)
Drainage Work Layout Plan- Ground Floor (Engineer Review\Approval)
Drainage Work Layout Plan- Typical Floor (Engineer Review\Approval)
Drainage Work Layout Plan- Roof Floor (Engineer Review\Approval)
Drainage Work Layout Plan- Typical Floor (Preparation & Submission)
Fire Protection Layout Plan- Basement Floor (Engineer Review\Approval)
Fire Protection Layout Plan- Roof Floor (Engineer Review\Approval)
Riser Pipes Diagram (Engineer Review\Approval)
Fire Protection Layout Plan- Ground Floor (Engineer Review\Approval)
Fire Protection Layout Plan- Typical Floor (Engineer Review\Approval)
Fire Protection Layout Plan- Basement Floor (Preparation & Submission)
Fire Protection Layout Plan- Typical Floor (Preparation & Submission)
Builders Work Drawing-Foundation (Engineer Review\Approval)
Builders Work Drawing-Foundation (Preparation & Submission)
Builders Work Drawing-Ground Floor (Engineer Review\Approval)
Builders Work Drawing- Typical Floor (Engineer Review\Approval)
Builders Work Drawing- Roof Floor (Engineer Review\Appr
A.C & Ventilation Layout Plan- Basement Floor (Engineer Review\Approval)
A.C & Ventilation Layout Plan- Ground Floor (Engineer Review\Approval)
A.C & Ventilation Layout Plan- Typical Floor (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 46 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.AC.065 A.C & Ventilation Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 07-Dec-17 20-Dec-17 -249
SD.AC.075 Gas Pipes-Ducting Riser Diagram (Engineer Review\Approval)
14 14 0% 28-Sep-17 11-Oct-17 -247
SD.AC.010 A.C & Ventilation Layout Plan- Basement Floor (Preparation
14 & Submission)14 0% 03-Jul-17 17-Jul-17 -243
SD.AC.040 A.C & Ventilation Layout Plan- Typical Floor (Preparation14
& Submission) 14 0% 29-Jul-17 10-Aug-17 -271
SD.AC.060 A.C & Ventilation Layout Plan- Roof Floor (Preparation &14
Submission) 14 0% 22-Nov-17 07-Dec-17 -249
SD.WS.015 Water Supply Layout Plan- Basement Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 32
SD.WS.075 Riser Diagram (Engineer Review\Approval) 14 14 0% 09-Jan-17 22-Jan-17 28
SD.WS.025 Water Supply Layout Plan- Ground Floor (Engineer Review\Approval)
14 14 0% 06-Oct-16 19-Oct-16 28
SD.WS.045 Water Supply Layout Plan- Typical Floor (Engineer Review\Approval)
14 14 0% 27-Oct-16 09-Nov-16 31
SD.WS.065 Water Supply Layout Plan- Roof Floor (Engineer Review\Approval)
14 14 0% 15-Mar-17 28-Mar-17 12
SD.WS.010 Water Supply Layout Plan- Basement Floor (Preparation14& Submission) 14 0% 13-Oct-16 27-Oct-16 32
SD.WS.040 Water Supply Layout Plan- Typical Floor (Preparation & 14
Submission) 14 0% 13-Oct-16 27-Oct-16 31
SD.CD.065 Co-ordination Drawing- Riser Diagram (Engineer Review\Approval)
14 14 0% 25-Oct-17 07-Nov-17 -247
SD.CD.015 Co-ordination Drawing- Basement Floor (Engineer Review\Approval)
14 14 0% 24-Aug-17 09-Sep-17 -243
SD.CD.025 Co-ordination Drawing- Ground Floor (Engineer Review\Approval)
14 14 0% 05-Aug-17 17-Aug-17 -213
SD.CD.045 Co-ordination Drawing- Typical Floor (Engineer Review\Approval)
14 14 0% 21-Sep-17 04-Oct-17 -250
SD.CD.055 Co-ordination Drawing- Roof Floor (Engineer Review\Approval)
14 14 0% 16-Jan-18 29-Jan-18 -219
SD.CD.060 Co-ordination Drawing- Riser Diagram (Preparation & Submission)
14 14 0% 11-Oct-17 25-Oct-17 -247
SD.ME.L20 Lift Work (Engineer Review\Approval) 14 14 0% 20-Jun-17 05-Jul-17 30
SD.ME.L50 Marble Jamb (Engineer Review\Approval) 14 14 0% 15-Jul-17 27-Jul-17 34
SD.AL.310 Aluminium Pergola (Engineer Review\Approval) 14 14 0% 26-Jun-17 12-Jul-17 30
SD.AL.410 Cat Ladder (Engineer Review\Approval) 14 14 0% 23-Aug-17 09-Sep-17 39
SD.AL.B20 Balcony Handrails (Engineer Review\Approval) 14 14 0% 09-Sep-17 23-Sep-17 32
SD.AL.T20 Steps Handrails (Engineer Review\Approval) 14 14 0% 04-Sep-17 18-Sep-17 29
SD.AL.110 Aluminium Windows\Doors (Engineer Review\Approval)14 14 0% 26-Jun-17 12-Jul-17 23
SD.AL.S20 Aluminium Louver For Sub-Station (Engineer Review\Approval)
14 14 0% 10-May-17 24-May-17 35
SD.AL.510 Powder Coat Aluminium Fence (Engineer Review\Approval)
14 14 0% 28-Aug-17 13-Sep-17 33
SD.WD.310 Wooden Door (Engineer Review\Approval) 14 14 0% 25-Jun-17 10-Jul-17 36
SD.WD.410 Wooden Door to Staircase (Engineer Review\Approval) 14 14 0% 17-Sep-17 30-Sep-17 30
SD.BL.210 Block Layout to G. Floor (Engineer Review\Approval) 14 14 0% 15-Dec-16 28-Dec-16 30
SD.BL.110 Block Layout to Basement Floor (Engineer Review\Approval)
14 14 0% 05-Dec-16 19-Dec-16 32
SD.BL.410 Block Layout to Typical Floor (Engineer Review\Approval)
14 14 0% 25-Dec-16 08-Jan-17 32
SD.CO.110 Reinforcement Detail to Foundation (Engineer Review\Approval)
14 14 0% 05-Oct-16 18-Oct-16 30
SD.CO.910 Reinforcement Detail to Roof Floor Slab (Engineer Review\Approval)
14 14 0% 17-Apr-17 01-May-17 29

Actual Level of Effort Remaining Work Page 47 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
A.C & Ventilation Layout Plan- Roof Floor (Engineer Review\Approva
Gas Pipes-Ducting Riser Diagram (Engineer Review\Approval)
A.C & Ventilation Layout Plan- Basement Floor (Preparation & Submission)
A.C & Ventilation Layout Plan- Typical Floor (Preparation & Submission)
A.C & Ventilation Layout Plan- Roof Floor (Preparation & Submission)
Water Supply Layout Plan- Basement Floor (Engineer Review\Approval)
Riser Diagram (Engineer Review\Approval)
Water Supply Layout Plan- Ground Floor (Engineer Review\Approval)
Water Supply Layout Plan- Typical Floor (Engineer Review\Approval)
Water Supply Layout Plan- Roof Floor (Engineer Review\Approval)
Water Supply Layout Plan- Basement Floor (Preparation & Submission)
Water Supply Layout Plan- Typical Floor (Preparation & Submission)
Co-ordination Drawing- Riser Diagram (Engineer Review\Approval)
Co-ordination Drawing- Basement Floor (Engineer Review\Approval)
Co-ordination Drawing- Ground Floor (Engineer Review\Approval)
Co-ordination Drawing- Typical Floor (Engineer Review\Approval)
Co-ordination Drawing- Roof Floor (Engineer Review\App
Co-ordination Drawing- Riser Diagram (Preparation & Submission)
Lift Work (Engineer Review\Approval)
Marble Jamb (Engineer Review\Approval)
Aluminium Pergola (Engineer Review\Approval)
Cat Ladder (Engineer Review\Approval)
Balcony Handrails (Engineer Review\Approval)
Steps Handrails (Engineer Review\Approval)
Aluminium Windows\Doors (Engineer Review\Approval)
Aluminium Louver For Sub-Station (Engineer Review\Approval)
Powder Coat Aluminium Fence (Engineer Review\Approval)
Wooden Door (Engineer Review\Approval)
Wooden Door to Staircase (Engineer Review\Approval)
Block Layout to G. Floor (Engineer Review\Approval)
Block Layout to Basement Floor (Engineer Review\Approval)
Block Layout to Typical Floor (Engineer Review\Approval)
Reinforcement Detail to Foundation (Engineer Review\Approval)
Reinforcement Detail to Roof Floor Slab (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 48 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.CO.410 Reinforcement Detail to G.Floor Slab (Engineer Review\Approval)
14 14 0% 02-Nov-16 15-Nov-16 20
SD.CO.810 Reinforcement Detail to Typical Floor Slab (Engineer Review\Approval)
14 14 0% 16-Nov-16 29-Nov-16 30
SD.CO.210 Reinforcement Detail Columns (Engineer Review\Approval)
14 14 0% 19-Oct-16 01-Nov-16 30
SD.PG.025 Roof Layout Plan (Engineer Review\Approval) 14 14 0% 10-Apr-17 24-Apr-17 32
SD.PG.015 Plans & Schematic Layout (Engineer Review\Approval) 14 14 0% 25-Jun-17 10-Jul-17 3
SD.GC.020 Garbage System (Engineer Review\Approval) 14 14 0% 04-May-17 17-May-17 33
SD.CL.W40 Wall Tiles For Wet Area- Typical Floor (Engineer Review\Approval)
14 14 0% 21-Mar-17 03-Apr-17 38
SD.CL.V20 Granite Cladding (Engineer Review\Approval) 14 14 0% 06-Jul-17 19-Jul-17 29
SD.CL.E20 Wall Tiles- Entrance\Lift Lobby- G. Floor (Engineer Review\Approval)
14 14 0% 30-May-17 12-Jun-17 31
SD.FO.020 Wardrobes (Engineer Review\Approval) 14 14 0% 12-Sep-17 25-Sep-17 32
SD.FO.160 Kitchen Cabinet- (Engineer Review\Approval) 14 14 0% 13-Aug-17 26-Aug-17 23
SD.FO.260 Vanity Counter- Typical Floor (Engineer Review\Approval)
14 14 0% 13-Aug-17 26-Aug-17 23
SD.FO.510 Remote Control Gate Barrier (Engineer Review\Approval)
14 14 0% 05-Oct-17 18-Oct-17 35
SD.FO.990 Biycle Rack (Engineer Review\Approval) 14 14 0% 15-Oct-17 28-Oct-17 35
SD.AL.710 Tesion Fabric (Engineer Review\Approval) 14 14 0% 12-Jul-17 26-Jul-17 36
SD.WP.G20 Garbage Chute Waterproofing (Engineer Review\Approval)
14 14 0% 29-Jun-17 12-Jul-17 10
SD.WP.R20 Roof Waterproofing (Engineer Review\Approval) 14 14 0% 29-Jun-17 12-Jul-17 32
SD.WP.B20 Balconies\Terrace Waterproofing (Engineer Review\Approval)
14 14 0% 29-Jun-17 12-Jul-17 29
SD.WP.W20 Waterproofing For Wet area (Engineer Review\Approval)
14 14 0% 29-Mar-17 11-Apr-17 39
SD.FL.C40 Floor Tiles For Corridor\Lift Labby (Engineer Review\Approval)
14 14 0% 28-May-17 10-Jun-17 29
SD.FL.W40 Floor Tiles For Wet Area (Engineer Review\Approval) 14 14 0% 17-Jun-17 02-Jul-17 6
SD.FL.B20 Floor Tiles For Balcony (Engineer Review\Approval) 14 14 0% 02-Jul-17 15-Jul-17 34
SD.FL.D40 Floor Tiles For Dry Area (Engineer Review\Approval) 14 14 0% 22-Jun-17 08-Jul-17 15
SD.FL.E20 Floor Tiles For Entrance\Lift Labby (Engineer Review\Approval)
14 14 0% 15-Jun-17 01-Jul-17 28
SD.FC.C20 False Ceiling to to Corridors\Lift Lobby (Engineer Review\Approval)
14 14 0% 01-Jun-17 14-Jun-17 29
SD.FC.D20 False Ceiling to Dry Area (Engineer Review\Approval) 14 14 0% 29-Jun-17 12-Jul-17 19
SD.FC.W20 False Ceiling to Wet Area (Engineer Review\Approval) 14 14 0% 29-Jun-17 12-Jul-17 6
SD.AL.610 Metal Doors (Engineer Review\Approval) 14 14 0% 12-Jul-17 26-Jul-17 40
SD.DW.015 Dewatering (Engineer Review\Approval) 14 14 0% 06-Aug-16 18-Aug-16 12
SD.CL.C20 Wall Tiles- Corridor\Lift Lobby- Typical Floor (Engineer Review\Approval)
14 14 0% 25-Mar-17 06-Apr-17 29
SD.FC.E20 False Ceiling to to Entrance\Lift Lobby (Engineer Review\Approval)
14 14 0% 25-Jun-17 10-Jul-17 32
SD.AL.810 Aluminium Louver (Engineer Review\Approval) 14 14 0% 28-Aug-17 13-Sep-17 33
SD.AL.210 Aluminium Element (Engineer Review\Approval) 14 14 0% 17-Jul-17 31-Jul-17 31
SD.AL.360 Aluminium Screen (Engineer Review\Approval) 14 14 0% 21-Jun-17 08-Jul-17 35

Actual Level of Effort Remaining Work Page 49 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Reinforcement Detail to G.Floor Slab (Engineer Review\Approval)
Reinforcement Detail to Typical Floor Slab (Engineer Review\Approval)
Reinforcement Detail Columns (Engineer Review\Approval)
Roof Layout Plan (Engineer Review\Approval)
Plans & Schematic Layout (Engineer Review\Approval)
Garbage System (Engineer Review\Approval)
Wall Tiles For Wet Area- Typical Floor (Engineer Review\Approval)
Granite Cladding (Engineer Review\Approval)
Wall Tiles- Entrance\Lift Lobby- G. Floor (Engineer Review\Approval)
Wardrobes (Engineer Review\Approval)
Kitchen Cabinet- (Engineer Review\Approval)
Vanity Counter- Typical Floor (Engineer Review\Approval)
Remote Control Gate Barrier (Engineer Review\Approval)
Biycle Rack (Engineer Review\Approval)
Tesion Fabric (Engineer Review\Approval)
Garbage Chute Waterproofing (Engineer Review\Approval)
Roof Waterproofing (Engineer Review\Approval)
Balconies\Terrace Waterproofing (Engineer Review\Approval)
Waterproofing For Wet area (Engineer Review\Approval)
Floor Tiles For Corridor\Lift Labby (Engineer Review\Approval)
Floor Tiles For Wet Area (Engineer Review\Approval)
Floor Tiles For Balcony (Engineer Review\Approval)
Floor Tiles For Dry Area (Engineer Review\Approval)
Floor Tiles For Entrance\Lift Labby (Engineer Review\Approval)
False Ceiling to to Corridors\Lift Lobby (Engineer Review\Approval)
False Ceiling to Dry Area (Engineer Review\Approval)
False Ceiling to Wet Area (Engineer Review\Approval)
Metal Doors (Engineer Review\Approval)
Dewatering (Engineer Review\Approval)
Wall Tiles- Corridor\Lift Lobby- Typical Floor (Engineer Review\Approval)
False Ceiling to to Entrance\Lift Lobby (Engineer Review\Approval)
Aluminium Louver (Engineer Review\Approval)
Aluminium Element (Engineer Review\Approval)
Aluminium Screen (Engineer Review\Approval)

Actual Level of Effort Remaining Work Page 50 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.AL.840 Aluminium Panels (Engineer Review\Approval) 14 14 0% 19-Aug-17 04-Sep-17 32
SD.FO.280 Reciption Counter- Typical Floor (Engineer Review\Approval)
14 14 0% 19-Oct-17 01-Nov-17 30
SD.EL.L20 Earthing System (Engineer Review\Approval) 14 14 0% 07-Sep-16 24-Sep-16 29
SD.EL.L10 Earthing System (Preparation & Submission) 14 14 0% 24-Aug-16 07-Sep-16 29
SD.FO.410 GRC Work (Engineer Review\Approval) 14 14 0% 20-Jul-17 02-Aug-17 35
SD.CL.W30 Wall Tiles For Wet Area- Typical Floor (Preparation & Submission)
17 17 0% 05-Mar-17 21-Mar-17 38
SD.EL.T70 Riser Diagram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.EL.T50 Tepehone System Layout Plan- Roof Floor (Preparation21
& Submission) 21 0% 23-Feb-17 15-Mar-17 29
SD.EL.T20 Telephone System Layout Plan- Ground Floor (Preparation
21 & Submission) 21 0% 17-Sep-16 06-Oct-16 28
SD.EL.E10 Lighting\Power Layout Plan- Basement Floor (Preparation
21 & Submission) 21 0% 09-Oct-16 29-Oct-16 30
SD.EL.F70 Riser Diagram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.EL.F50 Fire Alarm Layout Plan- Roof Floor (Preparation & Submission)
21 21 0% 23-Feb-17 15-Mar-17 29
SD.EL.F10 Fire Alarm Layout Plan- Basement Floor (Preparation & 21
Submission) 21 0% 09-Oct-16 29-Oct-16 30
SD.EL.F20 Fire Alarm Layout Plan- Ground Floor (Preparation & Submission)
21 21 0% 17-Sep-16 06-Oct-16 28
SD.EL.V10 Layout Plans & Schematic Layout (Preparation & Submission)
21 21 0% 05-Aug-17 24-Aug-17 30
SD.EL.S50 Security System Layout Plan- Roof Floor (Preparation &21
Submission) 21 0% 23-Feb-17 15-Mar-17 29
SD.EL.S70 Riser Diagram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.EL.C50 Central Battery Layout Plan- Roof Floor (Preparation & Submission)
21 21 0% 23-Feb-17 15-Mar-17 29
SD.EL.C70 Riser Diagram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.DR.020 Drainage Work Layout Plan- Basement Floor (Preparation
21 & Submission) 21 0% 09-Oct-16 29-Oct-16 30
SD.DR.080 Riser Didgram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.DR.070 Drainage Work Layout Plan- Roof Floor (Preparation & Submission)
21 21 0% 09-Feb-17 01-Mar-17 30
SD.FF.050 Fire Protection Layout Plan- Roof Floor (Preparation & Submission)
21 21 0% 23-Feb-17 15-Mar-17 29
SD.FF.070 Riser Pipes Diagram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.BW.060 Builders Work Drawing- Roof Floor (Preparation & Submission)
21 21 0% 20-Dec-17 10-Jan-18 -249
SD.AC.070 Gas Pipes-Ducting Riser Diagram (Preparation & Submission)
21 21 0% 09-Sep-17 28-Sep-17 -247
SD.WS.070 Riser Diagram (Preparation & Submission) 21 21 0% 19-Dec-16 09-Jan-17 28
SD.WS.060 Water Supply Layout Plan- Roof Floor (Preparation & Submission)
21 21 0% 23-Feb-17 15-Mar-17 12
SD.CD.010 Co-ordination Drawing- Basement Floor (Preparation & 28
Submission) 28 0% 30-Jul-17 24-Aug-17 -243
SD.CD.020 Co-ordination Drawing- Ground Floor (Preparation & Submission)
28 28 0% 09-Jul-17 05-Aug-17 -213
SD.CD.040 Co-ordination Drawing- Typical Floor (Preparation & Submission)
28 28 0% 23-Aug-17 21-Sep-17 -250
SD.CD.050 Co-ordination Drawing- Roof Floor (Preparation & Submission)
28 28 0% 20-Dec-17 16-Jan-18 -219
SD.ME.L10 Lift Work (Preparation & Submission) 28 28 0% 24-May-17 20-Jun-17 30
SD.ME.L40 Marble Jamb (Preparation & Submission) 28 28 0% 17-Jun-17 15-Jul-17 34

Actual Level of Effort Remaining Work Page 51 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Aluminium Panels (Engineer Review\Approval)
Reciption Counter- Typical Floor (Engineer Review\Approval)
Earthing System (Engineer Review\Approval)
Earthing System (Preparation & Submission)
GRC Work (Engineer Review\Approval)
Wall Tiles For Wet Area- Typical Floor (Preparation & Submission)
Riser Diagram (Preparation & Submission)
Tepehone System Layout Plan- Roof Floor (Preparation & Submission)
Telephone System Layout Plan- Ground Floor (Preparation & Submission)
Lighting\Power Layout Plan- Basement Floor (Preparation & Submission)
Riser Diagram (Preparation & Submission)
Fire Alarm Layout Plan- Roof Floor (Preparation & Submission)
Fire Alarm Layout Plan- Basement Floor (Preparation & Submission)
Fire Alarm Layout Plan- Ground Floor (Preparation & Submission)
Layout Plans & Schematic Layout (Preparation & Submission)
Security System Layout Plan- Roof Floor (Preparation & Submission)
Riser Diagram (Preparation & Submission)
Central Battery Layout Plan- Roof Floor (Preparation & Submission)
Riser Diagram (Preparation & Submission)
Drainage Work Layout Plan- Basement Floor (Preparation & Submission)
Riser Didgram (Preparation & Submission)
Drainage Work Layout Plan- Roof Floor (Preparation & Submission)
Fire Protection Layout Plan- Roof Floor (Preparation & Submission)
Riser Pipes Diagram (Preparation & Submission)
Builders Work Drawing- Roof Floor (Preparation & Submission
Gas Pipes-Ducting Riser Diagram (Preparation & Submission)
Riser Diagram (Preparation & Submission)
Water Supply Layout Plan- Roof Floor (Preparation & Submission)
Co-ordination Drawing- Basement Floor (Preparation & Submission)
Co-ordination Drawing- Ground Floor (Preparation & Submission)
Co-ordination Drawing- Typical Floor (Preparation & Submission)
Co-ordination Drawing- Roof Floor (Preparation & Submissio
Lift Work (Preparation & Submission)
Marble Jamb (Preparation & Submission)

Actual Level of Effort Remaining Work Page 52 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.AL.300 Aluminium Pergola (Preparation & Submission) 28 28 0% 31-May-17 26-Jun-17 30
SD.AL.400 Cat Ladder (Preparation & Submission) 28 28 0% 29-Jul-17 23-Aug-17 39
SD.AL.B10 Balcony Handrails (Preparation & Submission) 28 28 0% 12-Aug-17 09-Sep-17 32
SD.AL.T10 Steps Handrails (Preparation & Submission) 28 28 0% 07-Aug-17 04-Sep-17 29
SD.AL.100 Aluminium Windows\Doors (Preparation & Submission) 28 28 0% 31-May-17 26-Jun-17 23
SD.AL.S10 Aluminium Louver For Sub-Station (Preparation & Submission)
28 28 0% 13-Apr-17 10-May-17 35
SD.AL.500 Powder Coat Aluminium Fence (Preparation & Submission)
28 28 0% 02-Aug-17 28-Aug-17 33
SD.WD.400 Wooden Door to Staircase (Preparation & Submission) 28 28 0% 19-Aug-17 17-Sep-17 30
SD.WD.300 Wooden Door (Preparation & Submission) 28 28 0% 29-May-17 25-Jun-17 36
SD.PG.010 Plans & Schematic Layout (Preparation & Submission) 28 28 0% 29-May-17 25-Jun-17 3
SD.PG.020 Roof Layout Plan (Preparation & Submission) 28 28 0% 14-Mar-17 10-Apr-17 32
SD.GC.010 Garbage System (Preparation & Submission) 28 28 0% 06-Apr-17 04-May-17 33
SD.CL.V10 Granite Cladding (Preparation & Submission) 28 28 0% 07-Jun-17 06-Jul-17 29
SD.CL.E10 Wall Tiles- Entrance\Lift Lobby- G. Floor (Preparation & 28
Submission) 28 0% 04-May-17 30-May-17 31
SD.FO.010 Wardrobes (Preparation & Submission) 28 28 0% 14-Aug-17 12-Sep-17 32
SD.FO.150 Kitchen Cabinet- (Preparation & Submission) 28 28 0% 17-Jul-17 13-Aug-17 23
SD.FO.250 Vanity Counter- Typical Floor (Preparation & Submission)
28 28 0% 17-Jul-17 13-Aug-17 23
SD.FO.500 Remote Control Gate Barrier (Preparation & Submission)
28 28 0% 09-Sep-17 05-Oct-17 35
SD.FO.980 Biycle Rack (Preparation & Submission) 28 28 0% 18-Sep-17 15-Oct-17 35
SD.AL.700 Tesion Fabric (Preparation & Submission) 28 28 0% 14-Jun-17 12-Jul-17 36
SD.WP.G10 Garbage Chute Waterproofing (Preparation & Submission)
28 28 0% 01-Jun-17 29-Jun-17 10
SD.WP.R10 Roof Waterproofing (Preparation & Submission) 28 28 0% 01-Jun-17 29-Jun-17 32
SD.WP.B10 Balonies\Terrace Waterproofing (Preparation & Submission)
28 28 0% 01-Jun-17 29-Jun-17 29
SD.WP.W10 Waterproofing For Wet area (Preparation & Submission)28 28 0% 04-Mar-17 29-Mar-17 39
SD.FL.C30 Floor Tiles For Corridor\Lift Labby (Preparation & Submission)
28 28 0% 01-May-17 28-May-17 29
SD.FL.W30 Floor Tiles For Wet Area (Preparation & Submission) 28 28 0% 21-May-17 17-Jun-17 6
SD.FL.B10 Floor Tiles For Balcony (Preparation & Submission) 28 28 0% 03-Jun-17 02-Jul-17 34
SD.FL.D30 Floor Tiles For Dry Area (Preparation & Submission) 28 28 0% 28-May-17 22-Jun-17 15
SD.FL.E10 Floor Tiles For Entrance\Lift Labby (Preparation & Submission)
28 28 0% 20-May-17 15-Jun-17 28
SD.FC.C10 False Ceiling to to Corridors\Lift Lobby (Preparation & Submission)
28 28 0% 06-May-17 01-Jun-17 29
SD.FC.D10 False Ceiling to Dry Area (Preparation & Submission) 28 28 0% 01-Jun-17 29-Jun-17 19
SD.FC.W10 False Ceiling to Wet Area (Preparation & Submission) 28 28 0% 01-Jun-17 29-Jun-17 6
SD.AL.600 Metal Doors (Preparation & Submission) 28 28 0% 14-Jun-17 12-Jul-17 40
SD.CL.C10 Wall Tiles- Corridor\Lift Lobby- Typical Floor (Preparation
28& Submission) 28 0% 27-Feb-17 25-Mar-17 29

Actual Level of Effort Remaining Work Page 53 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Aluminium Pergola (Preparation & Submission)
Cat Ladder (Preparation & Submission)
Balcony Handrails (Preparation & Submission)
Steps Handrails (Preparation & Submission)
Aluminium Windows\Doors (Preparation & Submission)
Aluminium Louver For Sub-Station (Preparation & Submission)
Powder Coat Aluminium Fence (Preparation & Submission)
Wooden Door to Staircase (Preparation & Submission)
Wooden Door (Preparation & Submission)
Plans & Schematic Layout (Preparation & Submission)
Roof Layout Plan (Preparation & Submission)
Garbage System (Preparation & Submission)
Granite Cladding (Preparation & Submission)
Wall Tiles- Entrance\Lift Lobby- G. Floor (Preparation & Submission)
Wardrobes (Preparation & Submission)
Kitchen Cabinet- (Preparation & Submission)
Vanity Counter- Typical Floor (Preparation & Submission)
Remote Control Gate Barrier (Preparation & Submission)
Biycle Rack (Preparation & Submission)
Tesion Fabric (Preparation & Submission)
Garbage Chute Waterproofing (Preparation & Submission)
Roof Waterproofing (Preparation & Submission)
Balonies\Terrace Waterproofing (Preparation & Submission)
Waterproofing For Wet area (Preparation & Submission)
Floor Tiles For Corridor\Lift Labby (Preparation & Submission)
Floor Tiles For Wet Area (Preparation & Submission)
Floor Tiles For Balcony (Preparation & Submission)
Floor Tiles For Dry Area (Preparation & Submission)
Floor Tiles For Entrance\Lift Labby (Preparation & Submission)
False Ceiling to to Corridors\Lift Lobby (Preparation & Submission)
False Ceiling to Dry Area (Preparation & Submission)
False Ceiling to Wet Area (Preparation & Submission)
Metal Doors (Preparation & Submission)
Wall Tiles- Corridor\Lift Lobby- Typical Floor (Preparation & Submission)

Actual Level of Effort Remaining Work Page 54 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SD.FC.E10 False Ceiling to to Entrance\Lift Lobby (Preparation & Submission)
28 28 0% 29-May-17 25-Jun-17 32
SD.AL.800 Aluminium Louver (Preparation & Submission) 28 28 0% 02-Aug-17 28-Aug-17 33
SD.AL.200 Aluminium Element (Preparation & Submission) 28 28 0% 19-Jun-17 17-Jul-17 31
SD.AL.350 Aluminium Screen (Preparation & Submission) 28 28 0% 27-May-17 21-Jun-17 35
SD.AL.830 Aluminium Panels (Preparation & Submission) 28 28 0% 24-Jul-17 19-Aug-17 32
SD.FO.270 Reciption Counter- Typical Floor (Preparation & Submission)
28 28 0% 23-Sep-17 19-Oct-17 30
SD.FO.400 GRC Work (Preparation & Submission) 28 28 0% 21-Jun-17 20-Jul-17 35

- Earth and Foundation Work 606 606 0% 19-Jul-16 17-Mar-18 -214

SS.CO.F30 DM Inspection\Casting Raft 0 0 0% 28-Nov-16 1


SS.DW.030 Install Pump 2 2 0% 05-Sep-16 07-Sep-16 2
SS.DW.040 Time Required to Reduce Water Table Level 2 2 0% 07-Sep-16 09-Sep-16 2
SS.CO.T10 Concrete P.C.C 2 2 0% 05-Oct-16 06-Oct-16 1
SS.DW.020 Piping Net Work 3 3 0% 02-Sep-16 05-Sep-16 2
SS.ER.130 Application For Inspection\DM Inspection 3 3 0% 02-Oct-16 05-Oct-16 1
SS.WP.T10 Waterproofing Over Block 3 3 0% 11-Oct-16 13-Oct-16 1
SS.WP.T20 Waterproofing to External Wall 3 3 0% 24-Oct-16 26-Oct-16 1
SS.ER.T10 Back Filling Work 3 3 0% 26-Oct-16 29-Oct-16 1
SS.WP.010 Waterproofing Over P.C.C (Membrane)\Protection 4 4 0% 12-Nov-16 15-Nov-16 1
SS.CO.F10 PCC and Anti-termite 4 4 0% 30-Oct-16 02-Nov-16 1
SS.EL.L10 Earthing System 4 4 0% 23-Nov-16 27-Nov-16 2
SS.BL.T10 Block Work 4 4 0% 06-Oct-16 10-Oct-16 1
SS.FI.T20 Cat Ladder 4 4 0% 13-Mar-18 17-Mar-18 -224
SS.DR.010 Drainage Pipes 4 4 0% 23-Nov-16 27-Nov-16 2
SS.DW.010 Install Pipes (Deep Wells) 5 5 0% 28-Aug-16 02-Sep-16 2
SS.CO.T20 R.C.C Raft For Water Tank 5 5 0% 13-Oct-16 18-Oct-16 1
SS.CO.T30 R.C.C Walls For Water Tank 6 6 0% 18-Oct-16 24-Oct-16 1
SS.ER.120 Excavation Work Stage III - Water Tank (- 9.13 m) 7 7 0% 26-Sep-16 02-Oct-16 1
SS.FI.T10 GRP Lining 7 7 0% 07-Mar-18 13-Mar-18 -224
SS.WP.020 Guniting\Waterproofing Work Upto Ground Floor 10 10 0% 02-Nov-16 12-Nov-16 1
SS.ER.100 Excavation Work Stage I (0.5 m Above Water Table) 14 14 0% 15-Aug-16 28-Aug-16 2
SS.CO.F20 R.C.C Raft, Water Tank Slab 14 14 0% 15-Nov-16 28-Nov-16 1
SS.ER.110 Excavation Work Stage II (- 5.85 m) 14 14 0% 10-Sep-16 26-Sep-16 1
SS.SH.010 Shoring Piles Include Caping beams 28 28 0% 19-Jul-16 15-Aug-16 2

Actual Level of Effort Remaining Work Page 55 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
False Ceiling to to Entrance\Lift Lobby (Preparation & Submission)
Aluminium Louver (Preparation & Submission)
Aluminium Element (Preparation & Submission)
Aluminium Screen (Preparation & Submission)
Aluminium Panels (Preparation & Submission)
Reciption Counter- Typical Floor (Preparation & Submission)
GRC Work (Preparation & Submission)
17-Mar-18, - Earth and Foundation Work

DM Inspection\Casting Raft,
Install Pump
Time Required to Reduce Water Table Level
Concrete P.C.C
Piping Net Work
Application For Inspection\DM Inspection
Waterproofing Over Block
Waterproofing to External Wall
Back Filling Work
Waterproofing Over P.C.C (Membrane)\Protection
PCC and Anti-termite
Earthing System
Block Work
Cat Ladder
Drainage Pipes
Install Pipes (Deep Wells)
R.C.C Raft For Water Tank
R.C.C Walls For Water Tank
Excavation Work Stage III - Water Tank (- 9.13 m)
GRP Lining
Guniting\Waterproofing Work Upto Ground Floor
Excavation Work Stage I (0.5 m Above Water Table)
R.C.C Raft, Water Tank Slab
Excavation Work Stage II (- 5.85 m)
Shoring Piles Include Caping beams

Actual Level of Effort Remaining Work Page 56 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
SS.DW.100 Maintaining Dewatering System 417 417 0% 09-Sep-16 30-Oct-17 -259

- Basement Floor 640 640 0% 29-Nov-16 02-Aug-18 -257

BS.WS.900 Work Completion 0 0 0% 06-Jun-18 -265


BS.AC.900 Work Completion 0 0 0% 17-May-18 -270
BS.FF.900 Work Completion 0 0 0% 02-Jul-18 -265
BS.DR.900 Work Completion 0 0 0% 19-Jun-18 -261
BS.EL.E90 Work Completion 0 0 0% 07-Jun-18 -270
BS.EL.F90 Work Completion 0 0 0% 13-May-18 -270
BS.EL.L90 Work Completion 0 0 0% 18-Jun-18 -270
BS.FC.C10 MEP CLEARANCE 0 0 0% 26-Mar-18 -270
BS.AC.040 Pipes Testing 2 2 0% 30-Jan-18 01-Feb-18 -269
BS.FF.040 Pipes Testing 2 2 0% 26-Feb-18 28-Feb-18 -270
BS.FO.P30 Convex Mirror 2 2 0% 10-Jul-18 12-Jul-18 -253
GO.FO.P30 Convex Mirror 2 2 0% 12-Jul-18 15-Jul-18 -237
BS.EL.E30 Isolators In High Level 3 3 0% 13-Mar-18 17-Mar-18 -270
BS.AC.050 Duct Drops 3 3 0% 03-Apr-18 05-Apr-18 -270
BS.EL.C10 Emergency Light 4 4 0% 07-Jun-18 12-Jun-18 -270
BS.EL.010 Conduits\Boxes & DB's enclosers(walls) 4 4 0% 17-Sep-17 20-Sep-17 -237
BS.EL.E70 Switches, Sockets & Light Fittings 4 4 0% 04-Jun-18 07-Jun-18 -270
BS.CO.100 Dismantling Shutters 4 4 0% 28-Aug-17 04-Sep-17 -237
BS.PL.S10 Plaster Work 4 4 0% 20-Sep-17 24-Sep-17 -237
BS.PL.C10 Plaster Work 4 4 0% 24-Sep-17 27-Sep-17 -237
BS.SN.010 Work Completion\Snagging 5 5 0% 29-Jul-18 02-Aug-18 -270
BS.AC.100 Grills and Diffusers 5 5 0% 13-May-18 17-May-18 -270
BS.FF.050 Sprinklers Head Installation 5 5 0% 18-Jun-18 23-Jun-18 -270
BS.FF.060 Hose Reel\Fire Extinguisher 5 5 0% 23-Jun-18 27-Jun-18 -270
BS.EL.F20 Fixing Fire Alarm Devices 5 5 0% 08-May-18 13-May-18 -270
BS.PN.P70 Road Marking 5 5 0% 24-Jul-18 29-Jul-18 -270
BS.FL.C30 Floor Tiles- Corridors and Lobby 5 5 0% 21-Mar-18 26-Mar-18 -270
BS.AC.030 Gas Pipes net work 6 6 0% 24-Jan-18 30-Jan-18 -269
BS.AC.020 Mouse Connection & Fire Damper 6 6 0% 23-Jan-18 29-Jan-18 -267
BS.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 17-Mar-18 21-Mar-18 -270
BS.FL.S20 Screed Flooring 6 6 0% 05-Dec-17 11-Dec-17 -237

Actual Level of Effort Remaining Work Page 57 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Maintaining Dewatering System

Work Completion,
Work Completion,

Work Completion,
Work Completion,

MEP CLEARANCE, 26-Mar-18


Pipes Testing
Pipes Testing

Isolators In High Level


Duct Drops

Conduits\Boxes & DB's enclosers(walls)


Switches, Sockets &
Dismantling Shutters
Plaster Work
Plaster Work

Grills and Diffusers

Fixing Fire Alarm Devices

Floor Tiles- Corridors and Lobby


Gas Pipes net work
Mouse Connection & Fire Damper
Install Electric Cables Try\Power Cables
Screed Flooring

Actual Level of Effort Remaining Work Page 58 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
BS.PN.C10 Painting Work to False Ceiling (Lift Lobby) 6 6 0% 25-Apr-18 01-May-18 -262
BS.WS.030 Pipes H\L & Testing 7 7 0% 09-Jan-18 15-Jan-18 -267
BS.FF.030 Hz. Pipes H\L 7 7 0% 20-Feb-18 26-Feb-18 -270
BS.DR.030 Floor Trap & Drainage Pipes H\L 7 7 0% 28-Feb-18 07-Mar-18 -270
BS.EL.020 Pulling All Types Of Wires 7 7 0% 07-Mar-18 13-Mar-18 -270
BS.EL.S20 Security System Devices 7 7 0% 17-May-18 27-May-18 -270
BS.PN.P50 Thermoplastic Paint 7 7 0% 17-Jul-18 24-Jul-18 -270
BS.AL.700 Aluminium Louver For Extract Fans 7 7 0% 27-Jun-18 04-Jul-18 -270
BS.FC.C20 Suspension System 7 7 0% 26-Mar-18 03-Apr-18 -270
BS.FC.C30 Final Stage 7 7 0% 05-Apr-18 12-Apr-18 -270
BS.FO.P10 Corner Guard 7 7 0% 04-Jul-18 10-Jul-18 -270
BS.FO.P20 Wheel Stopper\Spead Breakers 7 7 0% 10-Jul-18 17-Jul-18 -270
BS.EL.C20 Emergency Light Control Panel 7 7 0% 12-Jun-18 18-Jun-18 -270
BS.AC.010 FCU & A.C Ducts 8 8 0% 15-Jan-18 23-Jan-18 -267
BS.BL.010 Block Work\Concrete Upstand,Lintels 8 8 0% 09-Sep-17 17-Sep-17 -243
BS.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 11-Dec-17 18-Dec-17 -230
BS.EL.S50 Security System Control Panel 9 9 0% 27-May-18 04-Jun-18 -270
BS.AL.010 Aluminium Doors\Glass Door\Louver Door 10 10 0% 08-May-18 17-May-18 -264
BS.AL.020 Steel Door 10 10 0% 17-May-18 29-May-18 -264
BS.WS.300 Supply and Install Transfer Pump 14 14 0% 08-May-18 22-May-18 -251
BS.AC.200 Ventilation System Fans (Extract\Fresh Air Fans) 14 14 0% 01-Feb-18 14-Feb-18 -269
BS.AC.210 Ventilation System Ducts 14 14 0% 14-Feb-18 27-Feb-18 -269
BS.FF.090 Fire Pump 14 14 0% 19-Jun-18 02-Jul-18 -265
BS.DR.040 Sump pump & Catch basin 14 14 0% 06-Jun-18 19-Jun-18 -265
BS.EL.E60 DB'S Dressing\Termination 14 14 0% 25-Apr-18 08-May-18 -270
BS.FL.P10 Epoxy Coating 14 14 0% 25-Apr-18 08-May-18 -265
BS.PN.050 Primer & Stucco 14 14 0% 11-Jan-18 24-Jan-18 -270
BS.PN.100 Painting Work 14 14 0% 12-Apr-18 25-Apr-18 -270
BS.PN.P10 Painting Work For Ceiling (Parking) 14 14 0% 11-Oct-17 24-Oct-17 -187
BS.PL.P20 Plaster Work 14 14 0% 27-Sep-17 11-Oct-17 -237
BS.WS.200 GRP Water Tank (A.C Condenser) 14 14 0% 08-May-18 22-May-18 -265
BS.WS.400 Irrigation Pump Set 14 14 0% 22-May-18 06-Jun-18 -265
BS.PN.P20 Painting Work 14 14 0% 19-Jun-18 02-Jul-18 -254
BS.CO.020 R.C.C Columns\Walls 21 21 0% 29-Nov-16 20-Dec-16 1

Actual Level of Effort Remaining Work Page 59 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Painting Work to False Ceiling (
Pipes H\L & Testing
Hz. Pipes H\L
Floor Trap & Drainage Pipes H\L
Pulling All Types Of Wires
Security System Device

Suspension System
Final Stage

FCU & A.C Ducts


Block Work\Concrete Upstand,Lintels
Wall Tiles- Corridors\Lift Lobby
Security System Cont
Aluminium Doors\Glass Do
Steel Door
Supply and Install Transfe
Ventilation System Fans (Extract\Fresh Air Fans)
Ventilation System Ducts

DB'S Dressing\Termination
Epoxy Coating
Primer & Stucco
Painting Work
Painting Work For Ceiling (Parking)
Plaster Work
GRP Water Tank (A.C Co
Irrigation Pump Set

R.C.C Columns\Walls

Actual Level of Effort Remaining Work Page 60 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
BS.CO.050 R.C.C Slab (G. Floor Slab)\Electric Conduits 21 21 0% 29-Jul-17 17-Aug-17 -247

- Ground Floor 379 379 0% 19-Aug-17 15-Aug-18 -252

GO.PG.900 Work Completion 0 0 0% 03-Jun-18 -226


GO.WS.900 Work Completion 0 0 0% 08-Jul-18 -231
GO.AC.900 Work Completion 0 0 0% 03-Jul-18 -253
GO.FF.900 Work Completion 0 0 0% 08-Jul-18 -271
GO.DR.900 Work Completion 0 0 0% 30-Jun-18 -235
GO.EL.E90 Work Completion 0 0 0% 09-Aug-18 -251
GO.EL.F90 Work Completion 0 0 0% 16-Jul-18 -266
GO.EL.L90 Work Completion 0 0 0% 28-Jun-18 -271
GO.FC.E10 MEP CLEARANCE 0 0 0% 24-Apr-18 -271
GO.FC.W10 MEP CLEARANCE 0 0 0% 10-Apr-18 -247
GO.PG.050 Flexible Hose 2 2 0% 20-May-18 22-May-18 -216
GO.AC.040 Pipes Testing 2 2 0% 12-Feb-18 13-Feb-18 -270
GO.FF.020 Pipes Testing 2 2 0% 18-Feb-18 20-Feb-18 -270
GO.DR.010 Pipes In Walls 2 2 0% 03-Mar-18 05-Mar-18 -258
GO.WS.050 Water Heater 2 2 0% 21-Mar-18 22-Mar-18 -268
GO.WS.090 Pipes Testing 2 2 0% 22-Mar-18 25-Mar-18 -268
GO.WS.100 Valves, Mixer's, etc... 2 2 0% 05-Jul-18 08-Jul-18 -231
GO.DR.100 Sanitary Ware, Kitchen Sink 2 2 0% 27-Jun-18 30-Jun-18 -235
GO.DR.030 Shower Try 2 2 0% 31-Mar-18 01-Apr-18 -265
GO.DR.060 Pipes Testing 2 2 0% 26-Feb-18 28-Feb-18 -242
GO.EL.E10 Isolators In High Level 3 3 0% 18-Mar-18 21-Mar-18 -271
GO.CO.010 R.C.C Columns\Walls 3 3 0% 19-Aug-17 21-Aug-17 -247
GO.WS.010 Hot and Cold Water 3 3 0% 17-Jan-18 20-Jan-18 -264
01.AL.510 Fixing Aluminium Glass 3 3 0% 13-May-18 15-May-18 -262
02.AL.510 Fixing Aluminium Glass 3 3 0% 19-May-18 22-May-18 -262
03.AL.510 Fixing Aluminium Glass 3 3 0% 28-May-18 30-May-18 -262
04.AL.510 Fixing Aluminium Glass 3 3 0% 03-Jun-18 06-Jun-18 -267
05.AL.510 Fixing Aluminium Glass 3 3 0% 13-May-18 15-May-18 -255
06.AL.510 Fixing Aluminium Glass 3 3 0% 19-May-18 22-May-18 -257
07.AL.510 Fixing Aluminium Glass 3 3 0% 28-May-18 30-May-18 -260
08.AL.510 Fixing Aluminium Glass 3 3 0% 06-Jun-18 09-Jun-18 -269

Actual Level of Effort Remaining Work Page 61 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
R.C.C Slab (G. Floor Slab)\Electric Conduits

Work Completion,

MEP CLEARANCE, 24-Apr-18


MEP CLEARANCE, 10-Apr-18
Flexible Hose
Pipes Testing
Pipes Testing
Pipes In Walls
Water Heater
Pipes Testing

Shower Try
Pipes Testing
Isolators In High Level
R.C.C Columns\Walls
Hot and Cold Water
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glas
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Gla

Actual Level of Effort Remaining Work Page 62 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
09.AL.510 Fixing Aluminium Glass 3 3 0% 22-May-18 27-May-18 -256
10.AL.510 Fixing Aluminium Glass 3 3 0% 02-Jun-18 04-Jun-18 -262
11.AL.510 Fixing Aluminium Glass 3 3 0% 05-Jun-18 07-Jun-18 -266
12.AL.510 Fixing Aluminium Glass 3 3 0% 09-Jun-18 12-Jun-18 -270
GO.WD.010 Fixing Sub Frames 4 4 0% 25-Oct-17 30-Oct-17 -247
GO.EL.C10 Emergency Light 4 4 0% 30-Jul-18 02-Aug-18 -251
GO.EL.010 Conduits\Boxes & DB's enclosers(walls) 4 4 0% 23-Oct-17 26-Oct-17 -254
GO.EL.E80 Switches, Sockets & Light Fittings 4 4 0% 26-Jul-18 30-Jul-18 -251
GO.PL.S10 Plaster Work 4 4 0% 26-Oct-17 30-Oct-17 -254
GO.CL.W10 Wall Tiles 4 4 0% 05-Mar-18 08-Mar-18 -258
GO.WP.W10 Waterproofing to Wet Area 4 4 0% 21-Mar-18 25-Mar-18 -271
GO.FC.W20 Suspension System 4 4 0% 15-Apr-18 18-Apr-18 -247
GO.FC.W30 Final Stage 4 4 0% 30-Apr-18 03-May-18 -255
GO.WP.W20 Waterproofing to Planter 4 4 0% 25-Mar-18 29-Mar-18 -271
GO.DR.020 Drainage Pipes-L\L 4 4 0% 26-Mar-18 31-Mar-18 -269
GO.AL.S50 Aluminium Louver Doors\Windows 5 5 0% 05-Dec-17 10-Dec-17 -168
GO.PL.S30 Spray Plaster (Ceiling) 5 5 0% 23-Nov-17 28-Nov-17 -254
GO.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 5 5 0% 10-Apr-18 15-Apr-18 -247
GO.SN.100 Work Completion\Snagging 5 5 0% 11-Aug-18 15-Aug-18 -252
GO.AC.400 Grills and Diffusers 5 5 0% 28-Jun-18 03-Jul-18 -253
GO.AC.030 Gas Pipes net work 5 5 0% 07-Feb-18 12-Feb-18 -270
GO.AC.020 Mouse Connection & Fire Damper 5 5 0% 01-Feb-18 06-Feb-18 -264
GO.FF.100 Sprinklers Head Installation 5 5 0% 28-Jun-18 03-Jul-18 -271
GO.FF.110 Hose Reel\Fire Extinguisher 5 5 0% 03-Jul-18 08-Jul-18 -271
GO.EL.F10 Fixing Fire Alarm Devices 5 5 0% 28-Jun-18 03-Jul-18 -266
GO.FO.P10 Corner Guard 5 5 0% 25-Jun-18 30-Jun-18 -242
GO.FL.W10 Floor Tiles 5 5 0% 05-Apr-18 10-Apr-18 -269
GO.AC.100 Duct Drops (Wet Area) 5 5 0% 18-Apr-18 23-Apr-18 -247
GO.AC.110 Duct Drops (Entrance Lobby) 5 5 0% 14-May-18 19-May-18 -271
01.AL.210 Fixing Aluminium Glass 5 5 0% 04-Mar-18 08-Mar-18 -202
01.AL.410 Fixing Aluminium Glass 5 5 0% 14-Mar-18 19-Mar-18 -202
02.AL.210 Fixing Aluminium Glass 5 5 0% 20-Mar-18 25-Mar-18 -212
02.AL.410 Fixing Aluminium Glass 5 5 0% 01-Apr-18 05-Apr-18 -212
03.AL.210 Fixing Aluminium Glass 5 5 0% 05-Apr-18 10-Apr-18 -222

Actual Level of Effort Remaining Work Page 63 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Fixing Aluminium Glass
Fixing Aluminium Glas
Fixing Aluminium Gla

Fixing Sub Frames

Conduits\Boxes & DB's enclosers(walls)

Plaster Work
Wall Tiles
Waterproofing to Wet Area
Suspension System
Final Stage
Waterproofing to Planter
Drainage Pipes-L\L
Aluminium Louver Doors\Windows
Spray Plaster (Ceiling)
Filling\Supply Pipes Installaion (Con

Gas Pipes net work


Mouse Connection & Fire Damper

Floor Tiles
Duct Drops (Wet Area)
Duct Drops (Entrance Lob
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass

Actual Level of Effort Remaining Work Page 64 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
03.AL.410 Fixing Aluminium Glass 5 5 0% 16-Apr-18 21-Apr-18 -222
04.AL.210 Fixing Aluminium Glass 5 5 0% 22-Apr-18 26-Apr-18 -237
04.AL.410 Fixing Aluminium Glass 5 5 0% 02-May-18 07-May-18 -237
05.AL.210 Fixing Aluminium Glass 5 5 0% 08-May-18 13-May-18 -252
05.AL.410 Fixing Aluminium Glass 5 5 0% 08-May-18 13-May-18 -252
06.AL.210 Fixing Aluminium Glass 5 5 0% 13-May-18 17-May-18 -253
06.AL.410 Fixing Aluminium Glass 5 5 0% 13-May-18 17-May-18 -253
07.AL.210 Fixing Aluminium Glass 5 5 0% 19-May-18 26-May-18 -255
07.AL.410 Fixing Aluminium Glass 5 5 0% 22-May-18 29-May-18 -259
08.AL.210 Fixing Aluminium Glass 5 5 0% 27-May-18 31-May-18 -260
08.AL.410 Fixing Aluminium Glass 5 5 0% 02-Jun-18 06-Jun-18 -266
09.AL.210 Fixing Aluminium Glass 5 5 0% 17-May-18 22-May-18 -253
09.AL.410 Fixing Aluminium Glass 5 5 0% 17-May-18 22-May-18 -253
10.AL.210 Fixing Aluminium Glass 5 5 0% 22-May-18 29-May-18 -256
10.AL.410 Fixing Aluminium Glass 5 5 0% 22-May-18 29-May-18 -256
11.AL.210 Fixing Aluminium Glass 5 5 0% 30-May-18 04-Jun-18 -262
11.AL.410 Fixing Aluminium Glass 5 5 0% 30-May-18 04-Jun-18 -262
12.AL.210 Fixing Aluminium Glass 5 5 0% 05-Jun-18 10-Jun-18 -268
12.AL.410 Fixing Aluminium Glass 5 5 0% 05-Jun-18 10-Jun-18 -268
GO.WD.030 Door Shutters & Ironmongery 6 6 0% 24-Apr-18 30-Apr-18 -267
GO.PL.S20 Plaster (Walls) 6 6 0% 18-Nov-17 23-Nov-17 -254
GO.FL.S40 Screed Flooring 6 6 0% 28-Nov-17 05-Dec-17 -237
GO.PG.040 Emergency Gas Off\On Switch With LED Indicator 6 6 0% 14-May-18 20-May-18 -226
GO.PG.020 Filling\Supply Pipes Installaion 6 6 0% 03-May-18 08-May-18 -226
GO.PG.030 Kitchen Gas Detector 6 6 0% 08-May-18 14-May-18 -226
GO.WS.030 Main Pipes 6 6 0% 20-Jan-18 25-Jan-18 -264
GO.EL.E20 Install Electric Cables Try\Power Cables 6 6 0% 21-Mar-18 26-Mar-18 -255
GO.FL.S10 Screed Flooring 6 6 0% 31-Mar-18 05-Apr-18 -269
GO.PN.E10 Painting Work to False Ceiling (Entrance Lobby) 6 6 0% 10-Jun-18 16-Jun-18 -271
GO.PL.E10 Plaster Work 6 6 0% 30-Oct-17 05-Nov-17 -254
GO.FL.S50 Flooring Tiles 6 6 0% 10-Apr-18 15-Apr-18 -257
01.AL.310 Fixing Aluminium Glass 6 6 0% 08-Mar-18 14-Mar-18 -202
02.AL.110 Fixing Aluminium Glass 6 6 0% 14-Mar-18 20-Mar-18 -212
02.AL.310 Fixing Aluminium Glass 6 6 0% 25-Mar-18 01-Apr-18 -212

Actual Level of Effort Remaining Work Page 65 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glas
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glas
Fixing Aluminium Glas
Fixing Aluminium Gla
Fixing Aluminium Gla
Door Shutters & Ironmongery
Plaster (Walls)
Screed Flooring
Emergency Gas Off\On S
Filling\Supply Pipes Installaion
Kitchen Gas Detector
Main Pipes
Install Electric Cables Try\Power Cables
Screed Flooring

Plaster Work
Flooring Tiles
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass

Actual Level of Effort Remaining Work Page 66 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
03.AL.110 Fixing Aluminium Glass 6 6 0% 01-Apr-18 05-Apr-18 -222
03.AL.310 Fixing Aluminium Glass 6 6 0% 10-Apr-18 16-Apr-18 -222
04.AL.110 Fixing Aluminium Glass 6 6 0% 16-Apr-18 22-Apr-18 -237
04.AL.310 Fixing Aluminium Glass 6 6 0% 26-Apr-18 02-May-18 -237
05.AL.110 Fixing Aluminium Glass 6 6 0% 02-May-18 08-May-18 -247
05.AL.310 Fixing Aluminium Glass 6 6 0% 02-May-18 08-May-18 -247
06.AL.110 Fixing Aluminium Glass 6 6 0% 09-May-18 15-May-18 -267
06.AL.310 Fixing Aluminium Glass 6 6 0% 09-May-18 15-May-18 -250
07.AL.110 Fixing Aluminium Glass 6 6 0% 22-May-18 30-May-18 -260
07.AL.310 Fixing Aluminium Glass 6 6 0% 17-May-18 22-May-18 -254
08.AL.110 Fixing Aluminium Glass 6 6 0% 02-Jun-18 07-Jun-18 -267
08.AL.310 Fixing Aluminium Glass 6 6 0% 27-May-18 02-Jun-18 -261
09.AL.110 Fixing Aluminium Glass 6 6 0% 19-May-18 27-May-18 -256
09.AL.310 Fixing Aluminium Glass 6 6 0% 19-May-18 27-May-18 -256
10.AL.110 Fixing Aluminium Glass 6 6 0% 29-May-18 03-Jun-18 -261
10.AL.310 Fixing Aluminium Glass 6 6 0% 29-May-18 03-Jun-18 -261
11.AL.110 Fixing Aluminium Glass 6 6 0% 05-Jun-18 11-Jun-18 -269
11.AL.310 Fixing Aluminium Glass 6 6 0% 05-Jun-18 11-Jun-18 -269
12.AL.110 Fixing Aluminium Glass 6 6 0% 04-Jun-18 10-Jun-18 -268
12.AL.310 Fixing Aluminium Glass 6 6 0% 04-Jun-18 10-Jun-18 -268
GO.AC.010 FCU & A.C Ducts 7 7 0% 25-Jan-18 01-Feb-18 -264
GO.FF.010 Hz. Pipes H\L 7 7 0% 12-Feb-18 18-Feb-18 -270
GO.DR.090 Catch basin 7 7 0% 11-Jun-18 17-Jun-18 -224
GO.DR.050 Floor Trap & Drainage Pipes- H\L 7 7 0% 20-Feb-18 26-Feb-18 -257
GO.EL.020 Pulling All Types Of Wires 7 7 0% 12-Mar-18 18-Mar-18 -271
GO.EL.S50 Security System Control Panel 7 7 0% 21-Jun-18 28-Jun-18 -271
GO.EL.S10 Security System Devices 7 7 0% 16-Jun-18 21-Jun-18 -271
GO.CO.100 Dismantling Shutters 7 7 0% 05-Oct-17 11-Oct-17 -270
GO.FO.P20 Wheel Stopper\Spead Breakers 7 7 0% 30-Jun-18 05-Jul-18 -242
GO.EL.C20 Emergency Light Control Panel 7 7 0% 02-Aug-18 09-Aug-18 -251
GO.FL.P20 Interlock 7 7 0% 13-May-18 20-May-18 -242
GO.PN.P60 Road Marking 8 8 0% 29-Jul-18 05-Aug-18 -246
GO.CO.S10 Trenches and Builders Work 9 9 0% 23-Oct-17 31-Oct-17 -235
GO.CO.020 R.C.C Slab (1st Floor Slab)\Electric Conduits 10 10 0% 14-Sep-17 24-Sep-17 -271

Actual Level of Effort Remaining Work Page 67 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Gla
Fixing Aluminium Glas
Fixing Aluminium Glass
Fixing Aluminium Glass
Fixing Aluminium Glas
Fixing Aluminium Glas
Fixing Aluminium Gl
Fixing Aluminium Gl
Fixing Aluminium Gla
Fixing Aluminium Gla
FCU & A.C Ducts
Hz. Pipes H\L

Floor Trap & Drainage Pipes- H\L


Pulling All Types Of Wires

Dismantling Shutters

Interlock

Trenches and Builders Work


R.C.C Slab (1st Floor Slab)\Electric Conduits

Actual Level of Effort Remaining Work Page 68 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
GO.PG.100 Gas Alarm Control Panel 12 12 0% 20-May-18 03-Jun-18 -226
GO.BL.010 Block Work\Concrete Upstand,Lintels (Include Planter) 12 12 0% 11-Oct-17 23-Oct-17 -270
GO.AL.010 Aluminium Doors\Glass Door\Louver Door 12 12 0% 04-Jul-18 15-Jul-18 -252
GO.AL.020 Fixing Aluminium Glass 12 12 0% 15-Jul-18 26-Jul-18 -251
GO.EL.S70 Finishing & Electric Work,etc.... 14 14 0% 10-Dec-17 23-Dec-17 -168
GO.PN.P50 Thermoplastic Paint 14 14 0% 15-Jul-18 29-Jul-18 -252
GO.FL.E10 Floor Tiles- Entrance and Lobby 14 14 0% 11-Apr-18 24-Apr-18 -271
GO.CL.E20 Wall Tiles- Entrance\Lift Lobby 14 14 0% 29-Mar-18 11-Apr-18 -271
GO.PN.010 Primer & Stucco 14 14 0% 24-Jan-18 07-Feb-18 -270
GO.PN.020 Painting Work 14 14 0% 30-Apr-18 13-May-18 -267
GO.PN.P10 Painting Work For Ceiling (Parking) 14 14 0% 18-Nov-17 03-Dec-17 -213
GO.PL.P10 Plaster Work 14 14 0% 05-Nov-17 18-Nov-17 -254
GO.FO.P40 Biycle Rack 14 14 0% 29-Jul-18 11-Aug-18 -252
GO.FO.E10 Reciption Counter 14 14 0% 26-Jul-18 08-Aug-18 -250
GO.EL.E40 Generator 14 14 0% 13-May-18 29-May-18 -267
GO.FF.200 Foam System 14 14 0% 29-May-18 11-Jun-18 -242
GO.EL.F50 Fire Alarm Control Panel 14 14 0% 03-Jul-18 16-Jul-18 -266
GO.EL.E50 DB'S Terminations\LV Panels\Capactor Bank 21 21 0% 29-May-18 17-Jun-18 -267
GO.FL.P50 Epoxy Coating 21 21 0% 20-May-18 11-Jun-18 -242
GO.FC.E20 Suspension System 21 21 0% 24-Apr-18 14-May-18 -271
GO.FC.E30 Final Stage 21 21 0% 19-May-18 10-Jun-18 -271

- 1st Floor 297 297 0% 25-Sep-17 05-Jul-18 -240

01.AC.900 Work Completion 0 0 0% 24-Jun-18 -243


01.FF.900 Work Completion 0 0 0% 14-Jun-18 -246
01.WS.900 Work Completion 0 0 0% 13-Jun-18 -246
01.EL.F90 Work Completion (Fire Alarm) 0 0 0% 18-Jun-18 -243
01.EL.T90 Work Completion (Telephone) 0 0 0% 13-Feb-18 -269
01.EL.L90 Work Completion (Low Current) 0 0 0% 01-Jul-18 -240
01.EL.E90 Work Completion (Electric) 0 0 0% 16-Jun-18 -251
01.DR.900 Work Completion 0 0 0% 07-Jun-18 -255
01.PG.900 Work Completion 0 0 0% 20-Jun-18 -245
01.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 15-May-18 -262
01.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 25-Feb-18 -219

Actual Level of Effort Remaining Work Page 69 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Gas Alarm Control Pa
Block Work\Concrete Upstand,Lintels (Include Planter)

Finishing & Electric Work,etc....

Floor Tiles- Entrance and Lobby


Wall Tiles- Entrance\Lift Lobby
Primer & Stucco
Painting Work
Painting Work For Ceiling (Parking)
Plaster Work

Generator
Foam System

Epoxy Coating
Suspension System
Final Stage

Work Completion (Telephone),

Work Completion,

Floor Weather Tight (to Sta


MEP CLEARANCE- Dry Area, 25-Feb-18

Actual Level of Effort Remaining Work Page 70 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
01.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 06-Mar-18 -219
01.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 11-Feb-18 -220
01.AC.040 Pipes Testing 2 2 0% 27-Nov-17 28-Nov-17 -252
01.FF.020 Pipes Testing 2 2 0% 03-Dec-17 05-Dec-17 -252
01.WS.040 Pipes Testing 2 2 0% 10-Jan-18 11-Jan-18 -243
01.DR.020 Pipes Testing 2 2 0% 09-Dec-17 11-Dec-17 -252
01.CO.010 R.C.C Columns\Walls 3 3 0% 25-Sep-17 27-Sep-17 -271
01.EL.C10 Emergency Light 3 3 0% 16-Jun-18 18-Jun-18 -233
01.FL.100 Marble Threshold 3 3 0% 10-Jun-18 12-Jun-18 -245
01.FF.030 Sprinkler Heads 4 4 0% 10-Jun-18 13-Jun-18 -245
01.EL.T20 Install Telephone Cables 4 4 0% 29-Jan-18 01-Feb-18 -269
01.PG.100 Flexible Hose 4 4 0% 17-Jun-18 20-Jun-18 -245
01.AL.500 Aluminium Windows-Shutters 4 4 0% 08-May-18 13-May-18 -262
01.FL.D20 Screed Flooring 4 4 0% 01-Feb-18 05-Feb-18 -227
01.WD.010 Fixing Sub Frames 4 4 0% 08-Nov-17 13-Nov-17 -237
01.AC.050 Duct Drops (Wet Area) 4 4 0% 25-Feb-18 28-Feb-18 -220
01.AC.060 Duct Drops (Dry Area) 4 4 0% 06-Mar-18 10-Mar-18 -192
01.AC.070 Duct Drops (Corridors) 4 4 0% 13-Mar-18 17-Mar-18 -192
11.BL.110 Block Work (Closing around Vertical Ducts & Risers) 4 4 0% 01-Apr-18 04-Apr-18 -270
12.BL.110 Block Work (Closing around Vertical Ducts & Risers) 4 4 0% 01-Apr-18 04-Apr-18 -267
01.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 10-Jun-18 14-Jun-18 -246
01.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 06-Nov-17 11-Nov-17 -252
01.WS.020 Main Pipes 5 5 0% 11-Nov-17 15-Nov-17 -252
01.EL.F20 Fixing Fire Alarm Devices 5 5 0% 13-Jun-18 18-Jun-18 -243
01.EL.010 Conduits, Boxes & enclosure 5 5 0% 06-Nov-17 11-Nov-17 -235
01.EL.E30 Isolators In High Level 5 5 0% 18-Jan-18 23-Jan-18 -269
01.FL.D90 Epoxy Coating 5 5 0% 05-Jun-18 10-Jun-18 -245
01.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 05-Jun-18 10-Jun-18 -251
01.SN.010 Work Completion\Snagging Work 5 5 0% 01-Jul-18 05-Jul-18 -240
01.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 11-Dec-17 16-Dec-17 -271
02.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 16-Dec-17 20-Dec-17 -262
03.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 26-Dec-17 31-Dec-17 -260
04.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 31-Dec-17 06-Jan-18 -251
05.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 23-Jan-18 28-Jan-18 -260

Actual Level of Effort Remaining Work Page 71 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MEP CLEARANCE- Corridors and Lift Lobby, 0
MEP CLEARANCE- Wet Area, 11-Feb-18
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing
R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-Shutte
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridors)
Block Work (Closing around Vertical D
Block Work (Closing around Vertical D

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level
Epoxy Coating
Painting Work to Fa

Block Work (Closing around Vertical Ducts & Risers)


Block Work (Closing around Vertical Ducts & Risers)
Block Work (Closing around Vertical Ducts & Risers)
Block Work (Closing around Vertical Ducts & Risers)
Block Work (Closing around Vertical Ducts & Risers)

Actual Level of Effort Remaining Work Page 72 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
06.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 28-Jan-18 01-Feb-18 -254
07.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 18-Feb-18 22-Feb-18 -270
08.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 22-Feb-18 27-Feb-18 -255
09.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 17-Mar-18 21-Mar-18 -271
10.BL.110 Block Work (Closing around Vertical Ducts & Risers) 5 5 0% 21-Mar-18 26-Mar-18 -267
01.AC.110 Grills and Diffusers 6 6 0% 18-Jun-18 24-Jun-18 -243
01.FF.010 Hz. Pipes H\L 6 6 0% 27-Nov-17 03-Dec-17 -252
01.WS.050 Valves, Mixer's, etc... 6 6 0% 07-Jun-18 13-Jun-18 -246
01.WS.030 Water Heater 6 6 0% 04-Jan-18 10-Jan-18 -243
01.EL.C20 Emergency Light Control Panel 6 6 0% 18-Jun-18 24-Jun-18 -233
01.EL.S20 Security System Devices 6 6 0% 18-Jun-18 24-Jun-18 -240
01.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 10-Jun-18 16-Jun-18 -251
01.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 23-Jan-18 29-Jan-18 -269
01.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 03-Jun-18 07-Jun-18 -255
01.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 03-Dec-17 09-Dec-17 -252
01.DR.030 Fixing Of Bath Tub 6 6 0% 17-Jan-18 23-Jan-18 -219
01.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 11-Feb-18 17-Feb-18 -220
01.AL.400 Aluminium Windows-Shutters 6 6 0% 26-Feb-18 04-Mar-18 -193
01.AL.200 Aluminium Windows-Shutters 6 6 0% 26-Feb-18 04-Mar-18 -204
01.FL.W40 Floor Tiles- Wet Area 6 6 0% 05-Feb-18 11-Feb-18 -220
01.CL.W10 Wall Tiles- Wet Area 6 6 0% 28-Dec-17 04-Jan-18 -243
01.FO.040 Mirrors & Bath Accessories 6 6 0% 13-Jun-18 19-Jun-18 -246
01.DR.050 Pipes In Walls 6 6 0% 11-Nov-17 16-Nov-17 -235
01.DR.910 Drinage Pipes L\L 6 6 0% 11-Jan-18 17-Jan-18 -233
01.AL.110 Fixing Aluminium Glass 6 6 0% 26-Feb-18 04-Mar-18 -202
01.CO.100 Dismantling Shutters 7 7 0% 17-Oct-17 24-Oct-17 -271
01.AC.020 Mouse Connection & Fire Damper 7 7 0% 20-Nov-17 27-Nov-17 -252
01.AC.030 Gas Pipes net work 7 7 0% 20-Nov-17 27-Nov-17 -252
01.EL.S40 Security System Control Panels 7 7 0% 24-Jun-18 01-Jul-18 -240
01.EL.020 Pulling All Types Of Wires 7 7 0% 11-Jan-18 18-Jan-18 -269
01.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 02-May-18 08-May-18 -267
01.WD.030 Door Shutters & Ironmongery 7 7 0% 15-May-18 22-May-18 -255
01.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 07-Mar-18 13-Mar-18 -220
01.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 22-May-18 31-May-18 -262

Actual Level of Effort Remaining Work Page 73 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Block Work (Closing around Vertical Ducts & Risers)
Block Work (Closing around Vertical Ducts & Rise
Block Work (Closing around Vertical Ducts & Ris
Block Work (Closing around Vertical Ducts
Block Work (Closing around Vertical Duc

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Power Cables


Sanitary Ware, Kitch
Floor Trap & Drainage Pipes H\L
Fixing Of Bath Tub
Filling\Supply Pipes Installaion (Concealed Part)
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Fixing Aluminium Glass
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and Lo
Door Shutters & Ironmon
Suspension System- Corridors and Lift Lobb
Final Stage- Corridors

Actual Level of Effort Remaining Work Page 74 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
01.FC.W30 Final Stage- Wet Area 7 7 0% 28-Feb-18 07-Mar-18 -220
01.WP.W20 Waterproofing- Wet Area 7 7 0% 04-Jan-18 10-Jan-18 -239
01.AL.100 Aluminium Windows-Shutters 8 8 0% 19-Feb-18 26-Feb-18 -210
01.AL.300 Aluminium Windows-Shutters 8 8 0% 19-Feb-18 26-Feb-18 -199
01.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 04-Jan-18 11-Jan-18 -229
01.FC.D30 Final Stage- Dry Area 8 8 0% 15-May-18 22-May-18 -262
01.CO.050 R.C.C Slab (2nd Floor Slab)\Electric Conduits 9 9 0% 27-Sep-17 07-Oct-17 -271
01.AC.010 FCU & A.C Ducts 9 9 0% 15-Nov-17 23-Nov-17 -252
01.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 24-Mar-18 02-Apr-18 -179
01.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 07-Mar-18 15-Mar-18 -215
01.PG.030 Kitchen Gas Detector 9 9 0% 15-Mar-18 24-Mar-18 -179
01.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 11-Feb-18 19-Feb-18 -213
01.FC.W20 Suspension System- Wet Area 9 9 0% 17-Feb-18 25-Feb-18 -220
01.FC.D20 Suspension System- Dry Area 10 10 0% 25-Feb-18 06-Mar-18 -219
01.PG.090 Gas Alarm Control Panel 12 12 0% 05-Jun-18 17-Jun-18 -245
01.PN.020 Painting Work 12 12 0% 22-May-18 05-Jun-18 -251
01.EL.T30 ONU Termination 13 13 0% 01-Feb-18 13-Feb-18 -269
01.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 24-Oct-17 06-Nov-17 -271
01.EL.E50 DB'S Dressing\Terminations 14 14 0% 29-Jan-18 11-Feb-18 -233
01.PL.010 Plaster Work- Service\Dry Area 14 14 0% 16-Dec-17 28-Dec-17 -271
01.FO.020 Kitchen Cabinet 14 14 0% 17-May-18 03-Jun-18 -255
01.FO.030 Vanity Counter 14 14 0% 17-May-18 03-Jun-18 -255
01.PN.010 Primer & Stucco 14 14 0% 28-Dec-17 11-Jan-18 -271
01.FO.010 Wardrobes 21 21 0% 05-Jun-18 25-Jun-18 -234

- 2nd Floor 291 291 0% 07-Oct-17 11-Jul-18 -247

02.AC.900 Work Completion 0 0 0% 01-Jul-18 -250


02.FF.900 Work Completion 0 0 0% 21-Jun-18 -253
02.WS.900 Work Completion 0 0 0% 20-Jun-18 -250
02.EL.F90 Work Completion (Fire Alarm) 0 0 0% 25-Jun-18 -250
02.EL.T90 Work Completion (Telephone) 0 0 0% 01-Mar-18 -269
02.EL.L90 Work Completion (Low Current) 0 0 0% 07-Jul-18 -247
02.EL.E90 Work Completion (Electric) 0 0 0% 21-Jun-18 -252
02.DR.900 Work Completion 0 0 0% 14-Jun-18 -256

Actual Level of Effort Remaining Work Page 75 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Final Stage- Wet Area
Waterproofing- Wet Area
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area
R.C.C Slab (2nd Floor Slab)\Electric Conduits
FCU & A.C Ducts
Emergency Gas Off\On Switch With LE
Filling\Supply Pipes Installaion (Exposed)
Kitchen Gas Detector
Flooring Tiles- Service\Dry Area
Suspension System- Wet Area
Suspension System- Dry Area

Painting Work
ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work- Service\Dry Area
Kitchen Cabinet
Vanity Counter
Primer & Stucco

Work Completion (Telephone),

Actual Level of Effort Remaining Work Page 76 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
02.PG.900 Work Completion 0 0 0% 26-Jun-18 -252
02.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 22-May-18 -262
02.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 22-Mar-18 -240
02.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 02-Apr-18 -240
02.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 26-Feb-18 -240
02.AC.040 Pipes Testing 2 2 0% 11-Dec-17 12-Dec-17 -252
02.FF.020 Pipes Testing 2 2 0% 17-Dec-17 18-Dec-17 -252
02.WS.040 Pipes Testing 2 2 0% 23-Jan-18 24-Jan-18 -249
02.DR.020 Pipes Testing 2 2 0% 21-Dec-17 24-Dec-17 -252
02.CO.010 R.C.C Columns\Walls 3 3 0% 07-Oct-17 10-Oct-17 -271
02.EL.C10 Emergency Light 3 3 0% 21-Jun-18 25-Jun-18 -240
02.FL.100 Marble Threshold 3 3 0% 17-Jun-18 19-Jun-18 -249
02.FF.030 Sprinkler Heads 4 4 0% 17-Jun-18 20-Jun-18 -252
02.EL.T20 Install Telephone Cables 4 4 0% 13-Feb-18 17-Feb-18 -269
02.PG.100 Flexible Hose 4 4 0% 23-Jun-18 26-Jun-18 -252
02.AL.500 Aluminium Windows-Shutters 4 4 0% 15-May-18 19-May-18 -262
02.FL.D20 Screed Flooring 4 4 0% 17-Feb-18 21-Feb-18 -240
02.WD.010 Fixing Sub Frames 4 4 0% 22-Nov-17 26-Nov-17 -237
02.AC.050 Duct Drops (Wet Area) 4 4 0% 12-Mar-18 17-Mar-18 -240
02.AC.060 Duct Drops (Dry Area) 4 4 0% 02-Apr-18 05-Apr-18 -213
02.AC.070 Duct Drops (Corridors) 4 4 0% 09-Apr-18 12-Apr-18 -212
02.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 17-Jun-18 21-Jun-18 -253
02.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 19-Nov-17 23-Nov-17 -252
02.WS.020 Main Pipes 5 5 0% 23-Nov-17 28-Nov-17 -252
02.EL.F20 Fixing Fire Alarm Devices 5 5 0% 20-Jun-18 25-Jun-18 -250
02.EL.010 Conduits, Boxes & enclosure 5 5 0% 19-Nov-17 23-Nov-17 -235
02.EL.E30 Isolators In High Level 5 5 0% 31-Jan-18 05-Feb-18 -266
02.FL.D90 Epoxy Coating 5 5 0% 12-Jun-18 17-Jun-18 -256
02.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 12-Jun-18 17-Jun-18 -253
02.SN.010 Work Completion\Snagging Work 5 5 0% 07-Jul-18 11-Jul-18 -247
02.AC.110 Grills and Diffusers 6 6 0% 25-Jun-18 01-Jul-18 -250
02.FF.010 Hz. Pipes H\L 6 6 0% 11-Dec-17 17-Dec-17 -252
02.WS.050 Valves, Mixer's, etc... 6 6 0% 14-Jun-18 20-Jun-18 -250
02.WS.030 Water Heater 6 6 0% 17-Jan-18 23-Jan-18 -249

Actual Level of Effort Remaining Work Page 77 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Floor Weather Tight (to S


MEP CLEARANCE- Dry Area, 22-Mar-18
MEP CLEARANCE- Corridors and Lift L
MEP CLEARANCE- Wet Area, 26-Feb-18
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing
R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-Shut
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridors)

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Hz. Pipes H\L

Water Heater

Actual Level of Effort Remaining Work Page 78 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
02.EL.C20 Emergency Light Control Panel 6 6 0% 25-Jun-18 01-Jul-18 -240
02.EL.S20 Security System Devices 6 6 0% 25-Jun-18 01-Jul-18 -247
02.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 17-Jun-18 21-Jun-18 -252
02.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 05-Feb-18 11-Feb-18 -266
02.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 09-Jun-18 14-Jun-18 -256
02.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 17-Dec-17 21-Dec-17 -252
02.DR.030 Fixing Of Bath Tub 6 6 0% 30-Jan-18 05-Feb-18 -227
02.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 26-Feb-18 04-Mar-18 -240
02.AL.400 Aluminium Windows-Shutters 6 6 0% 07-Mar-18 12-Mar-18 -196
02.AL.200 Aluminium Windows-Shutters 6 6 0% 07-Mar-18 12-Mar-18 -207
02.FL.W40 Floor Tiles- Wet Area 6 6 0% 21-Feb-18 26-Feb-18 -240
02.CL.W10 Wall Tiles- Wet Area 6 6 0% 11-Jan-18 17-Jan-18 -249
02.FO.040 Mirrors & Bath Accessories 6 6 0% 20-Jun-18 26-Jun-18 -247
02.DR.050 Pipes In Walls 6 6 0% 23-Nov-17 29-Nov-17 -235
02.DR.910 Drinage Pipes L\L 6 6 0% 24-Jan-18 30-Jan-18 -241
02.CO.100 Dismantling Shutters 7 7 0% 30-Oct-17 05-Nov-17 -270
02.AC.020 Mouse Connection & Fire Damper 7 7 0% 04-Dec-17 11-Dec-17 -252
02.AC.030 Gas Pipes net work 7 7 0% 04-Dec-17 11-Dec-17 -252
02.EL.S40 Security System Control Panels 7 7 0% 01-Jul-18 07-Jul-18 -247
02.EL.020 Pulling All Types Of Wires 7 7 0% 24-Jan-18 31-Jan-18 -266
02.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 08-May-18 15-May-18 -267
02.WD.030 Door Shutters & Ironmongery 7 7 0% 22-May-18 30-May-18 -256
02.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 02-Apr-18 09-Apr-18 -240
02.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 31-May-18 07-Jun-18 -262
02.FC.W30 Final Stage- Wet Area 7 7 0% 17-Mar-18 22-Mar-18 -240
02.WP.W20 Waterproofing- Wet Area 7 7 0% 17-Jan-18 24-Jan-18 -246
02.AL.100 Aluminium Windows-Shutters 8 8 0% 07-Mar-18 14-Mar-18 -219
02.AL.300 Aluminium Windows-Shutters 8 8 0% 07-Mar-18 14-Mar-18 -208
02.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 17-Jan-18 24-Jan-18 -235
02.FC.D30 Final Stage- Dry Area 8 8 0% 22-May-18 31-May-18 -262
02.CO.050 R.C.C Slab (3rd Floor Slab)\Electric Conduits 9 9 0% 10-Oct-17 18-Oct-17 -271
02.AC.010 FCU & A.C Ducts 9 9 0% 28-Nov-17 07-Dec-17 -252
02.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 10-Apr-18 18-Apr-18 -196
02.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 22-Mar-18 01-Apr-18 -223

Actual Level of Effort Remaining Work Page 79 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Install Electric Cables Try\Power Cables

Floor Trap & Drainage Pipes H\L


Fixing Of Bath Tub
Filling\Supply Pipes Installaion (Concealed Part)
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and L
Door Shutters & Ironm
Suspension System- Corridors and L
Final Stage- Corridor
Final Stage- Wet Area
Waterproofing- Wet Area
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area
R.C.C Slab (3rd Floor Slab)\Electric Conduits
FCU & A.C Ducts
Emergency Gas Off\On Switch Wi
Filling\Supply Pipes Installaion (Exposed

Actual Level of Effort Remaining Work Page 80 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
02.PG.030 Kitchen Gas Detector 9 9 0% 01-Apr-18 10-Apr-18 -196
02.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 26-Feb-18 07-Mar-18 -223
02.FC.W20 Suspension System- Wet Area 9 9 0% 04-Mar-18 12-Mar-18 -240
02.FC.D20 Suspension System- Dry Area 10 10 0% 22-Mar-18 02-Apr-18 -240
02.PG.090 Gas Alarm Control Panel 12 12 0% 12-Jun-18 23-Jun-18 -252
02.PN.020 Painting Work 12 12 0% 31-May-18 12-Jun-18 -256
02.EL.T30 ONU Termination 13 13 0% 17-Feb-18 01-Mar-18 -269
02.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 06-Nov-17 19-Nov-17 -271
02.EL.E50 DB'S Dressing\Terminations 14 14 0% 11-Feb-18 24-Feb-18 -233
02.PL.010 Plaster Work 14 14 0% 28-Dec-17 11-Jan-18 -271
02.FO.020 Kitchen Cabinet 14 14 0% 27-May-18 09-Jun-18 -256
02.FO.030 Vanity Counter 14 14 0% 27-May-18 09-Jun-18 -256
02.PN.010 Primer & Stucco 14 14 0% 11-Jan-18 24-Jan-18 -271
02.FO.010 Wardrobes 21 21 0% 12-Jun-18 01-Jul-18 -241

- 3rd Floor 285 285 0% 19-Oct-17 18-Jul-18 -254

03.AC.900 Work Completion 0 0 0% 07-Jul-18 -257


03.FF.900 Work Completion 0 0 0% 27-Jun-18 -260
03.WS.900 Work Completion 0 0 0% 26-Jun-18 -257
03.EL.F90 Work Completion (Fire Alarm) 0 0 0% 01-Jul-18 -257
03.EL.T90 Work Completion (Telephone) 0 0 0% 17-Mar-18 -269
03.EL.L90 Work Completion (Low Current) 0 0 0% 14-Jul-18 -254
03.EL.E90 Work Completion (Electric) 0 0 0% 28-Jun-18 -253
03.DR.900 Work Completion 0 0 0% 21-Jun-18 -257
03.PG.900 Work Completion 0 0 0% 03-Jul-18 -259
03.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 30-May-18 -262
03.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 09-Apr-18 -250
03.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 18-Apr-18 -250
03.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 14-Mar-18 -250
03.AC.040 Pipes Testing 2 2 0% 24-Dec-17 26-Dec-17 -252
03.FF.020 Pipes Testing 2 2 0% 30-Dec-17 31-Dec-17 -252
03.WS.040 Pipes Testing 2 2 0% 05-Feb-18 07-Feb-18 -255
03.DR.020 Pipes Testing 2 2 0% 06-Jan-18 07-Jan-18 -252
03.CO.010 R.C.C Columns\Walls 3 3 0% 19-Oct-17 22-Oct-17 -271

Actual Level of Effort Remaining Work Page 81 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Kitchen Gas Detector
Flooring Tiles- Service\Dry Area
Suspension System- Wet Area
Suspension System- Dry Area

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work
Kitchen Cabinet
Vanity Counter
Primer & Stucco

Work Completion (Telephone),

Floor Weather Tight (to


MEP CLEARANCE- Dry Area, 09-Apr
MEP CLEARANCE- Corridors and
MEP CLEARANCE- Wet Area, 14-Mar-18
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing
R.C.C Columns\Walls

Actual Level of Effort Remaining Work Page 82 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
03.EL.C10 Emergency Light 3 3 0% 28-Jun-18 01-Jul-18 -247
03.FL.100 Marble Threshold 3 3 0% 23-Jun-18 26-Jun-18 -253
03.FF.030 Sprinkler Heads 4 4 0% 23-Jun-18 26-Jun-18 -259
03.EL.T20 Install Telephone Cables 4 4 0% 01-Mar-18 05-Mar-18 -269
03.PG.100 Flexible Hose 4 4 0% 30-Jun-18 03-Jul-18 -259
03.AL.500 Aluminium Windows-Shutters 4 4 0% 22-May-18 28-May-18 -264
03.FL.D20 Screed Flooring 4 4 0% 05-Mar-18 08-Mar-18 -250
03.WD.010 Fixing Sub Frames 4 4 0% 06-Dec-17 10-Dec-17 -237
03.AC.050 Duct Drops (Wet Area) 4 4 0% 29-Mar-18 02-Apr-18 -250
03.AC.060 Duct Drops (Dry Area) 4 4 0% 18-Apr-18 22-Apr-18 -223
03.AC.070 Duct Drops (Corridors) 4 4 0% 24-Apr-18 29-Apr-18 -222
03.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 23-Jun-18 27-Jun-18 -260
03.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 03-Dec-17 07-Dec-17 -252
03.WS.020 Main Pipes 5 5 0% 07-Dec-17 12-Dec-17 -252
03.EL.F20 Fixing Fire Alarm Devices 5 5 0% 26-Jun-18 01-Jul-18 -257
03.EL.010 Conduits, Boxes & enclosure 5 5 0% 03-Dec-17 07-Dec-17 -235
03.EL.E30 Isolators In High Level 5 5 0% 13-Feb-18 18-Feb-18 -263
03.FL.D90 Epoxy Coating 5 5 0% 18-Jun-18 23-Jun-18 -258
03.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 18-Jun-18 23-Jun-18 -260
03.SN.010 Work Completion\Snagging Work 5 5 0% 14-Jul-18 18-Jul-18 -254
03.AC.110 Grills and Diffusers 6 6 0% 01-Jul-18 07-Jul-18 -257
03.FF.010 Hz. Pipes H\L 6 6 0% 24-Dec-17 30-Dec-17 -252
03.WS.050 Valves, Mixer's, etc... 6 6 0% 21-Jun-18 26-Jun-18 -257
03.WS.030 Water Heater 6 6 0% 30-Jan-18 05-Feb-18 -255
03.EL.C20 Emergency Light Control Panel 6 6 0% 01-Jul-18 07-Jul-18 -247
03.EL.S20 Security System Devices 6 6 0% 01-Jul-18 07-Jul-18 -254
03.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 23-Jun-18 28-Jun-18 -253
03.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 18-Feb-18 24-Feb-18 -263
03.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 16-Jun-18 21-Jun-18 -257
03.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 30-Dec-17 06-Jan-18 -252
03.DR.030 Fixing Of Bath Tub 6 6 0% 12-Feb-18 17-Feb-18 -234
03.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 14-Mar-18 20-Mar-18 -250
03.AL.400 Aluminium Windows-Shutters 6 6 0% 01-Apr-18 05-Apr-18 -215
03.AL.200 Aluminium Windows-Shutters 6 6 0% 01-Apr-18 05-Apr-18 -226

Actual Level of Effort Remaining Work Page 83 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Install Telephone Cables

Aluminium Windows-Sh
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridors)

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Power Cables

Floor Trap & Drainage Pipes H\L


Fixing Of Bath Tub
Filling\Supply Pipes Installaion (Concealed
Aluminium Windows-Shutters
Aluminium Windows-Shutters

Actual Level of Effort Remaining Work Page 84 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
03.FL.W40 Floor Tiles- Wet Area 6 6 0% 08-Mar-18 14-Mar-18 -250
03.CL.W10 Wall Tiles- Wet Area 6 6 0% 24-Jan-18 30-Jan-18 -255
03.FO.040 Mirrors & Bath Accessories 6 6 0% 26-Jun-18 02-Jul-18 -248
03.DR.050 Pipes In Walls 6 6 0% 07-Dec-17 13-Dec-17 -235
03.DR.910 Drinage Pipes L\L 6 6 0% 06-Feb-18 12-Feb-18 -248
03.CO.100 Dismantling Shutters 7 7 0% 11-Nov-17 18-Nov-17 -269
03.AC.020 Mouse Connection & Fire Damper 7 7 0% 17-Dec-17 24-Dec-17 -252
03.AC.030 Gas Pipes net work 7 7 0% 17-Dec-17 24-Dec-17 -252
03.EL.S40 Security System Control Panels 7 7 0% 07-Jul-18 14-Jul-18 -254
03.EL.020 Pulling All Types Of Wires 7 7 0% 07-Feb-18 13-Feb-18 -263
03.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 15-May-18 22-May-18 -267
03.WD.030 Door Shutters & Ironmongery 7 7 0% 30-May-18 06-Jun-18 -259
03.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 18-Apr-18 24-Apr-18 -250
03.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 07-Jun-18 13-Jun-18 -262
03.FC.W30 Final Stage- Wet Area 7 7 0% 02-Apr-18 09-Apr-18 -250
03.WP.W20 Waterproofing- Wet Area 7 7 0% 30-Jan-18 06-Feb-18 -253
03.AL.100 Aluminium Windows-Shutters 8 8 0% 22-Mar-18 01-Apr-18 -228
03.AL.300 Aluminium Windows-Shutters 8 8 0% 22-Mar-18 01-Apr-18 -217
03.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 30-Jan-18 07-Feb-18 -241
03.FC.D30 Final Stage- Dry Area 8 8 0% 30-May-18 07-Jun-18 -262
03.CO.050 R.C.C Slab (4th Floor Slab)\Electric Conduits 9 9 0% 22-Oct-17 30-Oct-17 -271
03.AC.010 FCU & A.C Ducts 9 9 0% 12-Dec-17 21-Dec-17 -252
03.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 25-Apr-18 03-May-18 -213
03.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 09-Apr-18 17-Apr-18 -231
03.PG.030 Kitchen Gas Detector 9 9 0% 17-Apr-18 25-Apr-18 -213
03.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 14-Mar-18 22-Mar-18 -233
03.FC.W20 Suspension System- Wet Area 9 9 0% 20-Mar-18 29-Mar-18 -250
03.FC.D20 Suspension System- Dry Area 10 10 0% 09-Apr-18 18-Apr-18 -250
03.PG.090 Gas Alarm Control Panel 12 12 0% 18-Jun-18 30-Jun-18 -259
03.PN.020 Painting Work 12 12 0% 07-Jun-18 18-Jun-18 -260
03.EL.T30 ONU Termination 13 13 0% 05-Mar-18 17-Mar-18 -269
03.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 19-Nov-17 03-Dec-17 -271
03.EL.E50 DB'S Dressing\Terminations 14 14 0% 24-Feb-18 08-Mar-18 -233
03.PL.010 Plaster Work 14 14 0% 11-Jan-18 24-Jan-18 -271

Actual Level of Effort Remaining Work Page 85 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and
Door Shutters & Iron
Suspension System- Corridors a

Final Stage- Wet Area


Waterproofing- Wet Area
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area
R.C.C Slab (4th Floor Slab)\Electric Conduits
FCU & A.C Ducts
Emergency Gas Off\On Switch
Filling\Supply Pipes Installaion (Exp
Kitchen Gas Detector
Flooring Tiles- Service\Dry Area
Suspension System- Wet Area
Suspension System- Dry Area

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work

Actual Level of Effort Remaining Work Page 86 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
03.FO.020 Kitchen Cabinet 14 14 0% 03-Jun-18 16-Jun-18 -257
03.FO.030 Vanity Counter 14 14 0% 03-Jun-18 16-Jun-18 -257
03.PN.010 Primer & Stucco 14 14 0% 24-Jan-18 07-Feb-18 -271
03.FO.010 Wardrobes 21 21 0% 18-Jun-18 08-Jul-18 -248

- 4th Floor 279 279 0% 31-Oct-17 24-Jul-18 -261

04.AC.900 Work Completion 0 0 0% 14-Jul-18 -264


04.FF.900 Work Completion 0 0 0% 04-Jul-18 -267
04.WS.900 Work Completion 0 0 0% 03-Jul-18 -264
04.EL.F90 Work Completion (Fire Alarm) 0 0 0% 08-Jul-18 -264
04.EL.T90 Work Completion (Telephone) 0 0 0% 03-Apr-18 -269
04.EL.L90 Work Completion (Low Current) 0 0 0% 19-Jul-18 -261
04.EL.E90 Work Completion (Electric) 0 0 0% 05-Jul-18 -246
04.DR.900 Work Completion 0 0 0% 27-Jun-18 -264
04.PG.900 Work Completion 0 0 0% 10-Jul-18 -266
04.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 06-Jun-18 -267
04.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 24-Apr-18 -260
04.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 03-May-18 -260
04.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 01-Apr-18 -260
04.AC.040 Pipes Testing 2 2 0% 07-Jan-18 09-Jan-18 -252
04.FF.020 Pipes Testing 2 2 0% 13-Jan-18 15-Jan-18 -252
04.WS.040 Pipes Testing 2 2 0% 18-Feb-18 20-Feb-18 -261
04.DR.020 Pipes Testing 2 2 0% 18-Jan-18 20-Jan-18 -252
04.FL.100 Marble Threshold 2 2 0% 30-Jun-18 01-Jul-18 -257
04.CO.010 R.C.C Columns\Walls 3 3 0% 31-Oct-17 04-Nov-17 -271
04.EL.C10 Emergency Light 3 3 0% 05-Jul-18 08-Jul-18 -254
04.FF.030 Sprinkler Heads 4 4 0% 30-Jun-18 03-Jul-18 -266
04.EL.T20 Install Telephone Cables 4 4 0% 17-Mar-18 21-Mar-18 -269
04.PG.100 Flexible Hose 4 4 0% 05-Jul-18 10-Jul-18 -266
04.AL.500 Aluminium Windows-Shutters 4 4 0% 30-May-18 03-Jun-18 -267
04.FL.D20 Screed Flooring 4 4 0% 21-Mar-18 25-Mar-18 -260
04.WD.010 Fixing Sub Frames 4 4 0% 19-Dec-17 23-Dec-17 -237
04.AC.050 Duct Drops (Wet Area) 4 4 0% 15-Apr-18 18-Apr-18 -260
04.AC.060 Duct Drops (Dry Area) 4 4 0% 03-May-18 08-May-18 -238

Actual Level of Effort Remaining Work Page 87 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Primer & Stucco

Work Completion (Telephone),

Floor Weather Tight (


MEP CLEARANCE- Dry Area, 24
MEP CLEARANCE- Corridors
MEP CLEARANCE- Wet Area, 01-Apr-1
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-S
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)

Actual Level of Effort Remaining Work Page 88 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
04.AC.070 Duct Drops (Corridors) 4 4 0% 10-May-18 14-May-18 -232
04.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 30-Jun-18 04-Jul-18 -267
04.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 17-Dec-17 21-Dec-17 -252
04.WS.020 Main Pipes 5 5 0% 21-Dec-17 26-Dec-17 -252
04.EL.F20 Fixing Fire Alarm Devices 5 5 0% 03-Jul-18 08-Jul-18 -264
04.EL.010 Conduits, Boxes & enclosure 5 5 0% 17-Dec-17 21-Dec-17 -235
04.EL.E30 Isolators In High Level 5 5 0% 26-Feb-18 03-Mar-18 -260
04.FL.D90 Epoxy Coating 5 5 0% 25-Jun-18 30-Jun-18 -260
04.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 25-Jun-18 30-Jun-18 -267
04.SN.010 Work Completion\Snagging Work 5 5 0% 19-Jul-18 24-Jul-18 -261
04.AC.110 Grills and Diffusers 6 6 0% 08-Jul-18 14-Jul-18 -264
04.FF.010 Hz. Pipes H\L 6 6 0% 07-Jan-18 13-Jan-18 -252
04.WS.050 Valves, Mixer's, etc... 6 6 0% 27-Jun-18 03-Jul-18 -264
04.WS.030 Water Heater 6 6 0% 12-Feb-18 18-Feb-18 -261
04.EL.C20 Emergency Light Control Panel 6 6 0% 08-Jul-18 14-Jul-18 -254
04.EL.S20 Security System Devices 6 6 0% 08-Jul-18 14-Jul-18 -261
04.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 30-Jun-18 05-Jul-18 -254
04.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 03-Mar-18 08-Mar-18 -260
04.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 21-Jun-18 27-Jun-18 -264
04.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 13-Jan-18 18-Jan-18 -252
04.DR.030 Fixing Of Bath Tub 6 6 0% 25-Feb-18 03-Mar-18 -242
04.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 01-Apr-18 05-Apr-18 -260
04.AL.400 Aluminium Windows-Shutters 6 6 0% 09-Apr-18 15-Apr-18 -218
04.AL.200 Aluminium Windows-Shutters 6 6 0% 09-Apr-18 15-Apr-18 -229
04.FL.W40 Floor Tiles- Wet Area 6 6 0% 25-Mar-18 01-Apr-18 -260
04.CL.W10 Wall Tiles- Wet Area 6 6 0% 07-Feb-18 12-Feb-18 -261
04.FO.040 Mirrors & Bath Accessories 6 6 0% 03-Jul-18 09-Jul-18 -249
04.DR.050 Pipes In Walls 6 6 0% 21-Dec-17 26-Dec-17 -235
04.DR.910 Drinage Pipes L\L 6 6 0% 19-Feb-18 25-Feb-18 -256
04.CO.100 Dismantling Shutters 7 7 0% 22-Nov-17 29-Nov-17 -271
04.AC.020 Mouse Connection & Fire Damper 7 7 0% 31-Dec-17 07-Jan-18 -252
04.AC.030 Gas Pipes net work 7 7 0% 31-Dec-17 07-Jan-18 -252
04.EL.S40 Security System Control Panels 7 7 0% 14-Jul-18 19-Jul-18 -261
04.EL.020 Pulling All Types Of Wires 7 7 0% 20-Feb-18 26-Feb-18 -264

Actual Level of Effort Remaining Work Page 89 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Duct Drops (Corridors)

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Power Cables

Floor Trap & Drainage Pipes H\L


Fixing Of Bath Tub
Filling\Supply Pipes Installaion (Concea
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires

Actual Level of Effort Remaining Work Page 90 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
04.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 22-May-18 30-May-18 -267
04.WD.030 Door Shutters & Ironmongery 7 7 0% 06-Jun-18 12-Jun-18 -266
04.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 03-May-18 10-May-18 -260
04.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 13-Jun-18 20-Jun-18 -262
04.FC.W30 Final Stage- Wet Area 7 7 0% 18-Apr-18 24-Apr-18 -260
04.WP.W20 Waterproofing- Wet Area 7 7 0% 12-Feb-18 19-Feb-18 -260
04.AL.100 Aluminium Windows-Shutters 8 8 0% 09-Apr-18 16-Apr-18 -237
04.AL.300 Aluminium Windows-Shutters 8 8 0% 09-Apr-18 16-Apr-18 -226
04.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 12-Feb-18 20-Feb-18 -247
04.FC.D30 Final Stage- Dry Area 8 8 0% 06-Jun-18 13-Jun-18 -267
04.CO.050 R.C.C Slab (5th Floor Slab)\Electric Conduits 9 9 0% 04-Nov-17 12-Nov-17 -271
04.AC.010 FCU & A.C Ducts 9 9 0% 26-Dec-17 04-Jan-18 -252
04.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 12-May-18 20-May-18 -230
04.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 24-Apr-18 03-May-18 -239
04.PG.030 Kitchen Gas Detector 9 9 0% 03-May-18 12-May-18 -230
04.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 01-Apr-18 09-Apr-18 -243
04.FC.W20 Suspension System- Wet Area 9 9 0% 05-Apr-18 15-Apr-18 -260
04.FC.D20 Suspension System- Dry Area 10 10 0% 24-Apr-18 03-May-18 -260
04.PG.090 Gas Alarm Control Panel 12 12 0% 25-Jun-18 05-Jul-18 -266
04.PN.020 Painting Work 12 12 0% 13-Jun-18 25-Jun-18 -267
04.EL.T30 ONU Termination 13 13 0% 21-Mar-18 03-Apr-18 -269
04.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 03-Dec-17 17-Dec-17 -271
04.EL.E50 DB'S Dressing\Terminations 14 14 0% 08-Mar-18 21-Mar-18 -233
04.PL.010 Plaster Work 14 14 0% 24-Jan-18 07-Feb-18 -271
04.FO.020 Kitchen Cabinet 14 14 0% 09-Jun-18 21-Jun-18 -264
04.FO.030 Vanity Counter 14 14 0% 09-Jun-18 21-Jun-18 -264
04.PN.010 Primer & Stucco 14 14 0% 07-Feb-18 20-Feb-18 -271
04.FO.010 Wardrobes 21 21 0% 25-Jun-18 15-Jul-18 -255

- 5th Floor 251 251 0% 13-Nov-17 10-Jul-18 -246

05.AC.900 Work Completion 0 0 0% 24-Jun-18 -243


05.FF.900 Work Completion 0 0 0% 14-Jun-18 -246
05.WS.900 Work Completion 0 0 0% 13-Jun-18 -246
05.EL.F90 Work Completion (Fire Alarm) 0 0 0% 18-Jun-18 -243

Actual Level of Effort Remaining Work Page 91 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Floor Tiles- Corridors a

Suspension System- Corrido

Final Stage- Wet Area


Waterproofing- Wet Area
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Wall Tiles- Corridors\Lift Lobby

R.C.C Slab (5th Floor Slab)\Electric Conduits


FCU & A.C Ducts
Emergency Gas Off\On S
Filling\Supply Pipes Installaion
Kitchen Gas Detector
Flooring Tiles- Service\Dry Area
Suspension System- Wet Area
Suspension System- Dry Area

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work

Primer & Stucco

Actual Level of Effort Remaining Work Page 92 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
05.EL.T90 Work Completion (Telephone) 0 0 0% 19-Apr-18 -269
05.EL.L90 Work Completion (Low Current) 0 0 0% 01-Jul-18 -240
05.EL.E90 Work Completion (Electric) 0 0 0% 16-Jun-18 -251
05.DR.900 Work Completion 0 0 0% 07-Jun-18 -255
05.PG.900 Work Completion 0 0 0% 21-Jun-18 -247
05.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 15-May-18 -255
05.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 30-Apr-18 -259
05.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 10-May-18 -260
05.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 16-Apr-18 -260
05.AC.040 Pipes Testing 2 2 0% 20-Jan-18 22-Jan-18 -252
05.FF.020 Pipes Testing 2 2 0% 25-Jan-18 28-Jan-18 -252
05.WS.040 Pipes Testing 2 2 0% 03-Mar-18 05-Mar-18 -267
05.DR.020 Pipes Testing 2 2 0% 31-Jan-18 03-Feb-18 -252
05.FL.100 Marble Threshold 2 2 0% 04-Jul-18 05-Jul-18 -260
05.CO.010 R.C.C Columns\Walls 3 3 0% 13-Nov-17 15-Nov-17 -270
05.EL.C10 Emergency Light 3 3 0% 16-Jun-18 18-Jun-18 -233
05.FF.030 Sprinkler Heads 4 4 0% 10-Jun-18 13-Jun-18 -245
05.EL.T20 Install Telephone Cables 4 4 0% 03-Apr-18 07-Apr-18 -269
05.PG.100 Flexible Hose 4 4 0% 18-Jun-18 21-Jun-18 -247
05.AL.500 Aluminium Windows-Shutters 4 4 0% 08-May-18 13-May-18 -257
05.FL.D20 Screed Flooring 4 4 0% 07-Apr-18 10-Apr-18 -269
05.WD.010 Fixing Sub Frames 4 4 0% 02-Jan-18 06-Jan-18 -237
05.AC.050 Duct Drops (Wet Area) 4 4 0% 30-Apr-18 03-May-18 -260
05.AC.060 Duct Drops (Dry Area) 4 4 0% 09-May-18 13-May-18 -249
05.AC.070 Duct Drops (Corridors) 4 4 0% 17-May-18 21-May-18 -244
05.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 10-Jun-18 14-Jun-18 -246
05.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 30-Dec-17 04-Jan-18 -267
05.WS.020 Main Pipes 5 5 0% 04-Jan-18 09-Jan-18 -267
05.EL.F20 Fixing Fire Alarm Devices 5 5 0% 13-Jun-18 18-Jun-18 -243
05.EL.010 Conduits, Boxes & enclosure 5 5 0% 30-Dec-17 04-Jan-18 -235
05.EL.E30 Isolators In High Level 5 5 0% 12-Mar-18 17-Mar-18 -269
05.FL.D90 Epoxy Coating 5 5 0% 30-Jun-18 04-Jul-18 -260
05.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 05-Jun-18 10-Jun-18 -251
05.SN.010 Work Completion\Snagging Work 5 5 0% 05-Jul-18 10-Jul-18 -246

Actual Level of Effort Remaining Work Page 93 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Work Completion (Telephone),

Work Completion,

Floor Weather Tight (to Sta


MEP CLEARANCE- Dry Area, 3
MEP CLEARANCE- Corridor
MEP CLEARANCE- Wet Area, 16-A
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-Shutte
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridors)

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Painting Work to Fa

Actual Level of Effort Remaining Work Page 94 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
05.AC.110 Grills and Diffusers 6 6 0% 18-Jun-18 24-Jun-18 -243
05.FF.010 Hz. Pipes H\L 6 6 0% 20-Jan-18 25-Jan-18 -252
05.WS.050 Valves, Mixer's, etc... 6 6 0% 07-Jun-18 13-Jun-18 -246
05.WS.030 Water Heater 6 6 0% 26-Feb-18 03-Mar-18 -267
05.EL.C20 Emergency Light Control Panel 6 6 0% 18-Jun-18 24-Jun-18 -233
05.EL.S20 Security System Devices 6 6 0% 18-Jun-18 24-Jun-18 -240
05.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 10-Jun-18 16-Jun-18 -251
05.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 17-Mar-18 21-Mar-18 -257
05.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 03-Jun-18 07-Jun-18 -255
05.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 25-Jan-18 31-Jan-18 -252
05.DR.030 Fixing Of Bath Tub 6 6 0% 10-Mar-18 15-Mar-18 -250
05.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 16-Apr-18 22-Apr-18 -260
05.AL.400 Aluminium Windows-Shutters 6 6 0% 02-May-18 08-May-18 -260
05.AL.200 Aluminium Windows-Shutters 6 6 0% 02-May-18 08-May-18 -260
05.FL.W40 Floor Tiles- Wet Area 6 6 0% 10-Apr-18 16-Apr-18 -267
05.CL.W10 Wall Tiles- Wet Area 6 6 0% 20-Feb-18 26-Feb-18 -267
05.FO.040 Mirrors & Bath Accessories 6 6 0% 13-Jun-18 19-Jun-18 -246
05.DR.050 Pipes In Walls 6 6 0% 04-Jan-18 10-Jan-18 -235
05.DR.910 Drinage Pipes L\L 6 6 0% 04-Mar-18 10-Mar-18 -264
05.CO.100 Dismantling Shutters 7 7 0% 06-Dec-17 12-Dec-17 -267
05.AC.020 Mouse Connection & Fire Damper 7 7 0% 14-Jan-18 20-Jan-18 -252
05.AC.030 Gas Pipes net work 7 7 0% 14-Jan-18 20-Jan-18 -252
05.EL.S40 Security System Control Panels 7 7 0% 24-Jun-18 01-Jul-18 -240
05.EL.020 Pulling All Types Of Wires 7 7 0% 05-Mar-18 12-Mar-18 -271
05.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 02-May-18 08-May-18 -266
05.WD.030 Door Shutters & Ironmongery 7 7 0% 15-May-18 22-May-18 -255
05.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 10-May-18 17-May-18 -260
05.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 22-May-18 31-May-18 -246
05.FC.W30 Final Stage- Wet Area 7 7 0% 03-May-18 10-May-18 -260
05.WP.W20 Waterproofing- Wet Area 7 7 0% 26-Feb-18 04-Mar-18 -267
05.AL.100 Aluminium Windows-Shutters 8 8 0% 24-Apr-18 02-May-18 -267
05.AL.300 Aluminium Windows-Shutters 8 8 0% 24-Apr-18 02-May-18 -266
05.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 26-Feb-18 05-Mar-18 -253
05.FC.D30 Final Stage- Dry Area 8 8 0% 15-May-18 22-May-18 -251

Actual Level of Effort Remaining Work Page 95 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Power Cables


Sanitary Ware, Kitch
Floor Trap & Drainage Pipes H\L
Fixing Of Bath Tub
Filling\Supply Pipes Installaion (Co
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and Lo
Door Shutters & Ironmon
Suspension System- Corri
Final Stage- Corridors
Final Stage- Wet Area
Waterproofing- Wet Area
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area

Actual Level of Effort Remaining Work Page 96 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
05.CO.050 R.C.C Slab (6th Floor Slab)\Electric Conduits 9 9 0% 15-Nov-17 23-Nov-17 -270
05.AC.010 FCU & A.C Ducts 9 9 0% 09-Jan-18 17-Jan-18 -252
05.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 29-May-18 07-Jun-18 -247
05.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 10-May-18 19-May-18 -247
05.PG.030 Kitchen Gas Detector 9 9 0% 19-May-18 29-May-18 -247
05.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 16-Apr-18 24-Apr-18 -267
05.FC.W20 Suspension System- Wet Area 9 9 0% 22-Apr-18 30-Apr-18 -260
05.FC.D20 Suspension System- Dry Area 10 10 0% 30-Apr-18 09-May-18 -259
05.PG.090 Gas Alarm Control Panel 12 12 0% 07-Jun-18 18-Jun-18 -247
05.PN.020 Painting Work 12 12 0% 22-May-18 05-Jun-18 -251
05.EL.T30 ONU Termination 13 13 0% 07-Apr-18 19-Apr-18 -269
05.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 17-Dec-17 30-Dec-17 -271
05.EL.E50 DB'S Dressing\Terminations 14 14 0% 21-Mar-18 05-Apr-18 -233
05.PL.010 Plaster Work 14 14 0% 07-Feb-18 20-Feb-18 -271
05.FO.020 Kitchen Cabinet 14 14 0% 17-May-18 03-Jun-18 -255
05.FO.030 Vanity Counter 14 14 0% 17-May-18 03-Jun-18 -255
05.PN.010 Primer & Stucco 14 14 0% 20-Feb-18 05-Mar-18 -271
05.FO.010 Wardrobes 21 21 0% 05-Jun-18 25-Jun-18 -234

- 6th Floor 240 240 0% 25-Nov-17 12-Jul-18 -248

06.AC.900 Work Completion 0 0 0% 01-Jul-18 -250


06.FF.900 Work Completion 0 0 0% 21-Jun-18 -253
06.WS.900 Work Completion 0 0 0% 20-Jun-18 -250
06.EL.F90 Work Completion (Fire Alarm) 0 0 0% 25-Jun-18 -250
06.EL.T90 Work Completion (Telephone) 0 0 0% 05-May-18 -269
06.EL.L90 Work Completion (Low Current) 0 0 0% 07-Jul-18 -247
06.EL.E90 Work Completion (Electric) 0 0 0% 21-Jun-18 -252
06.DR.900 Work Completion 0 0 0% 14-Jun-18 -256
06.PG.900 Work Completion 0 0 0% 26-Jun-18 -252
06.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 22-May-18 -257
06.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 03-May-18 -256
06.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 17-May-18 -260
06.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 19-Apr-18 -257
06.AC.040 Pipes Testing 2 2 0% 03-Feb-18 04-Feb-18 -250

Actual Level of Effort Remaining Work Page 97 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
R.C.C Slab (6th Floor Slab)\Electric Conduits
FCU & A.C Ducts
Emergency Gas Off\
Filling\Supply Pipes Install
Kitchen Gas Detector
Flooring Tiles- Service\Dry Area
Suspension System- Wet Area
Suspension System- Dry Are

Painting Work
ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work
Kitchen Cabinet
Vanity Counter
Primer & Stucco

Work Completion (Telephone)

Floor Weather Tight (to S


MEP CLEARANCE- Dry Area,
MEP CLEARANCE- Corrid
MEP CLEARANCE- Wet Area, 19-
Pipes Testing

Actual Level of Effort Remaining Work Page 98 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
06.FF.020 Pipes Testing 2 2 0% 07-Feb-18 10-Feb-18 -250
06.WS.040 Pipes Testing 2 2 0% 11-Mar-18 12-Mar-18 -267
06.DR.020 Pipes Testing 2 2 0% 13-Feb-18 15-Feb-18 -249
06.FL.100 Marble Threshold 2 2 0% 05-Jul-18 08-Jul-18 -260
06.CO.010 R.C.C Columns\Walls 3 3 0% 25-Nov-17 27-Nov-17 -270
06.EL.C10 Emergency Light 3 3 0% 21-Jun-18 25-Jun-18 -240
06.FF.030 Sprinkler Heads 4 4 0% 17-Jun-18 20-Jun-18 -252
06.EL.T20 Install Telephone Cables 4 4 0% 19-Apr-18 23-Apr-18 -269
06.PG.100 Flexible Hose 4 4 0% 23-Jun-18 26-Jun-18 -252
06.AL.500 Aluminium Windows-Shutters 4 4 0% 15-May-18 19-May-18 -260
06.FL.D20 Screed Flooring 4 4 0% 10-Apr-18 15-Apr-18 -269
06.WD.010 Fixing Sub Frames 4 4 0% 15-Jan-18 20-Jan-18 -240
06.AC.050 Duct Drops (Wet Area) 4 4 0% 03-May-18 08-May-18 -257
06.AC.060 Duct Drops (Dry Area) 4 4 0% 13-May-18 17-May-18 -252
06.AC.070 Duct Drops (Corridors) 4 4 0% 26-May-18 29-May-18 -246
06.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 17-Jun-18 21-Jun-18 -253
06.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 13-Jan-18 17-Jan-18 -264
06.WS.020 Main Pipes 5 5 0% 17-Jan-18 22-Jan-18 -250
06.EL.F20 Fixing Fire Alarm Devices 5 5 0% 20-Jun-18 25-Jun-18 -250
06.EL.010 Conduits, Boxes & enclosure 5 5 0% 13-Jan-18 17-Jan-18 -238
06.EL.E30 Isolators In High Level 5 5 0% 25-Mar-18 31-Mar-18 -254
06.FL.D90 Epoxy Coating 5 5 0% 12-Jun-18 17-Jun-18 -257
06.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 12-Jun-18 17-Jun-18 -253
06.SN.010 Work Completion\Snagging Work 5 5 0% 08-Jul-18 12-Jul-18 -248
06.AC.110 Grills and Diffusers 6 6 0% 25-Jun-18 01-Jul-18 -250
06.FF.010 Hz. Pipes H\L 6 6 0% 03-Feb-18 07-Feb-18 -250
06.WS.050 Valves, Mixer's, etc... 6 6 0% 14-Jun-18 20-Jun-18 -250
06.WS.030 Water Heater 6 6 0% 05-Mar-18 11-Mar-18 -267
06.EL.C20 Emergency Light Control Panel 6 6 0% 25-Jun-18 01-Jul-18 -240
06.EL.S20 Security System Devices 6 6 0% 25-Jun-18 01-Jul-18 -247
06.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 17-Jun-18 21-Jun-18 -252
06.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 31-Mar-18 05-Apr-18 -254
06.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 09-Jun-18 14-Jun-18 -256
06.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 07-Feb-18 13-Feb-18 -250

Actual Level of Effort Remaining Work Page 99 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-Shut
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridors)

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Power Cable

Floor Trap & Drainage Pipes H\L

Actual Level of Effort Remaining Work Page 100 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
06.DR.030 Fixing Of Bath Tub 6 6 0% 17-Mar-18 21-Mar-18 -251
06.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 19-Apr-18 25-Apr-18 -257
06.AL.400 Aluminium Windows-Shutters 6 6 0% 08-May-18 13-May-18 -260
06.AL.200 Aluminium Windows-Shutters 6 6 0% 08-May-18 13-May-18 -260
06.FL.W40 Floor Tiles- Wet Area 6 6 0% 15-Apr-18 19-Apr-18 -263
06.CL.W10 Wall Tiles- Wet Area 6 6 0% 26-Feb-18 03-Mar-18 -266
06.FO.040 Mirrors & Bath Accessories 6 6 0% 20-Jun-18 26-Jun-18 -247
06.DR.050 Pipes In Walls 6 6 0% 17-Jan-18 23-Jan-18 -234
06.DR.910 Drinage Pipes L\L 6 6 0% 11-Mar-18 17-Mar-18 -265
06.CO.100 Dismantling Shutters 7 7 0% 18-Dec-17 25-Dec-17 -266
06.AC.020 Mouse Connection & Fire Damper 7 7 0% 27-Jan-18 03-Feb-18 -250
06.AC.030 Gas Pipes net work 7 7 0% 27-Jan-18 03-Feb-18 -250
06.EL.S40 Security System Control Panels 7 7 0% 01-Jul-18 07-Jul-18 -247
06.EL.020 Pulling All Types Of Wires 7 7 0% 18-Mar-18 25-Mar-18 -254
06.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 08-May-18 15-May-18 -266
06.WD.030 Door Shutters & Ironmongery 7 7 0% 22-May-18 30-May-18 -256
06.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 17-May-18 26-May-18 -260
06.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 31-May-18 07-Jun-18 -248
06.FC.W30 Final Stage- Wet Area 7 7 0% 08-May-18 14-May-18 -257
06.WP.W20 Waterproofing- Wet Area 7 7 0% 04-Mar-18 11-Mar-18 -267
06.AL.100 Aluminium Windows-Shutters 8 8 0% 02-May-18 09-May-18 -267
06.AL.300 Aluminium Windows-Shutters 8 8 0% 02-May-18 09-May-18 -266
06.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 05-Mar-18 12-Mar-18 -253
06.FC.D30 Final Stage- Dry Area 8 8 0% 22-May-18 31-May-18 -257
06.CO.050 R.C.C Slab (7th Floor Slab)\Electric Conduits 9 9 0% 27-Nov-17 07-Dec-17 -270
06.AC.010 FCU & A.C Ducts 9 9 0% 22-Jan-18 30-Jan-18 -250
06.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 03-Jun-18 11-Jun-18 -251
06.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 14-May-18 22-May-18 -251
06.PG.030 Kitchen Gas Detector 9 9 0% 22-May-18 03-Jun-18 -251
06.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 19-Apr-18 29-Apr-18 -263
06.FC.W20 Suspension System- Wet Area 9 9 0% 25-Apr-18 03-May-18 -257
06.FC.D20 Suspension System- Dry Area 10 10 0% 03-May-18 13-May-18 -256
06.PG.090 Gas Alarm Control Panel 12 12 0% 12-Jun-18 23-Jun-18 -252
06.PN.020 Painting Work 12 12 0% 31-May-18 12-Jun-18 -257

Actual Level of Effort Remaining Work Page 101 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Fixing Of Bath Tub
Filling\Supply Pipes Installaion (C
Aluminium Windows-Shutte
Aluminium Windows-Shutte
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and L
Door Shutters & Ironm
Suspension System- Co
Final Stage- Corridor
Final Stage- Wet Area
Waterproofing- Wet Area
Aluminium Windows-Shutters
Aluminium Windows-Shutters
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area
R.C.C Slab (7th Floor Slab)\Electric Conduits
FCU & A.C Ducts
Emergency Gas Of
Filling\Supply Pipes Insta
Kitchen Gas Detector
Flooring Tiles- Service\Dry Area
Suspension System- Wet Area
Suspension System- Dry Ar

Actual Level of Effort Remaining Work Page 102 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
06.EL.T30 ONU Termination 13 13 0% 23-Apr-18 05-May-18 -269
06.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 30-Dec-17 13-Jan-18 -271
06.EL.E50 DB'S Dressing\Terminations 14 14 0% 05-Apr-18 18-Apr-18 -233
06.PL.010 Plaster Work 14 14 0% 01-Feb-18 14-Feb-18 -254
06.FO.020 Kitchen Cabinet 14 14 0% 27-May-18 09-Jun-18 -256
06.FO.030 Vanity Counter 14 14 0% 27-May-18 09-Jun-18 -256
06.PN.010 Primer & Stucco 14 14 0% 05-Mar-18 18-Mar-18 -264
06.FO.010 Wardrobes 21 21 0% 12-Jun-18 01-Jul-18 -241

- 7th Floor 233 233 0% 07-Dec-17 18-Jul-18 -254

07.AC.900 Work Completion 0 0 0% 07-Jul-18 -257


07.FF.900 Work Completion 0 0 0% 27-Jun-18 -260
07.WS.900 Work Completion 0 0 0% 26-Jun-18 -257
07.EL.F90 Work Completion (Fire Alarm) 0 0 0% 01-Jul-18 -257
07.EL.T90 Work Completion (Telephone) 0 0 0% 21-May-18 -269
07.EL.L90 Work Completion (Low Current) 0 0 0% 14-Jul-18 -254
07.EL.E90 Work Completion (Electric) 0 0 0% 28-Jun-18 -253
07.DR.900 Work Completion 0 0 0% 21-Jun-18 -257
07.PG.900 Work Completion 0 0 0% 03-Jul-18 -259
07.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 30-May-18 -260
07.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 08-May-18 -254
07.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 26-May-18 -260
07.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 24-Apr-18 -255
07.AC.040 Pipes Testing 2 2 0% 15-Feb-18 17-Feb-18 -257
07.FF.020 Pipes Testing 2 2 0% 21-Feb-18 22-Feb-18 -257
07.WS.040 Pipes Testing 2 2 0% 19-Mar-18 21-Mar-18 -268
07.DR.020 Pipes Testing 2 2 0% 26-Feb-18 28-Feb-18 -256
07.FL.100 Marble Threshold 2 2 0% 08-Jul-18 10-Jul-18 -260
07.CO.010 R.C.C Columns\Walls 3 3 0% 07-Dec-17 11-Dec-17 -270
07.EL.C10 Emergency Light 3 3 0% 28-Jun-18 01-Jul-18 -247
07.FF.030 Sprinkler Heads 4 4 0% 23-Jun-18 26-Jun-18 -259
07.EL.T20 Install Telephone Cables 4 4 0% 05-May-18 08-May-18 -269
07.PG.100 Flexible Hose 4 4 0% 30-Jun-18 03-Jul-18 -259
07.AL.500 Aluminium Windows-Shutters 4 4 0% 22-May-18 28-May-18 -263

Actual Level of Effort Remaining Work Page 103 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work
Kitchen Cabinet
Vanity Counter
Primer & Stucco

Work Completion (Teleph

Floor Weather Tight (to


MEP CLEARANCE- Dry Area
MEP CLEARANCE- Cor
MEP CLEARANCE- Wet Area, 24
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-Sh

Actual Level of Effort Remaining Work Page 104 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
07.FL.D20 Screed Flooring 4 4 0% 15-Apr-18 18-Apr-18 -269
07.WD.010 Fixing Sub Frames 4 4 0% 29-Jan-18 01-Feb-18 -247
07.AC.050 Duct Drops (Wet Area) 4 4 0% 08-May-18 12-May-18 -255
07.AC.060 Duct Drops (Dry Area) 4 4 0% 17-May-18 22-May-18 -253
07.AC.070 Duct Drops (Corridors) 4 4 0% 02-Jun-18 05-Jun-18 -253
07.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 23-Jun-18 27-Jun-18 -260
07.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 25-Jan-18 30-Jan-18 -257
07.WS.020 Main Pipes 5 5 0% 30-Jan-18 04-Feb-18 -257
07.EL.F20 Fixing Fire Alarm Devices 5 5 0% 26-Jun-18 01-Jul-18 -257
07.EL.010 Conduits, Boxes & enclosure 5 5 0% 25-Jan-18 30-Jan-18 -245
07.EL.E30 Isolators In High Level 5 5 0% 08-Apr-18 12-Apr-18 -256
07.FL.D90 Epoxy Coating 5 5 0% 18-Jun-18 23-Jun-18 -259
07.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 18-Jun-18 23-Jun-18 -260
07.SN.010 Work Completion\Snagging Work 5 5 0% 14-Jul-18 18-Jul-18 -254
07.AC.110 Grills and Diffusers 6 6 0% 01-Jul-18 07-Jul-18 -257
07.FF.010 Hz. Pipes H\L 6 6 0% 15-Feb-18 21-Feb-18 -257
07.WS.050 Valves, Mixer's, etc... 6 6 0% 21-Jun-18 26-Jun-18 -257
07.WS.030 Water Heater 6 6 0% 13-Mar-18 19-Mar-18 -268
07.EL.C20 Emergency Light Control Panel 6 6 0% 01-Jul-18 07-Jul-18 -247
07.EL.S20 Security System Devices 6 6 0% 01-Jul-18 07-Jul-18 -254
07.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 23-Jun-18 28-Jun-18 -253
07.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 12-Apr-18 18-Apr-18 -256
07.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 16-Jun-18 21-Jun-18 -257
07.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 21-Feb-18 26-Feb-18 -257
07.DR.030 Fixing Of Bath Tub 6 6 0% 26-Mar-18 01-Apr-18 -255
07.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 24-Apr-18 29-Apr-18 -255
07.AL.400 Aluminium Windows-Shutters 6 6 0% 17-May-18 22-May-18 -264
07.AL.200 Aluminium Windows-Shutters 6 6 0% 13-May-18 19-May-18 -260
07.FL.W40 Floor Tiles- Wet Area 6 6 0% 18-Apr-18 24-Apr-18 -258
07.CL.W10 Wall Tiles- Wet Area 6 6 0% 07-Mar-18 13-Mar-18 -270
07.FO.040 Mirrors & Bath Accessories 6 6 0% 26-Jun-18 02-Jul-18 -248
07.DR.050 Pipes In Walls 6 6 0% 30-Jan-18 05-Feb-18 -242
07.DR.910 Drinage Pipes L\L 6 6 0% 20-Mar-18 26-Mar-18 -269
07.CO.100 Dismantling Shutters 7 7 0% 31-Dec-17 07-Jan-18 -265

Actual Level of Effort Remaining Work Page 105 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridor

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Power C

Floor Trap & Drainage Pipes H\L


Fixing Of Bath Tub
Filling\Supply Pipes Installaion (
Aluminium Windows-Shu
Aluminium Windows-Shut
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters

Actual Level of Effort Remaining Work Page 106 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
07.AC.020 Mouse Connection & Fire Damper 7 7 0% 08-Feb-18 15-Feb-18 -257
07.AC.030 Gas Pipes net work 7 7 0% 08-Feb-18 15-Feb-18 -257
07.EL.S40 Security System Control Panels 7 7 0% 07-Jul-18 14-Jul-18 -254
07.EL.020 Pulling All Types Of Wires 7 7 0% 01-Apr-18 08-Apr-18 -257
07.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 15-May-18 22-May-18 -266
07.WD.030 Door Shutters & Ironmongery 7 7 0% 30-May-18 06-Jun-18 -259
07.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 26-May-18 02-Jun-18 -260
07.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 07-Jun-18 13-Jun-18 -255
07.FC.W30 Final Stage- Wet Area 7 7 0% 12-May-18 17-May-18 -255
07.WP.W20 Waterproofing- Wet Area 7 7 0% 13-Mar-18 20-Mar-18 -270
07.AL.100 Aluminium Windows-Shutters 8 8 0% 15-May-18 22-May-18 -267
07.AL.300 Aluminium Windows-Shutters 8 8 0% 09-May-18 17-May-18 -266
07.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 13-Mar-18 21-Mar-18 -254
07.FC.D30 Final Stage- Dry Area 8 8 0% 30-May-18 07-Jun-18 -260
07.CO.050 R.C.C Slab (8th Floor Slab)\Electric Conduits 9 9 0% 11-Dec-17 19-Dec-17 -270
07.AC.010 FCU & A.C Ducts 9 9 0% 04-Feb-18 12-Feb-18 -257
07.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 06-Jun-18 14-Jun-18 -255
07.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 17-May-18 29-May-18 -255
07.PG.030 Kitchen Gas Detector 9 9 0% 29-May-18 06-Jun-18 -255
07.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 24-Apr-18 02-May-18 -258
07.FC.W20 Suspension System- Wet Area 9 9 0% 29-Apr-18 08-May-18 -255
07.FC.D20 Suspension System- Dry Area 10 10 0% 08-May-18 17-May-18 -254
07.PG.090 Gas Alarm Control Panel 12 12 0% 18-Jun-18 30-Jun-18 -259
07.PN.020 Painting Work 12 12 0% 07-Jun-18 18-Jun-18 -260
07.EL.T30 ONU Termination 13 13 0% 08-May-18 21-May-18 -269
07.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 13-Jan-18 25-Jan-18 -271
07.EL.E50 DB'S Dressing\Terminations 14 14 0% 18-Apr-18 01-May-18 -233
07.PL.010 Plaster Work 14 14 0% 22-Feb-18 07-Mar-18 -270
07.FO.020 Kitchen Cabinet 14 14 0% 03-Jun-18 16-Jun-18 -257
07.FO.030 Vanity Counter 14 14 0% 03-Jun-18 16-Jun-18 -257
07.PN.010 Primer & Stucco 14 14 0% 18-Mar-18 01-Apr-18 -264
07.FO.010 Wardrobes 21 21 0% 18-Jun-18 08-Jul-18 -248

- 8th Floor 230 230 0% 20-Dec-17 28-Jul-18 -264

Actual Level of Effort Remaining Work Page 107 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and
Door Shutters & Iron
Suspension System- C

Final Stage- Wet Area


Waterproofing- Wet Area
Aluminium Windows-Shu
Aluminium Windows-Shutte
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area
R.C.C Slab (8th Floor Slab)\Electric Conduits
FCU & A.C Ducts

Filling\Supply Pipes Ins


Kitchen Gas Detecto
Flooring Tiles- Service\Dry Are
Suspension System- Wet Are
Suspension System- Dry A

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminations
Plaster Work

Primer & Stucco

Actual Level of Effort Remaining Work Page 108 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
08.AC.900 Work Completion 0 0 0% 16-Jul-18 -267
08.FF.900 Work Completion 0 0 0% 02-Jul-18 -265
08.WS.900 Work Completion 0 0 0% 05-Jul-18 -267
08.EL.F90 Work Completion (Fire Alarm) 0 0 0% 10-Jul-18 -267
08.EL.T90 Work Completion (Telephone) 0 0 0% 07-Jun-18 -260
08.EL.L90 Work Completion (Low Current) 0 0 0% 23-Jul-18 -264
08.EL.E90 Work Completion (Electric) 0 0 0% 04-Jul-18 -245
08.DR.900 Work Completion 0 0 0% 01-Jul-18 -267
08.PG.900 Work Completion 0 0 0% 12-Jul-18 -269
08.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 09-Jun-18 -269
08.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 27-May-18 -269
08.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 05-Jun-18 -264
08.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 28-Apr-18 -259
08.AC.040 Pipes Testing 2 2 0% 28-Feb-18 03-Mar-18 -254
08.FF.020 Pipes Testing 2 2 0% 06-Mar-18 07-Mar-18 -254
08.WS.040 Pipes Testing 2 2 0% 02-Apr-18 04-Apr-18 -258
08.DR.020 Pipes Testing 2 2 0% 12-Mar-18 13-Mar-18 -250
08.FL.100 Marble Threshold 2 2 0% 10-Jul-18 11-Jul-18 -260
08.CO.010 R.C.C Columns\Walls 3 3 0% 20-Dec-17 23-Dec-17 -270
08.EL.C10 Emergency Light 3 3 0% 04-Jul-18 07-Jul-18 -253
08.FF.030 Sprinkler Heads 4 4 0% 27-Jun-18 01-Jul-18 -264
08.EL.T20 Install Telephone Cables 4 4 0% 21-May-18 27-May-18 -269
08.PG.100 Flexible Hose 4 4 0% 09-Jul-18 12-Jul-18 -269
08.AL.500 Aluminium Windows-Shutters 4 4 0% 03-Jun-18 06-Jun-18 -269
08.FL.D20 Screed Flooring 4 4 0% 18-Apr-18 22-Apr-18 -269
08.WD.010 Fixing Sub Frames 4 4 0% 11-Feb-18 14-Feb-18 -241
08.AC.050 Duct Drops (Wet Area) 4 4 0% 12-May-18 15-May-18 -259
08.AC.060 Duct Drops (Dry Area) 4 4 0% 05-Jun-18 09-Jun-18 -269
08.AC.070 Duct Drops (Corridors) 4 4 0% 12-Jun-18 16-Jun-18 -264
08.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 27-Jun-18 02-Jul-18 -265
08.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 07-Feb-18 12-Feb-18 -254
08.WS.020 Main Pipes 5 5 0% 12-Feb-18 17-Feb-18 -254
08.EL.F20 Fixing Fire Alarm Devices 5 5 0% 05-Jul-18 10-Jul-18 -267
08.EL.010 Conduits, Boxes & enclosure 5 5 0% 07-Feb-18 12-Feb-18 -239

Actual Level of Effort Remaining Work Page 109 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Work Completion (Te

Floor Weather Tight


MEP CLEARANCE- Dry
MEP CLEARANCE- C
MEP CLEARANCE- Wet Area, 2
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Are

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure

Actual Level of Effort Remaining Work Page 110 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
08.EL.E30 Isolators In High Level 5 5 0% 21-Apr-18 25-Apr-18 -264
08.FL.D90 Epoxy Coating 5 5 0% 27-Jun-18 02-Jul-18 -264
08.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 23-Jun-18 27-Jun-18 -265
08.SN.010 Work Completion\Snagging Work 5 5 0% 23-Jul-18 28-Jul-18 -264
08.AC.110 Grills and Diffusers 6 6 0% 10-Jul-18 16-Jul-18 -267
08.FF.010 Hz. Pipes H\L 6 6 0% 28-Feb-18 06-Mar-18 -254
08.WS.050 Valves, Mixer's, etc... 6 6 0% 01-Jul-18 05-Jul-18 -267
08.WS.030 Water Heater 6 6 0% 26-Mar-18 02-Apr-18 -258
08.EL.C20 Emergency Light Control Panel 6 6 0% 07-Jul-18 12-Jul-18 -253
08.EL.S20 Security System Devices 6 6 0% 10-Jul-18 16-Jul-18 -264
08.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 28-Jun-18 04-Jul-18 -253
08.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 25-Apr-18 01-May-18 -264
08.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 25-Jun-18 01-Jul-18 -267
08.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 06-Mar-18 12-Mar-18 -254
08.DR.030 Fixing Of Bath Tub 6 6 0% 09-Apr-18 15-Apr-18 -263
08.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 28-Apr-18 03-May-18 -259
08.AL.400 Aluminium Windows-Shutters 6 6 0% 27-May-18 02-Jun-18 -266
08.AL.200 Aluminium Windows-Shutters 6 6 0% 19-May-18 27-May-18 -260
08.FL.W40 Floor Tiles- Wet Area 6 6 0% 22-Apr-18 28-Apr-18 -259
08.CL.W10 Wall Tiles- Wet Area 6 6 0% 21-Mar-18 26-Mar-18 -264
08.FO.040 Mirrors & Bath Accessories 6 6 0% 05-Jul-18 11-Jul-18 -252
08.DR.050 Pipes In Walls 6 6 0% 12-Feb-18 18-Feb-18 -250
08.DR.910 Drinage Pipes L\L 6 6 0% 03-Apr-18 09-Apr-18 -263
08.CO.100 Dismantling Shutters 7 7 0% 13-Jan-18 20-Jan-18 -264
08.AC.020 Mouse Connection & Fire Damper 7 7 0% 21-Feb-18 28-Feb-18 -254
08.AC.030 Gas Pipes net work 7 7 0% 21-Feb-18 28-Feb-18 -254
08.EL.S40 Security System Control Panels 7 7 0% 16-Jul-18 23-Jul-18 -264
08.EL.020 Pulling All Types Of Wires 7 7 0% 15-Apr-18 21-Apr-18 -264
08.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 27-May-18 03-Jun-18 -269
08.WD.030 Door Shutters & Ironmongery 7 7 0% 09-Jun-18 16-Jun-18 -268
08.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 05-Jun-18 12-Jun-18 -264
08.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 17-Jun-18 23-Jun-18 -265
08.FC.W30 Final Stage- Wet Area 7 7 0% 15-May-18 22-May-18 -259
08.WP.W20 Waterproofing- Wet Area 7 7 0% 26-Mar-18 03-Apr-18 -264

Actual Level of Effort Remaining Work Page 111 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Isolators In High Level

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\Powe

Floor Trap & Drainage Pipes H\L


Fixing Of Bath Tub
Filling\Supply Pipes Installaion
Aluminium Windows-S
Aluminium Windows-Sh
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors

Final Stage- Wet Area


Waterproofing- Wet Area

Actual Level of Effort Remaining Work Page 112 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
08.AL.100 Aluminium Windows-Shutters 8 8 0% 22-May-18 02-Jun-18 -267
08.AL.300 Aluminium Windows-Shutters 8 8 0% 17-May-18 27-May-18 -266
08.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 26-Mar-18 04-Apr-18 -260
08.FC.D30 Final Stage- Dry Area 8 8 0% 09-Jun-18 17-Jun-18 -269
08.CO.050 R.C.C Slab (9th Floor Slab)\Electric Conduits 9 9 0% 23-Dec-17 31-Dec-17 -270
08.AC.010 FCU & A.C Ducts 9 9 0% 17-Feb-18 26-Feb-18 -254
08.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 10-Jun-18 18-Jun-18 -259
08.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 22-May-18 02-Jun-18 -259
08.PG.030 Kitchen Gas Detector 9 9 0% 02-Jun-18 10-Jun-18 -259
08.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 28-Apr-18 06-May-18 -254
08.FC.W20 Suspension System- Wet Area 9 9 0% 03-May-18 12-May-18 -259
08.FC.D20 Suspension System- Dry Area 10 10 0% 27-May-18 05-Jun-18 -269
08.PG.090 Gas Alarm Control Panel 12 12 0% 27-Jun-18 09-Jul-18 -269
08.PN.020 Painting Work 12 12 0% 17-Jun-18 27-Jun-18 -269
08.EL.T30 ONU Termination 13 13 0% 27-May-18 07-Jun-18 -260
08.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 25-Jan-18 07-Feb-18 -271
08.EL.E50 DB'S Dressing\Terminations 14 14 0% 01-May-18 14-May-18 -233
08.PL.010 Plaster Work 14 14 0% 07-Mar-18 21-Mar-18 -264
08.FO.020 Kitchen Cabinet 14 14 0% 12-Jun-18 25-Jun-18 -267
08.FO.030 Vanity Counter 14 14 0% 12-Jun-18 25-Jun-18 -267
08.PN.010 Primer & Stucco 14 14 0% 01-Apr-18 15-Apr-18 -264
08.FO.010 Wardrobes 21 21 0% 27-Jun-18 17-Jul-18 -258

- 9th Floor 207 207 0% 02-Jan-18 18-Jul-18 -254

09.AC.900 Work Completion 0 0 0% 03-Jul-18 -253


09.FF.900 Work Completion 0 0 0% 20-Jun-18 -252
09.WS.900 Work Completion 0 0 0% 23-Jun-18 -256
09.EL.F90 Work Completion (Fire Alarm) 0 0 0% 27-Jun-18 -253
09.EL.T90 Work Completion (Telephone) 0 0 0% 22-May-18 -246
09.EL.L90 Work Completion (Low Current) 0 0 0% 10-Jul-18 -250
09.EL.E90 Work Completion (Electric) 0 0 0% 21-Jun-18 -257
09.DR.900 Work Completion 0 0 0% 17-Jun-18 -256
09.PG.900 Work Completion 0 0 0% 04-Jul-18 -260
09.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 27-May-18 -256

Actual Level of Effort Remaining Work Page 113 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Aluminium Windows-S
Aluminium Windows-Sh
Wall Tiles- Corridors\Lift Lobby

R.C.C Slab (9th Floor Slab)\Electric Conduits


FCU & A.C Ducts

Filling\Supply Pipes Ins


Kitchen Gas Detect
Flooring Tiles- Service\Dry Ar
Suspension System- Wet Ar
Suspension System-

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Termination
Plaster Work

Primer & Stucco

Work Completion (Teleph

Floor Weather Tight (to

Actual Level of Effort Remaining Work Page 114 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
09.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 13-May-18 -258
09.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 22-May-18 -258
09.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 29-Apr-18 -260
09.AC.040 Pipes Testing 2 2 0% 13-Mar-18 15-Mar-18 -262
09.FF.020 Pipes Testing 2 2 0% 19-Mar-18 21-Mar-18 -262
09.WS.040 Pipes Testing 2 2 0% 15-Apr-18 17-Apr-18 -264
09.DR.020 Pipes Testing 2 2 0% 25-Mar-18 26-Mar-18 -262
09.FL.100 Marble Threshold 2 2 0% 11-Jul-18 14-Jul-18 -260
09.CO.010 R.C.C Columns\Walls 3 3 0% 02-Jan-18 06-Jan-18 -270
09.EL.C10 Emergency Light 3 3 0% 21-Jun-18 24-Jun-18 -239
09.FF.030 Sprinkler Heads 4 4 0% 16-Jun-18 19-Jun-18 -251
09.EL.T20 Install Telephone Cables 4 4 0% 07-May-18 10-May-18 -264
09.PG.100 Flexible Hose 4 4 0% 01-Jul-18 04-Jul-18 -260
09.AL.500 Aluminium Windows-Shutters 4 4 0% 17-May-18 22-May-18 -265
09.FL.D20 Screed Flooring 4 4 0% 22-Apr-18 25-Apr-18 -269
09.WD.010 Fixing Sub Frames 4 4 0% 24-Feb-18 27-Feb-18 -248
09.AC.050 Duct Drops (Wet Area) 4 4 0% 13-May-18 16-May-18 -260
09.AC.060 Duct Drops (Dry Area) 4 4 0% 22-May-18 28-May-18 -257
09.AC.070 Duct Drops (Corridors) 4 4 0% 31-May-18 04-Jun-18 -257
09.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 16-Jun-18 20-Jun-18 -252
09.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 21-Feb-18 26-Feb-18 -262
09.WS.020 Main Pipes 5 5 0% 26-Feb-18 03-Mar-18 -262
09.EL.F20 Fixing Fire Alarm Devices 5 5 0% 23-Jun-18 27-Jun-18 -253
09.EL.010 Conduits, Boxes & enclosure 5 5 0% 21-Feb-18 26-Feb-18 -246
09.EL.E30 Isolators In High Level 5 5 0% 24-Apr-18 29-Apr-18 -261
09.FL.D90 Epoxy Coating 5 5 0% 02-Jul-18 07-Jul-18 -264
09.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 11-Jun-18 16-Jun-18 -257
09.SN.010 Work Completion\Snagging Work 5 5 0% 14-Jul-18 18-Jul-18 -254
09.AC.110 Grills and Diffusers 6 6 0% 27-Jun-18 03-Jul-18 -253
09.FF.010 Hz. Pipes H\L 6 6 0% 13-Mar-18 19-Mar-18 -262
09.WS.050 Valves, Mixer's, etc... 6 6 0% 17-Jun-18 23-Jun-18 -256
09.WS.030 Water Heater 6 6 0% 10-Apr-18 15-Apr-18 -264
09.EL.C20 Emergency Light Control Panel 6 6 0% 24-Jun-18 30-Jun-18 -239
09.EL.S20 Security System Devices 6 6 0% 27-Jun-18 03-Jul-18 -250

Actual Level of Effort Remaining Work Page 115 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
MEP CLEARANCE- Dry Are
MEP CLEARANCE- Corr
MEP CLEARANCE- Wet Area, 2
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Install Telephone Cables

Aluminium Windows-Shu
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Area)
Duct Drops (Corridor

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Isolators In High Level

Hz. Pipes H\L

Water Heater

Actual Level of Effort Remaining Work Page 116 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
09.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 16-Jun-18 21-Jun-18 -257
09.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 01-May-18 07-May-18 -264
09.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 12-Jun-18 17-Jun-18 -256
09.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 19-Mar-18 25-Mar-18 -262
09.DR.030 Fixing Of Bath Tub 6 6 0% 22-Apr-18 28-Apr-18 -271
09.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 29-Apr-18 03-May-18 -260
09.AL.400 Aluminium Windows-Shutters 6 6 0% 12-May-18 17-May-18 -268
09.AL.200 Aluminium Windows-Shutters 6 6 0% 12-May-18 17-May-18 -268
09.FL.W40 Floor Tiles- Wet Area 6 6 0% 28-Apr-18 03-May-18 -271
09.CL.W10 Wall Tiles- Wet Area 6 6 0% 04-Apr-18 10-Apr-18 -271
09.FO.040 Mirrors & Bath Accessories 6 6 0% 23-Jun-18 28-Jun-18 -256
09.DR.050 Pipes In Walls 6 6 0% 26-Feb-18 03-Mar-18 -258
09.DR.910 Drinage Pipes L\L 6 6 0% 16-Apr-18 22-Apr-18 -271
09.CO.100 Dismantling Shutters 7 7 0% 24-Jan-18 31-Jan-18 -263
09.AC.020 Mouse Connection & Fire Damper 7 7 0% 07-Mar-18 13-Mar-18 -262
09.AC.030 Gas Pipes net work 7 7 0% 07-Mar-18 13-Mar-18 -262
09.EL.S40 Security System Control Panels 7 7 0% 03-Jul-18 10-Jul-18 -250
09.EL.020 Pulling All Types Of Wires 7 7 0% 17-Apr-18 24-Apr-18 -261
09.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 12-May-18 17-May-18 -265
09.WD.030 Door Shutters & Ironmongery 7 7 0% 27-May-18 03-Jun-18 -256
09.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 22-May-18 31-May-18 -259
09.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 04-Jun-18 11-Jun-18 -257
09.FC.W30 Final Stage- Wet Area 7 7 0% 16-May-18 22-May-18 -260
09.WP.W20 Waterproofing- Wet Area 7 7 0% 10-Apr-18 16-Apr-18 -271
09.AL.100 Aluminium Windows-Shutters 8 8 0% 12-May-18 19-May-18 -271
09.AL.300 Aluminium Windows-Shutters 8 8 0% 12-May-18 19-May-18 -271
09.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 10-Apr-18 17-Apr-18 -266
09.FC.D30 Final Stage- Dry Area 8 8 0% 28-May-18 04-Jun-18 -257
09.CO.050 R.C.C Slab (10th Floor Slab)\Electric Conduits 9 9 0% 06-Jan-18 14-Jan-18 -270
09.AC.010 FCU & A.C Ducts 9 9 0% 03-Mar-18 11-Mar-18 -262
09.PG.040 Emergency Gas Off\On Switch With LED Indicator 9 9 0% 11-Jun-18 19-Jun-18 -260
09.PG.020 Filling\Supply Pipes Installaion (Exposed) 9 9 0% 22-May-18 03-Jun-18 -260
09.PG.030 Kitchen Gas Detector 9 9 0% 03-Jun-18 11-Jun-18 -260
09.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 03-May-18 12-May-18 -271

Actual Level of Effort Remaining Work Page 117 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Install Electric Cables Try\Pow

Floor Trap & Drainage Pipes H\L


Fixing Of Bath Tub
Filling\Supply Pipes Installaion
Aluminium Windows-Shutte
Aluminium Windows-Shutte
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors and
Door Shutters & Ironm
Suspension System- C
Final Stage- Corrido
Final Stage- Wet Area
Waterproofing- Wet Area
Aluminium Windows-Shut
Aluminium Windows-Shut
Wall Tiles- Corridors\Lift Lobby
Final Stage- Dry Area
R.C.C Slab (10th Floor Slab)\Electric Conduits
FCU & A.C Ducts

Filling\Supply Pipes In
Kitchen Gas Detect
Flooring Tiles- Service\Dry A

Actual Level of Effort Remaining Work Page 118 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
09.FC.W20 Suspension System- Wet Area 9 9 0% 03-May-18 13-May-18 -260
09.FC.D20 Suspension System- Dry Area 10 10 0% 13-May-18 22-May-18 -258
09.PG.090 Gas Alarm Control Panel 12 12 0% 19-Jun-18 01-Jul-18 -260
09.PN.020 Painting Work 12 12 0% 04-Jun-18 16-Jun-18 -257
09.EL.T30 ONU Termination 13 13 0% 10-May-18 22-May-18 -246
09.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 07-Feb-18 21-Feb-18 -271
09.EL.E50 DB'S Dressing\Terminations 14 14 0% 07-May-18 20-May-18 -253
09.PL.010 Plaster Work 14 14 0% 21-Mar-18 04-Apr-18 -271
09.FO.020 Kitchen Cabinet 14 14 0% 29-May-18 12-Jun-18 -256
09.FO.030 Vanity Counter 14 14 0% 29-May-18 12-Jun-18 -256
09.PN.010 Primer & Stucco 14 14 0% 04-Apr-18 17-Apr-18 -270
09.FO.010 Wardrobes 21 21 0% 16-Jun-18 05-Jul-18 -245

- 10th Floor 199 199 0% 15-Jan-18 23-Jul-18 -259

10.AC.900 Work Completion 0 0 0% 11-Jul-18 -262


10.FF.900 Work Completion 0 0 0% 02-Jul-18 -265
10.WS.900 Work Completion 0 0 0% 01-Jul-18 -262
10.EL.F90 Work Completion (Fire Alarm) 0 0 0% 05-Jul-18 -262
10.EL.T90 Work Completion (Telephone) 0 0 0% 03-Jun-18 -253
10.EL.L90 Work Completion (Low Current) 0 0 0% 18-Jul-18 -259
10.EL.E90 Work Completion (Electric) 0 0 0% 03-Jul-18 -264
10.DR.900 Work Completion 0 0 0% 26-Jun-18 -262
10.PG.900 Work Completion 0 0 0% 05-Jul-18 -261
10.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 04-Jun-18 -262
10.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 27-May-18 -265
10.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 05-Jun-18 -264
10.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 10-May-18 -265
10.AC.040 Pipes Testing 2 2 0% 26-Mar-18 29-Mar-18 -263
10.FF.020 Pipes Testing 2 2 0% 02-Apr-18 04-Apr-18 -263
10.WS.040 Pipes Testing 2 2 0% 23-Apr-18 24-Apr-18 -264
10.DR.020 Pipes Testing 2 2 0% 08-Apr-18 10-Apr-18 -262
10.PG.100 Flexible Hose 2 2 0% 03-Jul-18 05-Jul-18 -261
10.FL.100 Marble Threshold 2 2 0% 14-Jul-18 15-Jul-18 -260
10.CO.010 R.C.C Columns\Walls 3 3 0% 15-Jan-18 17-Jan-18 -270

Actual Level of Effort Remaining Work Page 119 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Suspension System- Wet A
Suspension System- Dry

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Terminatio
Plaster Work

Primer & Stucco

Work Completion (Tel

Floor Weather Tight (


MEP CLEARANCE- Dry
MEP CLEARANCE- C
MEP CLEARANCE- Wet Are
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Actual Level of Effort Remaining Work Page 120 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
10.EL.C10 Emergency Light 3 3 0% 03-Jul-18 05-Jul-18 -252
10.FF.030 Sprinkler Heads 4 4 0% 27-Jun-18 01-Jul-18 -264
10.EL.T20 Install Telephone Cables 4 4 0% 16-May-18 20-May-18 -270
10.EL.E30 Isolators In High Level 4 4 0% 07-May-18 10-May-18 -270
10.AL.500 Aluminium Windows-Shutters 4 4 0% 29-May-18 02-Jun-18 -270
10.FL.D20 Screed Flooring 4 4 0% 25-Apr-18 29-Apr-18 -265
10.WD.010 Fixing Sub Frames 4 4 0% 08-Mar-18 12-Mar-18 -253
10.AC.050 Duct Drops (Wet Area) 4 4 0% 27-May-18 30-May-18 -265
10.AC.060 Duct Drops (Dry Area) 4 4 0% 05-Jun-18 09-Jun-18 -265
10.AC.070 Duct Drops (Corridors) 4 4 0% 12-Jun-18 17-Jun-18 -265
10.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 27-Jun-18 02-Jul-18 -265
10.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 06-Mar-18 11-Mar-18 -263
10.WS.020 Main Pipes 5 5 0% 11-Mar-18 15-Mar-18 -263
10.EL.F20 Fixing Fire Alarm Devices 5 5 0% 01-Jul-18 05-Jul-18 -262
10.EL.010 Conduits, Boxes & enclosure 5 5 0% 06-Mar-18 11-Mar-18 -251
10.DR.030 Fixing Of Bath Tub 5 5 0% 28-Apr-18 02-May-18 -268
10.FL.D90 Epoxy Coating 5 5 0% 07-Jul-18 11-Jul-18 -264
10.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 23-Jun-18 27-Jun-18 -265
10.SN.010 Work Completion\Snagging Work 5 5 0% 18-Jul-18 23-Jul-18 -259
10.AC.110 Grills and Diffusers 6 6 0% 05-Jul-18 11-Jul-18 -262
10.FF.010 Hz. Pipes H\L 6 6 0% 26-Mar-18 02-Apr-18 -263
10.WS.050 Valves, Mixer's, etc... 6 6 0% 26-Jun-18 01-Jul-18 -262
10.WS.030 Water Heater 6 6 0% 17-Apr-18 23-Apr-18 -264
10.EL.C20 Emergency Light Control Panel 6 6 0% 05-Jul-18 11-Jul-18 -252
10.EL.S20 Security System Devices 6 6 0% 05-Jul-18 11-Jul-18 -259
10.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 27-Jun-18 03-Jul-18 -264
10.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 10-May-18 16-May-18 -270
10.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 20-Jun-18 26-Jun-18 -262
10.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 02-Apr-18 08-Apr-18 -263
10.PG.090 Gas Alarm Control Panel 6 6 0% 27-Jun-18 03-Jul-18 -261
10.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 10-May-18 16-May-18 -265
10.PG.040 Emergency Gas Off\On Switch With LED Indicator 6 6 0% 17-Jun-18 23-Jun-18 -256
10.PG.020 Filling\Supply Pipes Installaion (Exposed) 6 6 0% 06-Jun-18 12-Jun-18 -256
10.PG.030 Kitchen Gas Detector 6 6 0% 12-Jun-18 17-Jun-18 -256

Actual Level of Effort Remaining Work Page 121 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Install Telephone Cables


Isolators In High Level
Aluminium Windows-S
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area)
Duct Drops (Dry Are

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Fixing Of Bath Tub

Hz. Pipes H\L

Water Heater

Install Electric Cables Try\P

Floor Trap & Drainage Pipes H\L

Filling\Supply Pipes Installa

Actual Level of Effort Remaining Work Page 122 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
10.AL.400 Aluminium Windows-Shutters 6 6 0% 17-May-18 22-May-18 -268
10.AL.200 Aluminium Windows-Shutters 6 6 0% 17-May-18 22-May-18 -268
10.FL.W40 Floor Tiles- Wet Area 6 6 0% 02-May-18 08-May-18 -268
10.CL.W10 Wall Tiles- Wet Area 6 6 0% 09-Apr-18 15-Apr-18 -267
10.FO.040 Mirrors & Bath Accessories 6 6 0% 01-Jul-18 07-Jul-18 -259
10.DR.050 Pipes In Walls 6 6 0% 11-Mar-18 17-Mar-18 -250
10.DR.910 Drinage Pipes L\L 6 6 0% 22-Apr-18 28-Apr-18 -268
10.CO.100 Dismantling Shutters 7 7 0% 06-Feb-18 12-Feb-18 -262
10.AC.020 Mouse Connection & Fire Damper 7 7 0% 20-Mar-18 26-Mar-18 -263
10.AC.030 Gas Pipes net work 7 7 0% 20-Mar-18 26-Mar-18 -263
10.EL.S40 Security System Control Panels 7 7 0% 11-Jul-18 18-Jul-18 -259
10.EL.020 Pulling All Types Of Wires 7 7 0% 30-Apr-18 07-May-18 -270
10.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 20-May-18 29-May-18 -270
10.WD.030 Door Shutters & Ironmongery 7 7 0% 04-Jun-18 11-Jun-18 -262
10.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 06-Jun-18 12-Jun-18 -265
10.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 17-Jun-18 23-Jun-18 -265
10.FC.W30 Final Stage- Wet Area 7 7 0% 30-May-18 06-Jun-18 -265
10.WP.W20 Waterproofing- Wet Area 7 7 0% 15-Apr-18 21-Apr-18 -267
10.AL.100 Aluminium Windows-Shutters 8 8 0% 19-May-18 29-May-18 -271
10.AL.300 Aluminium Windows-Shutters 8 8 0% 19-May-18 29-May-18 -271
10.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 17-Apr-18 24-Apr-18 -266
10.FC.D30 Final Stage- Dry Area 8 8 0% 09-Jun-18 17-Jun-18 -265
10.CO.050 R.C.C Slab (11th Floor Slab)\Electric Conduits 9 9 0% 17-Jan-18 25-Jan-18 -270
10.AC.010 FCU & A.C Ducts 9 9 0% 15-Mar-18 24-Mar-18 -263
10.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 08-May-18 16-May-18 -268
10.FC.W20 Suspension System- Wet Area 9 9 0% 16-May-18 27-May-18 -265
10.FC.D20 Suspension System- Dry Area 10 10 0% 27-May-18 05-Jun-18 -265
10.PN.020 Painting Work 12 12 0% 17-Jun-18 27-Jun-18 -265
10.EL.T30 ONU Termination 13 13 0% 20-May-18 03-Jun-18 -253
10.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 21-Feb-18 06-Mar-18 -271
10.EL.E50 DB'S Dressing\Terminations 14 14 0% 20-May-18 04-Jun-18 -253
10.PL.010 Plaster Work 14 14 0% 26-Mar-18 09-Apr-18 -267
10.FO.020 Kitchen Cabinet 14 14 0% 07-Jun-18 20-Jun-18 -262
10.FO.030 Vanity Counter 14 14 0% 07-Jun-18 20-Jun-18 -262

Actual Level of Effort Remaining Work Page 123 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Aluminium Windows-Shu
Aluminium Windows-Shu
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Dismantling Shutters
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors a
Door Shutters & Iro

Final Stage- Wet Are


Waterproofing- Wet Area
Aluminium Windows-Sh
Aluminium Windows-Sh
Wall Tiles- Corridors\Lift Lobby

R.C.C Slab (11th Floor Slab)\Electric Conduits


FCU & A.C Ducts
Flooring Tiles- Service\Dry
Suspension System- W
Suspension System-

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Termin
Plaster Work

Actual Level of Effort Remaining Work Page 124 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
10.PN.010 Primer & Stucco 14 14 0% 17-Apr-18 30-Apr-18 -270
10.FO.010 Wardrobes 21 21 0% 27-Jun-18 17-Jul-18 -258

- 11th Floor 193 193 0% 27-Jan-18 29-Jul-18 -266

11.AC.900 Work Completion 0 0 0% 18-Jul-18 -269


11.FF.900 Work Completion 0 0 0% 05-Jul-18 -269
11.WS.900 Work Completion 0 0 0% 08-Jul-18 -269
11.EL.F90 Work Completion (Fire Alarm) 0 0 0% 12-Jul-18 -269
11.EL.T90 Work Completion (Telephone) 0 0 0% 07-Jun-18 -257
11.EL.L90 Work Completion (Low Current) 0 0 0% 24-Jul-18 -266
11.EL.E90 Work Completion (Electric) 0 0 0% 09-Jul-18 -264
11.DR.900 Work Completion 0 0 0% 02-Jul-18 -269
11.PG.900 Work Completion 0 0 0% 09-Jul-18 -265
11.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 11-Jun-18 -269
11.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 30-May-18 -269
11.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 09-Jun-18 -268
11.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 14-May-18 -269
11.AC.040 Pipes Testing 2 2 0% 27-Mar-18 31-Mar-18 -259
11.FF.020 Pipes Testing 2 2 0% 03-Apr-18 05-Apr-18 -259
11.WS.040 Pipes Testing 2 2 0% 29-Apr-18 30-Apr-18 -270
11.DR.020 Pipes Testing 2 2 0% 09-Apr-18 10-Apr-18 -259
11.PG.100 Flexible Hose 2 2 0% 07-Jul-18 09-Jul-18 -265
11.FL.100 Marble Threshold 2 2 0% 16-Jul-18 18-Jul-18 -261
11.CO.010 R.C.C Columns\Walls 3 3 0% 27-Jan-18 29-Jan-18 -270
11.EL.C10 Emergency Light 3 3 0% 09-Jul-18 11-Jul-18 -258
11.CO.100 Dismantling Shutters 4 4 0% 18-Feb-18 21-Feb-18 -270
11.FF.030 Sprinkler Heads 4 4 0% 01-Jul-18 05-Jul-18 -268
11.EL.T20 Install Telephone Cables 4 4 0% 20-May-18 26-May-18 -270
11.EL.E30 Isolators In High Level 4 4 0% 10-May-18 14-May-18 -270
11.AL.500 Aluminium Windows-Shutters 4 4 0% 02-Jun-18 05-Jun-18 -270
11.FL.D20 Screed Flooring 4 4 0% 30-Apr-18 03-May-18 -266
11.WD.010 Fixing Sub Frames 4 4 0% 12-Mar-18 17-Mar-18 -252
11.AC.050 Duct Drops (Wet Area) 4 4 0% 30-May-18 03-Jun-18 -269
11.AC.060 Duct Drops (Dry Area) 4 4 0% 09-Jun-18 12-Jun-18 -269

Actual Level of Effort Remaining Work Page 125 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Primer & Stucco

Work Completion (Te

Floor Weather Tigh


MEP CLEARANCE- Dr
MEP CLEARANCE-
MEP CLEARANCE- Wet Ar
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Dismantling Shutters

Install Telephone Cables


Isolators In High Level
Aluminium Windows-
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Area

Actual Level of Effort Remaining Work Page 126 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
11.AC.070 Duct Drops (Corridors) 4 4 0% 17-Jun-18 20-Jun-18 -269
11.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 01-Jul-18 05-Jul-18 -269
11.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 07-Mar-18 12-Mar-18 -259
11.WS.020 Main Pipes 5 5 0% 12-Mar-18 17-Mar-18 -259
11.EL.F20 Fixing Fire Alarm Devices 5 5 0% 08-Jul-18 12-Jul-18 -269
11.EL.010 Conduits, Boxes & enclosure 5 5 0% 07-Mar-18 12-Mar-18 -246
11.DR.030 Fixing Of Bath Tub 5 5 0% 03-May-18 08-May-18 -268
11.FL.D90 Epoxy Coating 5 5 0% 11-Jul-18 16-Jul-18 -264
11.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 26-Jun-18 01-Jul-18 -269
11.WP.W20 Waterproofing- Wet Area 5 5 0% 23-Apr-18 28-Apr-18 -268
11.SN.010 Work Completion\Snagging Work 5 5 0% 24-Jul-18 29-Jul-18 -266
11.AC.110 Grills and Diffusers 6 6 0% 12-Jul-18 18-Jul-18 -269
11.FF.010 Hz. Pipes H\L 6 6 0% 27-Mar-18 03-Apr-18 -259
11.WS.050 Valves, Mixer's, etc... 6 6 0% 02-Jul-18 08-Jul-18 -269
11.WS.030 Water Heater 6 6 0% 23-Apr-18 29-Apr-18 -270
11.EL.C20 Emergency Light Control Panel 6 6 0% 11-Jul-18 17-Jul-18 -258
11.EL.S20 Security System Devices 6 6 0% 12-Jul-18 18-Jul-18 -266
11.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 03-Jul-18 09-Jul-18 -264
11.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 14-May-18 20-May-18 -270
11.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 26-Jun-18 02-Jul-18 -269
11.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 03-Apr-18 09-Apr-18 -259
11.PG.090 Gas Alarm Control Panel 6 6 0% 01-Jul-18 07-Jul-18 -265
11.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 14-May-18 20-May-18 -269
11.PG.040 Emergency Gas Off\On Switch With LED Indicator 6 6 0% 21-Jun-18 26-Jun-18 -260
11.PG.020 Filling\Supply Pipes Installaion (Exposed) 6 6 0% 10-Jun-18 16-Jun-18 -260
11.PG.030 Kitchen Gas Detector 6 6 0% 16-Jun-18 21-Jun-18 -260
11.AL.400 Aluminium Windows-Shutters 6 6 0% 22-May-18 30-May-18 -268
11.AL.200 Aluminium Windows-Shutters 6 6 0% 22-May-18 30-May-18 -268
11.FL.W40 Floor Tiles- Wet Area 6 6 0% 08-May-18 13-May-18 -268
11.CL.W10 Wall Tiles- Wet Area 6 6 0% 17-Apr-18 23-Apr-18 -270
11.FO.040 Mirrors & Bath Accessories 6 6 0% 08-Jul-18 14-Jul-18 -260
11.DR.050 Pipes In Walls 6 6 0% 17-Mar-18 21-Mar-18 -250
11.DR.910 Drinage Pipes L\L 6 6 0% 28-Apr-18 03-May-18 -268
11.AC.020 Mouse Connection & Fire Damper 7 7 0% 21-Mar-18 27-Mar-18 -259

Actual Level of Effort Remaining Work Page 127 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Fixing Of Bath Tub

Waterproofing- Wet Area

Hz. Pipes H\L

Water Heater

Install Electric Cables Try

Floor Trap & Drainage Pipes H\L

Filling\Supply Pipes Install

Aluminium Windows-Sh
Aluminium Windows-Sh
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Mouse Connection & Fire Damper

Actual Level of Effort Remaining Work Page 128 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
11.AC.030 Gas Pipes net work 7 7 0% 21-Mar-18 27-Mar-18 -259
11.EL.S40 Security System Control Panels 7 7 0% 18-Jul-18 24-Jul-18 -266
11.EL.020 Pulling All Types Of Wires 7 7 0% 30-Apr-18 07-May-18 -266
11.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 26-May-18 02-Jun-18 -270
11.WD.030 Door Shutters & Ironmongery 7 7 0% 11-Jun-18 17-Jun-18 -269
11.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 10-Jun-18 17-Jun-18 -269
11.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 20-Jun-18 26-Jun-18 -269
11.FC.W30 Final Stage- Wet Area 7 7 0% 03-Jun-18 10-Jun-18 -269
11.AL.100 Aluminium Windows-Shutters 8 8 0% 29-May-18 05-Jun-18 -271
11.AL.300 Aluminium Windows-Shutters 8 8 0% 29-May-18 05-Jun-18 -271
11.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 24-Apr-18 02-May-18 -266
11.FC.D30 Final Stage- Dry Area 8 8 0% 12-Jun-18 20-Jun-18 -269
11.CO.050 R.C.C Slab (12th Floor Slab)\Electric Conduits 9 9 0% 29-Jan-18 07-Feb-18 -270
11.AC.010 FCU & A.C Ducts 9 9 0% 17-Mar-18 25-Mar-18 -259
11.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 13-May-18 22-May-18 -268
11.FC.W20 Suspension System- Wet Area 9 9 0% 20-May-18 30-May-18 -269
11.FC.D20 Suspension System- Dry Area 10 10 0% 30-May-18 09-Jun-18 -269
11.PN.020 Painting Work 12 12 0% 20-Jun-18 01-Jul-18 -269
11.EL.T30 ONU Termination 13 13 0% 26-May-18 07-Jun-18 -257
11.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 21-Feb-18 07-Mar-18 -270
11.EL.E50 DB'S Dressing\Terminations 14 14 0% 20-May-18 04-Jun-18 -267
11.PL.010 Plaster Work 14 14 0% 04-Apr-18 17-Apr-18 -270
11.FO.020 Kitchen Cabinet 14 14 0% 13-Jun-18 26-Jun-18 -269
11.FO.030 Vanity Counter 14 14 0% 13-Jun-18 26-Jun-18 -269
11.PN.010 Primer & Stucco 14 14 0% 17-Apr-18 30-Apr-18 -266
11.FO.010 Wardrobes 21 21 0% 01-Jul-18 21-Jul-18 -262

- 12th Floor 181 181 0% 07-Feb-18 30-Jul-18 -267

12.AC.900 Work Completion 0 0 0% 19-Jul-18 -270


12.FF.900 Work Completion 0 0 0% 07-Jul-18 -270
12.WS.900 Work Completion 0 0 0% 09-Jul-18 -270
12.EL.F90 Work Completion (Fire Alarm) 0 0 0% 14-Jul-18 -270
12.EL.T90 Work Completion (Telephone) 0 0 0% 07-Jun-18 -258
12.EL.L90 Work Completion (Low Current) 0 0 0% 25-Jul-18 -267

Actual Level of Effort Remaining Work Page 129 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors

Final Stage- Wet Ar


Aluminium Windows-
Aluminium Windows-
Wall Tiles- Corridors\Lift Lobby

R.C.C Slab (12th Floor Slab)\Electric Conduits


FCU & A.C Ducts
Flooring Tiles- Service\Dr
Suspension System- W
Suspension System

ONU Termination
Block Work\Concrete Upstand,Lintels
DB'S Dressing\Termin
Plaster Work

Primer & Stucco

Work Completion (Te

Actual Level of Effort Remaining Work Page 130 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
12.EL.E90 Work Completion (Electric) 0 0 0% 15-Jul-18 -256
12.DR.900 Work Completion 0 0 0% 03-Jul-18 -270
12.PG.900 Work Completion 0 0 0% 10-Jul-18 -266
12.AL.010 Floor Weather Tight (to Start F.C, Doors, Paint, F.O, Final0Fix, etc..) 0 0% 12-Jun-18 -270
12.FC.D10 MEP CLEARANCE- Dry Area 0 0 0% 31-May-18 -270
12.FC.E10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 10-Jun-18 -269
12.FC.W10 MEP CLEARANCE- Wet Area 0 0 0% 15-May-18 -270
12.AC.040 Pipes Testing 2 2 0% 10-Apr-18 12-Apr-18 -270
12.FF.020 Pipes Testing 2 2 0% 16-Apr-18 18-Apr-18 -270
12.WS.040 Pipes Testing 2 2 0% 06-May-18 08-May-18 -270
12.DR.020 Pipes Testing 2 2 0% 22-Apr-18 24-Apr-18 -270
12.PG.100 Flexible Hose 2 2 0% 08-Jul-18 10-Jul-18 -266
12.FL.100 Marble Threshold 2 2 0% 21-Jul-18 23-Jul-18 -264
12.CO.010 R.C.C Columns\Walls 3 3 0% 07-Feb-18 11-Feb-18 -269
12.EL.C10 Emergency Light 3 3 0% 15-Jul-18 17-Jul-18 -264
12.CO.100 Dismantling Shutters 4 4 0% 03-Mar-18 06-Mar-18 -269
12.FF.030 Sprinkler Heads 4 4 0% 02-Jul-18 05-Jul-18 -269
12.EL.T20 Install Telephone Cables 4 4 0% 21-May-18 27-May-18 -267
12.EL.E30 Isolators In High Level 4 4 0% 12-May-18 15-May-18 -270
12.AL.500 Aluminium Windows-Shutters 4 4 0% 05-Jun-18 09-Jun-18 -270
12.FL.D20 Screed Flooring 4 4 0% 08-May-18 12-May-18 -270
12.WD.010 Fixing Sub Frames 4 4 0% 22-Mar-18 26-Mar-18 -259
12.AC.050 Duct Drops (Wet Area) 4 4 0% 31-May-18 04-Jun-18 -270
12.AC.060 Duct Drops (Dry Area) 4 4 0% 10-Jun-18 13-Jun-18 -270
12.AC.070 Duct Drops (Corridors) 4 4 0% 17-Jun-18 21-Jun-18 -270
12.FF.040 Hose Reel\Fire Extinguisher 5 5 0% 02-Jul-18 07-Jul-18 -270
12.WS.010 Hot & Cold Water (Wet Area) 5 5 0% 20-Mar-18 25-Mar-18 -270
12.WS.020 Main Pipes 5 5 0% 25-Mar-18 31-Mar-18 -270
12.EL.F20 Fixing Fire Alarm Devices 5 5 0% 09-Jul-18 14-Jul-18 -270
12.EL.010 Conduits, Boxes & enclosure 5 5 0% 20-Mar-18 25-Mar-18 -257
12.DR.030 Fixing Of Bath Tub 5 5 0% 05-May-18 09-May-18 -268
12.FL.D90 Epoxy Coating 5 5 0% 16-Jul-18 21-Jul-18 -264
12.PN.E10 Painting Work to False Ceiling (Corridors\Lift Lobby) 5 5 0% 27-Jun-18 02-Jul-18 -270
12.WP.W20 Waterproofing- Wet Area 5 5 0% 24-Apr-18 29-Apr-18 -268

Actual Level of Effort Remaining Work Page 131 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

MEP CLEARANCE- D
MEP CLEARANCE-
MEP CLEARANCE- Wet Ar
Pipes Testing
Pipes Testing
Pipes Testing
Pipes Testing

R.C.C Columns\Walls

Dismantling Shutters

Install Telephone Cables


Isolators In High Level
Aluminium Windows
Screed Flooring
Fixing Sub Frames
Duct Drops (Wet Are

Hot & Cold Water (Wet Area)


Main Pipes

Conduits, Boxes & enclosure


Fixing Of Bath Tub

Waterproofing- Wet Area

Actual Level of Effort Remaining Work Page 132 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
12.SN.010 Work Completion\Snagging Work 5 5 0% 25-Jul-18 30-Jul-18 -267
12.AC.110 Grills and Diffusers 6 6 0% 14-Jul-18 19-Jul-18 -270
12.FF.010 Hz. Pipes H\L 6 6 0% 10-Apr-18 16-Apr-18 -270
12.WS.050 Valves, Mixer's, etc... 6 6 0% 03-Jul-18 09-Jul-18 -270
12.WS.030 Water Heater 6 6 0% 30-Apr-18 06-May-18 -270
12.EL.C20 Emergency Light Control Panel 6 6 0% 17-Jul-18 23-Jul-18 -264
12.EL.S20 Security System Devices 6 6 0% 14-Jul-18 19-Jul-18 -267
12.EL.E60 All Type Of Switches, Sockets, Light Fittings and Accessoeies
6 6 0% 09-Jul-18 15-Jul-18 -264
12.EL.E40 Install Electric Cables Try\Power Cables 6 6 0% 15-May-18 21-May-18 -267
12.DR.100 Sanitary Ware, Kitchen Sink 6 6 0% 27-Jun-18 03-Jul-18 -270
12.DR.010 Floor Trap & Drainage Pipes H\L 6 6 0% 16-Apr-18 22-Apr-18 -270
12.PG.090 Gas Alarm Control Panel 6 6 0% 02-Jul-18 08-Jul-18 -266
12.PG.010 Filling\Supply Pipes Installaion (Concealed Part) 6 6 0% 15-May-18 21-May-18 -270
12.PG.040 Emergency Gas Off\On Switch With LED Indicator 6 6 0% 21-Jun-18 27-Jun-18 -261
12.PG.020 Filling\Supply Pipes Installaion (Exposed) 6 6 0% 11-Jun-18 17-Jun-18 -261
12.PG.030 Kitchen Gas Detector 6 6 0% 17-Jun-18 21-Jun-18 -261
12.AL.400 Aluminium Windows-Shutters 6 6 0% 30-May-18 05-Jun-18 -268
12.AL.200 Aluminium Windows-Shutters 6 6 0% 30-May-18 05-Jun-18 -268
12.FL.W40 Floor Tiles- Wet Area 6 6 0% 12-May-18 17-May-18 -270
12.CL.W10 Wall Tiles- Wet Area 6 6 0% 19-Apr-18 24-Apr-18 -268
12.FO.040 Mirrors & Bath Accessories 6 6 0% 14-Jul-18 19-Jul-18 -260
12.DR.050 Pipes In Walls 6 6 0% 25-Mar-18 01-Apr-18 -253
12.DR.910 Drinage Pipes L\L 6 6 0% 29-Apr-18 05-May-18 -268
12.AC.020 Mouse Connection & Fire Damper 7 7 0% 04-Apr-18 10-Apr-18 -270
12.AC.030 Gas Pipes net work 7 7 0% 04-Apr-18 10-Apr-18 -270
12.EL.S40 Security System Control Panels 7 7 0% 19-Jul-18 25-Jul-18 -267
12.EL.020 Pulling All Types Of Wires 7 7 0% 05-May-18 12-May-18 -270
12.FL.C30 Floor Tiles- Corridors and Lobby 7 7 0% 28-May-18 03-Jun-18 -268
12.WD.030 Door Shutters & Ironmongery 7 7 0% 12-Jun-18 18-Jun-18 -270
12.FC.E20 Suspension System- Corridors and Lift Lobby 7 7 0% 11-Jun-18 17-Jun-18 -270
12.FC.E30 Final Stage- Corridors and Lift Lobby 7 7 0% 21-Jun-18 27-Jun-18 -270
12.FC.W30 Final Stage- Wet Area 7 7 0% 04-Jun-18 11-Jun-18 -270
12.AL.100 Aluminium Windows-Shutters 8 8 0% 28-May-18 04-Jun-18 -270
12.AL.300 Aluminium Windows-Shutters 8 8 0% 28-May-18 04-Jun-18 -270

Actual Level of Effort Remaining Work Page 133 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Hz. Pipes H\L

Water Heater

Install Electric Cables Try

Floor Trap & Drainage Pipes H\L

Filling\Supply Pipes Instal

Aluminium Windows-
Aluminium Windows-
Floor Tiles- Wet Area
Wall Tiles- Wet Area

Pipes In Walls
Drinage Pipes L\L
Mouse Connection & Fire Damper
Gas Pipes net work

Pulling All Types Of Wires


Floor Tiles- Corridors

Final Stage- Wet Ar


Aluminium Windows-S
Aluminium Windows-S

Actual Level of Effort Remaining Work Page 134 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
12.CL.C20 Wall Tiles- Corridors\Lift Lobby 8 8 0% 02-May-18 09-May-18 -266
12.FC.D30 Final Stage- Dry Area 8 8 0% 13-Jun-18 21-Jun-18 -270
12.CO.050 R.C.C Slab (Roof Floor Slab)\Electric Conduits 9 9 0% 11-Feb-18 19-Feb-18 -269
12.AC.010 FCU & A.C Ducts 9 9 0% 31-Mar-18 08-Apr-18 -270
12.FL.D30 Flooring Tiles- Service\Dry Area 9 9 0% 17-May-18 28-May-18 -270
12.FC.W20 Suspension System- Wet Area 9 9 0% 21-May-18 31-May-18 -270
12.FC.D20 Suspension System- Dry Area 10 10 0% 31-May-18 10-Jun-18 -270
12.PN.010 Primer & Stucco 12 12 0% 24-Apr-18 05-May-18 -270
12.PN.020 Painting Work 12 12 0% 21-Jun-18 02-Jul-18 -270
12.EL.T30 ONU Termination 13 13 0% 27-May-18 07-Jun-18 -258
12.BL.100 Block Work\Concrete Upstand,Lintels 14 14 0% 07-Mar-18 20-Mar-18 -270
12.EL.E50 DB'S Dressing\Terminations 14 14 0% 04-Jun-18 17-Jun-18 -267
12.PL.010 Plaster Work 14 14 0% 04-Apr-18 17-Apr-18 -267
12.FO.020 Kitchen Cabinet 14 14 0% 14-Jun-18 27-Jun-18 -270
12.FO.030 Vanity Counter 14 14 0% 14-Jun-18 27-Jun-18 -270
12.FO.010 Wardrobes 21 21 0% 02-Jul-18 22-Jul-18 -263

- Roof and Top Roof 126 126 0% 20-Feb-18 25-Jun-18 -222

RO.EL.E90 Work Completion (Electric) 0 0 0% 19-Jun-18 -256


RO.FF.900 Work Completion 0 0 0% 10-Jun-18 -257
RO.DR.R10 Rain Water Outlet 0 0 0% 17-Apr-18 -254
RO.DR.R90 Work Completion 0 0 0% 25-Jun-18 -222
RO.AC.900 Work Completion 0 0 0% 03-Jun-18 -266
RO.WS.900 Work Completion 0 0 0% 12-Jun-18 -251
RO.PG.900 Work Completion 0 0 0% 10-Jun-18 -264
RO.FC.C10 MEP CLEARANCE- Corridors and Lift Lobby 0 0 0% 17-May-18 -251
RO.EL.E80 Isolators & Connections (Roof Deck) 2 2 0% 18-Jun-18 19-Jun-18 -256
RO.FF.150 Fire Extinguisher 2 2 0% 22-May-18 27-May-18 -268
RO.DR.R20 Outlet Body 2 2 0% 17-Apr-18 19-Apr-18 -254
RO.AC.100 Grills and Diffusers 2 2 0% 10-Jun-18 12-Jun-18 -251
RO.AC.040 Pipes Testing 2 2 0% 18-Apr-18 20-Apr-18 -227
RO.WS.210 Pipes Testing 2 2 0% 11-Jun-18 12-Jun-18 -255
RO.a.CO.010 R.C.C Columns\Walls 2 2 0% 20-Feb-18 21-Feb-18 -269
RO.FL.D10 Screed Flooring 2 2 0% 08-May-18 09-May-18 -266

Actual Level of Effort Remaining Work Page 135 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Wall Tiles- Corridors\Lift Lob

R.C.C Slab (Roof Floor Slab)\Electric Conduits


FCU & A.C Ducts
Flooring Tiles- Service\D
Suspension System- W
Suspension System
Primer & Stucco

ONU Termination
Block Work\Concrete Upstand,Lintels

Plaster Work

Work Completion,
Rain Water Outlet, 17-Apr-18

Work Completion,

Work Completion,
MEP CLEARANCE- Corrid

Fire Extinguisher
Outlet Body

Pipes Testing

R.C.C Columns\Walls
Screed Flooring

Actual Level of Effort Remaining Work Page 136 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
RO.EL.E60 All Type Of Switches, Sockets, Light Fittings\Emergency Light
3 and Accessoeies
3 0% 12-Jun-18 15-Jun-18 -251
RO.DR.R50 Domical Grate 3 3 0% 23-Jun-18 25-Jun-18 -222
RO.FL.D50 Epoxy Coating 3 3 0% 22-May-18 28-May-18 -269
RO.AL.100 Steel Doors 3 3 0% 14-May-18 17-May-18 -254
RO.AL.200 Cat Ladder 3 3 0% 18-Jun-18 20-Jun-18 -246
RO.PN.C10 Painting Work to False Ceiling (Lift Lobby) 3 3 0% 28-May-18 30-May-18 -241
RO.EL.010 Conduits, Boxes & enclosure 4 4 0% 22-Mar-18 26-Mar-18 -254
RO.DR.R30 Foam Concrete\Cast Concrete around Outlet Body 4 4 0% 19-Apr-18 23-Apr-18 -254
RO.AC.030 Gas Pipes net work 4 4 0% 14-Apr-18 18-Apr-18 -227
RO.AC.020 Mouse Connection & Fire Damper 4 4 0% 14-Apr-18 18-Apr-18 -227
RO.AC.200 FAHU Units 4 4 0% 13-May-18 16-May-18 -263
RO.AC.230 Extract Fans 4 4 0% 13-May-18 16-May-18 -249
RO.AC.220 Pressurazation Unit 4 4 0% 13-May-18 16-May-18 -249
RO.a.CO.100 Dismantling Shutters 4 4 0% 12-Mar-18 15-Mar-18 -267
RO.PG.100 Explosion Proof Gas Leak Detector 4 4 0% 02-Jun-18 05-Jun-18 -264
RO.FC.C20 Suspension System- Corridors and Lift Lobby 4 4 0% 17-May-18 21-May-18 -251
RO.FC.C30 Final Stage- Corridors and Lift Lobby 4 4 0% 21-May-18 28-May-18 -251
RO.FL.C30 Floor Tiles- Corridor & Lift Lobby 4 4 0% 09-Apr-18 13-Apr-18 -250
RO.CL.C20 Wall Tiles- Corridors\Lift Lobby 4 4 0% 05-Apr-18 09-Apr-18 -250
RO.SN.010 Work Completion\Snagging Work 5 5 0% 20-Jun-18 25-Jun-18 -257
RO.DR.R40 Mastic Joint 5 5 0% 18-Jun-18 22-Jun-18 -222
RO.AC.010 FCU & A.C Ducts 5 5 0% 09-Apr-18 14-Apr-18 -227
RO.AL.600 Powder Coat Aluminium Fence 5 5 0% 10-Jun-18 14-Jun-18 -251
RO.PG.150 Pressure Regulating & Dist. Panel 5 5 0% 05-Jun-18 10-Jun-18 -264
RO.PN.020 Painting Work 5 5 0% 17-May-18 22-May-18 -254
RO.PN.010 Primer & Stucco 5 5 0% 09-May-18 14-May-18 -254
RO.PN.R40 Painting Work- Roof Deck 5 5 0% 12-Jun-18 17-Jun-18 -267
RO.CO.130 Roof Foundation 6 6 0% 01-May-18 07-May-18 -266
RO.EL.020 Pulling All Types Of Wires 6 6 0% 14-May-18 20-May-18 -237
RO.FL.R30 Roof Tiles- Roof Deck 6 6 0% 07-May-18 13-May-18 -266
RO.AC.210 Outdoor Units 7 7 0% 13-May-18 19-May-18 -266
RO.WS.200 Water Tanks\Booster Pump & Piping Net Work 7 7 0% 04-Jun-18 10-Jun-18 -255
RO.a.CO.050 R.C.C Slab 7 7 0% 21-Feb-18 28-Feb-18 -269
RO.BL.010 Block Work 8 8 0% 15-Mar-18 22-Mar-18 -267

Actual Level of Effort Remaining Work Page 137 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Epoxy Coating
Steel Doors

Painting Work to False


Conduits, Boxes & enclosure
Foam Concrete\Cast Concrete a
Gas Pipes net work
Mouse Connection & Fire Damper
FAHU Units
Extract Fans
Pressurazation Unit
Dismantling Shutters
Explosion Proof Gas
Suspension System- Cor
Final Stage- Corridors a
Floor Tiles- Corridor & Lift Lobby
Wall Tiles- Corridors\Lift Lobby

FCU & A.C Ducts

Pressure Regulating
Painting Work
Primer & Stucco

Roof Foundation
Pulling All Types Of Wires
Roof Tiles- Roof Deck
Outdoor Units
Water Tanks\Booste
R.C.C Slab
Block Work

Actual Level of Effort Remaining Work Page 138 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
RO.EL.E50 DB's\SMDB Terminations 9 9 0% 22-May-18 31-May-18 -239
RO.WP.R20 Waterproofing Include Protections- Roof Deck 9 9 0% 23-Apr-18 01-May-18 -266
RO.PL.D10 Plaster Work 10 10 0% 26-Mar-18 05-Apr-18 -254
RO.PG.010 LPG Tank, Filling\Supply Pipes Net Work 12 12 0% 19-May-18 02-Jun-18 -264
RO.PL.R10 Plaster- Roof Deck 12 12 0% 05-Apr-18 17-Apr-18 -266
RO.FF.300 Preaction System 14 14 0% 28-May-18 10-Jun-18 -269
RO.AC.300 Piping Net Work\Testing 14 14 0% 19-May-18 03-Jun-18 -266
RO.CO.120 R.C.C Parapet 14 14 0% 28-Feb-18 13-Mar-18 -269

- Floors Collection and External Finishes 661 661 0% 29-Nov-16 25-Aug-18 -259

FC.EL.E90 Work Completion (Electric) 0 0 0% 16-Jul-18 -259


FC.EL.T90 Work Completion (Telephone) 0 0 0% 04-Jul-18 -258
FC.FF.900 Work Completion 0 0 0% 05-Jul-18 -269
FC.WS.900 Work Completion 0 0 0% 29-Jul-18 -266
FC.DR.900 Work Completion 0 0 0% 03-Jun-18 -255
FC.EL.L90 Work Completion 0 0 0% 18-Jul-18 -258
FC.ME.G40 Supply & Install Trolley 3 3 0% 17-Jul-18 19-Jul-18 -255
FC.FO.P10 Remote Control Gate Barrier 3 3 0% 02-Aug-18 06-Aug-18 -269
FC.DR.400 Riser Pipes (7th & 8th Floor) 4 4 0% 07-Feb-18 12-Feb-18 -270
FC.DR.100 Riser Pipes (1st & 2nd Floor) 4 4 0% 29-Nov-17 04-Dec-17 -271
FC.DR.500 Riser Pipes (9th & 10th Floor) 4 4 0% 06-Mar-18 10-Mar-18 -271
FC.DR.600 Riser Pipes (11th & 12th Floor) 4 4 0% 20-Mar-18 24-Mar-18 -270
FC.DR.200 Riser Pipes (3rd & 4th Floor) 4 4 0% 17-Dec-17 20-Dec-17 -260
FC.DR.300 Riser Pipes (5th & 6th Floor) 4 4 0% 13-Jan-18 16-Jan-18 -260
FC.SN.010 Work Completion\Snagging Work 5 5 0% 02-Aug-18 07-Aug-18 -271
FC.02.AL.T10 Aluminium Windows 6 6 0% 21-Jun-18 27-Jun-18 -267
FC.02.PN.T20 Painting Work 6 6 0% 27-Jun-18 03-Jul-18 -267
FC.02.WD.T10 Wooden Doors 6 6 0% 10-Jul-18 15-Jul-18 -267
FC.01.PN.T20 Painting Work 6 6 0% 17-May-18 26-May-18 -267
FC.01.AL.T10 Aluminium Windows 6 6 0% 13-May-18 17-May-18 -267
FC.02.FL.T10 Internal Steps\Landing 7 7 0% 07-Jun-18 14-Jun-18 -267
FC.02.AL.T20 Steps Handrails 7 7 0% 03-Jul-18 10-Jul-18 -267
FC.01.AL.T20 Steps Handrails 7 7 0% 26-May-18 02-Jun-18 -233
FC.V1.FL.B10 Flooring Tiles 7 7 0% 29-Apr-18 06-May-18 -262

Actual Level of Effort Remaining Work Page 139 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
DB's\SMDB Terminatio
Waterproofing Include Protectio
Plaster Work
LPG Tank, Filling\Supp
Plaster- Roof Deck
Preaction System
Piping Net Work\Testi
R.C.C Parapet

Work Completion,

Riser Pipes (7th & 8th Floor)


Riser Pipes (1st & 2nd Floor)
Riser Pipes (9th & 10th Floor)
Riser Pipes (11th & 12th Floor)
Riser Pipes (3rd & 4th Floor)
Riser Pipes (5th & 6th Floor)

Painting Work
Aluminium Windows

Steps Handrails
Flooring Tiles

Actual Level of Effort Remaining Work Page 140 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
FC.V1.WP.B10 Waterproofing 7 7 0% 23-Apr-18 29-Apr-18 -262
FC.V3.WP.B10 Waterproofing 7 7 0% 23-Apr-18 29-Apr-18 -269
FC.V3.FL.B10 Flooring Tiles 7 7 0% 29-Apr-18 06-May-18 -269
FC.LF.060 Springs & Lift Pit Work 7 7 0% 26-Jun-18 03-Jul-18 -266
FC.DR.850 Valve Chamber\Gully Trap\Manholes (FIC) 7 7 0% 28-May-18 03-Jun-18 -255
FC.AC.100 Riser Ducts\Pipes (1st & 2nd Floor) 7 7 0% 04-Dec-17 11-Dec-17 -271
FC.AC.300 Riser Ducts\Pipes (9th & 10th Floor) 7 7 0% 10-Mar-18 17-Mar-18 -271
FC.AC.200 Riser Ducts\Pipes (7th & 8th Floor) 7 7 0% 12-Feb-18 18-Feb-18 -270
FC.FL.G10 Floor Tiles 7 7 0% 25-Apr-18 02-May-18 -267
FC.ME.G30 Install Compactor 7 7 0% 10-Jul-18 17-Jul-18 -255
FC.FO.010 Signage\Building Signage\Trafic Road Sign 7 7 0% 10-Jul-18 17-Jul-18 -267
FC.FL.X10 Curbstone\Interlock Paving 7 7 0% 28-Jul-18 02-Aug-18 -271
FC.AC.400 Riser Ducts\Pipes (11th & 12th Floor) 7 7 0% 24-Mar-18 01-Apr-18 -270
FC.AC.410 Riser Ducts\Pipes (3rd & 4th Floor) 7 7 0% 20-Dec-17 26-Dec-17 -260
FC.AC.420 Riser Ducts\Pipes (5th & 6th Floor) 7 7 0% 16-Jan-18 23-Jan-18 -260
FC.02.PN.T10 Primer & Stucco 8 8 0% 14-Jun-18 21-Jun-18 -267
FC.01.PN.T10 Primer & Stucco 8 8 0% 05-May-18 13-May-18 -267
FC.EL.L30 Earth Bus Bars 8 8 0% 16-Jul-18 23-Jul-18 -259
FC.EL.L40 Cooper Tape 8 8 0% 03-Jul-18 10-Jul-18 -258
FC.EL.L50 Air Terminal Rod 8 8 0% 10-Jul-18 18-Jul-18 -258
FC.EL.V20 Desh and Mixer 10 10 0% 19-Jun-18 28-Jun-18 -268
FC.CL.G10 Wall Tiles 10 10 0% 16-Apr-18 25-Apr-18 -267
FC.01.FL.T10 Internal Steps\Landing 12 12 0% 24-Apr-18 05-May-18 -267
FC.02.PL.T10 Internal Plaster 14 14 0% 26-May-18 07-Jun-18 -267
FC.01.PL.T10 Internal Plaster 14 14 0% 10-Apr-18 24-Apr-18 -267
FC.V3.AL.B10 Balcony Handrail 14 14 0% 08-Jul-18 21-Jul-18 -271
FC.V3.PN.010 External Paint 14 14 0% 25-Jun-18 08-Jul-18 -271
FC.LF.040 Lift Machine Equipment 14 14 0% 31-May-18 13-Jun-18 -266
FC.LF.050 Lift Cabin assembly\Marble Flooring 14 14 0% 13-Jun-18 26-Jun-18 -266
FC.BL.G10 Block Work\Concrete Upstand,Lintels 14 14 0% 20-Mar-18 03-Apr-18 -267
FC.WP.G10 Waterproofing Include Protection 14 14 0% 03-Apr-18 16-Apr-18 -267
FC.V1.AL.030 Aluminium Powder Coated Element 14 14 0% 13-May-18 28-May-18 -269
FC.V3.AL.030 Aluminium Powder Coated Element 14 14 0% 28-May-18 10-Jun-18 -269
FC.V3.CO.010 R.C.C Decorative Columns 14 14 0% 13-Mar-18 26-Mar-18 -269

Actual Level of Effort Remaining Work Page 141 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Waterproofing
Waterproofing
Flooring Tiles

Valve Chamber\Gully
Riser Ducts\Pipes (1st & 2nd Floor)
Riser Ducts\Pipes (9th & 10th Floor)
Riser Ducts\Pipes (7th & 8th Floor)
Floor Tiles

Riser Ducts\Pipes (11th & 12th Floor)


Riser Ducts\Pipes (3rd & 4th Floor)
Riser Ducts\Pipes (5th & 6th Floor)

Primer & Stucco

Wall Tiles
Internal Steps\Landing
Internal Plaster
Internal Plaster

Block Work\Concrete Upstand,Lintels


Waterproofing Include Protection
Aluminium Powder Coa
Aluminium Powder C
R.C.C Decorative Columns

Actual Level of Effort Remaining Work Page 142 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
FC.V3.GR.040 GRC Decorative Corbles\Brakets 14 14 0% 12-Jun-18 25-Jun-18 -271
FC.V3.GR.100 GRC Decorative Cladding to R.C.C Columns 14 14 0% 10-Jun-18 23-Jun-18 -269
FC.V3.GR.030 GRC Decorative Frames 14 14 0% 05-Jun-18 18-Jun-18 -271
FC.V1.AL.B10 Balcony Handrail 14 14 0% 08-Jul-18 21-Jul-18 -271
FC.ME.G20 Vent Tube\Centerifugal Ext. Fane\Intake Doors 16 16 0% 25-Jun-18 10-Jul-18 -255
FC.V2.PN.010 External Paint 21 21 0% 08-Jul-18 28-Jul-18 -271
FC.V4.PN.010 External Paint 21 21 0% 08-Jul-18 28-Jul-18 -271
FC.V1.PN.010 External Paint 21 21 0% 18-Jun-18 08-Jul-18 -271
FC.LF.020 Lift Doors Frames\Marble Jamb 21 21 0% 09-May-18 31-May-18 -266
FC.EL.C10 Data Cables 21 21 0% 05-May-18 27-May-18 -253
FC.EL.V30 Pulling Coaxial Cables, Spliter Dressing(SMATV) 21 21 0% 28-Jun-18 18-Jul-18 -268
FC.ME.G10 Vertical Shaft 21 21 0% 28-Feb-18 20-Mar-18 -267
FC.PN.010 Final Coat Painting Work (Internaly) 21 21 0% 02-Aug-18 25-Aug-18 -259
FC.AW.PL.100 External Plaster 21 21 0% 19-May-18 10-Jun-18 -264
FC.AW.PN.100 External Paint 21 21 0% 10-Jun-18 30-Jun-18 -234
FC.V1.AL.010 Aluminium Screen 21 21 0% 23-Apr-18 13-May-18 -269
FC.V1.AL.020 Aluminium Pergola 21 21 0% 23-Apr-18 13-May-18 -269
FC.V1.GR.020 GRC Decorative Cornice 21 21 0% 10-Jun-18 30-Jun-18 -269
FC.V1.GR.040 GRC Decorative Corbles\Brakets 21 21 0% 12-Jun-18 01-Jul-18 -271
FC.V1.CO.010 R.C.C Decorative Columns 21 21 0% 13-Mar-18 03-Apr-18 -269
FC.V1.GR.100 GRC Decorative Cladding to R.C.C Columns 21 21 0% 28-May-18 17-Jun-18 -269
FC.V1.GR.030 GRC Decorative Frames 21 21 0% 05-Jun-18 25-Jun-18 -271
FC.V2.AL.010 Aluminium Channels 21 21 0% 20-Mar-18 10-Apr-18 -255
FC.V2.AL.020 Aluminium Panels 21 21 0% 19-May-18 10-Jun-18 -241
FC.V2.AL.030 Aluminium Powder Coated Element 21 21 0% 28-May-18 17-Jun-18 -248
FC.V3.AL.020 Aluminium Pergola 21 21 0% 06-May-18 28-May-18 -269
FC.V4.AL.010 Aluminium Channels 21 21 0% 10-Apr-18 29-Apr-18 -255
FC.V4.AL.030 Aluminium Powder Coated Element 21 21 0% 10-Jun-18 30-Jun-18 -262
FC.V1.PL.10 External Cladding 21 21 0% 23-Apr-18 13-May-18 -262
FC.EL.L20 ECC Cables 22 22 0% 12-Jun-18 03-Jul-18 -258
FC.V2.PL.010 External Plaster 28 28 0% 23-Apr-18 19-May-18 -264
FC.V4.PL.010 External Plaster 28 28 0% 29-Apr-18 28-May-18 -255
FC.V1.PL.010 External Plaster 28 28 0% 26-Mar-18 23-Apr-18 -269
FC.V3.PL.010 External Plaster 28 28 0% 26-Mar-18 23-Apr-18 -269

Actual Level of Effort Remaining Work Page 143 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Lift Doors Frames\Mar


Data Cables

Vertical Shaft

External Plaster

Aluminium Screen
Aluminium Pergola

R.C.C Decorative Columns

Aluminium Channels
Aluminium Panels

Aluminium Pergola
Aluminium Channels

External Cladding

External Plaster
External Plaster
External Plaster
External Plaster

Actual Level of Effort Remaining Work Page 144 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
FC.LF.010 Fixing Lift Realing 28 28 0% 20-Mar-18 16-Apr-18 -241
FC.EL.E10 Riser Cable\Tray (Electric) 28 28 0% 19-Jun-18 16-Jul-18 -259
FC.EL.T20 Riser Cables\Telephone Cabinet 28 28 0% 07-Jun-18 04-Jul-18 -258
FC.FF.010 Riser Pipes 28 28 0% 10-Jun-18 05-Jul-18 -269
FC.WS.010 Riser Pipes 28 28 0% 02-Jul-18 29-Jul-18 -266
FC.V1.GR.010 GRC Decorative Panels 28 28 0% 13-May-18 10-Jun-18 -262
FC.V1.AL.100 Tension Fabric 28 28 0% 13-May-18 10-Jun-18 -269
FC.EL.L10 UPVC Pipes (Floating With R.C.C Columns) 470 470 0% 29-Nov-16 21-Feb-18 -269

- Boundary Wall 158 158 0% 19-Feb-18 19-Jul-18 -262

BW.EL.020 Light Fitting (Boundary Wall) 4 4 0% 16-Jul-18 19-Jul-18 -262


BW.ER.020 Backfilling 7 7 0% 26-Apr-18 03-May-18 -262
BW.CO.050 Neck Columns\Solid Block 14 14 0% 24-Mar-18 07-Apr-18 -262
BW.CO.020 P.C.C 14 14 0% 04-Mar-18 17-Mar-18 -262
BW.WP.010 Bitumen Paint 14 14 0% 14-Apr-18 26-Apr-18 -262
BW.ER.010 Excavation Work 14 14 0% 19-Feb-18 04-Mar-18 -262
BW.CO.080 R.C.C Columns 14 14 0% 16-May-18 31-May-18 -262
BW.CO.090 R.C.C Coping Beams 14 14 0% 22-May-18 07-Jun-18 -262
BW.PN.020 Painting Work 14 14 0% 03-Jul-18 16-Jul-18 -262
BW.CO.060 Tie-Beams 21 21 0% 01-Apr-18 19-Apr-18 -262
BW.CO.030 R.C.C Footing 21 21 0% 11-Mar-18 01-Apr-18 -262
BW.PL.010 Plaster Work 21 21 0% 31-May-18 20-Jun-18 -262
BW.BL.010 Block Work 21 21 0% 03-May-18 22-May-18 -262
BW.FO.010 GRC Work 21 21 0% 13-Jun-18 03-Jul-18 -262

- Testing & Commissoning 45 45 0% 03-Jul-18 14-Aug-18 -270

HO.TC.A10 A.C Work Completion 0 0 0% 19-Jul-18 -270


HO.TC.W10 Water Supply Work Completion 0 0 0% 29-Jul-18 -266
HO.TC.D10 Drainage Site Work Completion 0 0 0% 16-Jul-18 -254
HO.TC.E10 Electric Work Completion 0 0 0% 19-Jul-18 -262
HO.TC.V10 SMATV Work Completion 0 0 0% 18-Jul-18 -268
HO.TC.L50 Low Current Work Completion 0 0 0% 25-Jul-18 -266
HO.TC.F30 Fire Alarm Work Completion 0 0 0% 16-Jul-18 -266
HO.TC.T10 Telephone Work Completion 0 0 0% 04-Jul-18 -258
HO.TC.F10 Fire Fighting Work Completion 0 0 0% 08-Jul-18 -271

Actual Level of Effort Remaining Work Page 145 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Fixing Lift Realing

GRC Decorative Pa
Tension Fabric
UPVC Pipes (Floating With R.C.C Columns)

Backfilling
Neck Columns\Solid Block
P.C.C
Bitumen Paint
Excavation Work
R.C.C Columns
R.C.C Coping Beam

Tie-Beams
R.C.C Footing

Block Work

Actual Level of Effort Remaining Work Page 146 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
HO.TC.L10 Elevator Work Completion 0 0 0% 03-Jul-18 -266
HO.TC.G10 LPG Work Completion 0 0 0% 12-Jul-18 -269
HO.TC.G20 Testing & Commissoning For LPG System 7 7 0% 12-Jul-18 19-Jul-18 -269
HO.TC.W20 Testing & Commissoning For Water Supply Work 14 14 0% 29-Jul-18 11-Aug-18 -266
HO.TC.D20 Testing & Commissoning For Drainage Work 14 14 0% 17-Jul-18 31-Jul-18 -255
HO.TC.E20 Testing & Commissoning For Electric Work 14 14 0% 19-Jul-18 02-Aug-18 -257
HO.TC.V20 Testing & Commissoning For SMATV Work 14 14 0% 18-Jul-18 31-Jul-18 -268
HO.TC.L60 Testing & Commissoning For Security System 14 14 0% 25-Jul-18 07-Aug-18 -266
HO.TC.F40 Testing & Commissoning For Fire Alarm System 14 14 0% 16-Jul-18 29-Jul-18 -253
HO.TC.T20 Testing & Commissoning For Telephone System 14 14 0% 04-Jul-18 17-Jul-18 -258
HO.TC.F20 Testing & Commissoning For Fire Fighting Work 14 14 0% 08-Jul-18 21-Jul-18 -271
HO.TC.L20 Testing & Commissoning For Elevator 14 14 0% 03-Jul-18 16-Jul-18 -266
HO.TC.A20 Testing & Commissoning For A.C Work (Include Air Balancing)
28 28 0% 19-Jul-18 14-Aug-18 -270

- Documents Deliverable 135 135 0% 19-Apr-18 29-Aug-18 -263

HO.AB.M20 O&M Manuals 28 28 0% 03-Jun-18 28-Jun-18 -261


HO.AB.M10 As Built Drawing (MEP) 30 30 0% 29-Jul-18 29-Aug-18 -263
HO.AB.C10 As Built Drawing (Structure\Architectural) 45 45 0% 19-Apr-18 03-Jun-18 -261

- Final Snagging 31 31 0% 02-Aug-18 04-Sep-18 -270

HO.SN.C10 Final Inspection For Consultant\Snagging Report 5 5 0% 02-Aug-18 07-Aug-18 -271


HO.SN.M10 Final Inspection For Consultant\Snagging Report 5 5 0% 14-Aug-18 22-Aug-18 -270
HO.SN.M20 Snagging Work 14 14 0% 22-Aug-18 04-Sep-18 -270
HO.SN.C20 Snagging Work 21 21 0% 07-Aug-18 30-Aug-18 -265

- Authority Final Inspection 94 94 0% 04-Jun-18 05-Sep-18 -262

HO.AU.D40 Drainage Connection 0 0 0% 17-Jul-18 -170


HO.AU.C30 Civil Defense Final approval 0 0 0% 07-Aug-18 -181
HO.AU.C85 Civil Defense Final approval 0 0 0% 30-Aug-18 -180
HO.AU.C45 Civil Defense Initial Inspection\Comments 0 0 0% 24-Jul-18 -180
HO.AU.C60 Civil Defense Final approval 0 0 0% 06-Aug-18 -180
HO.AU.M20 DM Initial Inspection\Comments 1 1 0% 13-Aug-18 13-Aug-18 -181
HO.AU.C15 Civil Defense Initial Inspection\Comments 2 2 0% 25-Jul-18 26-Jul-18 -181
HO.AU.C75 Civil Defense Initial Inspection\Comments 2 2 0% 12-Aug-18 14-Aug-18 -181
HO.AU.EL.E20 DEWA LV Inspection, Comments 3 3 0% 26-Jul-18 30-Jul-18 -175
HO.AU.DP.L10 Application For Inspection 3 3 0% 07-Aug-18 11-Aug-18 -266

Actual Level of Effort Remaining Work Page 147 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

As Built Drawing (Stru

Actual Level of Effort Remaining Work Page 148 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 3, 2016
Qtr 2, 2016
Duration Complete Mar Apr May Jun Jul
HO.AU.M40 DM Completion Certificate 3 3 0% 28-Aug-18 30-Aug-18 -181
HO.AU.C10 Application For Estimation 3 3 0% 22-Jul-18 24-Jul-18 -181
HO.AU.C40 Application For Estimation 3 3 0% 19-Jul-18 23-Jul-18 -180
HO.AU.C70 Application For Inspection 3 3 0% 07-Aug-18 12-Aug-18 -181
HO.AU.M10 Application For Inspection 3 3 0% 08-Aug-18 12-Aug-18 -181
HO.AU.E90 Permanent Electric Connection 4 4 0% 02-Sep-18 05-Sep-18 -181
HO.AU.W90 Permanent Water Supply Connection 4 4 0% 02-Sep-18 05-Sep-18 -181
HO.AU.W20 DEWA Initial Inspection, Comments 4 4 0% 02-Aug-18 07-Aug-18 -177
HO.AU.C90 DCD 24\7 Panel 4 4 0% 30-Aug-18 05-Sep-18 -180
HO.AU.EL.E10 Application For Inspection 4 4 0% 22-Jul-18 25-Jul-18 -175
HO.AU.W10 Application For Inspection 4 4 0% 29-Jul-18 01-Aug-18 -177
HO.AU.T10 Application For Estimation 4 4 0% 17-Jul-18 23-Jul-18 -172
HO.AU.D10 Application For Inspection Of FIC 5 5 0% 04-Jun-18 10-Jun-18 -170
HO.AU.D20 Drainage department Approval of FIC Manhole 7 7 0% 11-Jun-18 19-Jun-18 -170
HO.AU.DP.L20 Dubai Police Inspection\Approval for Security System 7 7 0% 11-Aug-18 16-Aug-18 -266
HO.AU.M30 Rectify DM Comments\Final Inspection 7 7 0% 14-Aug-18 27-Aug-18 -181
HO.AU.EL.E40 Main Cable Delevery and Install (by DEWA) 7 7 0% 13-Aug-18 22-Aug-18 -263
HO.AU.EL.E30 Incorporating Comments\Re-Inspection & Approval 14 14 0% 30-Jul-18 13-Aug-18 -263
HO.AU.W80 Rectify Comments\Re-Inspection & Approval 14 14 0% 07-Aug-18 25-Aug-18 -265
HO.AU.C20 Rectify CD Comments 14 14 0% 25-Jul-18 07-Aug-18 -271
HO.AU.C80 Rectify CD Comments 14 14 0% 14-Aug-18 30-Aug-18 -271
HO.AU.C50 Rectify CD Comments 14 14 0% 24-Jul-18 06-Aug-18 -270
HO.AU.T20 Etisalat Checking, Supply & Install Devices\Cables 21 21 0% 23-Jul-18 26-Aug-18 -172
HO.AU.D30 Period Required for Drainage Connection 28 28 0% 20-Jun-18 17-Jul-18 -244

Actual Level of Effort Remaining Work Page 149 of 150 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
(B+G+12+R) RESIDENTIAL BUILDING- AL NAHDA SECOND base line 018 12-May-18 13:16
Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Application For Insp

Actual Level of Effort Remaining Work Page 150 of 150 TASK filter: All Activities