Hide Row

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 179

Two-Storey Two (2) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED TWO STOREY TW0 (2) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


Services/Demobilization / Standard Billboard
lot 1.00 10,054.53 6,703.02 10,054.53 6,703.02
Safety and Health lot 1.00 10,054.53 0.00 10,054.53 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 85.50 0.00 20.00 0.00 1,710.00
1.02 Structural Excavation cu.m 59.90 0.00 200.00 0.00 11,980.00
1.03 Backfilling and Compaction cu.m 49.54 0.00 45.00 0.00 2,229.31
1.06 Select Fill cu.m 19.24 150.00 45.00 2,885.63 865.69
1.04 Gravel Bedding G-1 cu.m 13.07 980.00 180.00 12,808.60 2,352.60
1.05 Soil Poisoning sq.m 94.05 15.00 4.50 1,410.75 423.23
Sub-total
2.00 Concreting Works
Column Footing cu.m 0.00
2.01 Portland Cement bag 0.00 218.00 65.40 0.00 0.00
2.05 Crushed Gravel 1" cu.m 0.00 980.00 294.00 0.00 0.00
2.03 Washed Sand cu.m 0.00 900.00 270.00 0.00 0.00
Tie beams cu.m 6.90
2.01 Portland Cement bag 63.00 218.00 65.40 13,734.00 4,120.20
2.02 Crushed Gravel 3/4" cu.m 7.00 980.00 294.00 6,860.00 2,058.00
2.03 Washed Sand cu.m 3.50 900.00 270.00 3,150.00 945.00
Wall Footing cu.m 1.40
2.01 Portland Cement bag 13.00 218.00 65.40 2,834.00 850.20
2.05 Crushed Gravel 1" cu.m 1.50 980.00 294.00 1,470.00 441.00
2.03 Washed Sand cu.m 0.75 900.00 270.00 675.00 202.50
Columns cu.m 10.30
2.01 Portland Cement bag 93.00 218.00 65.40 20,274.00 6,082.20
2.02 Crushed Gravel 3/4" cu.m 10.50 980.00 294.00 10,290.00 3,087.00
2.03 Washed Sand cu.m 5.25 900.00 270.00 4,725.00 1,417.50
Second Floor Beams and Girders cu.m 6.86
2.01 Portland Cement bag 62.00 218.00 65.40 13,516.00 4,054.80
2.02 Crushed Gravel 3/4" cu.m 7.00 980.00 294.00 6,860.00 2,058.00
2.03 Washed Sand cu.m 3.50 900.00 270.00 3,150.00 945.00
Second Floor Slab cu.m 9.40
2.01 Portland Cement bag 85.00 218.00 65.40 18,530.00 5,559.00
2.02 Crushed Gravel 3/4" cu.m 9.50 980.00 294.00 9,310.00 2,793.00
2.03 Washed Sand cu.m 4.75 900.00 270.00 4,275.00 1,282.50
Roof Beams cu.m 4.86
2.01 Portland Cement bag 44.00 218.00 65.40 9,592.00 2,877.60
2.02 Crushed Gravel 3/4" cu.m 5.00 980.00 294.00 4,900.00 1,470.00
2.03 Washed Sand cu.m 2.50 900.00 270.00 2,250.00 675.00
Stairs cu.m 3.65
2.01 Portland Cement bag 33.00 218.00 65.40 7,194.00 2,158.20
2.02 Crushed Gravel 3/4" cu.m 3.75 980.00 294.00 3,675.00 1,102.50
2.03 Washed Sand cu.m 2.00 900.00 270.00 1,800.00 540.00
Slab on Grade cu.m 8.55
2.01 Portland Cement bag 77.00 218.00 65.40 16,786.00 5,035.80
2.05 Crushed Gravel 1" cu.m 8.75 980.00 294.00 8,575.00 2,572.50

2Sty2CL Schoolbuilding 1 of 179


Two-Storey Two (2) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
2.03 Washed Sand cu.m 4.50 900.00 270.00 4,050.00 1,215.00
Ramp on Fill cu.m 1.00
2.01 Portland Cement bag 9.00 218.00 65.40 1,962.00 588.60
2.05 Crushed Gravel 1" cu.m 1.00 980.00 294.00 980.00 294.00
2.03 Washed Sand cu.m 0.50 900.00 270.00 450.00 135.00
Media Agua cu.m 0.60
2.01 Portland Cement bag 6.00 218.00 65.40 1,308.00 392.40
2.02 Crushed Gravel 3/4" cu.m 0.75 980.00 294.00 735.00 220.50
2.03 Washed Sand cu.m 0.50 900.00 270.00 450.00 135.00
Sub-total
3.00 Rebar Works
Column Footing kg 639.64
Tie beams kg 986.47
Wall Footing kg 59.14
Columns kg 3,138.35
Second Floor Beams and Girders kg 1,533.48
Second Floor Slab kg 736.96
Roof Beams kg 589.60
Stairs kg 266.11
Slab on Grade kg 328.12
Ramp on Fill kg 42.09
Media Agua kg 110.88
3.01 Deformed Round Bars, Grade 40 kg 8,430.83 40.10 12.03 338,076.34 101,422.90
3.02 G.I. Tie Wire kg 169.00 60.00 18.00 10,140.00 3,042.00
Sub-total
4.00 Formworks
Tie beams sq.m 46.00
4.01 Coco Lumber bd.ft 506.00 16.00 4.80 8,096.00 2,428.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 12.00 580.00 174.00 6,960.00 2,088.00
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00
Columns sq.m 117.71
4.01 Coco Lumber bd.ft 2,001.00 16.00 4.80 32,016.00 9,604.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 31.00 580.00 174.00 17,980.00 5,394.00
4.04 CWN, Assorted kg 29.00 60.00 18.00 1,740.00 522.00
Beams and Girders sq.m 83.40
4.01 Coco Lumber bd.ft 1,418.00 16.00 4.80 22,688.00 6,806.40
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 22.00 580.00 174.00 12,760.00 3,828.00
4.04 CWN, Assorted kg 20.00 60.00 18.00 1,200.00 360.00
Suspended Slab sq.m 94.00
4.01 Coco Lumber bd.ft 1,598.00 16.00 4.80 25,568.00 7,670.40
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 25.00 580.00 174.00 14,500.00 4,350.00
4.04 CWN, Assorted kg 23.00 60.00 18.00 1,380.00 414.00
Roof Beams sq.m 59.70
4.01 Coco Lumber bd.ft 1,015.00 16.00 4.80 16,240.00 4,872.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 16.00 580.00 174.00 9,280.00 2,784.00
4.04 CWN, Assorted kg 15.00 60.00 18.00 900.00 270.00
Stairs sq.m 9.80
4.01 Coco Lumber bd.ft 167.00 16.00 4.80 2,672.00 801.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 3.00 580.00 174.00 1,740.00 522.00
4.04 CWN, Assorted kg 3.00 60.00 18.00 180.00 54.00
Media Agua sq.m 5.40
4.01 Coco Lumber bd.ft 92.00 16.00 4.80 1,472.00 441.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 2.00 580.00 174.00 1,160.00 348.00
4.04 CWN, Assorted kg 2.00 60.00 18.00 120.00 36.00
Sub-total
5.00 Masonry Works

2Sty2CL Schoolbuilding 2 of 179


Two-Storey Two (2) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Masonry Wall sq.m 212.71
5.05 CHB 6" thk pc 2,659.00 12.00 3.60 31,908.00 9,572.40
5.02 Portland Cement bag 107.00 218.00 65.40 23,326.00 6,997.80
5.03 Washed Sand cu.m 10.00 900.00 270.00 9,000.00 2,700.00
5.06 10mm x 6m RSB kg 282.00 40.10 12.03 11,308.20 3,392.46
5.07 G.I. Tie Wire kg 6.00 60.00 18.00 360.00 108.00
Plastering sq.m 425.42
5.02 Portland Cement bag 141.00 218.00 65.40 30,738.00 9,221.40
5.03 Washed Sand cu.m 15.00 900.00 270.00 13,500.00 4,050.00
Floor Topping sq.m 94.00
5.02 Portland Cement bag 63.00 218.00 65.40 13,734.00 4,120.20
5.03 Washed Sand cu.m 7.00 900.00 270.00 6,300.00 1,890.00
Sub-total
6.00 Doors and Windows

6.03 set 4.00 7,317.50 1,463.50 29,270.00 5,854.00


D-1, Panel Door 0.90m x 2.10m on 150mm Wooden
Jamb complete with Accessories (lever type door knob)

6.07 W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass set 4.00 8,444.00 1,688.80 33,776.00 6,755.20
Blades on JalouPlus Type Silver Colored Frame and
Fixed Clear Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

6.08 W - 2, ( 1.5 x 1.6 m) Jalousie Window with Clear Glass set 4.00 4,672.00 934.40 18,688.00 3,737.60
Blades on JalouPlus Type Silver Colored Frame and
Fixed Clear Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 542.88 32.00 9.60 17,372.16 5,211.65
7.14 L 50 x 50 x 6mm kg 643.68 32.00 9.60 20,597.76 6,179.33
7.09 LC 120 x 50 x 20 x 2.0mm kg 601.47 43.00 12.90 25,863.36 7,759.01
7.18 Plain Round Bar 10mmØ x 6m pc 4.00 107.00 32.10 428.00 128.40
7.19 Plain Round Bar 12mmØ x 6m pc 8.00 185.00 55.50 1,480.00 444.00
7.30 Turn Buckle 12 mmØ pc 8.00 60.00 18.00 480.00 144.00

7.34 Anchor Bolt with Nuts and Washer, 12mmØ x 50mm x pc 27.00 8.10 972.00 291.60
300mm 36.00

7.35 Anchor Bolt with Nuts and Washer, 10mmØ x 50mm x pc 12.00 3.60 432.00 129.60
200mm 36.00
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 0.75 8,635.00 2,590.50 6,476.25 1,942.88
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 1.50 5,390.00 1,617.00 8,085.00 2,425.50
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 7.00 1,069.00 320.70 7,483.00 2,244.90
7.45 G.I. Pipe 2"Ø Sch.40 pc 5.00 1,781.00 534.30 8,905.00 2,671.50
7.23 Square Bar 19mm□ x 6m pc 7.00 620.00 186.00 4,340.00 1,302.00
7.46 Welding Rod kg 36.00 67.00 20.10 2,412.00 723.60
13.12 Primer, Zinc Chromate gal 3.00 537.00 161.10 1,611.00 483.30
Sub-total
8.00 Roofing Works

8.16 Long-Span Roofing, Corrugated, Pre-Painted, 1220mm x


0.4mm thk m 151.20 380.00 76.00 57,456.00 11,491.20

8.22 Gutter, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm


thk pc 10.00 415.00 0.00 4,150.00 0.00

8.19 Flashing, Pre-Painted, Ordinary, 0.610m x 2.440m x


0.4mm thk pc 12.00 560.00 0.00 6,720.00 0.00

8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m x 2.440m x


0.4mm thk pc 5.00 560.00 0.00 2,800.00 0.00
8.35 Teckscrew 2-1/2" pc 1,209.60 1.80 0.00 2,177.28 0.00

2Sty2CL Schoolbuilding 3 of 179


Two-Storey Two (2) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
8.36 Roof Sealant L 1.00 299.75 0.00 299.75 0.00
8.37 Blind Rivets pc 270.00 1.35 0.00 364.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 85.50
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 374.00 38.00 11.40 14,212.00 4,263.60
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 29.00 350.00 105.00 10,150.00 3,045.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 7.00 50.00 15.00 350.00 105.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00
Exterior ceiling sq.m 33.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 145.00 38.00 11.40 5,510.00 1,653.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 12.00 360.00 108.00 4,320.00 1,296.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 3.00 50.00 15.00 150.00 45.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 4.00 245.00 73.50 980.00 294.00
9.16 Fascia Board, Wooden bd.ft 162.36 36.00 10.80 5,844.96 1,753.49
Blackboards sq.m 11.52
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 74.00 38.00 11.40 2,812.00 843.60
9.43 Lawanit, 1/4" thk pc 4.00 280.00 84.00 1,120.00 336.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 2.00 50.00 15.00 100.00 30.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 42.00 50.00 15.00 2,100.00 630.00
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00 52.50
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00 10.50
10.16 Junction Box, 4" x 4" G.I. pc 30.00 15.00 4.50 450.00 135.00
10.17 Utility Box, 2" x 4" G.I. pc 30.00 30.00 4.28 900.00 128.25
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 378.00 33.00 7.02 12,474.00 2,653.56
10.12 5.5 mm2 THW Wire, Stranded m 10.00 50.50 10.14 505.00 101.40
10.28 Duplex C.O. with Plate pc 6.00 263.80 21.00 1,582.80 126.00
10.23 Single Switch with Plate pc 2.00 97.68 13.46 195.36 26.93
10.24 2-Gang Switch with Plate pc 2.00 153.00 21.53 306.00 43.05
10.20 FL 2 x 40W Industrial Type set 8.00 840.00 126.00 6,720.00 1,008.00
10.21 FL 1 x 40W Industrial Type set 2.00 490.00 73.50 980.00 147.00
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41
10.43 Circuit Breaker, 100A 2P set 1.00 650.00 97.50 650.00 97.50
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 4.00 1,500.00 450.00 6,000.00 1,800.00
12.02 Concrete Pipe 150mmØ pc 30.00 200.00 60.00 6,000.00 1,800.00
12.08 uPVC Sanitary Pipe 3"Ø pc 12.00 420.00 126.00 5,040.00 1,512.00
12.12 uPVC Elbow 90o x 3"Ø pc 12.00 53.00 15.90 636.00 190.80
12.33 PVC Cement can 1.00 150.00 45.00 150.00 45.00
Sub-total

2Sty2CL Schoolbuilding 4 of 179


Two-Storey Two (2) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
13.00 Painting Works
Concrete surfaces sq.m 736.57
13.18 Neutralizer gal 10.00 132.00 39.60 1,320.00 396.00
13.01 Latex, Flat gal 37.00 424.00 127.20 15,688.00 4,706.40
13.14 Masonry Putty gal 37.00 319.00 95.70 11,803.00 3,540.90
13.02 Latex, Semi Gloss gal 37.00 492.50 147.75 18,222.50 5,466.75
13.20 Acri Color qrt 10.00 165.00 49.50 1,650.00 495.00
Wood surfaces sq.m 199.42
13.04 Enamel, Flatwall gal 10.00 483.00 144.90 4,830.00 1,449.00
13.15 Glazing Putty gal 10.00 492.00 147.60 4,920.00 1,476.00
13.05 Enamel, Semi Gloss gal 10.00 497.00 149.10 4,970.00 1,491.00
13.16 Paint Thinner gal 8.00 260.00 78.00 2,080.00 624.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HE
Project Engineer, PFSED Area Supervisor, PFSED Chief, PF

2Sty2CL Schoolbuilding 5 of 179


Two-Storey Two (2) Classroom

c of the Philippines
NT OF EDUCATION
SCHOOLS ENGINEERING DIVISION
Pasig City

GRAND TOTAL

16,757.55
10,054.53
26,812.08

1,710.00
11,980.00
2,229.31
3,751.31
15,161.20
1,833.98
36,665.79

0.00
0.00
0.00

17,854.20
8,918.00
4,095.00

3,684.20
1,911.00
877.50

26,356.20
13,377.00
6,142.50

17,570.80
8,918.00
4,095.00

24,089.00
12,103.00
5,557.50

12,469.60
6,370.00
2,925.00

9,352.20
4,777.50
2,340.00

21,821.80
11,147.50

2Sty2CL Schoolbuilding 6 of 179


Two-Storey Two (2) Classroom

GRAND TOTAL

5,265.00

2,550.60
1,274.00
585.00

1,700.40
955.50
585.00
239,668.00

439,499.25
13,182.00
452,681.25

10,524.80
9,048.00
624.00

41,620.80
23,374.00
2,262.00

29,494.40
16,588.00
1,560.00

33,238.40
18,850.00
1,794.00

21,112.00
12,064.00
1,170.00

3,473.60
2,262.00
234.00

1,913.60
1,508.00
156.00
232,871.60

2Sty2CL Schoolbuilding 7 of 179


Two-Storey Two (2) Classroom

GRAND TOTAL

41,480.40
30,323.80
11,700.00
14,700.66
468.00

39,959.40
17,550.00

17,854.20
8,190.00
182,226.46

35,124.00

40,531.20

22,425.60

98,080.80

22,583.81
26,777.09
33,622.37
556.40
1,924.00
624.00

1,263.60

561.60

8,419.13
10,510.50
9,727.90
11,576.50
5,642.00
3,135.60
2,094.30
139,018.80

68,947.20

4,150.00

6,720.00

2,800.00
2,177.28

2Sty2CL Schoolbuilding 8 of 179


Two-Storey Two (2) Classroom

GRAND TOTAL

299.75
364.50
85,458.73

18,475.60
13,195.00
182.00
455.00
182.00
3,510.00

7,163.00
5,616.00
91.00
195.00
91.00
2,340.00
1,274.00
7,598.45

3,655.60
1,456.00
91.00
130.00
91.00
65,791.65

2,730.00
227.50
80.50
585.00
1,028.25
172.50

15,127.56
606.40
1,708.80
222.29
349.05
7,728.00
1,127.00
1,383.16
747.50
1,079.85
86.25
34,989.61

7,800.00
7,800.00
6,552.00
826.80
195.00
23,173.80

2Sty2CL Schoolbuilding 9 of 179


Two-Storey Two (2) Classroom

GRAND TOTAL

1,716.00
20,394.40
15,343.90
23,689.25
2,145.00

6,279.00
6,396.00
6,461.00
2,704.00
85,128.55

1,702,567.11
323,487.75
243,126.58
2,269,181.45
22,691.81
PhP2,291,873.26
PhP2,292,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

2Sty2CL Schoolbuilding 10 of 179


Two-Storey Four (4) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED TWO STOREY FOUR (4) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard
Billboard
lot 1.00 19,327.16 14,412.44 19,327.16 14,412.44
Safety and Health lot 1.00 19,327.16 0.00 19,327.16 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 213.75 0.00 20.00 0.00 4,275.00
1.02 Structural Excavation cu.m 114.89 0.00 200.00 0.00 22,978.20
1.03 Backfilling and Compaction cu.m 206.68 0.00 45.00 0.00 9,300.59
1.06 Select Fill cu.m 176.34 150.00 45.00 26,451.56 7,935.47
1.04 Gravel Bedding G-1 cu.m 30.34 980.00 180.00 29,729.28 5,460.48
1.05 Soil Poisoning sq.m 235.13 15.00 4.50 3,526.88 1,058.06
Sub-total
2.00 Concreting Works
Column Footing cu.m 17.03
2.01 Portland Cement bag 154.00 218.00 65.40 33,572.00 10,071.60
2.05 Crushed Gravel 1" cu.m 17.25 980.00 150.00 16,905.00 2,587.50
2.03 Washed Sand cu.m 8.75 900.00 150.00 7,875.00 1,312.50
Tie beams cu.m 15.83
2.01 Portland Cement bag 143.00 218.00 65.40 31,174.00 9,352.20
2.02 Crushed Gravel 3/4" cu.m 16.00 980.00 294.00 15,680.00 4,704.00
2.03 Washed Sand cu.m 8.00 900.00 270.00 7,200.00 2,160.00
Wall Footing cu.m 1.40
2.01 Portland Cement bag 13.00 218.00 65.40 2,834.00 850.20
2.05 Crushed Gravel 1" cu.m 1.50 980.00 294.00 1,470.00 441.00
2.03 Washed Sand cu.m 0.75 900.00 270.00 675.00 202.50
Columns cu.m 18.38
2.01 Portland Cement bag 166.00 218.00 65.40 36,188.00 10,856.40
2.02 Crushed Gravel 3/4" cu.m 18.50 980.00 294.00 18,130.00 5,439.00
2.03 Washed Sand cu.m 9.25 900.00 270.00 8,325.00 2,497.50
Beams and Girders cu.m 14.58
2.01 Portland Cement bag 132.00 218.00 65.40 28,776.00 8,632.80
2.02 Crushed Gravel 3/4" cu.m 14.75 980.00 294.00 14,455.00 4,336.50
2.03 Washed Sand cu.m 7.50 900.00 270.00 6,750.00 2,025.00
Suspended Slab cu.m 19.07
2.01 Portland Cement bag 172.00 218.00 65.40 37,496.00 11,248.80
2.02 Crushed Gravel 3/4" cu.m 19.25 980.00 294.00 18,865.00 5,659.50
2.03 Washed Sand cu.m 9.75 900.00 270.00 8,775.00 2,632.50
Roof Beams cu.m 10.80
2.01 Portland Cement bag 98.00 218.00 65.40 21,364.00 6,409.20
2.02 Crushed Gravel 3/4" cu.m 11.00 980.00 294.00 10,780.00 3,234.00
2.03 Washed Sand cu.m 5.50 900.00 270.00 4,950.00 1,485.00
Stairs cu.m 4.86
2.01 Portland Cement bag 44.00 218.00 65.40 9,592.00 2,877.60
2.02 Crushed Gravel 3/4" cu.m 5.00 980.00 294.00 4,900.00 1,470.00
2.03 Washed Sand cu.m 2.50 900.00 270.00 2,250.00 675.00
Slab on Grade cu.m 21.38
2.01 Portland Cement bag 193.00 218.00 65.40 42,074.00 12,622.20

2Sty4CL Schoolbuilding 11 of 179


Two-Storey Four (4) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
2.05 Crushed Gravel 1" cu.m 21.50 980.00 294.00 21,070.00 6,321.00
2.03 Washed Sand cu.m 10.75 900.00 270.00 9,675.00 2,902.50
Ramp on Fill cu.m 1.00
2.01 Portland Cement bag 9.00 218.00 65.40 1,962.00 588.60
2.05 Crushed Gravel 1" cu.m 1.00 980.00 294.00 980.00 294.00
2.03 Washed Sand cu.m 0.50 900.00 270.00 450.00 135.00
Media Agua cu.m 1.50
2.01 Portland Cement bag 14.00 218.00 65.40 3,052.00 915.60
2.02 Crushed Gravel 3/4" cu.m 1.50 980.00 294.00 1,470.00 441.00
2.03 Washed Sand cu.m 0.75 900.00 270.00 675.00 202.50
Sub-total
3.00 Rebar Works
Column Footing kg 1,189.74
Tie beams kg 2,258.19
Wall Footing kg 59.14
Columns kg 5,737.22
Beams and Girders kg 3,236.75
Suspended Slab kg 1,495.11
Roof Beams kg 1,680.35
Stairs kg 276.64
Slab on Grade kg 820.30
Ramp on Fill kg 42.09
Media Agua kg 110.90
3.01 Deformed Round Bars, Grade 40 kg 16,906.43 40.10 12.03 677,947.71 203,384.31
3.02 G.I. Tie Wire kg 339.00 60.00 18.00 20,340.00 6,102.00
Sub-total
4.00 Formworks
Tie beams sq.m 105.50
4.01 Coco Lumber bd.ft 1,161.00 16.00 4.80 18,576.00 5,572.80
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 19.00 350.00 105.00 6,650.00 1,995.00
4.04 CWN, Assorted kg 17.00 60.00 18.00 1,020.00 306.00
Columns sq.m 212.07
4.01 Coco Lumber bd.ft 3,606.00 16.00 4.80 57,696.00 17,308.80
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 37.00 350.00 105.00 12,950.00 3,885.00
4.04 CWN, Assorted kg 51.00 60.00 18.00 3,060.00 918.00
Beams and Girders sq.m 168.00
4.01 Coco Lumber bd.ft 2,856.00 16.00 4.80 45,696.00 13,708.80
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 29.00 350.00 105.00 10,150.00 3,045.00
4.04 CWN, Assorted kg 40.00 60.00 18.00 2,400.00 720.00
Suspended Slab sq.m 190.69
4.01 Coco Lumber bd.ft 3,242.00 16.00 4.80 51,872.00 15,561.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 33.00 580.00 174.00 19,140.00 5,742.00
4.04 CWN, Assorted kg 46.00 60.00 18.00 2,760.00 828.00
Roof Beams sq.m 132.90
4.01 Coco Lumber bd.ft 2,260.00 16.00 4.80 36,160.00 10,848.00
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 23.00 350.00 105.00 8,050.00 2,415.00
4.04 CWN, Assorted kg 32.00 60.00 18.00 1,920.00 576.00
Stairs sq.m 14.30
4.01 Coco Lumber bd.ft 244.00 16.00 4.80 3,904.00 1,171.20
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 3.00 350.00 105.00 1,050.00 315.00
4.04 CWN, Assorted kg 4.00 60.00 18.00 240.00 72.00
Media Agua sq.m 13.50 `
4.01 Coco Lumber bd.ft 230.00 16.00 4.80 3,680.00 1,104.00
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 3.00 350.00 105.00 1,050.00 315.00
4.04 CWN, Assorted kg 4.00 60.00 18.00 240.00 72.00
Sub-total
5.00 Masonry Works

2Sty4CL Schoolbuilding 12 of 179


Two-Storey Four (4) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Masonry Wall sq.m 418.15
5.05 CHB 6" thk pc 5,227.00 12.00 3.60 62,724.00 18,817.20
5.02 Portland Cement bag 210.00 218.00 65.40 45,780.00 13,734.00
5.03 Washed Sand cu.m 18.00 900.00 270.00 16,200.00 4,860.00
5.06 10mm x 6m RSB kg 554.00 40.10 12.03 22,215.40 6,664.62
5.07 G.I. Tie Wire kg 12.00 60.00 18.00 720.00 216.00
Plastering sq.m 836.31
5.02 Portland Cement bag 276.00 218.00 65.40 60,168.00 18,050.40
5.03 Washed Sand cu.m 28.00 900.00 270.00 25,200.00 7,560.00
Floor Topping sq.m 190.69
5.02 Portland Cement bag 126.00 218.00 65.40 27,468.00 8,240.40
5.03 Washed Sand cu.m 13.00 900.00 270.00 11,700.00 3,510.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 8.00 7,317.50 1,463.50 58,540.00 11,708.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 1.00 4,167.50 833.50 4,167.50 833.50
(lever type door knob)

6.05 set 2.00 3,567.50 713.50 7,135.00 1,427.00


D-3 Flush Door 0.70m x 2.10m on 150mm
Wooden Jamb complete with Accessories
D-4 Cubicle Door 0.60m x 1.20m on
6.06 150mm Wooden Jamb complete with set 2.00 3,408.75 681.75 6,817.50 1,363.50
Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


6.07 Clear Glass Blades on JalouPlus Type set 9.00 8,444.00 1,688.80 75,996.00 15,199.20
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


6.08 Clear Glass Blades on JalouPlus Type set 8.00 4,672.00 934.40 37,376.00 7,475.20
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window with


6.09 Clear Glass Blades on JalouPlus Type set 1.00 4,248.00 849.60 4,248.00 849.60
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,085.76 32.00 9.60 34,744.32 10,423.30
7.14 L 50 x 50 x 6mm kg 1,287.36 32.00 9.60 41,195.52 12,358.66
7.09 LC 120 x 50 x 20 x 2.0mm kg 1,397.54 43.00 12.90 60,094.29 18,028.29
7.18 Plain Round Bar 10mmØ x 6m pc 10.00 107.00 32.10 1,070.00 321.00
7.19 Plain Round Bar 12mmØ x 6m pc 12.00 185.00 55.50 2,220.00 666.00
7.30 Turn Buckle 12 mmØ pc 12.00 60.00 18.00 720.00 216.00

7.34 Anchor Bolt with Nuts and Washer, 12mmØ pc 27.00 8.10 1,944.00 583.20
x 50mm x 300mm 72.00

7.35 Anchor Bolt with Nuts and Washer, 10mmØ pc 12.00 3.60 864.00 259.20
x 50mm x 200mm 72.00
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 1.25 8,635.00 2,590.50 10,793.75 3,238.13
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 2.50 5,390.00 1,617.00 13,475.00 4,042.50

2Sty4CL Schoolbuilding 13 of 179


Two-Storey Four (4) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 7.00 1,069.00 320.70 7,483.00 2,244.90
7.45 G.I. Pipe 2"Ø Sch.40 pc 10.00 1,781.00 534.30 17,810.00 5,343.00
7.23 Square Bar 19mm□ x 6m pc 7.00 620.00 186.00 4,340.00 1,302.00
7.46 Welding Rod kg 76.00 67.00 20.10 5,092.00 1,527.60
13.12 Primer, Zinc Chromate gal 6.00 537.00 161.10 3,222.00 966.60
Sub-total
8.00 Roofing Works

8.16 Long-Span Roofing, Corrugated, Pre-


Painted, 1220mm x 0.4mm thk m 340.20 380.00 76.00 129,276.00 25,855.20

8.22 Gutter, Pre-Painted, Ordinary, 0.610m x


2.440m x 0.4mm thk pc 22.00 415.00 0.00 9,130.00 0.00

8.19 Flashing, Pre-Painted, Ordinary, 0.610m x


2.440m x 0.4mm thk pc 12.00 560.00 0.00 6,720.00 0.00

8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m


x 2.440m x 0.4mm thk pc 11.00 560.00 0.00 6,160.00 0.00
8.35 Teckscrew 2-1/2" pc 2,721.60 1.80 0.00 4,898.88 0.00
8.36 Roof Sealant L 3.00 299.75 0.00 899.25 0.00
8.37 Blind Rivets pc 450.00 1.35 0.00 607.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 213.75
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 935.00 38.00 11.40 35,530.00 10,659.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 72.00 350.00 105.00 25,200.00 7,560.00
9.22 Finishing Nails kg 4.00 70.00 21.00 280.00 84.00
9.23 Common Wire Nails kg 17.00 50.00 15.00 850.00 255.00
9.24 Concrete Nails kg 4.00 70.00 21.00 280.00 84.00
9.42 Wood Preservative, Brown L 7.00 900.00 270.00 6,300.00 1,890.00
Exterior ceiling sq.m 60.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 263.00 38.00 11.40 9,994.00 2,998.20
9.06 Plywood, Marine 1/4" x 4' x 8' pc 21.00 360.00 108.00 7,560.00 2,268.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 10.00 245.00 73.50 2,450.00 735.00
9.16 Fascia Board, Wooden bd.ft 250.92 36.00 10.80 9,033.12 2,709.94
Blackboards sq.m 23.04
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 147.00 38.00 11.40 5,586.00 1,675.80
9.43 Lawanit, 1/4" thk pc 8.00 280.00 84.00 2,240.00 672.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 3.00 50.00 15.00 150.00 45.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 96.00 50.00 15.00 4,800.00 1,440.00
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00 52.50
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00 10.50
10.16 Junction Box, 4" x 4" G.I. pc 30.00 15.00 4.50 450.00 135.00
10.17 Utility Box, 2" x 4" G.I. pc 30.00 30.00 4.28 900.00 128.25
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 864.00 33.00 7.02 28,512.00 6,065.28
10.14 14.0 mm2 THW Wire, Stranded m 10.00 84.50 25.35 845.00 253.50
10.28 Duplex C.O. with Plate pc 12.00 263.80 21.00 3,165.60 252.00
10.23 Single Switch with Plate pc 3.00 97.68 13.46 293.04 40.39

2Sty4CL Schoolbuilding 14 of 179


Two-Storey Four (4) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
10.24 2-Gang Switch with Plate pc 5.00 153.00 21.53 765.00 107.63
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18
10.20 FL 2 x 40W Industrial Type set 23.00 840.00 126.00 19,320.00 2,898.00
10.53 Incandescent Bulb 50W set 3.00 35.00 5.25 105.00 15.75
10.33 Ceiling Receptacle 3-1/2"Ø pc 3.00 25.00 3.75 75.00 11.25
10.49 Panel Box, Flush Type, 8 Branches set 1.00 1,580.00 237.00 1,580.00 237.00
10.42 Circuit Breaker, 60A 2P set 1.00 441.25 66.19 441.25 66.19
10.38 Circuit Breaker, 20A 2P set 6.00 313.00 46.95 1,878.00 281.70
10.58 Electrical Tape pc 4.00 37.50 5.63 150.00 22.50
10.54 Vibrating Bell 8" set 2.00 1,500.00 225.00 3,000.00 450.00
10.55 Fire Alarm Bell, Vibrating Type set 2.00 2,000.00 300.00 4,000.00 600.00

10.56 Fire Alarm Station, Manual Single set 1,750.00 262.50 3,500.00 525.00
Action 2.00
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 3.00 5,500.00 825.00 16,500.00 2,475.00
11.63 Urinal 0.8gpf set 2.00 5,900.00 885.00 11,800.00 1,770.00
11.64 Concrete Counter Sink Type, with Lever Typ set 5.00 3,150.00 472.50 15,750.00 2,362.50
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 5.00 160.00 24.00 800.00 120.00
11.61 Water Closet Flange set 3.00 262.50 39.38 787.50 118.13
11.67 Tissue Holder pc 3.00 250.00 37.50 750.00 112.50
11.05 PP-R Pipe 3/4"Ø pc 10.00 345.00 103.50 3,450.00 1,035.00
11.09 PP-R Coupling, 3/4"Ø pc 10.00 15.00 4.50 150.00 45.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 4.00 23.00 6.90 92.00 27.60
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 11.00 3.30 22.00 6.60
11.06 PP-R Pipe 1/2"Ø pc 8.00 217.00 65.10 1,736.00 520.80
11.21 PP-R Elbow 90o x 1/2"Ø pc 20.00 14.00 4.20 280.00 84.00
11.08 PP-R Coupling, 1/2"Ø pc 6.00 9.00 2.70 54.00 16.20
11.15 PP-R Tee, 1/2"Ø pc 10.00 17.00 5.10 170.00 51.00
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 13.00 84.97 25.49 1,104.61 331.38
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 1.00 250.00 75.00 250.00 75.00
11.65 S.S.Floor Drain 4' x 4" pc 12.00 97.50 14.63 1,170.00 175.50
11.68 S.S. Grab Rail 1-1/2"Ø set 1.00 5,000.00 435.00 5,000.00 435.00
11.69 Mirror sq.ft 24.00 100.00 15.00 2,400.00 360.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 6.00 1,500.00 450.00 9,000.00 2,700.00
12.02 Concrete Pipe 150mmØ pc 52.00 200.00 60.00 10,400.00 3,120.00
12.32 Three Chamber Septic Vault unit 1.00 42,878.52 14,039.42 42,878.52 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 4.00 560.00 168.00 2,240.00 672.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 2.00 82.50 24.75 165.00 49.50
12.13 uPVC Elbow 90o x 4"Ø pc 3.00 96.00 28.80 288.00 86.40
12.27 uPVC Wye 4" x 4" pc 3.00 165.00 49.50 495.00 148.50
12.21 uPVC Tee 4" x 4" pc 5.00 138.00 41.40 690.00 207.00
12.25 uPVC Wye 4" x 2" pc 6.00 97.00 29.10 582.00 174.60
12.29 Brass Cleanout 6" x 6" pc 4.00 675.00 202.50 2,700.00 810.00
12.28 Brass Cleanout 4" x 4" pc 2.00 350.00 105.00 700.00 210.00
12.11 uPVC Elbow 90o x 2"Ø pc 10.00 25.00 7.50 250.00 75.00
12.07 uPVC Sanitary Pipe 2"Ø pc 10.00 210.00 63.00 2,100.00 630.00
12.22 uPVC Wye 2" x 2" pc 4.00 38.00 11.40 152.00 45.60
12.17 uPVC Tee 2" x 2" pc 6.00 36.00 10.80 216.00 64.80
12.30 uPVC P-Trap 2" pc 4.00 66.00 19.80 264.00 79.20
12.08 uPVC Sanitary Pipe 3"Ø pc 18.00 420.00 126.00 7,560.00 2,268.00

2Sty4CL Schoolbuilding 15 of 179


Two-Storey Four (4) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
12.12 uPVC Elbow 90o x 3"Ø pc 18.00 53.00 15.90 954.00 286.20
12.33 PVC Cement can 3.00 150.00 45.00 450.00 135.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 1,461.73
13.18 Neutralizer gal 19.00 132.00 39.60 2,508.00 752.40
13.01 Latex, Flat gal 74.00 424.00 127.20 31,376.00 9,412.80
13.14 Masonry Putty gal 74.00 319.00 95.70 23,606.00 7,081.80
13.02 Latex, Semi Gloss gal 74.00 492.50 147.75 36,445.00 10,933.50
13.20 Acri Color qrt 19.00 165.00 49.50 3,135.00 940.50
Wood surfaces sq.m 464.79
13.04 Enamel, Flatwall gal 24.00 483.00 144.90 11,592.00 3,477.60
13.15 Glazing Putty gal 24.00 492.00 147.60 11,808.00 3,542.40
13.05 Enamel, Semi Gloss gal 24.00 497.00 149.10 11,928.00 3,578.40
13.16 Paint Thinner gal 18.00 260.00 78.00 4,680.00 1,404.00
Sub-total
14.00 Tile Works
Wall sq.m 27.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 696.00 14.00 4.20 9,744.00 2,923.20
14.16 Tile Adhesive 25 kg/bag bag 5.00 224.10 67.23 1,120.50 336.15
14.13 Tile Trim 6mm pc 8.00 97.75 29.33 782.00 234.60
14.15 Tile Grout 5 kg/bag bag 3.00 150.00 45.00 450.00 135.00
14.15 Flooring sq.m 15.00
14.01 Unglazed Floor Tiles 20cm x 20cm pc 387.00 12.00 3.60 4,644.00 1,393.20
14.16 Tile Adhesive 25 kg/bag bag 3.00 224.10 67.23 672.30 201.69
14.15 Tile Grout 5 kg/bag bag 2.00 150.00 45.00 300.00 90.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNANDE
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

2Sty4CL Schoolbuilding 16 of 179


Two-Storey Four (4) Classroom

Republic of the Philippines


ARTMENT OF EDUCATION
ES AND SCHOOLS ENGINEERING DIVISION
Pasig City

) CLASSROOM

GRAND TOTAL

33,739.60
19,327.16
53,066.77

4,275.00
22,978.20
9,300.59
34,387.03
35,189.76
4,584.94
110,715.52

43,643.60
19,492.50
9,187.50

40,526.20
20,384.00
9,360.00

3,684.20
1,911.00
877.50

47,044.40
23,569.00
10,822.50

37,408.80
18,791.50
8,775.00

48,744.80
24,524.50
11,407.50

27,773.20
14,014.00
6,435.00

12,469.60
6,370.00
2,925.00

54,696.20

2Sty4CL Schoolbuilding 17 of 179


Two-Storey Four (4) Classroom

GRAND TOTAL

27,391.00
12,577.50

2,550.60
1,274.00
585.00

3,967.60
1,911.00
877.50
555,971.70

881,332.02
26,442.00
907,774.02

24,148.80
8,645.00
1,326.00

75,004.80
16,835.00
3,978.00

59,404.80
13,195.00
3,120.00

67,433.60
24,882.00
3,588.00

47,008.00
10,465.00
2,496.00

5,075.20
1,365.00
312.00

4,784.00
1,365.00
312.00
374,743.20

2Sty4CL Schoolbuilding 18 of 179


Two-Storey Four (4) Classroom

GRAND TOTAL

81,541.20
59,514.00
21,060.00
28,880.02
936.00

78,218.40
32,760.00

35,708.40
15,210.00
353,828.02

70,248.00

5,001.00

8,562.00

8,181.00

91,195.20

44,851.20

5,097.60

233,136.00

45,167.62
53,554.18
78,122.58
1,391.00
2,886.00
936.00

2,527.20

1,123.20

14,031.88
17,517.50

2Sty4CL Schoolbuilding 19 of 179


Two-Storey Four (4) Classroom

GRAND TOTAL

9,727.90
23,153.00
5,642.00
6,619.60
4,188.60
266,588.24

155,131.20

9,130.00

6,720.00

6,160.00
4,898.88
899.25
607.50
183,546.83

46,189.00
32,760.00
364.00
1,105.00
364.00
8,190.00

12,992.20
9,828.00
182.00
325.00
182.00
2,340.00
3,185.00
11,743.06

7,261.80
2,912.00
91.00
195.00
91.00
140,300.06

6,240.00
227.50
80.50
585.00
1,028.25
172.50

34,577.28
1,098.50
3,417.60
333.43

2Sty4CL Schoolbuilding 20 of 179


Two-Storey Four (4) Classroom

GRAND TOTAL

872.63
475.18
22,218.00
120.75
86.25
1,817.00
507.44
2,159.70
172.50
3,450.00
4,600.00

4,025.00

6,325.00
94,590.00

18,975.00
13,570.00
18,112.50
920.00
905.63
862.50
4,485.00
195.00
119.60
28.60
2,256.80
364.00
70.20
221.00
1,435.99
416.00
325.00
1,345.50
5,435.00
2,760.00
72,803.32

11,700.00
13,520.00
56,917.93
2,912.00
214.50
374.40
643.50
897.00
756.60
3,510.00
910.00
325.00
2,730.00
197.60
280.80
343.20
9,828.00

2Sty4CL Schoolbuilding 21 of 179


Two-Storey Four (4) Classroom

GRAND TOTAL

1,240.20
585.00
107,885.73

3,260.40
40,788.80
30,687.80
47,378.50
4,075.50

15,069.60
15,350.40
15,506.40
6,084.00
178,201.40

12,667.20
1,456.65
1,016.60
585.00

6,037.20
873.99
390.00
23,026.64

3,656,177.43
694,673.71
522,102.14
4,872,953.28
48,729.53
PhP4,921,682.82
PhP4,922,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

2Sty4CL Schoolbuilding 22 of 179


Two-Storey Six (6) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED TWO STOREY SIX (6) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard
Billboard
lot 1.00 27,841.89 20,416.36 27,841.89 20,416.36
Safety and Health lot 1.00 27,841.89 0.00 27,841.89 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 299.25 0.00 20.00 0.00 5,985.00
1.02 Structural Excavation cu.m 153.47 0.00 200.00 0.00 30,693.60
1.03 Backfilling and Compaction cu.m 288.79 0.00 45.00 0.00 12,995.74
1.06 Select Fill cu.m 246.88 150.00 45.00 37,032.19 11,109.66
1.04 Gravel Bedding G-1 cu.m 41.91 980.00 180.00 41,074.74 7,544.34
1.05 Soil Poisoning sq.m 329.18 15.00 4.50 4,937.63 1,481.29
Sub-total
2.00 Concreting Works
Column Footing cu.m 22.70
2.01 Portland Cement bag 205.00 218.00 65.40 44,690.00 13,407.00
2.05 Crushed Gravel 1" cu.m 22.75 980.00 294.00 22,295.00 6,688.50
2.03 Washed Sand cu.m 11.50 900.00 270.00 10,350.00 3,105.00
Tie beams cu.m 27.69
2.01 Portland Cement bag 250.00 218.00 65.40 54,500.00 16,350.00
2.02 Crushed Gravel 3/4" cu.m 27.75 980.00 294.00 27,195.00 8,158.50
2.03 Washed Sand cu.m 14.00 900.00 270.00 12,600.00 3,780.00
Wall Footing cu.m 1.40
2.01 Portland Cement bag 13.00 218.00 65.40 2,834.00 850.20
2.05 Crushed Gravel 1" cu.m 1.50 980.00 294.00 1,470.00 441.00
2.03 Washed Sand cu.m 0.75 900.00 270.00 675.00 202.50
Columns cu.m 24.42
2.01 Portland Cement bag 220.00 218.00 65.40 47,960.00 14,388.00
2.02 Crushed Gravel 3/4" cu.m 24.50 980.00 294.00 24,010.00 7,203.00
2.03 Washed Sand cu.m 12.25 900.00 270.00 11,025.00 3,307.50
Beams and Girders cu.m 19.61
2.01 Portland Cement bag 177.00 218.00 65.40 38,586.00 11,575.80
2.02 Crushed Gravel 3/4" cu.m 19.75 980.00 294.00 19,355.00 5,806.50
2.03 Washed Sand cu.m 10.00 900.00 270.00 9,000.00 2,700.00
Suspended Slab cu.m 27.62
2.01 Portland Cement bag 249.00 218.00 65.40 54,282.00 16,284.60
2.02 Crushed Gravel 3/4" cu.m 27.75 980.00 294.00 27,195.00 8,158.50
2.03 Washed Sand cu.m 14.00 900.00 270.00 12,600.00 3,780.00
Roof Beams cu.m 14.76
2.01 Portland Cement bag 133.00 218.00 65.40 28,994.00 8,698.20
2.02 Crushed Gravel 3/4" cu.m 15.00 980.00 294.00 14,700.00 4,410.00
2.03 Washed Sand cu.m 7.50 900.00 270.00 6,750.00 2,025.00
Stairs cu.m 4.86
2.01 Portland Cement bag 44.00 218.00 65.40 9,592.00 2,877.60
2.02 Crushed Gravel 3/4" cu.m 5.00 980.00 294.00 4,900.00 1,470.00
2.03 Washed Sand cu.m 2.50 900.00 270.00 2,250.00 675.00
Slab on Grade cu.m 29.93
2.01 Portland Cement bag 270.00 218.00 65.40 58,860.00 17,658.00

2Sty6CL Schoolbuilding 23 of 179


Two-Storey Six (6) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
2.05 Crushed Gravel 1" cu.m 30.00 980.00 294.00 29,400.00 8,820.00
2.03 Washed Sand cu.m 15.00 900.00 270.00 13,500.00 4,050.00
Ramp on Fill cu.m 1.00
2.01 Portland Cement bag 9.00 218.00 65.40 1,962.00 588.60
2.05 Crushed Gravel 1" cu.m 1.00 980.00 294.00 980.00 294.00
2.03 Washed Sand cu.m 0.50 900.00 270.00 450.00 135.00
Media Agua cu.m 2.10
2.01 Portland Cement bag 19.00 218.00 65.40 4,142.00 1,242.60
2.02 Crushed Gravel 3/4" cu.m 2.25 980.00 294.00 2,205.00 661.50
2.03 Washed Sand cu.m 1.25 900.00 270.00 1,125.00 337.50
Sub-total
3.00 Rebar Works
Column Footing kg 1,586.33
Tie beams kg 3,947.68
Wall Footing kg 59.14
Columns kg 7,649.62
Beams and Girders kg 4,373.20
Suspended Slab kg 2,170.63
Roof Beams kg 2,300.01
Stairs kg 276.64
Slab on Grade kg 1,263.27
Ramp on Fill kg 42.09
Media Agua kg 155.26
3.01 Deformed Round Bars, Grade 40 kg 23,823.86 40.10 12.03 955,336.85 286,601.06
3.02 G.I. Tie Wire kg 477.00 60.00 18.00 28,620.00 8,586.00
Sub-total
4.00 Formworks
Tie beams sq.m 213.00
4.01 Coco Lumber bd.ft 2,343.00 16.00 4.80 37,488.00 11,246.40
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 55.00 580.00 174.00 31,900.00 9,570.00
4.04 CWN, Assorted kg 33.00 60.00 18.00 1,980.00 594.00
Columns sq.m 281.16
4.01 Coco Lumber bd.ft 4,780.00 16.00 4.80 76,480.00 22,944.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 73.00 580.00 174.00 42,340.00 12,702.00
4.04 CWN, Assorted kg 67.00 60.00 18.00 4,020.00 1,206.00
Beams and Girders sq.m 226.50
4.01 Coco Lumber bd.ft 3,851.00 16.00 4.80 61,616.00 18,484.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 59.00 580.00 174.00 34,220.00 10,266.00
4.04 CWN, Assorted kg 54.00 60.00 18.00 3,240.00 972.00
Suspended Slab sq.m 276.19
4.01 Coco Lumber bd.ft 4,696.00 16.00 4.80 75,136.00 22,540.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 71.00 580.00 174.00 41,180.00 12,354.00
4.04 CWN, Assorted kg 66.00 60.00 18.00 3,960.00 1,188.00
Roof Beams sq.m 181.70
4.01 Coco Lumber bd.ft 3,089.00 16.00 4.80 49,424.00 14,827.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 47.00 580.00 174.00 27,260.00 8,178.00
4.04 CWN, Assorted kg 44.00 60.00 18.00 2,640.00 792.00
Stairs sq.m 14.30
4.01 Coco Lumber bd.ft 244.00 16.00 4.80 3,904.00 1,171.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 4.00 580.00 174.00 2,320.00 696.00
4.04 CWN, Assorted kg 4.00 60.00 18.00 240.00 72.00
Media Agua sq.m 18.90
4.01 Coco Lumber bd.ft 322.00 16.00 4.80 5,152.00 1,545.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 5.00 580.00 174.00 2,900.00 870.00
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00
Sub-total

2Sty6CL Schoolbuilding 24 of 179


Two-Storey Six (6) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
5.00 Masonry Works
Masonry Wall sq.m 558.24
5.05 CHB 6" thk pc 6,978.00 12.00 3.60 83,736.00 25,120.80
5.02 Portland Cement bag 280.00 218.00 65.40 61,040.00 18,312.00
5.03 Washed Sand cu.m 24.00 900.00 270.00 21,600.00 6,480.00
5.06 10mm x 6m RSB kg 740.00 40.10 12.03 29,674.00 8,902.20
5.07 G.I. Tie Wire kg 15.00 60.00 18.00 900.00 270.00
Plastering sq.m 1,116.48
5.02 Portland Cement bag 369.00 218.00 65.40 80,442.00 24,132.60
5.03 Washed Sand cu.m 37.00 900.00 270.00 33,300.00 9,990.00
Floor Topping sq.m 276.19
5.02 Portland Cement bag 183.00 218.00 65.40 39,894.00 11,968.20
5.03 Washed Sand cu.m 19.00 900.00 270.00 17,100.00 5,130.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 12.00 7,317.50 1,463.50 87,810.00 17,562.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 1.00 4,167.50 833.50 4,167.50 833.50
(lever type door knob)

6.05 set 2.00 3,567.50 713.50 7,135.00 1,427.00


D-3 Flush Door 0.70m x 2.10m on 150mm
Wooden Jamb complete with Accessories
D-4 Cubicle Door 0.60m x 1.20m on
6.06 150mm Wooden Jamb complete with set 2.00 3,408.75 681.75 6,817.50 1,363.50
Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


6.07 Clear Glass Blades on JalouPlus Type set 13.00 8,444.00 1,688.80 109,772.00 21,954.40
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


6.08 Clear Glass Blades on JalouPlus Type set 12.00 4,672.00 934.40 56,064.00 11,212.80
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window with


6.09 Clear Glass Blades on JalouPlus Type set 1.00 4,248.00 849.60 4,248.00 849.60
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,592.45 32.00 9.60 50,958.34 15,287.50
7.14 L 50 x 50 x 6mm kg 1,888.13 32.00 9.60 60,420.10 18,126.03
7.09 LC 120 x 50 x 20 x 2.0mm kg 2,020.08 43.00 12.90 86,863.23 26,058.97
7.18 Plain Round Bar 10mmØ x 6m pc 14.00 107.00 32.10 1,498.00 449.40
7.19 Plain Round Bar 12mmØ x 6m pc 16.00 185.00 55.50 2,960.00 888.00
7.30 Turn Buckle 12 mmØ pc 16.00 60.00 18.00 960.00 288.00

7.34 Anchor Bolt with Nuts and Washer, 12mmØ pc 27.00 8.10 2,592.00 777.60
x 50mm x 300mm 96.00

7.35 Anchor Bolt with Nuts and Washer, 10mmØ pc 12.00 3.60 1,152.00 345.60
x 50mm x 200mm 96.00
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 2.00 8,635.00 2,590.50 17,270.00 5,181.00
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 4.00 5,390.00 1,617.00 21,560.00 6,468.00
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 7.00 1,069.00 320.70 7,483.00 2,244.90

2Sty6CL Schoolbuilding 25 of 179


Two-Storey Six (6) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
7.45 G.I. Pipe 2"Ø Sch.40 pc 13.00 1,781.00 534.30 23,153.00 6,945.90
7.23 Square Bar 19mm□ x 6m pc 7.00 620.00 186.00 4,340.00 1,302.00
7.46 Welding Rod kg 111.00 67.00 20.10 7,437.00 2,231.10
13.12 Primer, Zinc Chromate gal 8.00 537.00 161.10 4,296.00 1,288.80
Sub-total
8.00 Roofing Works

8.16 Long-Span Roofing, Corrugated, Pre-


Painted, 1220mm x 0.4mm thk m 453.60 380.00 76.00 172,368.00 34,473.60

8.22 Gutter, Pre-Painted, Ordinary, 0.610m x


2.440m x 0.4mm thk pc 30.00 415.00 0.00 12,450.00 0.00

8.19 Flashing, Pre-Painted, Ordinary, 0.610m x


2.440m x 0.4mm thk pc 12.00 560.00 0.00 6,720.00 0.00

8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m


x 2.440m x 0.4mm thk pc 15.00 560.00 0.00 8,400.00 0.00
8.35 Teckscrew 2-1/2" pc 3,628.80 1.80 0.00 6,531.84 0.00
8.36 Roof Sealant L 6.00 299.75 0.00 1,798.50 0.00
8.37 Blind Rivets pc 570.00 1.35 0.00 769.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 299.25
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 1,308.00 38.00 11.40 49,704.00 14,911.20
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 101.00 350.00 105.00 35,350.00 10,605.00
9.22 Finishing Nails kg 6.00 70.00 21.00 420.00 126.00
9.23 Common Wire Nails kg 24.00 50.00 15.00 1,200.00 360.00
9.24 Concrete Nails kg 6.00 70.00 21.00 420.00 126.00
9.42 Wood Preservative, Brown L 10.00 900.00 270.00 9,000.00 2,700.00
Exterior ceiling sq.m 78.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 342.00 38.00 11.40 12,996.00 3,898.80
9.06 Plywood, Marine 1/4" x 4' x 8' pc 27.00 360.00 108.00 9,720.00 2,916.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 7.00 50.00 15.00 350.00 105.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 14.00 245.00 73.50 3,430.00 1,029.00
9.16 Fascia Board, Wooden bd.ft 309.96 36.00 10.80 11,158.56 3,347.57
Blackboards sq.m 34.56
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 220.00 38.00 11.40 8,360.00 2,508.00
9.43 Lawanit, 1/4" thk pc 12.00 280.00 84.00 3,360.00 1,008.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 4.00 50.00 15.00 200.00 60.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 144.00 50.00 15.00 7,200.00 2,160.00
10.08 RSC 32mmØ pc 1.00 339.00 101.70 339.00 101.70
10.35 Entrance Cap 32mm dia. pc 1.00 75.00 11.25 75.00 11.25
10.16 Junction Box, 4" x 4" G.I. pc 42.00 15.00 4.50 630.00 189.00
10.17 Utility Box, 2" x 4" G.I. pc 42.00 30.00 4.28 1,260.00 179.55
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 1,555.20 33.00 7.02 51,321.60 10,917.50
10.10 30.0 mm2 THW Wire, Stranded m 10.00 180.00 54.00 1,800.00 540.00
10.28 Duplex C.O. with Plate pc 18.00 263.80 21.00 4,748.40 378.00
10.23 Single Switch with Plate pc 3.00 97.68 13.46 293.04 40.39
10.24 2-Gang Switch with Plate pc 11.00 153.00 21.53 1,683.00 236.78

2Sty6CL Schoolbuilding 26 of 179


Two-Storey Six (6) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
10.20 FL 2 x 40W Industrial Type set 33.00 840.00 126.00 27,720.00 4,158.00
10.53 Incandescent Bulb 50W set 3.00 35.00 5.25 105.00 15.75
10.33 Ceiling Receptacle 3-1/2"Ø pc 3.00 25.00 3.75 75.00 11.25
10.51 Panel Box, Flush Type, 10 Branches set 1.00 1,850.00 277.50 1,850.00 277.50
10.43 Circuit Breaker, 100A 2P set 1.00 650.00 97.50 650.00 97.50
10.38 Circuit Breaker, 20A 2P set 8.00 313.00 46.95 2,504.00 375.60
10.58 Electrical Tape pc 6.00 37.50 5.63 225.00 33.75
10.54 Vibrating Bell 8" set 2.00 1,500.00 225.00 3,000.00 450.00
10.55 Fire Alarm Bell, Vibrating Type set 2.00 2,000.00 300.00 4,000.00 600.00

10.56 Fire Alarm Station, Manual Single set 1,750.00 262.50 3,500.00 525.00
Action 2.00
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 3.00 5,500.00 825.00 16,500.00 2,475.00
11.63 Urinal 0.8gpf set 2.00 5,900.00 885.00 11,800.00 1,770.00
11.64 Concrete Counter Sink Type, with Lever Typ set 5.00 3,150.00 472.50 15,750.00 2,362.50
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 5.00 160.00 24.00 800.00 120.00
11.61 Water Closet Flange set 3.00 262.50 39.38 787.50 118.13
11.67 Tissue Holder pc 3.00 250.00 37.50 750.00 112.50
11.05 PP-R Pipe 3/4"Ø pc 10.00 345.00 103.50 3,450.00 1,035.00
11.09 PP-R Coupling, 3/4"Ø pc 10.00 15.00 4.50 150.00 45.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 4.00 23.00 6.90 92.00 27.60
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 11.00 3.30 22.00 6.60
11.06 PP-R Pipe 1/2"Ø pc 8.00 217.00 65.10 1,736.00 520.80
11.21 PP-R Elbow 90o x 1/2"Ø pc 20.00 14.00 4.20 280.00 84.00
11.08 PP-R Coupling, 1/2"Ø pc 6.00 9.00 2.70 54.00 16.20
11.15 PP-R Tee, 1/2"Ø pc 10.00 17.00 5.10 170.00 51.00
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 13.00 84.97 25.49 1,104.61 331.38
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 1.00 250.00 75.00 250.00 75.00
11.65 S.S.Floor Drain 4' x 4" pc 14.00 97.50 14.63 1,365.00 204.75
11.68 S.S. Grab Rail 1-1/2"Ø set 1.00 5,000.00 435.00 5,000.00 435.00
11.69 Mirror sq.ft 24.00 100.00 15.00 2,400.00 360.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 10.00 1,500.00 450.00 15,000.00 4,500.00
12.02 Concrete Pipe 150mmØ pc 80.00 200.00 60.00 16,000.00 4,800.00
12.32 Three Chamber Septic Vault unit 1.00 42,878.52 14,039.42 42,878.52 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 4.00 560.00 168.00 2,240.00 672.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 2.00 82.50 24.75 165.00 49.50
12.13 uPVC Elbow 90o x 4"Ø pc 3.00 96.00 28.80 288.00 86.40
12.27 uPVC Wye 4" x 4" pc 3.00 165.00 49.50 495.00 148.50
12.21 uPVC Tee 4" x 4" pc 5.00 138.00 41.40 690.00 207.00
12.25 uPVC Wye 4" x 2" pc 6.00 97.00 29.10 582.00 174.60
12.29 Brass Cleanout 6" x 6" pc 4.00 675.00 202.50 2,700.00 810.00
12.28 Brass Cleanout 4" x 4" pc 2.00 350.00 105.00 700.00 210.00
12.11 uPVC Elbow 90o x 2"Ø pc 12.00 25.00 7.50 300.00 90.00
12.07 uPVC Sanitary Pipe 2"Ø pc 12.00 210.00 63.00 2,520.00 756.00
12.22 uPVC Wye 2" x 2" pc 4.00 38.00 11.40 152.00 45.60
12.17 uPVC Tee 2" x 2" pc 6.00 36.00 10.80 216.00 64.80
12.30 uPVC P-Trap 2" pc 4.00 66.00 19.80 264.00 79.20
12.08 uPVC Sanitary Pipe 3"Ø pc 24.00 420.00 126.00 10,080.00 3,024.00
12.12 uPVC Elbow 90o x 3"Ø pc 24.00 53.00 15.90 1,272.00 381.60
12.33 PVC Cement can 4.00 150.00 45.00 600.00 180.00

2Sty6CL Schoolbuilding 27 of 179


Two-Storey Six (6) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 1,974.64
13.18 Neutralizer gal 25.00 132.00 39.60 3,300.00 990.00
13.01 Latex, Flat gal 99.00 424.00 127.20 41,976.00 12,592.80
13.14 Masonry Putty gal 99.00 319.00 95.70 31,581.00 9,474.30
13.02 Latex, Semi Gloss gal 99.00 492.50 147.75 48,757.50 14,627.25
13.20 Acri Color qrt 25.00 165.00 49.50 4,125.00 1,237.50
Wood surfaces sq.m 649.09
13.04 Enamel, Flatwall gal 33.00 483.00 144.90 15,939.00 4,781.70
13.15 Glazing Putty gal 33.00 492.00 147.60 16,236.00 4,870.80
13.05 Enamel, Semi Gloss gal 33.00 497.00 149.10 16,401.00 4,920.30
13.16 Paint Thinner gal 25.00 260.00 78.00 6,500.00 1,950.00
Sub-total
14.00 Tile Works
Wall sq.m 27.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 696.00 14.00 4.20 9,744.00 2,923.20
14.16 Tile Adhesive 25 kg/bag bag 5.00 224.10 67.23 1,120.50 336.15
14.13 Tile Trim 6mm pc 8.00 97.75 29.33 782.00 234.60
14.15 Tile Grout 5 kg/bag bag 3.00 150.00 45.00 450.00 135.00
14.15 Flooring sq.m 15.00
14.01 Unglazed Floor Tiles 20cm x 20cm pc 387.00 12.00 3.60 4,644.00 1,393.20
14.16 Tile Adhesive 25 kg/bag bag 3.00 224.10 67.23 672.30 201.69
14.15 Tile Grout 5 kg/bag bag 2.00 150.00 45.00 300.00 90.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNANDE
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

2Sty6CL Schoolbuilding 28 of 179


Two-Storey Six (6) Classroom

Republic of the Philippines


ARTMENT OF EDUCATION
S AND SCHOOLS ENGINEERING DIVISION
Pasig City

LASSROOM

GRAND TOTAL

48,258.26
27,841.89
76,100.15

5,985.00
30,693.60
12,995.74
48,141.84
48,619.08
6,418.91
152,854.18

58,097.00
28,983.50
13,455.00

70,850.00
35,353.50
16,380.00

3,684.20
1,911.00
877.50

62,348.00
31,213.00
14,332.50

50,161.80
25,161.50
11,700.00

70,566.60
35,353.50
16,380.00

37,692.20
19,110.00
8,775.00

12,469.60
6,370.00
2,925.00

76,518.00

2Sty6CL Schoolbuilding 29 of 179


Two-Storey Six (6) Classroom

GRAND TOTAL

38,220.00
17,550.00

2,550.60
1,274.00
585.00

5,384.60
2,866.50
1,462.50
780,561.60

1,241,937.91
37,206.00
1,279,143.91

48,734.40
41,470.00
2,574.00

99,424.00
55,042.00
5,226.00

80,100.80
44,486.00
4,212.00

97,676.80
53,534.00
5,148.00

64,251.20
35,438.00
3,432.00

5,075.20
3,016.00
312.00

6,697.60
3,770.00
390.00
660,010.00

2Sty6CL Schoolbuilding 30 of 179


Two-Storey Six (6) Classroom

GRAND TOTAL

108,856.80
79,352.00
28,080.00
38,576.20
1,170.00

104,574.60
43,290.00

51,862.20
22,230.00
477,991.80

105,372.00

5,001.00

8,562.00

8,181.00

131,726.40

67,276.80

5,097.60

331,216.80

66,245.84
78,546.12
112,922.20
1,947.40
3,848.00
1,248.00

3,369.60

1,497.60

22,451.00
28,028.00
9,727.90

2Sty6CL Schoolbuilding 31 of 179


Two-Storey Six (6) Classroom

GRAND TOTAL

30,098.90
5,642.00
9,668.10
5,584.80
380,825.47

206,841.60

12,450.00

6,720.00

8,400.00
6,531.84
1,798.50
769.50
243,511.44

64,615.20
45,955.00
546.00
1,560.00
546.00
11,700.00

16,894.80
12,636.00
182.00
455.00
182.00
3,510.00
4,459.00
14,506.13

10,868.00
4,368.00
91.00
260.00
91.00
193,425.13

9,360.00
440.70
86.25
819.00
1,439.55
172.50

62,239.10
2,340.00
5,126.40
333.43
1,919.78

2Sty6CL Schoolbuilding 32 of 179


Two-Storey Six (6) Classroom

GRAND TOTAL

31,878.00
120.75
86.25
2,127.50
747.50
2,879.60
258.75
3,450.00
4,600.00

4,025.00

6,325.00
140,775.06

18,975.00
13,570.00
18,112.50
920.00
905.63
862.50
4,485.00
195.00
119.60
28.60
2,256.80
364.00
70.20
221.00
1,435.99
416.00
325.00
1,569.75
5,435.00
2,760.00
73,027.57

19,500.00
20,800.00
56,917.93
2,912.00
214.50
374.40
643.50
897.00
756.60
3,510.00
910.00
390.00
3,276.00
197.60
280.80
343.20
13,104.00
1,653.60
780.00

2Sty6CL Schoolbuilding 33 of 179


Two-Storey Six (6) Classroom

GRAND TOTAL

127,461.13

4,290.00
54,568.80
41,055.30
63,384.75
5,362.50

20,720.70
21,106.80
21,321.30
8,450.00
240,260.15

12,667.20
1,456.65
1,016.60
585.00

6,037.20
873.99
390.00
23,026.64

5,180,191.01
984,236.29
739,731.28
6,904,158.58
69,041.59
PhP6,973,200.17
PhP6,974,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

2Sty6CL Schoolbuilding 34 of 179


Two-Storey Eight (8) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED TWO STOREY EIGHT (8) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard
Billboard lot 1.00 38,492.58 28,216.65 38,492.58 28,216.65
Safety and Health lot 1.00 38,492.58 0.00 38,492.58 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 427.50 0.00 20.00 0.00 8,550.00
1.02 Structural Excavation cu.m 212.33 0.00 200.00 0.00 42,466.20
1.03 Backfilling and Compaction cu.m 412.11 0.00 45.00 0.00 18,544.88
1.06 Select Fill cu.m 352.69 150.00 45.00 52,903.13 15,870.94
1.04 Gravel Bedding G-1 cu.m 59.42 980.00 180.00 58,232.58 10,695.78
1.05 Soil Poisoning sq.m 470.25 15.00 4.50 7,053.75 2,116.13
Sub-total
2.00 Concreting Works
Column Footing cu.m 31.21
2.01 Portland Cement bag 281.00 218.00 65.40 61,258.00 18,377.40
2.05 Crushed Gravel 1" cu.m 31.25 980.00 294.00 30,625.00 9,187.50
2.03 Washed Sand cu.m 15.75 900.00 270.00 14,175.00 4,252.50
Tie beams cu.m 39.29
2.01 Portland Cement bag 354.00 218.00 65.40 77,172.00 23,151.60
2.02 Crushed Gravel 3/4" cu.m 39.50 980.00 294.00 38,710.00 11,613.00
2.03 Washed Sand cu.m 19.75 900.00 270.00 17,775.00 5,332.50
Wall Footing cu.m 1.40
2.01 Portland Cement bag 13.00 218.00 65.40 2,834.00 850.20
2.05 Crushed Gravel 1" cu.m 1.50 980.00 294.00 1,470.00 441.00
2.03 Washed Sand cu.m 0.75 900.00 270.00 675.00 202.50
Columns cu.m 33.73
2.01 Portland Cement bag 304.00 218.00 65.40 66,272.00 19,881.60
2.02 Crushed Gravel 3/4" cu.m 33.75 980.00 294.00 33,075.00 9,922.50
2.03 Washed Sand cu.m 17.00 900.00 270.00 15,300.00 4,590.00
Beams and Girders cu.m 28.09
2.01 Portland Cement bag 253.00 218.00 65.40 55,154.00 16,546.20
2.02 Crushed Gravel 3/4" cu.m 28.25 980.00 294.00 27,685.00 8,305.50
2.03 Washed Sand cu.m 14.25 900.00 270.00 12,825.00 3,847.50
Suspended Slab cu.m 38.14
2.01 Portland Cement bag 344.00 218.00 65.40 74,992.00 22,497.60
2.02 Crushed Gravel 3/4" cu.m 38.25 980.00 294.00 37,485.00 11,245.50
2.03 Washed Sand cu.m 19.25 900.00 270.00 17,325.00 5,197.50
Roof Beams cu.m 20.70
2.01 Portland Cement bag 187.00 218.00 65.40 40,766.00 12,229.80
2.02 Crushed Gravel 3/4" cu.m 20.75 980.00 294.00 20,335.00 6,100.50
2.03 Washed Sand cu.m 10.50 900.00 270.00 9,450.00 2,835.00
Stairs cu.m 9.72
2.01 Portland Cement bag 88.00 218.00 65.40 19,184.00 5,755.20
2.02 Crushed Gravel 3/4" cu.m 9.75 980.00 294.00 9,555.00 2,866.50
2.03 Washed Sand cu.m 5.00 900.00 270.00 4,500.00 1,350.00
Slab on Grade cu.m 42.75
2.01 Portland Cement bag 385.00 218.00 65.40 83,930.00 25,179.00

2Sty8CL Schoolbuilding 35 of 179


Two-Storey Eight (8) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
2.05 Crushed Gravel 1" cu.m 42.75 980.00 294.00 41,895.00 12,568.50
2.03 Washed Sand cu.m 21.50 900.00 270.00 19,350.00 5,805.00
Ramp on Fill cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 65.40 3,924.00 1,177.20
2.05 Crushed Gravel 1" cu.m 2.00 980.00 294.00 1,960.00 588.00
2.03 Washed Sand cu.m 1.00 900.00 270.00 900.00 270.00
Media Agua cu.m 3.00
2.01 Portland Cement bag 27.00 218.00 65.40 5,886.00 1,765.80
2.02 Crushed Gravel 3/4" cu.m 3.00 980.00 294.00 2,940.00 882.00
2.03 Washed Sand cu.m 1.50 900.00 270.00 1,350.00 405.00
Sub-total
3.00 Rebar Works
Column Footing kg 2,181.20
Tie beams kg 5,600.91
Wall Footing kg 118.28
Columns kg 10,518.23
Beams and Girders kg 6,187.78
Suspended Slab kg 2,990.22
Roof Beams kg 3,229.52
Stairs kg 553.28
Slab on Grade kg 1,640.61
Ramp on Fill kg 84.17
Media Agua kg 221.80
3.01 Deformed Round Bars, Grade 40 kg 33,326.00 40.10 12.03 1,336,372.54 400,911.76
3.02 G.I. Tie Wire kg 667.00 60.00 18.00 40,020.00 12,006.00
Sub-total
4.00 Formworks
Tie beams sq.m 261.95
4.01 Coco Lumber bd.ft 2,882.00 16.00 4.80 46,112.00 13,833.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 68.00 580.00 174.00 39,440.00 11,832.00
4.04 CWN, Assorted kg 41.00 60.00 18.00 2,460.00 738.00
Columns sq.m 389.60
4.01 Coco Lumber bd.ft 6,624.00 16.00 4.80 105,984.00 31,795.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 101.00 580.00 174.00 58,580.00 17,574.00
4.04 CWN, Assorted kg 93.00 60.00 18.00 5,580.00 1,674.00
Beams and Girders sq.m 324.75
4.01 Coco Lumber bd.ft 5,521.00 16.00 4.80 88,336.00 26,500.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 84.00 580.00 174.00 48,720.00 14,616.00
4.04 CWN, Assorted kg 78.00 60.00 18.00 4,680.00 1,404.00
Suspended Slab sq.m 381.38
4.01 Coco Lumber bd.ft 6,484.00 16.00 4.80 103,744.00 31,123.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 98.00 580.00 174.00 56,840.00 17,052.00
4.04 CWN, Assorted kg 91.00 60.00 18.00 5,460.00 1,638.00
Roof Beams sq.m 254.90
4.01 Coco Lumber bd.ft 4,334.00 16.00 4.80 69,344.00 20,803.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 66.00 580.00 174.00 38,280.00 11,484.00
4.04 CWN, Assorted kg 61.00 60.00 18.00 3,660.00 1,098.00
Stairs sq.m 28.60
4.01 Coco Lumber bd.ft 487.00 16.00 4.80 7,792.00 2,337.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 8.00 580.00 174.00 4,640.00 1,392.00
4.04 CWN, Assorted kg 7.00 60.00 18.00 420.00 126.00
Media Agua sq.m 27.00
4.01 Coco Lumber bd.ft 459.00 16.00 4.80 7,344.00 2,203.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 7.00 580.00 174.00 4,060.00 1,218.00
4.04 CWN, Assorted kg 7.00 60.00 18.00 420.00 126.00
Sub-total

2Sty8CL Schoolbuilding 36 of 179


Two-Storey Eight (8) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
5.00 Masonry Works
Masonry Wall sq.m 751.08
5.05 CHB 6" thk pc 9,389.00 12.00 3.60 112,668.00 33,800.40
5.02 Portland Cement bag 376.00 218.00 65.40 81,968.00 24,590.40
5.03 Washed Sand cu.m 32.00 900.00 270.00 28,800.00 8,640.00
5.06 10mm x 6m RSB kg 995.00 40.10 12.03 39,899.50 11,969.85
5.07 G.I. Tie Wire kg 20.00 60.00 18.00 1,200.00 360.00
Plastering sq.m 1,502.16
5.02 Portland Cement bag 496.00 218.00 65.40 108,128.00 32,438.40
5.03 Washed Sand cu.m 50.00 900.00 270.00 45,000.00 13,500.00
Floor Topping sq.m 381.38
5.02 Portland Cement bag 252.00 218.00 65.40 54,936.00 16,480.80
5.03 Washed Sand cu.m 26.00 900.00 270.00 23,400.00 7,020.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 16.00 7,317.50 1,463.50 117,080.00 23,416.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 4.00 4,167.50 833.50 16,670.00 3,334.00
(lever type door knob)

6.05 set 2.00 3,567.50 713.50 7,135.00 1,427.00


D-3 Flush Door 0.70m x 2.10m on 150mm
Wooden Jamb complete with Accessories
D-4 Cubicle Door 0.60m x 1.20m on
6.06 150mm Wooden Jamb complete with set 3.00 3,408.75 681.75 10,226.25 2,045.25
Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


6.07 Clear Glass Blades on JalouPlus Type set 18.00 8,444.00 1,688.80 151,992.00 30,398.40
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


6.08 Clear Glass Blades on JalouPlus Type set 16.00 4,672.00 934.40 74,752.00 14,950.40
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window with


6.09 Clear Glass Blades on JalouPlus Type set 2.00 4,248.00 849.60 8,496.00 1,699.20
Silver Colored Frame and Fixed Clear
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,990.56 32.00 9.60 63,697.92 19,109.38
7.14 L 50 x 50 x 6mm kg 2,360.16 32.00 9.60 75,525.12 22,657.54
7.09 LC 120 x 50 x 20 x 2.0mm kg 2,724.32 43.00 12.90 117,145.83 35,143.75
7.18 Plain Round Bar 10mmØ x 6m pc 20.00 107.00 32.10 2,140.00 642.00
7.19 Plain Round Bar 12mmØ x 6m pc 20.00 185.00 55.50 3,700.00 1,110.00
7.30 Turn Buckle 12 mmØ pc 20.00 60.00 18.00 1,200.00 360.00

7.34 Anchor Bolt with Nuts and Washer, 12mmØ pc 27.00 8.10 3,564.00 1,069.20
x 50mm x 300mm 132.00

7.35 Anchor Bolt with Nuts and Washer, 10mmØ pc 12.00 3.60 1,584.00 475.20
x 50mm x 200mm 132.00

2Sty8CL Schoolbuilding 37 of 179


Two-Storey Eight (8) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 2.75 8,635.00 2,590.50 23,746.25 7,123.88
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 5.50 5,390.00 1,617.00 29,645.00 8,893.50
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 14.00 1,069.00 320.70 14,966.00 4,489.80
7.45 G.I. Pipe 2"Ø Sch.40 pc 17.00 1,781.00 534.30 30,277.00 9,083.10
7.23 Square Bar 19mm□ x 6m pc 14.00 620.00 186.00 8,680.00 2,604.00
7.46 Welding Rod kg 142.00 67.00 20.10 9,514.00 2,854.20
13.12 Primer, Zinc Chromate gal 11.00 537.00 161.10 5,907.00 1,772.10
Sub-total
8.00 Roofing Works

8.16 Long-Span Roofing, Corrugated, Pre-


Painted, 1220mm x 0.4mm thk m 642.60 380.00 76.00 244,188.00 48,837.60

8.22 Gutter, Pre-Painted, Ordinary, 0.610m x


2.440m x 0.4mm thk pc 42.00 415.00 0.00 17,430.00 0.00

8.19 Flashing, Pre-Painted, Ordinary, 0.610m x


2.440m x 0.4mm thk pc 12.00 560.00 0.00 6,720.00 0.00

8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m


x 2.440m x 0.4mm thk pc 21.00 560.00 0.00 11,760.00 0.00
8.35 Teckscrew 2-1/2" pc 5,140.80 1.80 0.00 9,253.44 0.00
8.36 Roof Sealant L 6.00 299.75 0.00 1,798.50 0.00
8.37 Blind Rivets pc 750.00 1.35 0.00 1,012.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 427.50
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 1,869.00 38.00 11.40 71,022.00 21,306.60
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 144.00 350.00 105.00 50,400.00 15,120.00
9.22 Finishing Nails kg 8.00 70.00 21.00 560.00 168.00
9.23 Common Wire Nails kg 34.00 50.00 15.00 1,700.00 510.00
9.24 Concrete Nails kg 8.00 70.00 21.00 560.00 168.00
9.42 Wood Preservative, Brown L 14.00 900.00 270.00 12,600.00 3,780.00
Exterior ceiling sq.m 105.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 460.00 38.00 11.40 17,480.00 5,244.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 36.00 360.00 108.00 12,960.00 3,888.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 9.00 50.00 15.00 450.00 135.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 4.00 900.00 270.00 3,600.00 1,080.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 20.00 245.00 73.50 4,900.00 1,470.00
9.16 Fascia Board, Wooden bd.ft 398.52 36.00 10.80 14,346.72 4,304.02
Blackboards sq.m 46.08
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 293.00 38.00 11.40 11,134.00 3,340.20
9.43 Lawanit, 1/4" thk pc 16.00 280.00 84.00 4,480.00 1,344.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 6.00 50.00 15.00 300.00 90.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 192.00 50.00 15.00 9,600.00 2,880.00
10.08 RSC 32mmØ pc 1.00 339.00 101.70 339.00 101.70
10.35 Entrance Cap 32mm dia. pc 1.00 75.00 11.25 75.00 11.25
10.16 Junction Box, 4" x 4" G.I. pc 54.00 15.00 4.50 810.00 243.00
10.17 Utility Box, 2" x 4" G.I. pc 50.00 30.00 4.28 1,500.00 213.75
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 1,728.00 33.00 7.02 57,024.00 12,130.56
10.10 30.0 mm2 THW Wire, Stranded m 10.00 180.00 54.00 1,800.00 540.00

2Sty8CL Schoolbuilding 38 of 179


Two-Storey Eight (8) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
10.28 Duplex C.O. with Plate pc 22.00 263.80 21.00 5,803.60 462.00
10.23 Single Switch with Plate pc 3.00 97.68 13.46 293.04 40.39
10.24 2-Gang Switch with Plate pc 11.00 153.00 21.53 1,683.00 236.78
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18
10.20 FL 2 x 40W Industrial Type set 43.00 840.00 126.00 36,120.00 5,418.00
10.53 Incandescent Bulb 50W set 3.00 35.00 5.25 105.00 15.75
10.33 Ceiling Receptacle 3-1/2"Ø pc 3.00 25.00 3.75 75.00 11.25
10.50 Panel Box, Flush Type, 12 Branches set 1.00 2,530.75 379.61 2,530.75 379.61
10.43 Circuit Breaker, 100A 2P set 1.00 650.00 97.50 650.00 97.50
10.38 Circuit Breaker, 20A 2P set 10.00 313.00 46.95 3,130.00 469.50
10.58 Electrical Tape pc 8.00 37.50 5.63 300.00 45.00
10.54 Vibrating Bell 8" set 2.00 1,500.00 225.00 3,000.00 450.00
10.55 Fire Alarm Bell, Vibrating Type set 2.00 2,000.00 300.00 4,000.00 600.00

10.56 Fire Alarm Station, Manual Single set 1,750.00 262.50 3,500.00 525.00
Action 2.00
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 5.00 5,500.00 825.00 27,500.00 4,125.00
11.64 Concrete Counter Sink Type, with Lever Typ set 2.00 3,150.00 472.50 6,300.00 945.00
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 10.00 160.00 24.00 1,600.00 240.00
11.61 Water Closet Flange set 5.00 262.50 39.38 1,312.50 196.88
11.67 Tissue Holder pc 4.00 250.00 37.50 1,000.00 150.00
11.05 PP-R Pipe 3/4"Ø pc 12.00 345.00 103.50 4,140.00 1,242.00
11.09 PP-R Coupling, 3/4"Ø pc 10.00 15.00 4.50 150.00 45.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 11.00 3.30 22.00 6.60
11.06 PP-R Pipe 1/2"Ø pc 6.00 217.00 65.10 1,302.00 390.60
11.21 PP-R Elbow 90o x 1/2"Ø pc 18.00 14.00 4.20 252.00 75.60
11.08 PP-R Coupling, 1/2"Ø pc 2.00 9.00 2.70 18.00 5.40
11.15 PP-R Tee, 1/2"Ø pc 12.00 17.00 5.10 204.00 61.20
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 17.00 84.97 25.49 1,444.49 433.35
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 2.00 250.00 75.00 500.00 150.00
11.65 S.S.Floor Drain 4' x 4" pc 9.00 97.50 14.63 877.50 131.63
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00 870.00
11.66 Teflon Tape roll 20.00 12.00 1.80 240.00 36.00
11.69 Mirror sq.ft 48.00 100.00 15.00 4,800.00 720.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 12.00 1,500.00 450.00 18,000.00 5,400.00
12.02 Concrete Pipe 150mmØ pc 100.00 200.00 60.00 20,000.00 6,000.00
12.32 Three Chamber Septic Vault unit 1.00 55,743.00 14,039.42 55,743.00 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 22.00 560.00 168.00 12,320.00 3,696.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 2.00 82.50 24.75 165.00 49.50
12.13 uPVC Elbow 90o x 4"Ø pc 8.00 96.00 28.80 768.00 230.40
12.27 uPVC Wye 4" x 4" pc 8.00 165.00 49.50 1,320.00 396.00
12.21 uPVC Tee 4" x 4" pc 6.00 138.00 41.40 828.00 248.40
12.25 uPVC Wye 4" x 2" pc 8.00 97.00 29.10 776.00 232.80
12.29 Brass Cleanout 6" x 6" pc 10.00 675.00 202.50 6,750.00 2,025.00
12.28 Brass Cleanout 4" x 4" pc 4.00 350.00 105.00 1,400.00 420.00
12.11 uPVC Elbow 90o x 2"Ø pc 20.00 25.00 7.50 500.00 150.00
12.07 uPVC Sanitary Pipe 2"Ø pc 20.00 210.00 63.00 4,200.00 1,260.00
12.22 uPVC Wye 2" x 2" pc 8.00 38.00 11.40 304.00 91.20
12.17 uPVC Tee 2" x 2" pc 8.00 36.00 10.80 288.00 86.40
12.30 uPVC P-Trap 2" pc 4.00 66.00 19.80 264.00 79.20

2Sty8CL Schoolbuilding 39 of 179


Two-Storey Eight (8) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
12.08 uPVC Sanitary Pipe 3"Ø pc 36.00 420.00 126.00 15,120.00 4,536.00
12.12 uPVC Elbow 90o x 3"Ø pc 36.00 53.00 15.90 1,908.00 572.40
12.33 PVC Cement can 6.00 150.00 45.00 900.00 270.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 2,713.58
13.18 Neutralizer gal 34.00 132.00 39.60 4,488.00 1,346.40
13.01 Latex, Flat gal 136.00 424.00 127.20 57,664.00 17,299.20
13.14 Masonry Putty gal 136.00 319.00 95.70 43,384.00 13,015.20
13.02 Latex, Semi Gloss gal 136.00 492.50 147.75 66,980.00 20,094.00
13.20 Acri Color qrt 34.00 165.00 49.50 5,610.00 1,683.00
Wood surfaces sq.m 906.06
13.04 Enamel, Flatwall gal 46.00 483.00 144.90 22,218.00 6,665.40
13.15 Glazing Putty gal 46.00 492.00 147.60 22,632.00 6,789.60
13.05 Enamel, Semi Gloss gal 46.00 497.00 149.10 22,862.00 6,858.60
13.16 Paint Thinner gal 35.00 260.00 78.00 9,100.00 2,730.00
Sub-total
14.00 Tile Works
Wall sq.m 64.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 1,648.00 14.00 4.20 23,072.00 6,921.60
14.16 Tile Adhesive 25 kg/bag bag 12.00 224.10 67.23 2,689.20 806.76
14.13 Tile Trim 6mm pc 8.00 97.75 29.33 782.00 234.60
14.15 Tile Grout 5 kg/bag bag 5.00 150.00 45.00 750.00 225.00
14.15 Flooring sq.m 39.00
14.01 Unglazed Floor Tiles 20cm x 20cm pc 1,005.00 12.00 3.60 12,060.00 3,618.00
14.16 Tile Adhesive 25 kg/bag bag 8.00 224.10 67.23 1,792.80 537.84
14.15 Tile Grout 5 kg/bag bag 3.00 150.00 45.00 450.00 135.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNANDE
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

2Sty8CL Schoolbuilding 40 of 179


Two-Storey Eight (8) Classroom

Republic of the Philippines


RTMENT OF EDUCATION
S AND SCHOOLS ENGINEERING DIVISION
Pasig City

CLASSROOM

GRAND TOTAL

66,709.23
38,492.58
105,201.80

8,550.00
42,466.20
18,544.88
68,774.06
68,928.36
9,169.88
216,433.38

79,635.40
39,812.50
18,427.50

100,323.60
50,323.00
23,107.50

3,684.20
1,911.00
877.50

86,153.60
42,997.50
19,890.00

71,700.20
35,990.50
16,672.50

97,489.60
48,730.50
22,522.50

52,995.80
26,435.50
12,285.00

24,939.20
12,421.50
5,850.00

109,109.00

2Sty8CL Schoolbuilding 41 of 179


Two-Storey Eight (8) Classroom

GRAND TOTAL

54,463.50
25,155.00

5,101.20
2,548.00
1,170.00

7,651.80
3,822.00
1,755.00
1,105,951.60

1,737,284.30
52,026.00
1,789,310.30

59,945.60
51,272.00
3,198.00

137,779.20
76,154.00
7,254.00

114,836.80
63,336.00
6,084.00

134,867.20
73,892.00
7,098.00

90,147.20
49,764.00
4,758.00

10,129.60
6,032.00
546.00

9,547.20
5,278.00
546.00
912,464.80

2Sty8CL Schoolbuilding 42 of 179


Two-Storey Eight (8) Classroom

GRAND TOTAL

146,468.40
106,558.40
37,440.00
51,869.35
1,560.00

140,566.40
58,500.00

71,416.80
30,420.00
644,799.35

140,496.00

20,004.00

8,562.00

12,271.50

182,390.40

89,702.40

10,195.20

463,621.50

82,807.30
98,182.66
152,289.58
2,782.00
4,810.00
1,560.00

4,633.20

2,059.20

2Sty8CL Schoolbuilding 43 of 179


Two-Storey Eight (8) Classroom

GRAND TOTAL

30,870.13
38,538.50
19,455.80
39,360.10
11,284.00
12,368.20
7,679.10
508,679.75

293,025.60

17,430.00

6,720.00

11,760.00
9,253.44
1,798.50
1,012.50
341,000.04

92,328.60
65,520.00
728.00
2,210.00
728.00
16,380.00

22,724.00
16,848.00
182.00
585.00
182.00
4,680.00
6,370.00
18,650.74

14,474.20
5,824.00
91.00
390.00
91.00
268,986.54

12,480.00
440.70
86.25
1,053.00
1,713.75
172.50

69,154.56
2,340.00

2Sty8CL Schoolbuilding 44 of 179


Two-Storey Eight (8) Classroom

GRAND TOTAL

6,265.60
333.43
1,919.78
475.18
41,538.00
120.75
86.25
2,910.36
747.50
3,599.50
345.00
3,450.00
4,600.00

4,025.00

6,325.00
164,182.10

31,625.00
7,245.00
1,840.00
1,509.38
1,150.00
5,382.00
195.00
28.60
1,692.60
327.60
23.40
265.20
1,877.84
416.00
650.00
1,009.13
10,870.00
276.00
5,520.00
71,902.74

23,400.00
26,000.00
69,782.42
16,016.00
214.50
998.40
1,716.00
1,076.40
1,008.80
8,775.00
1,820.00
650.00
5,460.00
395.20
374.40
343.20

2Sty8CL Schoolbuilding 45 of 179


Two-Storey Eight (8) Classroom

GRAND TOTAL

19,656.00
2,480.40
1,170.00
181,336.72

5,834.40
74,963.20
56,399.20
87,074.00
7,293.00

28,883.40
29,421.60
29,720.60
11,830.00
331,419.40

29,993.60
3,495.96
1,016.60
975.00

15,678.00
2,330.64
585.00
54,074.80

7,159,364.82
1,360,279.32
1,022,357.30
9,542,001.44
95,420.01
PhP9,637,421.45
PhP9,638,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

2Sty8CL Schoolbuilding 46 of 179


Republic of the Philippines
DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED THREE-STOREY SIX-CLASSROOM


SCHOOL : E. RODRIGUEZ ELEMENTARY SCHOOL
LOCATION : CALOOCAN CITY
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 34,438.35 22,958.90 34,438.35 22,958.90
Billboard
Safety and Health lot 1.00 34,438.35 0.00 34,438.35 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 213.75 0.00 20.00 0.00 4,275.00
1.02 Structural Excavation cu.m 167.94 0.00 200.00 0.00 33,587.40
1.03 Backfilling and Compaction cu.m 210.32 0.00 45.00 0.00 9,464.21
1.06 Select Fill cu.m 176.34 150.00 45.00 26,451.56 7,935.47
1.04 Gravel Bedding G-1 cu.m 33.97 980.00 180.00 33,292.56 6,114.96
1.05 Soil Poisoning sq.m 235.13 15.00 4.50 3,526.88 1,058.06
Sub-total
2.00 Concreting Works
Column Footing cu.m 30.73
2.01 Portland Cement bag 277.00 218.00 65.40 60,386.00 18,115.80
2.05 Crushed Gravel 1" cu.m 30.75 980.00 294.00 30,135.00 9,040.50
2.03 Washed Sand cu.m 15.50 900.00 270.00 13,950.00 4,185.00
Tie beams cu.m 18.68
2.01 Portland Cement bag 169.00 218.00 65.40 36,842.00 11,052.60
2.02 Crushed Gravel 3/4" cu.m 18.75 980.00 294.00 18,375.00 5,512.50
2.03 Washed Sand cu.m 9.50 900.00 270.00 8,550.00 2,565.00
Wall Footing cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 65.40 3,924.00 1,177.20
2.05 Crushed Gravel 1" cu.m 2.00 980.00 294.00 1,960.00 588.00
2.03 Washed Sand cu.m 1.00 900.00 270.00 900.00 270.00
Columns cu.m 27.35
2.01 Portland Cement bag 247.00 218.00 65.40 53,846.00 16,153.80
2.02 Crushed Gravel 3/4" cu.m 27.50 980.00 294.00 26,950.00 8,085.00
2.03 Washed Sand cu.m 13.75 900.00 270.00 12,375.00 3,712.50
Beams and Girders cu.m 29.74
2.01 Portland Cement bag 268.00 218.00 65.40 58,424.00 17,527.20
2.02 Crushed Gravel 3/4" cu.m 29.75 980.00 294.00 29,155.00 8,746.50
2.03 Washed Sand cu.m 15.00 900.00 270.00 13,500.00 4,050.00
Suspended Slab cu.m 38.14
2.01 Portland Cement bag 344.00 218.00 65.40 74,992.00 22,497.60
2.02 Crushed Gravel 3/4" cu.m 38.25 980.00 294.00 37,485.00 11,245.50
2.03 Washed Sand cu.m 19.25 900.00 270.00 17,325.00 5,197.50
Roof Beams cu.m 10.80
2.01 Portland Cement bag 98.00 218.00 65.40 21,364.00 6,409.20
2.02 Crushed Gravel 3/4" cu.m 11.00 980.00 294.00 10,780.00 3,234.00
2.03 Washed Sand cu.m 5.50 900.00 270.00 4,950.00 1,485.00

e. rodriguez es 47 of 179
UNIT COST TOTAL COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Stairs cu.m 9.72
2.01 Portland Cement bag 88.00 218.00 65.40 19,184.00 5,755.20
2.02 Crushed Gravel 3/4" cu.m 9.75 980.00 294.00 9,555.00 2,866.50
2.03 Washed Sand cu.m 5.00 900.00 270.00 4,500.00 1,350.00
Slab on Grade cu.m 21.38
2.01 Portland Cement bag 193.00 218.00 65.40 42,074.00 12,622.20
2.05 Crushed Gravel 1" cu.m 21.50 980.00 294.00 21,070.00 6,321.00
2.03 Washed Sand cu.m 10.75 900.00 270.00 9,675.00 2,902.50
Ramp on Fill cu.m 1.00
2.01 Portland Cement bag 9.00 218.00 65.40 1,962.00 588.60
2.05 Crushed Gravel 1" cu.m 1.00 980.00 294.00 980.00 294.00
2.03 Washed Sand cu.m 0.50 900.00 270.00 450.00 135.00
Media Agua cu.m 3.00
2.01 Portland Cement bag 27.00 218.00 65.40 5,886.00 1,765.80
2.02 Crushed Gravel 3/4" cu.m 3.00 980.00 294.00 2,940.00 882.00
2.03 Washed Sand cu.m 1.50 900.00 270.00 1,350.00 405.00
Sub-total
3.00 Rebar Works
Column Footing kg 2,261.15
Tie beams kg 3,732.83
Wall Footing kg 59.14
Columns kg 9,017.93
Beams and Girders kg 6,512.45
Suspended Slab kg 3,132.61
Roof Beams kg 1,710.86
Stairs kg 553.28
Slab on Grade kg 902.33
Ramp on Fill kg 42.09
Media Agua kg 221.80
3.01 Deformed Round Bars, Grade 40 kg 28,146.46 40.10 12.03 1,128,673.22 338,601.97
3.02 G.I. Tie Wire kg 563.00 60.00 18.00 33,780.00 10,134.00
Sub-total
4.00 Formworks
Tie beams sq.m 161.85
4.01 Coco Lumber bd.ft 1,781.00 16.00 5.76 28,496.00 10,258.56
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 42.00 580.00 194.40 24,360.00 8,164.80
4.04 CWN, Assorted kg 25.00 60.00 21.60 1,500.00 540.00
Columns sq.m 302.31
4.01 Coco Lumber bd.ft 5,140.00 16.00 5.76 82,240.00 29,606.40
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 78.00 580.00 194.40 45,240.00 15,163.20
4.04 CWN, Assorted kg 72.00 60.00 21.60 4,320.00 1,555.20
Beams and Girders sq.m 343.20
4.01 Coco Lumber bd.ft 5,835.00 16.00 5.76 93,360.00 33,609.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 89.00 580.00 194.40 51,620.00 17,301.60
4.04 CWN, Assorted kg 82.00 60.00 21.60 4,920.00 1,771.20
Suspended Slab sq.m 381.38
4.01 Coco Lumber bd.ft 6,484.00 16.00 5.76 103,744.00 37,347.84
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 98.00 580.00 194.40 56,840.00 19,051.20
4.04 CWN, Assorted kg 91.00 60.00 21.60 5,460.00 1,965.60
Roof Beams sq.m 132.90
4.01 Coco Lumber bd.ft 2,260.00 16.00 5.76 36,160.00 13,017.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 35.00 580.00 194.40 20,300.00 6,804.00
4.04 CWN, Assorted kg 32.00 60.00 21.60 1,920.00 691.20
Stairs sq.m 28.60
4.01 Coco Lumber bd.ft 487.00 16.00 5.76 7,792.00 2,805.12
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 10.00 580.00 194.40 5,800.00 1,944.00

e. rodriguez es 48 of 179
UNIT COST TOTAL COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
4.04 CWN, Assorted kg 7.00 60.00 21.60 420.00 151.20
Media Agua sq.m 27.00
4.01 Coco Lumber bd.ft 345.00 16.00 5.76 5,520.00 1,987.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 10.00 580.00 194.40 5,800.00 1,944.00
4.04 CWN, Assorted kg 5.00 60.00 21.60 300.00 108.00
Sub-total
5.00 Masonry Works
Masonry Wall sq.m 635.32
5.05 CHB 6" thk pc 7,942.00 12.00 3.60 95,304.00 28,591.20
5.02 Portland Cement bag 318.00 218.00 65.40 69,324.00 20,797.20
5.03 Washed Sand cu.m 28.00 900.00 270.00 25,200.00 7,560.00
5.06 10mm x 6m RSB kg 842.00 40.10 12.03 33,764.20 10,129.26
5.07 G.I. Tie Wire kg 17.00 60.00 18.00 1,020.00 306.00
Plastering sq.m 1,270.63
5.02 Portland Cement bag 420.00 218.00 65.40 91,560.00 27,468.00
5.03 Washed Sand cu.m 42.00 900.00 270.00 37,800.00 11,340.00
Floor Topping sq.m 381.38
5.02 Portland Cement bag 252.00 218.00 65.40 54,936.00 16,480.80
5.03 Washed Sand cu.m 26.00 900.00 270.00 23,400.00 7,020.00
Sub-total
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm
6.03 Wooden Jamb complete with Accessories set 12.00 7,317.50 1,463.50 87,810.00 17,562.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 2.00 4,167.50 833.50 8,335.00 1,667.00
(lever type door knob)

D-3 Flush Door 0.80m x 1.8m on 150mm


6.05 set 1.00 3,567.50 713.50 3,567.50 713.50
Wooden Jamb complete with Accessories

D-4 Cubicle Door 0.60m x 1.20m on 150mm


6.06 set 2.00 3,408.75 681.75 6,817.50 1,363.50
Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type Silver
6.07 Colored Frame and Fixed Clear Glass set 14.00 8,444.00 1,688.80 118,216.00 23,643.20
Transom on 50 x 150 mm Wooden Jamb
complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type Silver
6.08 Colored Frame and Fixed Clear Glass set 12.00 4,672.00 934.40 56,064.00 11,212.80
Transom on 50 x 150 mm Wooden Jamb
complete with Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type Silver
6.09 Colored Frame and Fixed Clear Glass set 1.00 4,248.00 849.60 4,248.00 849.60
Transom on 50 x 150 mm Wooden Jamb
complete with Accessories

6.26 Security Grilles - 2.60 x 1.60m set 14.00 4,027.94 1,812.58 56,391.23 25,376.05
6.26 Security Grilles - 1.50 x 1.60m set 12.00 2,323.81 1,045.72 27,885.77 12,548.60
6.26 Security Grilles - 0.70 x 2.60m set 1.00 1,762.23 793.00 1,762.23 793.00
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,302.91 32.00 9.60 41,693.18 12,507.96
7.14 L 50 x 50 x 6mm kg 1,544.83 32.00 9.60 49,434.62 14,830.39

e. rodriguez es 49 of 179
UNIT COST TOTAL COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
7.07 LC 150 x 65 x 20 x 2.0mm kg 2,274.29 43.00 12.90 97,794.47 29,338.34
7.18 Plain Round Bar 10mmØ x 6m pc 10.00 107.00 32.10 1,070.00 321.00
7.19 Plain Round Bar 12mmØ x 6m pc 12.00 185.00 55.50 2,220.00 666.00
7.30 Turn Buckle 12 mmØ pc 6.00 60.00 18.00 360.00 108.00
Anchor Bolt with Nuts and Washer,
7.34 pc 72.00 27.00 8.10 1,944.00 583.20
12mmØ x 50mm x 300mm
Anchor Bolt with Nuts and Washer,
7.35 pc 72.00 12.00 3.60 864.00 259.20
10mmØ x 50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 1.50 9,300.00 2,790.00 13,950.00 4,185.00
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 3.00 5,390.00 1,617.00 16,170.00 4,851.00
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 7.00 1,069.00 320.70 7,483.00 2,244.90
7.45 G.I. Pipe 2"Ø Sch.40 pc 17.00 1,781.00 534.30 30,277.00 9,083.10
7.23 Square Bar 19mm□ x 6m pc 18.00 620.00 186.00 11,160.00 3,348.00
7.46 Welding Rod kg 103.00 67.00 20.10 6,901.00 2,070.30
13.12 Primer, Zinc Chromate gal 6.00 537.00 161.10 3,222.00 966.60
FIRE SCAPE LADDER
7.14 6x50x200mm I-beam (Post & Girder) kg 177.43 32.00 9.60 5,677.68 1,703.30
6mm thk. Chekered Steel Plate shts 7.00 6,000.00 1,800.00 42,000.00 12,600.00
7.14 3mmx50x150mm square tubing kg 265.90 32.00 9.60 8,508.75 2,552.62
7.14 6mm thk. 38x38mm angle bar (frame) kg 195.29 32.00 9.60 6,249.39 1,874.82
7.14 6mm thk. 50x508mm angle bar (stringer) kg 143.14 32.00 9.60 4,580.48 1,374.14
7.45 2" dia. G.I. Pipe (Railings) pc 6.00 1,781.00 534.30 10,686.00 3,205.80
7.14 20x20mm square bar (Railings) kg 695.20 32.00 9.60 22,246.27 6,673.88
Anchor Bolt with Nuts and Washer,
7.33 pc 100.00 45.00 13.50 4,500.00 1,350.00
16mmØ x 50mm x 300mm
7.46 Welding Rod kg 30.00 67.00 20.10 2,010.00 603.00
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted,
8.16 m 302.40 380.00 83.60 114,912.00 25,280.64
1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.610m x
8.22 pc 22.00 415.00 0.00 9,130.00 0.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x
8.19 pc 12.00 560.00 0.00 6,720.00 0.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x
8.17 pc 11.00 560.00 0.00 6,160.00 0.00
2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 2,419.20 1.80 0.00 4,354.56 0.00
8.36 Roof Sealant L 6.00 299.75 0.00 1,798.50 0.00
8.37 Blind Rivets pc 450.00 1.35 0.00 607.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 213.75
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 935.00 38.00 11.40 35,530.00 10,659.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 72.00 350.00 105.00 25,200.00 7,560.00
9.22 Finishing Nails kg 4.00 70.00 21.00 280.00 84.00
9.23 Common Wire Nails kg 17.00 50.00 15.00 850.00 255.00
9.24 Concrete Nails kg 4.00 70.00 21.00 280.00 84.00
9.42 Wood Preservative, Brown L 7.00 900.00 270.00 6,300.00 1,890.00
Exterior ceiling sq.m 60.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 263.00 38.00 11.40 9,994.00 2,998.20
9.06 Plywood, Marine 1/4" x 4' x 8' pc 21.00 360.00 108.00 7,560.00 2,268.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 16.00 245.00 73.50 3,920.00 1,176.00
9.16 Fascia Board, Wooden bd.ft 250.92 36.00 10.80 9,033.12 2,709.94

e. rodriguez es 50 of 179
UNIT COST TOTAL COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Blackboards sq.m 34.56
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 220.00 38.00 11.40 8,360.00 2,508.00
9.43 Lawanit, 1/4" thk pc 12.00 280.00 84.00 3,360.00 1,008.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 4.00 50.00 15.00 200.00 60.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 154.00 50.00 15.00 7,700.00 2,310.00
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00 52.50
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00 10.50
10.16 Junction Box, 4" x 4" G.I. pc 46.00 15.00 4.50 690.00 207.00
10.17 Utility Box, 2" x 4" G.I. pc 47.00 30.00 4.28 1,410.00 200.93
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 1,593.90 33.00 7.02 52,598.70 11,189.18
10.14 14.0 mm2 THW Wire, Stranded m 10.00 84.50 25.35 845.00 253.50
10.28 Duplex C.O. with Plate pc 15.00 263.80 21.00 3,957.00 315.00
10.23 Single Switch with Plate pc 4.00 97.68 13.46 390.72 53.85
10.24 2-Gang Switch with Plate pc 7.00 153.00 21.53 1,071.00 150.68
10.25 3-Gang Switch with Plate pc 3.00 208.00 29.59 624.00 88.76
10.20 FL 2 x 40W Industrial Type set 35.00 840.00 126.00 29,400.00 4,410.00
10.53 Incandescent Bulb 50W set 3.00 35.00 5.25 105.00 15.75
10.33 Ceiling Receptacle 3-1/2"Ø pc 3.00 25.00 3.75 75.00 11.25
10.50 Panel Box, Flush Type, 12 Branches set 1.00 2,530.75 379.61 2,530.75 379.61
10.43 Circuit Breaker, 100A 2P set 1.00 650.00 97.50 650.00 97.50
10.38 Circuit Breaker, 20A 2P set 11.00 313.00 46.95 3,443.00 516.45
10.58 Electrical Tape pc 6.00 37.50 5.63 225.00 33.75
10.54 Vibrating Bell 8" set 3.00 1,500.00 225.00 4,500.00 675.00
10.55 Fire Alarm Bell, Vibrating Type set 3.00 2,000.00 300.00 6,000.00 900.00
10.56 Fire Alarm Station, Manual Single Action set 3.00 1,750.00 262.50 5,250.00 787.50
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 3.00 5,500.00 825.00 16,500.00 2,475.00
11.64 Concrete Counter Sink Type, with Lever Type set 1.00 3,150.00 472.50 3,150.00 472.50
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 5.00 160.00 24.00 800.00 120.00
11.61 Water Closet Flange set 3.00 262.50 39.38 787.50 118.13
11.67 Tissue Holder pc 2.00 250.00 37.50 500.00 75.00
11.05 PP-R Pipe 3/4"Ø pc 5.00 345.00 103.50 1,725.00 517.50
11.09 PP-R Coupling, 3/4"Ø pc 4.00 15.00 4.50 60.00 18.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 1.00 11.00 3.30 11.00 3.30
11.06 PP-R Pipe 1/2"Ø pc 3.00 217.00 65.10 651.00 195.30
11.21 PP-R Elbow 90o x 1/2"Ø pc 9.00 14.00 4.20 126.00 37.80
11.08 PP-R Coupling, 1/2"Ø pc 1.00 9.00 2.70 9.00 2.70
11.15 PP-R Tee, 1/2"Ø pc 6.00 17.00 5.10 102.00 30.60
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 1.00 250.00 75.00 250.00 75.00
11.65 S.S.Floor Drain 4' x 4" pc 8.00 97.50 14.63 780.00 117.00
11.68 S.S. Grab Rail 1-1/2"Ø set 1.00 5,000.00 435.00 5,000.00 435.00
11.66 Teflon Tape roll 9.00 12.00 1.80 108.00 16.20
11.69 Mirror sq.ft 24.00 100.00 15.00 2,400.00 360.00
Sub-total
12.00 Sanitary Works

e. rodriguez es 51 of 179
UNIT COST TOTAL COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
12.01 Catch Basin unit 6.00 1,500.00 450.00 9,000.00 2,700.00
12.02 Concrete Pipe 150mmØ pc 44.00 200.00 60.00 8,800.00 2,640.00
12.32 Three Chamber Septic Vault unit 1.00 42,879.00 14,039.42 42,879.00 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 26.00 560.00 168.00 14,560.00 4,368.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 1.00 82.50 24.75 82.50 24.75
12.13 uPVC Elbow 90o x 4"Ø pc 4.00 96.00 28.80 384.00 115.20
12.27 uPVC Wye 4" x 4" pc 4.00 165.00 49.50 660.00 198.00
12.21 uPVC Tee 4" x 4" pc 3.00 138.00 41.40 414.00 124.20
12.25 uPVC Wye 4" x 2" pc 10.00 97.00 29.10 970.00 291.00
12.29 Brass Cleanout 6" x 6" pc 6.00 675.00 202.50 4,050.00 1,215.00
12.28 Brass Cleanout 4" x 4" pc 2.00 350.00 105.00 700.00 210.00
12.11 uPVC Elbow 90o x 2"Ø pc 10.00 25.00 7.50 250.00 75.00
12.07 uPVC Sanitary Pipe 2"Ø pc 10.00 210.00 63.00 2,100.00 630.00
12.22 uPVC Wye 2" x 2" pc 4.00 38.00 11.40 152.00 45.60
12.17 uPVC Tee 2" x 2" pc 4.00 36.00 10.80 144.00 43.20
12.30 uPVC P-Trap 2" pc 2.00 66.00 19.80 132.00 39.60
12.08 uPVC Sanitary Pipe 3"Ø pc 20.00 420.00 126.00 8,400.00 2,520.00
12.12 uPVC Elbow 90o x 3"Ø pc 15.00 53.00 15.90 795.00 238.50
12.33 PVC Cement can 6.00 150.00 45.00 900.00 270.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 2,334.86
13.18 Neutralizer gal 30.00 132.00 39.60 3,960.00 1,188.00
13.01 Latex, Flat gal 117.00 424.00 127.20 49,608.00 14,882.40
13.14 Masonry Putty gal 117.00 319.00 95.70 37,323.00 11,196.90
13.02 Latex, Semi Gloss gal 117.00 492.50 147.75 57,622.50 17,286.75
13.20 Acri Color qrt 30.00 165.00 49.50 4,950.00 1,485.00
Wood surfaces sq.m 553.91
13.04 Enamel, Flatwall gal 28.00 483.00 144.90 13,524.00 4,057.20
13.15 Glazing Putty gal 28.00 492.00 147.60 13,776.00 4,132.80
13.05 Enamel, Semi Gloss gal 28.00 497.00 149.10 13,916.00 4,174.80
13.16 Paint Thinner gal 21.00 260.00 78.00 5,460.00 1,638.00
Sub-total
14.00 Tile Works
Wall sq.m 32.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 880.00 14.00 4.20 12,320.00 3,696.00
14.16 Tile Adhesive 25 kg/bag bag 6.00 224.10 67.23 1,344.60 403.38
14.13 Tile Trim 6mm pc 16.00 97.75 29.33 1,564.00 469.20
14.15 Tile Grout 5 kg/bag bag 3.00 150.00 45.00 450.00 135.00
14.15 Flooring sq.m 19.50
14.01 Unglazed Floor Tiles 20cm x 20cm pc 537.00 12.00 3.60 6,444.00 1,933.20
14.16 Tile Adhesive 25 kg/bag bag 4.00 224.10 67.23 896.40 268.92
14.15 Tile Grout 5 kg/bag bag 2.00 150.00 45.00 300.00 90.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

e. rodriguez es 52 of 179
UNIT COST TOTAL COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR

OLIVER R. HERNAND
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

e. rodriguez es 53 of 179
epublic of the Philippines
RTMENT OF EDUCATION
AND SCHOOLS ENGINEERING DIVISION
Pasig City

X-CLASSROOM

GRAND TOTAL

57,397.25

34,438.35
91,835.60

4,275.00
33,587.40
9,464.21
34,387.03
39,407.52
4,584.94
125,706.10

78,501.80
39,175.50
18,135.00

47,894.60
23,887.50
11,115.00

5,101.20
2,548.00
1,170.00

69,999.80
35,035.00
16,087.50

75,951.20
37,901.50
17,550.00

97,489.60
48,730.50
22,522.50

27,773.20
14,014.00
6,435.00

e. rodriguez es 54 of 179
GRAND TOTAL

24,939.20
12,421.50
5,850.00

54,696.20
27,391.00
12,577.50

2,550.60
1,274.00
585.00

7,651.80
3,822.00
1,755.00
852,532.20

1,467,275.19
43,914.00
1,511,189.19

38,754.56
32,524.80
2,040.00

111,846.40
60,403.20
5,875.20

126,969.60
68,921.60
6,691.20

141,091.84
75,891.20
7,425.60

49,177.60
27,104.00
2,611.20

10,597.12
7,744.00

e. rodriguez es 55 of 179
GRAND TOTAL

571.20

7,507.20
7,744.00
408.00
791,899.52

123,895.20
90,121.20
32,760.00
43,893.46
1,326.00

119,028.00
49,140.00

71,416.80
30,420.00
562,000.66

105,372.00

10,002.00

4,281.00

8,181.00

141,859.20

67,276.80

5,097.60

81,767.28
40,434.37
2,555.23
466,826.48

54,201.14
64,265.01

e. rodriguez es 56 of 179
GRAND TOTAL

127,132.81
1,391.00
2,886.00
468.00

2,527.20

1,123.20

18,135.00
21,021.00
9,727.90
39,360.10
14,508.00
8,971.30
4,188.60

7,380.99
54,600.00
11,061.37
8,124.20
5,954.62
13,891.80
28,920.15

5,850.00

2,613.00
508,302.40

140,192.64

9,130.00

6,720.00

6,160.00

4,354.56
1,798.50
607.50
168,963.20

46,189.00
32,760.00
364.00
1,105.00
364.00
8,190.00

12,992.20
9,828.00
182.00
325.00
182.00
2,340.00
5,096.00
11,743.06

e. rodriguez es 57 of 179
GRAND TOTAL

10,868.00
4,368.00
91.00
260.00
91.00
147,338.26

10,010.00
227.50
80.50
897.00
1,610.93
172.50

63,787.88
1,098.50
4,272.00
444.57
1,221.68
712.76
33,810.00
120.75
86.25
2,910.36
747.50
3,959.45
258.75
5,175.00
6,900.00
6,037.50
6,325.00
150,866.37

18,975.00
3,622.50
920.00
905.63
575.00
2,242.50
78.00
14.30
846.30
163.80
11.70
132.60
416.00
325.00
897.00
5,435.00
124.20
2,760.00
38,444.53

e. rodriguez es 58 of 179
GRAND TOTAL

11,700.00
11,440.00
56,918.42
18,928.00
107.25
499.20
858.00
538.20
1,261.00
5,265.00
910.00
325.00
2,730.00
197.60
187.20
171.60
10,920.00
1,033.50
1,170.00
125,159.97

5,148.00
64,490.40
48,519.90
74,909.25
6,435.00

17,581.20
17,908.80
18,090.80
7,098.00
260,181.35

16,016.00
1,747.98
2,033.20
585.00

8,377.20
1,165.32
390.00
30,314.70

5,831,560.51
1,107,996.50
832,746.84
7,772,303.85
77,723.04
PhP7,850,026.89
PhP7,851,000.00

e. rodriguez es 59 of 179
GRAND TOTAL

OLIVER R. HERNANDEZ
Chief, PFSED

e. rodriguez es 60 of 179
Three-Storey Nine (9) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED THREE STOREY NINE (9) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 47,977.56 34,739.43 47,977.56 34,739.43
Billboard
Safety and Health lot 1.00 47,977.56 0.00 47,977.56 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 342.00 0.00 20.00 0.00 6,840.00
1.02 Structural Excavation cu.m 253.32 0.00 200.00 0.00 50,664.60
1.03 Backfilling and Compaction cu.m 335.45 0.00 45.00 0.00 15,095.16
1.06 Select Fill cu.m 282.15 150.00 45.00 42,322.50 12,696.75
1.04 Gravel Bedding G-1 cu.m 53.30 980.00 180.00 52,232.04 9,593.64
1.05 Soil Poisoning sq.m 376.20 15.00 4.50 5,643.00 1,692.90
Sub-total
2.00 Concreting Works
Column Footing cu.m 46.10
2.01 Portland Cement bag 415.00 218.00 65.40 90,470.00 27,141.00
2.05 Crushed Gravel 1" cu.m 46.25 980.00 294.00 45,325.00 13,597.50
2.03 Washed Sand cu.m 23.25 900.00 270.00 20,925.00 6,277.50
Tie beams cu.m 37.73
2.01 Portland Cement bag 340.00 218.00 65.40 74,120.00 22,236.00
2.02 Crushed Gravel 3/4" cu.m 37.75 980.00 294.00 36,995.00 11,098.50
2.03 Washed Sand cu.m 19.00 900.00 270.00 17,100.00 5,130.00
Wall Footing cu.m 4.00
2.01 Portland Cement bag 36.00 218.00 65.40 7,848.00 2,354.40
2.05 Crushed Gravel 1" cu.m 4.00 980.00 294.00 3,920.00 1,176.00
2.03 Washed Sand cu.m 2.00 900.00 270.00 1,800.00 540.00
Columns cu.m 40.84
2.01 Portland Cement bag 368.00 218.00 65.40 80,224.00 24,067.20
2.02 Crushed Gravel 3/4" cu.m 41.00 980.00 294.00 40,180.00 12,054.00
2.03 Washed Sand cu.m 20.50 900.00 270.00 18,450.00 5,535.00
Beams and Girders cu.m 46.11
2.01 Portland Cement bag 415.00 218.00 65.40 90,470.00 27,141.00
2.02 Crushed Gravel 3/4" cu.m 46.25 980.00 294.00 45,325.00 13,597.50
2.03 Washed Sand cu.m 23.25 900.00 270.00 20,925.00 6,277.50
Suspended Slab cu.m 59.18
2.01 Portland Cement bag 533.00 218.00 65.40 116,194.00 34,858.20
2.02 Crushed Gravel 3/4" cu.m 59.25 980.00 294.00 58,065.00 17,419.50
2.03 Washed Sand cu.m 29.75 900.00 270.00 26,775.00 8,032.50
Roof Beams cu.m 16.74
2.01 Portland Cement bag 151.00 218.00 65.40 32,918.00 9,875.40
2.02 Crushed Gravel 3/4" cu.m 16.75 980.00 294.00 16,415.00 4,924.50
2.03 Washed Sand cu.m 8.50 900.00 270.00 7,650.00 2,295.00
Stairs cu.m 19.44
2.01 Portland Cement bag 175.00 218.00 65.40 38,150.00 11,445.00
2.02 Crushed Gravel 3/4" cu.m 19.50 980.00 294.00 19,110.00 5,733.00
2.03 Washed Sand cu.m 9.75 900.00 270.00 8,775.00 2,632.50
Slab on Grade cu.m 34.20
2.01 Portland Cement bag 308.00 218.00 65.40 67,144.00 20,143.20

3Sty9CL Schoolbuilding 61 of 179


Three-Storey Nine (9) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
2.05 Crushed Gravel 1" cu.m 34.25 980.00 294.00 33,565.00 10,069.50
2.03 Washed Sand cu.m 17.25 900.00 270.00 15,525.00 4,657.50
Ramp on Fill cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 65.40 3,924.00 1,177.20
2.05 Crushed Gravel 1" cu.m 2.00 980.00 294.00 1,960.00 588.00
2.03 Washed Sand cu.m 1.00 900.00 270.00 900.00 270.00
Media Agua cu.m 4.80
2.01 Portland Cement bag 44.00 218.00 65.40 9,592.00 2,877.60
2.02 Crushed Gravel 3/4" cu.m 5.00 980.00 294.00 4,900.00 1,470.00
2.03 Washed Sand cu.m 2.50 900.00 270.00 2,250.00 675.00
Sub-total
3.00 Rebar Works
Column Footing kg 3,391.72
Tie beams kg 5,775.83
Wall Footing kg 118.28
Columns kg 13,482.12
Beams and Girders kg 10,015.18
Suspended Slab kg 4,849.85
Roof Beams kg 2,651.37
Stairs kg 1,106.56
Slab on Grade kg 1,443.74
Ramp on Fill kg 84.17
Media Agua kg 354.88
3.01 Deformed Round Bars, Grade 40 kg 43,273.69 40.10 12.03 1,735,275.02 520,582.50
3.02 G.I. Tie Wire kg 866.00 60.00 18.00 51,960.00 15,588.00
Sub-total
4.00 Formworks
Tie beams sq.m 251.55
4.01 Coco Lumber bd.ft 2,768.00 16.00 5.76 44,288.00 15,943.68
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 65.00 580.00 194.40 37,700.00 12,636.00
4.04 CWN, Assorted kg 39.00 60.00 21.60 2,340.00 842.40
Columns sq.m 460.67
4.01 Coco Lumber bd.ft 7,832.00 16.00 5.76 125,312.00 45,112.32
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 119.00 580.00 194.40 69,020.00 23,133.60
4.04 CWN, Assorted kg 110.00 60.00 21.60 6,600.00 2,376.00
Beams and Girders sq.m 532.50
4.01 Coco Lumber bd.ft 9,053.00 16.00 5.76 144,848.00 52,145.28
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 137.00 580.00 194.40 79,460.00 26,632.80
4.04 CWN, Assorted kg 127.00 60.00 21.60 7,620.00 2,743.20
Suspended Slab sq.m 591.75
4.01 Coco Lumber bd.ft 10,060.00 16.00 5.76 160,960.00 57,945.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 152.00 580.00 194.40 88,160.00 29,548.80
4.04 CWN, Assorted kg 141.00 60.00 21.60 8,460.00 3,045.60
Roof Beams sq.m 132.90
4.01 Coco Lumber bd.ft 2,260.00 16.00 5.76 36,160.00 13,017.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 35.00 580.00 194.40 20,300.00 6,804.00
4.04 CWN, Assorted kg 32.00 60.00 21.60 1,920.00 691.20
Stairs sq.m 57.20
4.01 Coco Lumber bd.ft 973.00 16.00 5.76 15,568.00 5,604.48
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 20.00 580.00 194.40 11,600.00 3,888.00
4.04 CWN, Assorted kg 14.00 60.00 21.60 840.00 302.40
Media Agua sq.m 43.20
4.01 Coco Lumber bd.ft 551.00 16.00 5.76 8,816.00 3,173.76
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 15.00 580.00 194.40 8,700.00 2,916.00
4.04 CWN, Assorted kg 8.00 60.00 21.60 480.00 172.80
Sub-total

3Sty9CL Schoolbuilding 62 of 179


Three-Storey Nine (9) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
5.00 Masonry Works
Masonry Wall sq.m 982.94
5.05 CHB 6" thk pc 12,287.00 12.00 3.60 147,444.00 44,233.20
5.02 Portland Cement bag 492.00 218.00 65.40 107,256.00 32,176.80
5.03 Washed Sand cu.m 42.00 900.00 270.00 37,800.00 11,340.00
5.06 10mm x 6m RSB kg 1,302.00 40.10 12.03 52,210.20 15,663.06
5.07 G.I. Tie Wire kg 27.00 60.00 18.00 1,620.00 486.00
Plastering sq.m 1,965.88
5.02 Portland Cement bag 649.00 218.00 65.40 141,482.00 42,444.60
5.03 Washed Sand cu.m 65.00 900.00 270.00 58,500.00 17,550.00
Floor Topping sq.m 591.75
5.02 Portland Cement bag 391.00 218.00 65.40 85,238.00 25,571.40
5.03 Washed Sand cu.m 40.00 900.00 270.00 36,000.00 10,800.00
Sub-total
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm
6.03 Wooden Jamb complete with Accessories set 18.00 7,317.50 1,463.50 131,715.00 26,343.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 2.00 4,167.50 833.50 8,335.00 1,667.00
(lever type door knob)

D-3 Flush Door 0.70m x 2.10m on 150mm


6.05 set 4.00 3,567.50 713.50 14,270.00 2,854.00
Wooden Jamb complete with Accessories

D-4 Cubicle Door 0.60m x 1.20m on


6.06 150mm Wooden Jamb complete with set 3.00 3,408.75 681.75 10,226.25 2,045.25
Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type
6.07 Silver Colored Frame and Fixed Clear set 22.00 8,444.00 1,688.80 185,768.00 37,153.60
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type
6.08 Silver Colored Frame and Fixed Clear set 18.00 4,672.00 934.40 84,096.00 16,819.20
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type
6.09 Silver Colored Frame and Fixed Clear set 2.00 4,248.00 849.60 8,496.00 1,699.20
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

6.26 Security Grilles - 2.60 x 1.60m set 22.00 4,027.94 1,812.58 88,614.79 39,876.66
6.26 Security Grilles - 1.50 x 1.60m set 18.00 2,323.81 1,045.72 41,828.66 18,822.90
6.26 Security Grilles - 0.70 x 2.60m set 2.00 1,762.23 793.00 3,524.45 1,586.00
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,954.37 32.00 9.60 62,539.78 18,761.93
7.14 L 50 x 50 x 6mm kg 2,317.25 32.00 9.60 74,151.94 22,245.58
7.07 LC 150 x 65 x 20 x 2.0mm kg 4,001.60 43.00 12.90 172,068.74 51,620.62
7.18 Plain Round Bar 10mmØ x 6m pc 16.00 107.00 32.10 1,712.00 513.60
7.19 Plain Round Bar 12mmØ x 6m pc 16.00 185.00 55.50 2,960.00 888.00
7.30 Turn Buckle 12 mmØ pc 8.00 60.00 18.00 480.00 144.00

3Sty9CL Schoolbuilding 63 of 179


Three-Storey Nine (9) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Anchor Bolt with Nuts and Washer, 12mmØ
7.34 pc 108.00 27.00 8.10 2,916.00 874.80
x 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ
7.35 pc 108.00 12.00 3.60 1,296.00 388.80
x 50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 2.25 9,300.00 2,790.00 20,925.00 6,277.50
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 4.50 5,390.00 1,617.00 24,255.00 7,276.50
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 14.00 1,069.00 320.70 14,966.00 4,489.80
7.45 G.I. Pipe 2"Ø Sch.40 pc 23.00 1,781.00 534.30 40,963.00 12,288.90
7.23 Square Bar 19mm□ x 6m pc 45.00 620.00 186.00 27,900.00 8,370.00
7.46 Welding Rod kg 166.00 67.00 20.10 11,122.00 3,336.60
13.12 Primer, Zinc Chromate gal 9.00 537.00 161.10 4,833.00 1,449.90
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-
8.16 m 516.60 380.00 83.60 196,308.00 43,187.76
Painted, 1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.610m x
8.22 pc 34.00 415.00 0.00 14,110.00 0.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x
8.19 pc 12.00 560.00 0.00 6,720.00 0.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m
8.17 pc 17.00 560.00 0.00 9,520.00 0.00
x 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 4,132.80 1.80 0.00 7,439.04 0.00
8.36 Roof Sealant L 6.00 299.75 0.00 1,798.50 0.00
8.37 Blind Rivets pc 630.00 1.35 0.00 850.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 342.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 1,495.00 38.00 11.40 56,810.00 17,043.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 116.00 350.00 105.00 40,600.00 12,180.00
9.22 Finishing Nails kg 7.00 70.00 21.00 490.00 147.00
9.23 Common Wire Nails kg 27.00 50.00 15.00 1,350.00 405.00
9.24 Concrete Nails kg 7.00 70.00 21.00 490.00 147.00
9.42 Wood Preservative, Brown L 11.00 900.00 270.00 9,900.00 2,970.00
Exterior ceiling sq.m 87.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 381.00 38.00 11.40 14,478.00 4,343.40
9.06 Plywood, Marine 1/4" x 4' x 8' pc 30.00 360.00 108.00 10,800.00 3,240.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 7.00 50.00 15.00 350.00 105.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 16.00 245.00 73.50 3,920.00 1,176.00
9.16 Fascia Board, Wooden bd.ft 339.48 36.00 10.80 12,221.28 3,666.38
Blackboards sq.m 51.84
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 330.00 38.00 11.40 12,540.00 3,762.00
9.43 Lawanit, 1/4" thk pc 18.00 280.00 84.00 5,040.00 1,512.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 6.00 50.00 15.00 300.00 90.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 230.00 50.00 15.00 11,500.00 3,450.00
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00 52.50
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00 10.50
10.16 Junction Box, 4" x 4" G.I. pc 70.00 15.00 4.50 1,050.00 315.00
10.17 Utility Box, 2" x 4" G.I. pc 67.00 30.00 4.28 2,010.00 286.43

3Sty9CL Schoolbuilding 64 of 179


Three-Storey Nine (9) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 2,380.50 33.00 7.02 78,556.50 16,711.11
10.14 14.0 mm2 THW Wire, Stranded m 10.00 84.50 25.35 845.00 253.50
10.28 Duplex C.O. with Plate pc 27.00 263.80 21.00 7,122.60 567.00
10.23 Single Switch with Plate pc 8.00 97.68 13.46 781.44 107.70
10.24 2-Gang Switch with Plate pc 15.00 153.00 21.53 2,295.00 322.88
10.25 3-Gang Switch with Plate pc 3.00 208.00 29.59 624.00 88.76
10.20 FL 2 x 40W Industrial Type set 55.00 840.00 126.00 46,200.00 6,930.00
10.53 Incandescent Bulb 50W set 6.00 35.00 5.25 210.00 31.50
10.33 Ceiling Receptacle 3-1/2"Ø pc 6.00 25.00 3.75 150.00 22.50
10.50 Panel Box, Flush Type, 12 Branches set 1.00 2,530.75 379.61 2,530.75 379.61
10.43 Circuit Breaker, 100A 2P set 1.00 650.00 97.50 650.00 97.50
10.38 Circuit Breaker, 20A 2P set 11.00 313.00 46.95 3,443.00 516.45
10.58 Electrical Tape pc 9.00 37.50 5.63 337.50 50.63
10.54 Vibrating Bell 8" set 3.00 1,500.00 225.00 4,500.00 675.00
10.55 Fire Alarm Bell, Vibrating Type set 3.00 2,000.00 300.00 6,000.00 900.00

10.56 Fire Alarm Station, Manual Single Action set 3.00 1,750.00 262.50 5,250.00 787.50

10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 5.00 5,500.00 825.00 27,500.00 4,125.00
11.64 Concrete Counter Sink Type, with Lever Ty set 2.00 3,150.00 472.50 6,300.00 945.00
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 9.00 160.00 24.00 1,440.00 216.00
11.61 Water Closet Flange set 5.00 262.50 39.38 1,312.50 196.88
11.67 Tissue Holder pc 4.00 250.00 37.50 1,000.00 150.00
11.05 PP-R Pipe 3/4"Ø pc 10.00 345.00 103.50 3,450.00 1,035.00
11.09 PP-R Coupling, 3/4"Ø pc 8.00 15.00 4.50 120.00 36.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 11.00 3.30 22.00 6.60
11.06 PP-R Pipe 1/2"Ø pc 6.00 217.00 65.10 1,302.00 390.60
11.21 PP-R Elbow 90o x 1/2"Ø pc 17.00 14.00 4.20 238.00 71.40
11.08 PP-R Coupling, 1/2"Ø pc 2.00 9.00 2.70 18.00 5.40
11.15 PP-R Tee, 1/2"Ø pc 12.00 17.00 5.10 204.00 61.20
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 16.00 84.97 25.49 1,359.52 407.86
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 2.00 250.00 75.00 500.00 150.00
11.65 S.S.Floor Drain 4' x 4" pc 14.00 97.50 14.63 1,365.00 204.75
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00 870.00
11.66 Teflon Tape roll 18.00 12.00 1.80 216.00 32.40
11.69 Mirror sq.ft 48.00 100.00 15.00 4,800.00 720.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 10.00 1,500.00 450.00 15,000.00 4,500.00
12.02 Concrete Pipe 150mmØ pc 88.00 200.00 60.00 17,600.00 5,280.00
12.32 Three Chamber Septic Vault unit 1.00 42,879.00 14,039.42 42,879.00 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 20.00 560.00 168.00 11,200.00 3,360.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 2.00 82.50 24.75 165.00 49.50
12.13 uPVC Elbow 90o x 4"Ø pc 8.00 96.00 28.80 768.00 230.40
12.27 uPVC Wye 4" x 4" pc 8.00 165.00 49.50 1,320.00 396.00
12.21 uPVC Tee 4" x 4" pc 6.00 138.00 41.40 828.00 248.40
12.25 uPVC Wye 4" x 2" pc 8.00 97.00 29.10 776.00 232.80
12.29 Brass Cleanout 6" x 6" pc 8.00 675.00 202.50 5,400.00 1,620.00
12.28 Brass Cleanout 4" x 4" pc 4.00 350.00 105.00 1,400.00 420.00
12.11 uPVC Elbow 90o x 2"Ø pc 20.00 25.00 7.50 500.00 150.00

3Sty9CL Schoolbuilding 65 of 179


Three-Storey Nine (9) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
12.07 uPVC Sanitary Pipe 2"Ø pc 20.00 210.00 63.00 4,200.00 1,260.00
12.22 uPVC Wye 2" x 2" pc 8.00 38.00 11.40 304.00 91.20
12.17 uPVC Tee 2" x 2" pc 8.00 36.00 10.80 288.00 86.40
12.30 uPVC P-Trap 2" pc 4.00 66.00 19.80 264.00 79.20
12.08 uPVC Sanitary Pipe 3"Ø pc 40.00 420.00 126.00 16,800.00 5,040.00
12.12 uPVC Elbow 90o x 3"Ø pc 30.00 53.00 15.90 1,590.00 477.00
12.33 PVC Cement can 9.00 150.00 45.00 1,350.00 405.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 3,553.76
13.18 Neutralizer gal 45.00 132.00 39.60 5,940.00 1,782.00
13.01 Latex, Flat gal 178.00 424.00 127.20 75,472.00 22,641.60
13.14 Masonry Putty gal 178.00 319.00 95.70 56,782.00 17,034.60
13.02 Latex, Semi Gloss gal 178.00 492.50 147.75 87,665.00 26,299.50
13.20 Acri Color qrt 45.00 165.00 49.50 7,425.00 2,227.50
Wood surfaces sq.m 863.80
13.04 Enamel, Flatwall gal 44.00 483.00 144.90 21,252.00 6,375.60
13.15 Glazing Putty gal 44.00 492.00 147.60 21,648.00 6,494.40
13.05 Enamel, Semi Gloss gal 44.00 497.00 149.10 21,868.00 6,560.40
13.16 Paint Thinner gal 33.00 260.00 78.00 8,580.00 2,574.00
Sub-total
14.00 Tile Works
Wall sq.m 64.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 1,760.00 14.00 4.20 24,640.00 7,392.00
14.16 Tile Adhesive 25 kg/bag bag 12.00 224.10 67.23 2,689.20 806.76
14.13 Tile Trim 6mm pc 16.00 97.75 29.33 1,564.00 469.20
14.15 Tile Grout 5 kg/bag bag 5.00 150.00 45.00 750.00 225.00
14.15 Flooring sq.m 39.00
14.01 Unglazed Floor Tiles 20cm x 20cm pc 1,073.00 12.00 3.60 12,876.00 3,862.80
14.16 Tile Adhesive 25 kg/bag bag 8.00 224.10 67.23 1,792.80 537.84
14.15 Tile Grout 5 kg/bag bag 3.00 150.00 45.00 450.00 135.00
Sub-total 0.40

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

3Sty9CL Schoolbuilding 66 of 179


Three-Storey Nine (9) Classroom

Republic of the Philippines


RTMENT OF EDUCATION
S AND SCHOOLS ENGINEERING DIVISION
Pasig City

CLASSROOM

GRAND TOTAL

82,716.99

47,977.56
130,694.56

6,840.00
50,664.60
15,095.16
55,019.25
61,825.68
7,335.90
196,780.59

117,611.00
58,922.50
27,202.50

96,356.00
48,093.50
22,230.00

10,202.40
5,096.00
2,340.00

104,291.20
52,234.00
23,985.00

117,611.00
58,922.50
27,202.50

151,052.20
75,484.50
34,807.50

42,793.40
21,339.50
9,945.00

49,595.00
24,843.00
11,407.50

87,287.20

3Sty9CL Schoolbuilding 67 of 179


Three-Storey Nine (9) Classroom

GRAND TOTAL

43,634.50
20,182.50

5,101.20
2,548.00
1,170.00

12,469.60
6,370.00
2,925.00
1,375,255.70

2,255,857.52
67,548.00
2,323,405.52

60,231.68
50,336.00
3,182.40

170,424.32
92,153.60
8,976.00

196,993.28
106,092.80
10,363.20

218,905.60
117,708.80
11,505.60

49,177.60
27,104.00
2,611.20

21,172.48
15,488.00
1,142.40

11,989.76
11,616.00
652.80
1,187,827.52

3Sty9CL Schoolbuilding 68 of 179


Three-Storey Nine (9) Classroom

GRAND TOTAL

191,677.20
139,432.80
49,140.00
67,873.26
2,106.00

183,926.60
76,050.00

110,809.40
46,800.00
867,815.26

158,058.00

10,002.00

17,124.00

12,271.50

222,921.60

100,915.20

10,195.20

128,491.44
60,651.56
5,110.46
725,740.96

81,301.71
96,397.52
223,689.37
2,225.60
3,848.00
624.00

3Sty9CL Schoolbuilding 69 of 179


Three-Storey Nine (9) Classroom

GRAND TOTAL

3,790.80

1,684.80

27,202.50
31,531.50
19,455.80
53,251.90
36,270.00
14,458.60
6,282.90
602,014.99

239,495.76

14,110.00

6,720.00

9,520.00

7,439.04
1,798.50
850.50
279,933.80

73,853.00
52,780.00
637.00
1,755.00
637.00
12,870.00

18,821.40
14,040.00
182.00
455.00
182.00
3,510.00
5,096.00
15,887.66

16,302.00
6,552.00
91.00
390.00
91.00
224,132.06

14,950.00
227.50
80.50
1,365.00
2,296.43

3Sty9CL Schoolbuilding 70 of 179


Three-Storey Nine (9) Classroom

GRAND TOTAL

172.50

95,267.61
1,098.50
7,689.60
889.14
2,617.88
712.76
53,130.00
241.50
172.50
2,910.36
747.50
3,959.45
388.13
5,175.00
6,900.00

6,037.50

6,325.00
213,354.35

31,625.00
7,245.00
1,656.00
1,509.38
1,150.00
4,485.00
156.00
28.60
1,692.60
309.40
23.40
265.20
1,767.38
416.00
650.00
1,569.75
10,870.00
248.40
5,520.00
71,187.10

19,500.00
22,880.00
56,918.42
14,560.00
214.50
998.40
1,716.00
1,076.40
1,008.80
7,020.00
1,820.00
650.00

3Sty9CL Schoolbuilding 71 of 179


Three-Storey Nine (9) Classroom

GRAND TOTAL

5,460.00
395.20
374.40
343.20
21,840.00
2,067.00
1,755.00
160,597.32

7,722.00
98,113.60
73,816.60
113,964.50
9,652.50

27,627.60
28,142.40
28,428.40
11,154.00
398,621.60

32,032.00
3,495.96
2,033.20
975.00

16,738.80
2,330.64
585.00
58,190.60

8,815,551.93
1,674,954.87
1,258,860.82
11,749,367.61
117,493.68
PhP11,866,861.29
PhP11,867,000.00

3Sty9CL Schoolbuilding 72 of 179


Republic of the Philippines
DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED THREE STOREY TWELVE (12) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 68,576.21 45,717.47 68,576.21
Billboard
Safety and Health lot 1.00 68,576.21 0.00 68,576.21
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 427.50 0.00 20.00 0.00
1.02 Structural Excavation cu.m 337.52 0.00 200.00 0.00
1.03 Backfilling and Compaction cu.m 418.87 0.00 45.00 0.00
1.06 Select Fill cu.m 352.69 150.00 45.00 52,903.13
1.04 Gravel Bedding G-1 cu.m 66.18 980.00 180.00 64,858.36
1.05 Soil Poisoning sq.m 470.25 15.00 4.50 7,053.75
Sub-total
2.00 Concreting Works
Column Footing cu.m 51.22
2.01 Portland Cement bag 461.00 218.00 65.40 100,498.00
2.05 Crushed Gravel 1" cu.m 51.25 980.00 294.00 50,225.00
2.03 Washed Sand cu.m 25.75 900.00 270.00 23,175.00
Tie beams cu.m 46.70
2.01 Portland Cement bag 421.00 218.00 65.40 91,778.00
2.02 Crushed Gravel 3/4" cu.m 46.75 980.00 294.00 45,815.00
2.03 Washed Sand cu.m 23.50 900.00 270.00 21,150.00
Wall Footing cu.m 6.82
2.01 Portland Cement bag 62.00 218.00 65.40 13,516.00
2.05 Crushed Gravel 1" cu.m 7.00 980.00 294.00 6,860.00
2.03 Washed Sand cu.m 3.50 900.00 270.00 3,150.00
Columns cu.m 54.02
2.01 Portland Cement bag 487.00 218.00 65.40 106,166.00
2.02 Crushed Gravel 3/4" cu.m 54.25 980.00 294.00 53,165.00
2.03 Washed Sand cu.m 27.25 900.00 270.00 24,525.00
Beams and Girders cu.m 61.20
2.01 Portland Cement bag 551.00 218.00 65.40 120,118.00
2.02 Crushed Gravel 3/4" cu.m 61.25 980.00 294.00 60,025.00
2.03 Washed Sand cu.m 30.75 900.00 270.00 27,675.00
Suspended Slab cu.m 78.53
2.01 Portland Cement bag 707.00 218.00 65.40 154,126.00
2.02 Crushed Gravel 3/4" cu.m 78.75 980.00 294.00 77,175.00
2.03 Washed Sand cu.m 39.50 900.00 270.00 35,550.00
Roof Beams cu.m 20.70
2.01 Portland Cement bag 187.00 218.00 65.40 40,766.00
2.02 Crushed Gravel 3/4" cu.m 20.75 980.00 294.00 20,335.00
2.03 Washed Sand cu.m 10.50 900.00 270.00 9,450.00
Stairs cu.m 19.44
2.01 Portland Cement bag 175.00 218.00 65.40 38,150.00
2.02 Crushed Gravel 3/4" cu.m 19.50 980.00 294.00 19,110.00
2.03 Washed Sand cu.m 9.75 900.00 270.00 8,775.00
Slab on Grade cu.m 42.75
2.01 Portland Cement bag 385.00 218.00 65.40 83,930.00
2.05 Crushed Gravel 1" cu.m 42.75 980.00 294.00 41,895.00
2.03 Washed Sand cu.m 21.50 900.00 270.00 19,350.00
Ramp on Fill cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 65.40 3,924.00
2.05 Crushed Gravel 1" cu.m 2.00 980.00 294.00 1,960.00
2.03 Washed Sand cu.m 1.00 900.00 270.00 900.00
Media Agua cu.m 6.00
2.01 Portland Cement bag 54.00 218.00 65.40 11,772.00
2.02 Crushed Gravel 3/4" cu.m 6.00 980.00 294.00 5,880.00
2.03 Washed Sand cu.m 3.00 900.00 270.00 2,700.00
Sub-total
3.00 Rebar Works
Column Footing kg 3,957.01
Tie beams kg 5,437.75
Wall Footing kg 193.03
Columns kg 17,141.23
Beams and Girders kg 16,842.75
Suspended Slab kg 6,144.47
Roof Beams kg 4,825.35
Stairs kg 1,106.56
Slab on Grade kg 1,804.67
Ramp on Fill kg 193.03
Media Agua kg 354.88
3.01 Deformed Round Bars, Grade 40 kg 58,000.73 40.10 12.03 2,325,829.19
3.02 G.I. Tie Wire kg 1,161.00 60.00 18.00 69,660.00
Sub-total
4.00 Formworks
Tie beams sq.m 311.35
4.01 Coco Lumber bd.ft 3,425.00 16.00 4.80 54,800.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 80.00 580.00 174.00 46,400.00
4.04 CWN, Assorted kg 48.00 60.00 18.00 2,880.00
Columns sq.m 602.84
4.01 Coco Lumber bd.ft 10,249.00 16.00 4.80 163,984.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 155.00 580.00 174.00 89,900.00
4.04 CWN, Assorted kg 144.00 60.00 18.00 8,640.00
Beams and Girders sq.m 708.00
4.01 Coco Lumber bd.ft 12,036.00 16.00 4.80 192,576.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 182.00 580.00 174.00 105,560.00
4.04 CWN, Assorted kg 169.00 60.00 18.00 10,140.00
Suspended Slab sq.m 785.25
4.01 Coco Lumber bd.ft 13,350.00 16.00 4.80 213,600.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 202.00 580.00 174.00 117,160.00
4.04 CWN, Assorted kg 187.00 60.00 18.00 11,220.00
Roof Beams sq.m 254.90
4.01 Coco Lumber bd.ft 4,334.00 16.00 4.80 69,344.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 66.00 580.00 174.00 38,280.00
4.04 CWN, Assorted kg 61.00 60.00 18.00 3,660.00
Stairs sq.m 57.20
4.01 Coco Lumber bd.ft 973.00 16.00 4.80 15,568.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 20.00 580.00 174.00 11,600.00
4.04 CWN, Assorted kg 14.00 60.00 18.00 840.00
Media Agua sq.m 43.20
4.01 Coco Lumber bd.ft 551.00 16.00 4.80 8,816.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 15.00 580.00 174.00 8,700.00
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00
Sub-total
5.00 Masonry Works
Masonry Wall sq.m 1,352.33
5.05 CHB 6" thk pc 16,905.00 12.00 3.60 202,860.00
5.02 Portland Cement bag 677.00 218.00 65.40 147,586.00
5.03 Washed Sand cu.m 58.00 900.00 270.00 52,200.00
5.06 10mm x 6m RSB kg 1,792.00 40.10 12.03 71,859.20
5.07 G.I. Tie Wire kg 36.00 60.00 18.00 2,160.00
Plastering sq.m 2,704.65
5.02 Portland Cement bag 893.00 218.00 65.40 194,674.00
5.03 Washed Sand cu.m 90.00 900.00 270.00 81,000.00
Floor Topping sq.m 785.25
5.02 Portland Cement bag 519.00 218.00 65.40 113,142.00
5.03 Washed Sand cu.m 52.00 900.00 270.00 46,800.00
Sub-total
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm
6.03 Wooden Jamb complete with Accessories set 24.00 7,317.50 1,463.50 175,620.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 6.00 4,167.50 833.50 25,005.00
(lever type door knob)

D-3 Flush Door 0.70m x 2.10m on 150mm


6.05 set 4.00 3,567.50 713.50 14,270.00
Wooden Jamb complete with Accessories

D-4 Cubicle Door 0.60m x 1.20m on


6.06 150mm Wooden Jamb complete with set 13.00 3,408.75 681.75 44,313.75
Accessories
Steel Encased Clear Glass Window with
6.25 set 13.00 8,068.80 1,613.76 104,894.40
Grilles (4.00 x 1.50m)

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type
6.08 Silver Colored Frame and Fixed Clear set 24.00 4,672.00 934.40 112,128.00
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

Steel Encased Clear Glass Window with


6.27 set 4.00 6,035.46 1,207.09 24,141.85
Grilles (2.00 x 0.60m)
Steel Encased Clear Glass Window with
6.28 set 4.00 47,586.55 9,517.31 190,346.22
Grilles (0.95 x 0.60m)
6.25 Security Grilles -2.30 X 1.30m set 4.00 4,020.95 1,809.43 16,083.81
6.26 Security Grilles -4.30 X 1.30m set 10.00 5,412.55 2,435.65 54,125.51
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 2,388.67 32.00 9.60 76,437.50
7.14 L 50 x 50 x 6mm kg 2,832.19 32.00 9.60 90,630.14
7.07 LC 150 x 65 x 20 x 2.0mm kg 4,433.43 43.00 12.90 190,637.31
7.18 Plain Round Bar 10mmØ x 6m pc 20.00 107.00 32.10 2,140.00
7.19 Plain Round Bar 12mmØ x 6m pc 20.00 185.00 55.50 3,700.00
7.30 Turn Buckle 12 mmØ pc 10.00 60.00 18.00 600.00
Anchor Bolt with Nuts and Washer, 12mmØ
7.34 pc 132.00 27.00 8.10 3,564.00
x 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ
7.35 pc 132.00 12.00 3.60 1,584.00
x 50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 2.75 9,300.00 2,790.00 25,575.00
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 5.50 5,390.00 1,617.00 29,645.00
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 14.00 1,069.00 320.70 14,966.00
7.45 G.I. Pipe 2"Ø Sch.40 pc 25.00 1,781.00 534.30 44,525.00
7.23 Square Bar 19mm□ x 6m pc 45.00 620.00 186.00 27,900.00
7.46 Welding Rod kg 194.00 67.00 20.10 12,998.00
13.12 Primer, Zinc Chromate gal 11.00 537.00 161.10 5,907.00
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-
8.16 m 652.80 380.00 76.00 248,064.00
Painted, 1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.915m x
8.22 pc 42.00 415.00 0.00 17,430.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.915m x
8.19 pc 12.00 560.00 0.00 6,720.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.915m
8.17 pc 21.00 560.00 0.00 11,760.00
x 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 5,913.60 1.80 0.00 10,644.48
8.36 Roof Sealant L 10.00 299.75 0.00 2,997.50
8.37 Blind Rivets pc 750.00 1.35 0.00 1,012.50
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 427.50
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 1,869.00 38.00 11.40 71,022.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 144.00 350.00 105.00 50,400.00
9.22 Finishing Nails kg 8.00 70.00 21.00 560.00
9.23 Common Wire Nails kg 34.00 50.00 15.00 1,700.00
9.24 Concrete Nails kg 8.00 70.00 21.00 560.00
9.42 Wood Preservative, Brown L 14.00 900.00 270.00 12,600.00
Exterior ceiling sq.m 105.36
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 461.00 38.00 11.40 17,518.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 36.00 360.00 108.00 12,960.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00
9.23 Common Wire Nails kg 9.00 50.00 15.00 450.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00
9.42 Wood Preservative, Brown L 4.00 900.00 270.00 3,600.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 16.00 245.00 73.50 3,920.00
9.16 Fascia Board, Wooden bd.ft 398.52 36.00 10.80 14,346.72
Blackboards sq.m 69.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 439.00 38.00 11.40 16,682.00
9.43 Lawanit, 1/4" thk pc 24.00 280.00 84.00 6,720.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00
9.23 Common Wire Nails kg 8.00 50.00 15.00 400.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.02 Electrical Conduit uPVC, 20mmØ pc 306.67 69.75 20.93 21,390.00
10.04 Electrical Conduit uPVC, 40mmØ pc 24.00 192.50 57.75 4,620.00
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00
10.16 Junction Box, 4" x 4" G.I. pc 94.00 15.00 4.50 1,410.00
10.17 Utility Box, 2" x 4" G.I. pc 90.00 30.00 4.28 2,700.00
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 2,760.00 33.00 7.02 91,080.00
10.14 8.0 mm2 THW Wire, Stranded m 71.00 84.50 25.35 5,999.50
10.10 30.0 mm THW Wire, Stranded
2
m 54.00 180.00 54.00 9,720.00
10.28 Duplex C.O. with Plate pc 36.00 263.80 21.00 9,496.80
10.23 Single Switch with Plate pc 48.00 97.68 13.46 4,688.64
10.24 2-Gang Switch with Plate pc 28.00 153.00 21.53 4,284.00
10.25 3-Gang Switch with Plate pc 4.00 208.00 29.59 832.00
10.20 FL 2 x 40W Industrial Type set 48.00 840.00 126.00 40,320.00
10.21 FL 1 x 40W Industrial Type set 20.00 490.00 73.50 9,800.00
Compact Fluorescent Lamp 18W pc 36.00 165.00 33.00 5,940.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 36.00 25.00 3.75 900.00
Panel Box, Bolt-on type, 8 Branches with
set 3.00 4,877.50 731.63 14,632.50
60AT/100AF Main (Lugs)
Panel Box, Bolt-on type, 4 Branches with
set 1.00 4,452.75 667.91 4,452.75
100AT/100AF Main
10.58 Electrical Tape pc 12.00 37.50 5.63 450.00
10.54 Vibrating Bell 8" set 3.00 1,500.00 225.00 4,500.00
10.55 Fire Alarm Bell, Vibrating Type set 3.00 2,000.00 300.00 6,000.00
10.56 Fire Alarm Station, Manual Single Action set 3.00 1,750.00 262.50 5,250.00
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 15.00 5,500.00 825.00 82,500.00
11.64 Concrete Counter Sink Type, with Lever Ty set 6.00 3,150.00 472.50 18,900.00
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 20.00 160.00 24.00 3,200.00
11.61 Water Closet Flange set 15.00 262.50 39.38 3,937.50
11.67 Tissue Holder pc 8.00 250.00 37.50 2,000.00
11.05 PP-R Pipe 3/4"Ø pc 20.00 345.00 103.50 6,900.00
11.09 PP-R Coupling, 3/4"Ø pc 16.00 15.00 4.50 240.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 4.00 11.00 3.30 44.00
11.06 PP-R Pipe 1/2"Ø pc 12.00 217.00 65.10 2,604.00
11.21 PP-R Elbow 90o x 1/2"Ø pc 34.00 14.00 4.20 476.00
11.08 PP-R Coupling, 1/2"Ø pc 4.00 9.00 2.70 36.00
11.15 PP-R Tee, 1/2"Ø pc 36.00 17.00 5.10 612.00
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 41.00 84.97 25.49 3,483.77
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00
11.44 Gate Valve, 1/2"Ø pc 4.00 250.00 75.00 1,000.00
11.65 S.S.Floor Drain 4' x 4" pc 28.00 97.50 14.63 2,730.00
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00
11.66 Teflon Tape roll 36.00 12.00 1.80 432.00
11.69 Mirror sq.ft 96.00 100.00 15.00 9,600.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 13.00 1,500.00 450.00 19,500.00
12.02 Concrete Pipe 150mmØ pc 117.33 200.00 60.00 23,466.67
12.32 Three Chamber Septic Vault unit 2.00 42,878.52 14,039.42 85,757.03
12.09 uPVC Sanitary Pipe 4"Ø pc 40.00 560.00 168.00 22,400.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 6.00 82.50 24.75 495.00
12.13 uPVC Elbow 90o x 4"Ø pc 16.00 96.00 28.80 1,536.00
12.27 uPVC Wye 4" x 4" pc 16.00 165.00 49.50 2,640.00
12.21 uPVC Tee 4" x 4" pc 12.00 138.00 41.40 1,656.00
12.25 uPVC Wye 4" x 2" pc 16.00 97.00 29.10 1,552.00
12.29 Brass Cleanout 6" x 6" pc 16.00 675.00 202.50 10,800.00
12.28 Brass Cleanout 4" x 4" pc 10.00 350.00 105.00 3,500.00
12.11 uPVC Elbow 90o x 2"Ø pc 40.00 25.00 7.50 1,000.00
12.07 uPVC Sanitary Pipe 2"Ø pc 40.00 210.00 63.00 8,400.00
12.22 uPVC Wye 2" x 2" pc 16.00 38.00 11.40 608.00
12.17 uPVC Tee 2" x 2" pc 16.00 36.00 10.80 576.00
12.30 uPVC P-Trap 2" pc 10.00 66.00 19.80 660.00
12.08 uPVC Sanitary Pipe 3"Ø pc 60.00 420.00 126.00 25,200.00
12.12 uPVC Elbow 90o x 3"Ø pc 26.00 53.00 15.90 1,378.00
12.33 PVC Cement can 20.00 150.00 45.00 3,000.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 4,854.62
13.18 Neutralizer gal 61.00 132.00 39.60 8,052.00
13.01 Latex, Flat gal 243.00 424.00 127.20 103,032.00
13.14 Masonry Putty gal 243.00 319.00 95.70 77,517.00
13.02 Latex, Semi Gloss gal 243.00 492.50 147.75 119,677.50
13.20 Acri Color qrt 61.00 165.00 49.50 10,065.00
Wood surfaces sq.m 1,017.66
13.04 Enamel, Flatwall gal 51.00 483.00 144.90 24,633.00
13.15 Glazing Putty gal 51.00 492.00 147.60 25,092.00
13.05 Enamel, Semi Gloss gal 51.00 497.00 149.10 25,347.00
13.16 Paint Thinner gal 39.00 260.00 78.00 10,140.00
Sub-total
14.00 Tile Works
Wall sq.m 131.03
14.04 Glazed Wall Tiles 20cm x 20cm pc 3,604.00 14.00 4.20 50,456.00
14.16 Tile Adhesive 25 kg/bag bag 24.00 224.10 67.23 5,378.40
14.13 Tile Trim 6mm pc 16.00 97.75 29.33 1,564.00
14.15 Tile Grout 5 kg/bag bag 10.00 150.00 45.00 1,500.00
14.15 Flooring sq.m 52.45
14.01 Unglazed Floor Tiles 20cm x 20cm pc 1,443.00 12.00 3.60 17,316.00
14.16 Tile Adhesive 25 kg/bag bag 10.00 224.10 67.23 2,241.00
14.15 Tile Grout 5 kg/bag bag 4.00 150.00 45.00 600.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked:

Project Engineer, PFSED Area Supervisor, PFSED

F-1 11.00 1.50 1.50 0.25


F-2 11.00 2.60 2.60 0.35
F-3 11.00 2.40 2.40 0.30

WF RAMP 2.00 0.40 0.25 6.40


CR's 2.00 0.40 0.25 27.69
TG-1 11.00 0.30 0.50 2.50
TG-2 11.00 0.30 0.50 7.00
TG-3 30.00 0.30 0.50 4.50

DC-1 4.00 0.20 0.20 6.00


C-1 11.00 0.35 0.35 6.03
C-2 11.00 0.40 0.35 6.03
C-3 11.00 0.40 0.35 6.03

2DC-1 4.00 0.20 0.20 3.20


2C-1 11.00 0.35 0.35 3.20
2C-2 11.00 0.35 0.35 3.20
2C-3 11.00 0.35 0.35 3.20

3C-1 11.00 0.35 0.35 3.20


3C-2 11.00 0.35 0.35 3.20
3C-3 11.00 0.35 0.35 3.20

2G-1 10.00 0.20 0.40 4.50


2G-2 10.00 0.20 0.40 4.50
2G-3 10.00 0.20 0.40 4.50
2G-3a 2.00 0.20 0.80 4.50
2G-4 2.00 0.20 0.40 2.50
2G-5 2.00 0.25 0.50 7.00
2G-6 10.00 0.20 0.40 2.50
2G-7 10.00 0.25 0.50 7.00
2B-1 10.00 0.20 0.40 4.50
2B-2 2.00 0.20 0.40 3.75
2STB-2 2.00 0.20 0.50 4.50
2CB-1 2.00 0.20 0.40 2.25

3G-1 10.00 0.20 0.40 4.50


3G-2 10.00 0.20 0.40 4.50
3G-3 10.00 0.20 0.40 4.50
3G-3a 2.00 0.20 0.80 4.50
3G-4 2.00 0.20 0.40 2.50
3G-5 2.00 0.25 0.50 7.00
3G-6 10.00 0.20 0.40 2.50
3G-7 10.00 0.25 0.50 7.00
3B-1 10.00 0.20 0.40 4.50
3B-2 2.00 0.20 0.40 3.75
3STB-2 2.00 0.20 0.50 4.50
3CB-1 2.00 0.20 0.40 2.25

2S-1 16.00 4.50 3.50 0.10


2S-2 11.00 4.50 2.50 0.10
2S-2 2.00 2.25 3.75 0.10
3S-1 16.00 4.50 3.50 0.10
3S-2 11.00 4.50 2.50 0.10
3S-2 2.00 2.25 3.75 0.10

RG-1 30.00 0.20 0.40 4.50


RG-1 11.00 0.20 0.40 2.50
RG-2 11.00 0.20 0.50 7.00

F-1 1.58 11.00 16.00 1.75


F-2 2.47 11.00 22.00 2.85
F-3 2.47 11.00 22.00 2.65

TG-1 2.47 11.00 4.00 2.50


2.47 11.00 7.00 0.63
2.47 11.00 4.00 0.50
0.62 11.00 22.00 1.43
0.89 11.00 2.00 2.50
TG-2 2.47 11.00 4.00 7.00
2.47 11.00 8.00 1.75
2.47 11.00 4.00 1.40
2.47 11.00 4.00 4.20
0.62 11.00 19.00 1.43
0.89 11.00 2.00 7.00
TG-3 2.47 11.00 4.00 4.50
2.47 11.00 9.00 1.13
2.47 11.00 2.00 0.90
0.62 11.00 32.00 1.43
0.89 11.00 2.00 4.50

WF RAMP 0.62 2.00 3.00 6.40


0.62 2.00 22.00 0.40
0.62 2.00 3.00 27.69
0.62 2.00 93.00 0.40

C-1 1.58 11.00 8.00 5.28


0.62 11.00 45.00 1.23
0.62 11.00 45.00 1.00
C-2 2.47 11.00 14.00 5.28
0.62 11.00 45.00 1.33
0.62 11.00 90.00 1.00
C-3 2.47 11.00 12.00 5.28
0.62 11.00 45.00 1.33
0.62 11.00 90.00 0.85

2C-1 1.58 11.00 6.00 3.20


0.62 11.00 45.00 1.23
0.62 11.00 90.00 0.42
2C-2 2.47 11.00 12.00 5.28
0.62 11.00 45.00 1.33
0.62 11.00 90.00 0.85
2C-3 2.47 11.00 12.00 5.28
0.62 11.00 45.00 1.33
0.62 11.00 90.00 0.85

3C-1 1.58 11.00 6.00 3.20


0.62 11.00 31.00 1.23
0.62 11.00 31.00 0.42
3C-2 2.47 11.00 8.00 3.20
0.62 11.00 31.00 1.23
0.62 11.00 31.00 1.00
3C-3 2.47 11.00 8.00 3.20
0.62 11.00 31.00 1.23
0.62 11.00 31.00 1.00

2S-1 SHORT 0.62 16.00 36 1.43


0.62 16.00 12 4.50
2S-1 LONG 0.62 16.00 36 1.10
0.62 16.00 15 3.50
2S-2 SHORT 0.62 11.00 18 1.43
0.62 11.00 9 4.50
2S-2 LONG 0.62 11.00 30 0.77
0.62 11.00 15 2.50
2S-2a SHORT 0.62 2.00 16 1.18
0.62 2.00 8 3.75
2S-2a LONG 0.62 2.00 26 0.68
0.62 2.00 13 2.25

3S-1 SHORT 0.62 16.00 36 1.43


0.62 16.00 12 4.50
3S-1 LONG 0.62 16.00 36 1.10
0.62 16.00 15 3.50
3S-2 SHORT 0.62 11.00 18 1.43
0.62 11.00 9 4.50
3S-2 LONG 0.62 11.00 30 0.77
0.62 11.00 15 2.50
3S-2a SHORT 0.62 2.00 16 1.18
0.62 2.00 8 3.75
3S-2a LONG 0.62 2.00 26 0.68
0.62 2.00 13 2.25

2G-1 2.47 10.00 4.00 4.50


2.47 10.00 4.00 1.50
2.47 10.00 2.00 0.90
2.47 10.00 2.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
2G-2 2.47 10.00 4.00 4.50
2.47 10.00 4.00 1.50
2.47 10.00 2.00 0.90
2.47 10.00 2.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
2G-3 2.47 10.00 4.00 4.50
2.47 10.00 5.00 1.50
2.47 10.00 2.00 0.90
2.47 10.00 2.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
2G-3a 2.47 2.00 4.00 4.50
2.47 2.00 4.00 1.50
2.47 2.00 2.00 0.90
2.47 2.00 2.00 2.70
0.62 2.00 32.00 1.83
0.89 2.00 2.00 4.50
2G-4 2.47 2.00 4.00 2.50
2.47 2.00 5.00 0.83
2.47 2.00 2.00 0.50
2.47 2.00 2.00 1.50
0.62 2.00 22.00 1.03
0.89 2.00 2.00 2.50
2G-5 2.47 2.00 4.00 7.00
2.47 2.00 8.00 2.33
2.47 2.00 4.00 1.40
2.47 2.00 2.00 4.20
0.62 2.00 45.00 1.33
0.89 2.00 2.00 7.00
2G-6 2.47 10.00 4.00 2.50
2.47 10.00 6.00 0.83
2.47 10.00 3.00 0.50
2.47 10.00 2.00 1.50
0.62 10.00 22.00 1.03
0.89 10.00 2.00 2.50
2G-7 2.47 10.00 4.00 7.00
2.47 10.00 8.00 2.33
2.47 10.00 4.00 1.40
2.47 10.00 4.00 4.20
0.62 10.00 45.00 1.33
0.89 10.00 2.00 7.00
2B-1 1.58 10.00 4.00 4.50
1.58 10.00 6.00 1.50
1.58 10.00 4.00 0.90
1.58 10.00 4.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
2B-2 1.58 2.00 4.00 3.75
1.58 2.00 4.00 1.25
1.58 2.00 4.00 0.75
1.58 2.00 2.00 2.25
0.62 2.00 29.00 1.03
0.89 2.00 2.00 4.00
2CB-1 1.58 2.00 6.00 2.25
1.58 2.00 4.00 0.75
1.58 2.00 4.00 0.45
1.58 2.00 2.00 1.35
0.62 2.00 21.00 1.03
0.89 2.00 2.00 2.25

3G-1 2.47 10.00 4.00 4.50


2.47 10.00 4.00 1.50
2.47 10.00 4.00 0.90
2.47 10.00 4.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
3G-2 2.47 10.00 4.00 4.50
2.47 10.00 4.00 1.50
2.47 10.00 2.00 0.90
2.47 10.00 2.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
3G-3 2.47 10.00 4.00 4.50
2.47 10.00 4.00 1.50
2.47 10.00 2.00 0.90
2.47 10.00 2.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
3G-3a 2.47 2.00 4.00 4.50
2.47 2.00 4.00 1.50
2.47 2.00 2.00 0.90
2.47 2.00 2.00 2.70
0.62 2.00 32.00 1.83
0.89 2.00 2.00 4.50
3G-4 2.47 2.00 4.00 2.50
2.47 2.00 5.00 0.83
2.47 2.00 2.00 0.50
2.47 2.00 2.00 1.50
0.62 2.00 22.00 1.03
0.89 2.00 2.00 2.50
3G-5 2.47 2.00 4.00 7.00
2.47 2.00 6.00 2.33
2.47 2.00 2.00 1.40
2.47 2.00 2.00 4.20
0.62 2.00 45.00 1.33
0.89 2.00 2.00 7.00
3G-6 2.47 10.00 4.00 2.50
2.47 10.00 5.00 0.83
2.47 10.00 2.00 0.50
2.47 10.00 2.00 1.50
0.62 10.00 22.00 1.03
0.89 10.00 2.00 2.50
3G-7 2.47 10.00 4.00 7.00
2.47 10.00 8.00 2.33
2.47 10.00 4.00 1.40
2.47 10.00 4.00 4.20
0.62 10.00 45.00 1.33
0.89 10.00 2.00 7.00
3B-1 1.58 10.00 4.00 4.50
1.58 10.00 4.00 1.50
1.58 10.00 4.00 0.90
1.58 10.00 4.00 2.70
0.62 10.00 32.00 1.03
0.89 10.00 2.00 4.50
3B-2 1.58 2.00 4.00 3.75
1.58 2.00 4.00 1.25
1.58 2.00 4.00 0.75
1.58 2.00 2.00 2.25
0.62 2.00 29.00 1.03
0.89 2.00 2.00 3.75
3CB-1 1.58 2.00 6.00 2.25
1.58 2.00 6.00 0.75
1.58 2.00 6.00 0.45
1.58 2.00 6.00 1.35
0.62 2.00 21.00 1.03
0.89 2.00 2.00 2.25

RG-1 1.58 30.00 4.00 4.50


1.58 30.00 4.00 1.50
1.58 30.00 4.00 0.90
1.58 30.00 4.00 2.70
0.62 30.00 32.00 1.03
0.89 30.00 2.00 4.50
RG-1 1.58 11.00 4.00 2.50
1.58 11.00 4.00 0.83
1.58 11.00 4.00 0.50
1.58 11.00 4.00 1.50
0.62 11.00 22.00 1.03
0.89 11.00 2.00 2.50
RG-2 1.58 11.00 4.00 7.00
1.58 11.00 4.00 2.33
1.58 11.00 2.00 1.40
1.58 11.00 2.00 4.20
0.62 11.00 45.00 1.23
0.89 11.00 2.00 7.00

TG-1 11.00 0.30 0.50 2.50


TG-2 11.00 0.30 0.50 7.00
TG-3 30.00 0.30 0.50 4.50

DC-1 4.00 0.20 0.20 3.00


C-1 11.00 0.35 0.35 6.03
C-2 11.00 0.35 0.35 6.03
C-3 11.00 0.35 0.35 6.03

2DC-1 4.00 0.20 0.20 3.00


2C-1 11.00 0.35 0.35 3.20
2C-2 11.00 0.35 0.35 3.20
2C-3 11.00 0.35 0.35 3.20

3DC-1 4.00 0.20 0.20 3.00


3C-1 11.00 0.35 0.35 3.20
3C-2 11.00 0.35 0.35 3.20
3C-3 11.00 0.35 0.35 3.20

2G-1 10.00 0.20 0.40 4.50


2G-2 10.00 0.20 0.40 4.50
2G-3 10.00 0.20 0.40 4.50
2G-3a 2.00 0.20 0.80 4.50
2G-4 2.00 0.20 0.40 2.50
2G-5 2.00 0.25 0.50 7.00
2G-6 10.00 0.20 0.40 2.50
2G-7 10.00 0.25 0.50 7.00
2B-1 10.00 0.20 0.40 4.50
2B-2 2.00 0.20 0.40 3.75
2STB-2 2.00 0.20 0.50 4.50
2CB-1 2.00 0.20 0.40 2.25

3G-1 10.00 0.20 0.40 4.50


3G-2 10.00 0.20 0.40 4.50
3G-3 10.00 0.20 0.40 4.50
3G-3a 2.00 0.20 0.80 4.50
3G-4 2.00 0.20 0.40 2.50
3G-5 2.00 0.25 0.50 7.00
3G-6 10.00 0.20 0.40 2.50
3G-7 10.00 0.25 0.50 7.00
3B-1 10.00 0.20 0.40 4.50
3B-2 2.00 0.20 0.40 3.75
3STB-2 2.00 0.20 0.50 4.50
3CB-1 2.00 0.20 0.40 2.25

RG-1 30.00 0.20 0.40 4.50


RG-1 11.00 0.20 0.40 2.50
RG-2 11.00 0.20 0.50 7.00

SIDES 6.00 7.00 9.93 416.85


FRONT/REAR 20.00 4.50 9.93 893.25
PARA 2.00 9.50 1.25 23.75
CORR 28.00 4.50 1.20 151.20
CORR 6.00 2.50 1.20 18.00
MINUS -24.00 2.10 1.00 -50.40
MINUS -24.00 2.60 1.60 -99.84
MINUS -24.00 1.50 1.60 -57.60
MINUS -4.00 0.70 2.60 -7.28
MINUS -4.00 0.60 0.95 -2.28
1,352.33
G DIVISION

TOTAL COST
GRAND TOTAL
LABOR

45,717.47 114,293.68

0.00 68,576.21
182,869.89 182,869.89 234,231.78

8,550.00 8,550.00
67,503.10 67,503.10
18,849.13 18,849.13
15,870.94 68,774.06
11,912.76 76,771.12
2,116.13 9,169.88
249,617.28 249,617.28 300,286.13

50,668.85
30,149.40 130,647.40
15,067.50 65,292.50
6,952.50 30,127.50

27,533.40 119,311.40
13,744.50 59,559.50
6,345.00 27,495.00

4,054.80 17,570.80
2,058.00 8,918.00
945.00 4,095.00

31,849.80 138,015.80
15,949.50 69,114.50
7,357.50 31,882.50

36,035.40 156,153.40
18,007.50 78,032.50
8,302.50 35,977.50

46,237.80 200,363.80
23,152.50 100,327.50
10,665.00 46,215.00

12,229.80 52,995.80
6,100.50 26,435.50
2,835.00 12,285.00
11,445.00 49,595.00
5,733.00 24,843.00
2,632.50 11,407.50

25,179.00 109,109.00
12,568.50 54,463.50
5,805.00 25,155.00

1,177.20 5,101.20
588.00 2,548.00
270.00 1,170.00

3,531.60 15,303.60
1,764.00 7,644.00
810.00 3,510.00
1,720,665.70 1,720,665.70 2,517,944.00

697,748.76 3,023,577.95
20,898.00 90,558.00
3,114,135.95 3,114,135.95 3,287,544.83

16,440.00 71,240.00
13,920.00 60,320.00
864.00 3,744.00

49,195.20 213,179.20
26,970.00 116,870.00
2,592.00 11,232.00

57,772.80 250,348.80
31,668.00 137,228.00
3,042.00 13,182.00

64,080.00 277,680.00
35,148.00 152,308.00
3,366.00 14,586.00

20,803.20 90,147.20
11,484.00 49,764.00
1,098.00 4,758.00

4,670.40 20,238.40
3,480.00 15,080.00
252.00 1,092.00
2,644.80 11,460.80
2,610.00 11,310.00
144.00 624.00
1,526,392.40 1,526,392.40 1,792,859.84

60,858.00 263,718.00
44,275.80 191,861.80
15,660.00 67,860.00
21,557.76 93,416.96
648.00 2,808.00

58,402.20 253,076.20
24,300.00 105,300.00

33,942.60 147,084.60
14,040.00 60,840.00
1,185,965.56 1,185,965.56 2,230,021.82

35,124.00 210,744.00

5,001.00 30,006.00

2,854.00 17,124.00

8,862.75 53,176.50

20,978.88 125,873.28

22,425.60 134,553.60

4,828.37 28,970.22

38,069.24 228,415.46

7,237.71 23,321.52
24,356.48 78,481.99
930,666.57 930,666.57 0.00

22,931.25 99,368.76
27,189.04 117,819.19
57,191.19 247,828.51
642.00 2,782.00
1,110.00 4,810.00
180.00 780.00

1,069.20 4,633.20

475.20 2,059.20

7,672.50 33,247.50
8,893.50 38,538.50
4,489.80 19,455.80
13,357.50 57,882.50
8,370.00 36,270.00
3,899.40 16,897.40
1,772.10 7,679.10
690,051.65 690,051.65 0.00

49,612.80 297,676.80

0.00 17,430.00

0.00 6,720.00

0.00 11,760.00

0.00 10,644.48
0.00 2,997.50
0.00 1,012.50
348,241.28 348,241.28 0.00

21,306.60 92,328.60
15,120.00 65,520.00
168.00 728.00
510.00 2,210.00
168.00 728.00
3,780.00 16,380.00

5,255.40 22,773.40
3,888.00 16,848.00
42.00 182.00
135.00 585.00
42.00 182.00
1,080.00 4,680.00
1,176.00 5,096.00
4,304.02 18,650.74

5,004.60 21,686.60
2,016.00 8,736.00
42.00 182.00
120.00 520.00
42.00 182.00
278,198.34 278,198.34 0.00

6,417.00 27,807.00
1,386.00 6,006.00
52.50 227.50
10.50 80.50
423.00 1,833.00
384.75 3,084.75
22.50 172.50

19,375.20 110,455.20
1,799.85 7,799.35
2,916.00 12,636.00
756.00 10,252.80
646.20 5,334.84
602.70 4,886.70
118.35 950.35
6,048.00 46,368.00
1,470.00 11,270.00
1,188.00 7,128.00
135.00 1,035.00

2,194.88 16,827.38

667.91 5,120.66

67.50 517.50
675.00 5,175.00
900.00 6,900.00
787.50 6,037.50
825.00 6,325.00
304,230.53 304,230.53 0.00

12,375.00 94,875.00
2,835.00 21,735.00
480.00 3,680.00
590.63 4,528.13
300.00 2,300.00
2,070.00 8,970.00
72.00 312.00
13.20 57.20
781.20 3,385.20
142.80 618.80
10.80 46.80
183.60 795.60
1,045.13 4,528.90
96.00 416.00
300.00 1,300.00
409.50 3,139.50
870.00 10,870.00
64.80 496.80
1,440.00 11,040.00
173,094.93 173,094.93 0.00

5,850.00 25,350.00
7,040.00 30,506.67
28,078.83 113,835.86
6,720.00 29,120.00
148.50 643.50
460.80 1,996.80
792.00 3,432.00
496.80 2,152.80
465.60 2,017.60
3,240.00 14,040.00
1,050.00 4,550.00
300.00 1,300.00
2,520.00 10,920.00
182.40 790.40
172.80 748.80
198.00 858.00
7,560.00 32,760.00
413.40 1,791.40
900.00 3,900.00
280,713.83 280,713.83 0.00
2,415.60 10,467.60
30,909.60 133,941.60
23,255.10 100,772.10
35,903.25 155,580.75
3,019.50 13,084.50

7,389.90 32,022.90
7,527.60 32,619.60
7,604.10 32,951.10
3,042.00 13,182.00
524,622.15 524,622.15 0.00

15,136.80 65,592.80
1,613.52 6,991.92
469.20 2,033.20
450.00 1,950.00

5,194.80 22,510.80
672.30 2,913.30
180.00 780.00
102,772.02 102,772.02 0.00

11,612,238.08 11,612,238.08 10,362,888.39


2,206,325.24
1,658,227.60 ABC
15,476,790.91 15,390,000.00
156,331.22 1,282,500.00 -244,000.00
PhP15,633,122.13
PhP15,634,000.00 Materials 8,971,951.81 13,500,000.00
Labor 2,640,286.27 29.43%
Per Room 1,737,111.11 13,366,336.63
Approved: Per Square 27,573.19
1,302,833.33
OLIVER R. HERNANDEZ
Chief, PFSED 1,302,833.33

Concrete Excavation Gravel Bed


6.19 1.60 39.60 2.48
26.03 1.60 118.98 7.44
19.01 1.60 101.38 6.34
51.22 259.95 16.25

1.28 0.70 5.12 0.51


5.54 0.70 22.15 2.21
6.82 27.27 2.73
4.13 0.70 5.78 0.83
11.55 0.70 16.17 2.31
20.25 0.70 28.35 4.05
35.93 50.30 7.19

0.96
8.12
9.28
9.28
27.64

0.51
4.31
4.31
4.31
13.45

4.31
4.31
4.31
12.94

3.60
3.60
3.60
1.44
0.40
1.75
2.00
8.75
3.60
0.60
0.90
0.36
30.60

3.60
3.60
3.60
1.44
0.40
1.75
2.00
8.75
3.60
0.60
0.90
0.36
30.60

25.20
12.38
1.69
39.26
25.20
12.38
1.69
39.26

10.80
2.20
7.70
20.70

Rebars
486.33
1,700.80
1,581.45
3,957.01

271.26
118.68
54.25
213.17
48.84
759.53
379.76
151.91
455.72
184.10
136.75
488.27
274.65
48.83
310.07
87.91
4,182.88

23.81
10.91
102.99
46.13
193.03

732.97
375.05
304.92
2,003.26
405.54
609.84
1,717.08
405.54
518.36
7,426.19

333.48
375.05
256.13
1,717.08
405.54
518.36
1,717.08
405.54
518.36
6,558.97

333.48
258.37
88.22
694.43
258.37
210.06
694.43
258.37
210.06
3,156.07

508.57
532.22
390.30
517.44
174.82
274.43
155.85
254.10
23.33
36.96
21.89
36.04
3,072.24

508.57
532.22
390.30
517.44
174.82
274.43
155.85
254.10
23.33
36.96
21.89
36.04
3,072.24

443.88
147.96
44.39
133.16
203.03
79.92
443.88
147.96
44.39
133.16
203.03
79.92
443.88
184.95
44.39
133.16
203.03
79.92
88.78
29.59
8.88
26.63
72.15
15.98
49.32
20.55
4.93
14.80
27.92
8.88
138.10
92.06
27.62
41.43
73.74
24.86
246.60
123.30
36.99
73.98
139.59
44.40
690.48
460.32
138.10
414.29
368.68
124.32
284.22
142.11
56.84
170.53
203.03
79.92
47.37
15.79
9.47
14.21
36.80
14.21
42.63
9.47
5.68
8.53
26.65
7.99
8,396.58

443.88
147.96
88.78
266.33
203.03
79.92
443.88
147.96
44.39
133.16
203.03
79.92
443.88
147.96
44.39
133.16
203.03
79.92
88.78
29.59
8.88
26.63
72.15
15.98
49.32
20.55
4.93
14.80
27.92
8.88
138.10
69.05
13.81
41.43
73.74
24.86
246.60
102.75
24.66
73.98
139.59
44.40
690.48
460.32
138.10
414.29
368.68
124.32
284.22
94.74
56.84
170.53
203.03
79.92
47.37
15.79
9.47
14.21
36.80
13.32
42.63
14.21
8.53
25.58
26.65
7.99
8,446.17

852.66
284.22
170.53
511.60
609.10
239.76
173.69
57.90
34.74
104.21
153.54
48.84
486.33
162.11
48.63
145.90
375.05
136.75
4,825.35

Forms
27.50
77.00
135.00
239.50

9.60
92.79
92.79
92.79
287.96

9.60
49.28
49.28
49.28
157.44

9.60
49.28
49.28
49.28
157.44

45.00
45.00
45.00
16.20
5.00
17.50
25.00
87.50
45.00
7.50
10.80
4.50
354.00

45.00
45.00
45.00
16.20
5.00
17.50
25.00
87.50
45.00
7.50
10.80
4.50
354.00

135.00
27.50
92.40
254.90

Masonry
-2,133,122.13

-2,110,454.28
Three-Storey Fifteen (15) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED THREE STOREY FIFTEEN (15) CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF
DEPARTMENT OFEDUCATION
EDUCATION
SUBJECT : APPROVED
APPROVEDAGENCY
AGENCYESTIMATE
ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor
I. GENERAL REQUIREMENTS

Mobilization / Temporary Structures,


Utilities and Services/Demobilization / lot 1.00 87,836.92 58,557.94 87,836.92 58,557.94 146,394.86
Standard Billboard

Safety and Health lot 1.00 87,836.92 0.00 87,836.92 0.00 87,836.92
Sub-total 234,231.78
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 513.00 0.00 20.00 0.00 10,260.00 10,260.00
1.02 Structural Excavation cu.m 394.44 0.00 200.00 0.00 78,887.90 78,887.90
1.03 Backfilling and Compaction cu.m 505.02 0.00 45.00 0.00 22,725.80 22,725.80
1.06 Select Fill cu.m 423.23 150.00 45.00 63,483.75 19,045.13 82,528.88
1.04 Gravel Bedding G-1 cu.m 81.79 980.00 180.00 80,156.99 14,722.71 94,879.70
1.05 Soil Poisoning sq.m 564.30 15.00 4.50 8,464.50 2,539.35 11,003.85
Sub-total 300,286.13
2.00 Concreting Works
Column Footing cu.m 60.53
2.01 Portland Cement bag 935.00 218.00 65.40 203,830.00 61,149.00 264,979.00
2.05 Crushed Gravel 1" cu.m 104.00 980.00 294.00 101,920.00 30,576.00 132,496.00
2.03 Washed Sand cu.m 52.00 900.00 270.00 46,800.00 14,040.00 60,840.00
Tie beams cu.m 55.67
2.01 Portland Cement bag 502.00 218.00 65.40 109,436.00 32,830.80 142,266.80
2.02 Crushed Gravel 3/4" cu.m 55.75 980.00 294.00 54,635.00 16,390.50 71,025.50
2.03 Washed Sand cu.m 28.00 900.00 270.00 25,200.00 7,560.00 32,760.00
Wall Footing cu.m 6.82
2.01 Portland Cement bag 552.00 218.00 65.40 120,336.00 36,100.80 156,436.80
2.05 Crushed Gravel 1" cu.m 61.50 980.00 294.00 60,270.00 18,081.00 78,351.00
2.03 Washed Sand cu.m 30.75 900.00 270.00 27,675.00 8,302.50 35,977.50
Columns cu.m 59.75
2.01 Portland Cement bag 830.00 218.00 65.40 180,940.00 54,282.00 235,222.00
2.02 Crushed Gravel 3/4" cu.m 92.25 980.00 294.00 90,405.00 27,121.50 117,526.50
2.03 Washed Sand cu.m 46.25 900.00 270.00 41,625.00 12,487.50 54,112.50
Beams and Girders cu.m 66.23
2.01 Portland Cement bag 597.00 218.00 65.40 130,146.00 39,043.80 169,189.80
2.02 Crushed Gravel 3/4" cu.m 66.25 980.00 294.00 64,925.00 19,477.50 84,402.50
2.03 Washed Sand cu.m 33.25 900.00 270.00 29,925.00 8,977.50 38,902.50
Suspended Slab cu.m 97.88
2.01 Portland Cement bag 881.00 218.00 65.40 192,058.00 57,617.40 249,675.40
2.02 Crushed Gravel 3/4" cu.m 98.00 980.00 294.00 96,040.00 28,812.00 124,852.00
2.03 Washed Sand cu.m 49.00 900.00 270.00 44,100.00 13,230.00 57,330.00
Roof Beams cu.m 24.66
2.01 Portland Cement bag 222.00 218.00 65.40 48,396.00 14,518.80 62,914.80
2.02 Crushed Gravel 3/4" cu.m 24.75 980.00 294.00 24,255.00 7,276.50 31,531.50
2.03 Washed Sand cu.m 12.50 900.00 270.00 11,250.00 3,375.00 14,625.00
Stairs cu.m 15.05

3Sty15CL Schoolbuilding 100 of 179


Three-Storey Fifteen (15) Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor
2.01 Portland Cement bag 136.00 218.00 65.40 29,648.00 8,894.40 38,542.40
2.02 Crushed Gravel 3/4" cu.m 15.25 980.00 294.00 14,945.00 4,483.50 19,428.50
2.03 Washed Sand cu.m 7.75 900.00 270.00 6,975.00 2,092.50 9,067.50
Slab on Grade cu.m 51.30
2.01 Portland Cement bag 462.00 218.00 65.40 100,716.00 30,214.80 130,930.80
2.05 Crushed Gravel 1" cu.m 51.50 980.00 294.00 50,470.00 15,141.00 65,611.00
2.03 Washed Sand cu.m 25.75 900.00 270.00 23,175.00 6,952.50 30,127.50
Ramp on Fill cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 65.40 3,924.00 1,177.20 5,101.20
2.05 Crushed Gravel 1" cu.m 2.00 980.00 294.00 1,960.00 588.00 2,548.00
2.03 Washed Sand cu.m 1.00 900.00 270.00 900.00 270.00 1,170.00
Sub-total 2,517,944.00
3.00 Rebar Works
Column Footing kg 4,453.77
Tie beams kg 8,103.29
Wall Footing kg 183.84
Columns kg 18,956.82
Beams and Girders kg 14,692.02
Suspended Slab kg 7,294.80
Roof Beams kg 3,905.37
Stairs kg 1,106.56
Slab on Grade kg 1,968.73
Ramp on Fill kg 84.17
Media Agua kg 354.88
3.01 Deformed Round Bars, Grade 40 kg 61,104.26 40.10 12.03 2,450,280.64 735,084.19 3,185,364.83
3.02 G.I. Tie Wire kg 1,310.00 60.00 18.00 78,600.00 23,580.00 102,180.00
Sub-total 3,287,544.83
4.00 Formworks
Tie beams sq.m 371.15
4.01 Coco Lumber bd.ft 4,083.00 16.00 5.76 65,328.00 23,518.08 88,846.08
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 96.00 580.00 194.40 55,680.00 18,662.40 74,342.40
4.04 CWN, Assorted kg 58.00 60.00 21.60 3,480.00 1,252.80 4,732.80
Columns sq.m 652.61
4.01 Coco Lumber bd.ft 11,095.00 16.00 5.76 177,520.00 63,907.20 241,427.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 168.00 580.00 194.40 97,440.00 32,659.20 130,099.20
4.04 CWN, Assorted kg 156.00 60.00 21.60 9,360.00 3,369.60 12,729.60
Beams and Girders sq.m 766.50
4.01 Coco Lumber bd.ft 13,031.00 16.00 5.76 208,496.00 75,058.56 283,554.56
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 197.00 580.00 194.40 114,260.00 38,296.80 152,556.80
4.04 CWN, Assorted kg 183.00 60.00 21.60 10,980.00 3,952.80 14,932.80
Suspended Slab sq.m 978.75
4.01 Coco Lumber bd.ft 16,639.00 16.00 5.76 266,224.00 95,840.64 362,064.64
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 252.00 580.00 194.40 146,160.00 48,988.80 195,148.80
4.04 CWN, Assorted kg 233.00 60.00 21.60 13,980.00 5,032.80 19,012.80
Roof Beams sq.m 303.70
4.01 Coco Lumber bd.ft 5,163.00 16.00 5.76 82,608.00 29,738.88 112,346.88
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 79.00 580.00 194.40 45,820.00 15,357.60 61,177.60
4.04 CWN, Assorted kg 73.00 60.00 21.60 4,380.00 1,576.80 5,956.80
Stairs sq.m 57.20
4.01 Coco Lumber bd.ft 973.00 16.00 5.76 15,568.00 5,604.48 21,172.48
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 15.00 580.00 194.40 8,700.00 2,916.00 11,616.00
4.04 CWN, Assorted kg 14.00 60.00 21.60 840.00 302.40 1,142.40
Sub-total 1,792,859.84
5.00 Masonry Works
Masonry Wall sq.m 2,728.55
5.05 CHB 6" thk pc 34,107.00 12.00 3.60 409,284.00 122,785.20 532,069.20
5.02 Portland Cement bag 1,365.00 218.00 65.40 297,570.00 89,271.00 386,841.00
5.03 Washed Sand cu.m 116.00 900.00 270.00 104,400.00 31,320.00 135,720.00

3Sty15CL Schoolbuilding 101 of 179


Three-Storey Fifteen (15) Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor
5.06 10mm x 6m RSB kg 3,614.00 40.10 12.03 144,921.40 43,476.42 188,397.82
5.07 G.I. Tie Wire kg 73.00 60.00 18.00 4,380.00 1,314.00 5,694.00
Plastering sq.m 5,457.10
5.02 Portland Cement bag 1,801.00 218.00 65.40 392,618.00 117,785.40 510,403.40
5.03 Washed Sand cu.m 181.00 900.00 270.00 162,900.00 48,870.00 211,770.00
Floor Topping sq.m 978.75
5.02 Portland Cement bag 646.00 218.00 65.40 140,828.00 42,248.40 183,076.40
5.03 Washed Sand cu.m 65.00 900.00 270.00 58,500.00 17,550.00 76,050.00
Sub-total 2,230,021.82
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on


6.03 150mm Wooden Jamb complete with set 30.00 7,317.50 1,463.50 219,525.00 43,905.00 263,430.00
Accessories (lever type door knob)

D-2 Flush Door 0.90m x 2.10m on


6.04 150mm Wooden Jamb complete with set 6.00 4,167.50 833.50 25,005.00 5,001.00 30,006.00
Accessories (lever type door knob)

D-3 Flush Door 0.70m x 2.10m on


6.05 set 6.00 3,567.50 713.50 21,405.00 4,281.00 25,686.00
150mm Wooden Jamb complete with
Accessories

D-4 Cubicle Door 0.60m x 1.20m on


6.06 150mm Wooden Jamb complete with set 9.00 3,408.75 681.75 30,678.75 6,135.75 36,814.50
Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window


with Clear Glass Blades on JalouPlus
6.07 Type Silver Colored Frame and Fixed set 30.00 8,444.00 1,688.80 253,320.00 50,664.00 303,984.00
Clear Glass Transom on 50 x 150 mm
Wooden Jamb complete with
Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window


with Clear Glass Blades on JalouPlus
6.08 Type Silver Colored Frame and Fixed set 30.00 4,672.00 934.40 140,160.00 28,032.00 168,192.00
Clear Glass Transom on 50 x 150 mm
Wooden Jamb complete with
Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window


with Clear Glass Blades on JalouPlus
6.09 Type Silver Colored Frame and Fixed set 6.00 4,248.00 849.60 25,488.00 5,097.60 30,585.60
Clear Glass Transom on 50 x 150 mm
Wooden Jamb complete with
Accessories

W - 4, ( 0.6 x 0.95 m) Jalousie Window


6.39a with Clear Glass Blades on Standard set 6.00 912.00 182.40 5,472.00 1,094.40 6,566.40
Aluminum Casing and Fixed Clear Glass
Transom on 50 x 150 mm Wooden Jamb
complete with Accessories
6.26 Security Grilles - 2.60 x 1.60m set 30.00 4,027.94 1,812.58 120,838.35 54,377.26 175,215.61
6.26 Security Grilles - 1.50 x 1.60m set 30.00 2,323.81 1,045.72 69,714.43 31,371.49 101,085.93
Sub-total 1,141,566.03
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,754.42 32.00 9.60 56,141.46 16,842.44 72,983.90
7.14 L 50 x 50 x 6mm kg 2,871.32 32.00 9.60 91,882.23 27,564.67 119,446.90
7.07 LC 150 x 65 x 20 x 2.0mm kg 5,959.22 43.00 12.90 256,246.26 76,873.88 333,120.14
7.18 Plain Round Bar 10mmØ x 6m pc 24.00 107.00 32.10 2,568.00 770.40 3,338.40
7.19 Plain Round Bar 12mmØ x 6m pc 24.00 185.00 55.50 4,440.00 1,332.00 5,772.00
7.30 Turn Buckle 12 mmØ pc 12.00 60.00 18.00 720.00 216.00 936.00

7.34 Anchor Bolt with Nuts and Washer, pc 156.00 27.00 8.10 4,212.00 1,263.60 5,475.60
12mmØ x 50mm x 300mm

3Sty15CL Schoolbuilding 102 of 179


Three-Storey Fifteen (15) Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor

7.35 Anchor Bolt with Nuts and Washer, pc 156.00 12.00 3.60 1,872.00 561.60 2,433.60
10mmØ x 50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 3.25 9,300.00 2,790.00 30,225.00 9,067.50 39,292.50
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 6.50 5,390.00 1,617.00 35,035.00 10,510.50 45,545.50
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 8.00 1,069.00 320.70 8,552.00 2,565.60 11,117.60
7.45 G.I. Pipe 2"Ø Sch.40 pc 32.00 1,781.00 534.30 56,992.00 17,097.60 74,089.60
7.23 Square Bar 19mm□ x 6m pc 45.00 620.00 186.00 27,900.00 8,370.00 36,270.00
7.46 Welding Rod kg 212.00 67.00 20.10 14,204.00 4,261.20 18,465.20
13.12 Primer, Zinc Chromate gal 12.00 537.00 161.10 6,444.00 1,933.20 8,377.20
Sub-total 776,664.15
8.00 Roofing Works

8.16 Long-Span Roofing, Corrugated, Pre- m 791.00 380.00 76.00 300,580.00 60,116.00 360,696.00
Painted, 1220mm x 0.4mm thk

8.23 Gutter, Pre-Painted, Ordinary, 0.915m x pc 54.00 605.00 0.00 32,670.00 0.00 32,670.00
2.440m x 0.4mm thk

8.20 Flashing, Pre-Painted, Ordinary, 0.915m pc 13.00 605.00 0.00 7,865.00 0.00 7,865.00
x 2.440m x 0.4mm thk

8.18 Ridge Roll, Pre-Painted, Ordinary, pc 27.00 605.00 0.00 16,335.00 0.00 16,335.00
0.915m x 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 8,635.58 1.80 0.00 15,544.04 0.00 15,544.04
8.36 Roof Sealant L 10.00 299.75 0.00 2,997.50 0.00 2,997.50
8.37 Blind Rivets pc 940.00 1.35 0.00 1,269.00 0.00 1,269.00
Sub-total 437,376.54
9.00 Carpentry Works
Interior ceiling sq.m 513.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 2,242.00 38.00 11.40 85,196.00 25,558.80 110,754.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 173.00 350.00 105.00 60,550.00 18,165.00 78,715.00
9.22 Finishing Nails kg 10.00 70.00 21.00 700.00 210.00 910.00
9.23 Common Wire Nails kg 41.00 50.00 15.00 2,050.00 615.00 2,665.00
9.24 Concrete Nails kg 10.00 70.00 21.00 700.00 210.00 910.00
9.42 Wood Preservative, Brown L 17.00 900.00 270.00 15,300.00 4,590.00 19,890.00
Exterior ceiling sq.m 123.64
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 541.00 38.00 11.40 20,558.00 6,167.40 26,725.40
9.06 Plywood, Marine 1/4" x 4' x 8' pc 42.00 360.00 108.00 15,120.00 4,536.00 19,656.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.23 Common Wire Nails kg 10.00 50.00 15.00 500.00 150.00 650.00
9.24 Concrete Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.42 Wood Preservative, Brown L 4.00 900.00 270.00 3,600.00 1,080.00 4,680.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 24.00 245.00 73.50 5,880.00 1,764.00 7,644.00
9.20 Fascia Board, Fiber Cement 12" x 12' pc 62.00 405.00 121.50 25,110.00 7,533.00 32,643.00
Blackboards sq.m 86.40
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 549.00 38.00 11.40 20,862.00 6,258.60 27,120.60
9.43 Lawanit, 1/4" thk pc 30.00 280.00 84.00 8,400.00 2,520.00 10,920.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 10.00 50.00 15.00 500.00 150.00 650.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
Sub-total 345,443.80
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 383.33 50.00 15.00 19,166.67 5,750.00 24,916.67
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00 52.50 227.50
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00 10.50 80.50
10.16 Junction Box, 4" x 4" G.I. pc 117.00 15.00 4.50 1,755.00 526.50 2,281.50
10.17 Utility Box, 2" x 4" G.I. pc 112.00 30.00 4.28 3,360.00 478.80 3,838.80
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures

3Sty15CL Schoolbuilding 103 of 179


Three-Storey Fifteen (15) Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor
10.11 3.5 mm2 THW Wire, Stranded m 3,450.00 33.00 7.02 113,850.00 24,219.00 138,069.00
10.14 14.0 mm2 THW Wire, Stranded m 10.00 84.50 25.35 845.00 253.50 1,098.50
10.28 Duplex C.O. with Plate pc 45.00 263.80 21.00 11,871.00 945.00 12,816.00
10.23 Single Switch with Plate pc 14.00 97.68 13.46 1,367.52 188.48 1,556.00
10.24 2-Gang Switch with Plate pc 25.00 153.00 21.53 3,825.00 538.13 4,363.13
10.25 3-Gang Switch with Plate pc 5.00 208.00 29.59 1,040.00 147.94 1,187.94
10.20 FL 2 x 40W Industrial Type set 85.00 840.00 126.00 71,400.00 10,710.00 82,110.00
10.53 Incandescent Bulb 50W set 18.00 35.00 5.25 630.00 94.50 724.50
10.33 Ceiling Receptacle 3-1/2"Ø pc 18.00 25.00 3.75 450.00 67.50 517.50
10.49 Panel Box, Flush Type, 8 Branches set 2.00 1,580.00 237.00 3,160.00 474.00 3,634.00
10.43 Circuit Breaker, 100A 2P set 2.00 650.00 97.50 1,300.00 195.00 1,495.00
10.38 Circuit Breaker, 20A 2P set 14.00 313.00 46.95 4,382.00 657.30 5,039.30
10.58 Electrical Tape pc 15.00 37.50 5.63 562.50 84.38 646.88
10.54 Vibrating Bell 8" set 3.00 1,500.00 225.00 4,500.00 675.00 5,175.00
10.55 Fire Alarm Bell, Vibrating Type set 3.00 2,000.00 300.00 6,000.00 900.00 6,900.00

10.56 Fire Alarm Station, Manual Single set 3.00 1,750.00 262.50 5,250.00 787.50 6,037.50
Action
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00 6,325.00
Sub-total 309,212.70
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 15.00 5,500.00 825.00 82,500.00 12,375.00 94,875.00

11.64 Concrete Counter Sink Type, with Lever set 6.00 3,150.00 472.50 18,900.00 2,835.00 21,735.00
Type Faucet and Complete Accessories
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 27.00 160.00 24.00 4,320.00 648.00 4,968.00
11.61 Water Closet Flange set 15.00 262.50 39.38 3,937.50 590.63 4,528.13
11.67 Tissue Holder pc 12.00 250.00 37.50 3,000.00 450.00 3,450.00
11.05 PP-R Pipe 3/4"Ø pc 30.00 345.00 103.50 10,350.00 3,105.00 13,455.00
11.09 PP-R Coupling, 3/4"Ø pc 24.00 15.00 4.50 360.00 108.00 468.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 6.00 11.00 3.30 66.00 19.80 85.80
11.06 PP-R Pipe 1/2"Ø pc 18.00 217.00 65.10 3,906.00 1,171.80 5,077.80
11.21 PP-R Elbow 90o x 1/2"Ø pc 51.00 14.00 4.20 714.00 214.20 928.20
11.08 PP-R Coupling, 1/2"Ø pc 6.00 9.00 2.70 54.00 16.20 70.20
11.15 PP-R Tee, 1/2"Ø pc 36.00 17.00 5.10 612.00 183.60 795.60
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 48.00 84.97 25.49 4,078.56 1,223.57 5,302.13
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00 416.00
11.44 Gate Valve, 1/2"Ø pc 6.00 250.00 75.00 1,500.00 450.00 1,950.00
11.65 S.S.Floor Drain 4' x 4" pc 42.00 97.50 14.63 4,095.00 614.25 4,709.25
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00 870.00 10,870.00
11.66 Teflon Tape roll 54.00 12.00 1.80 648.00 97.20 745.20
11.69 Mirror sq.ft 144.00 100.00 15.00 14,400.00 2,160.00 16,560.00
Sub-total 190,989.30
12.00 Sanitary Works
12.01 Catch Basin unit 14.00 1,500.00 450.00 21,000.00 6,300.00 27,300.00
12.02 Concrete Pipe 150mmØ pc 146.67 200.00 60.00 29,333.33 8,800.00 38,133.33
12.32 Three Chamber Septic Vault unit 2.00 42,878.52 14,039.42 85,757.03 28,078.83 113,835.86
12.09 uPVC Sanitary Pipe 4"Ø pc 60.00 560.00 168.00 33,600.00 10,080.00 43,680.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 6.00 82.50 24.75 495.00 148.50 643.50
12.13 uPVC Elbow 90o x 4"Ø pc 24.00 96.00 28.80 2,304.00 691.20 2,995.20
12.27 uPVC Wye 4" x 4" pc 24.00 165.00 49.50 3,960.00 1,188.00 5,148.00
12.21 uPVC Tee 4" x 4" pc 18.00 138.00 41.40 2,484.00 745.20 3,229.20
12.25 uPVC Wye 4" x 2" pc 24.00 97.00 29.10 2,328.00 698.40 3,026.40
12.29 Brass Cleanout 6" x 6" pc 24.00 675.00 202.50 16,200.00 4,860.00 21,060.00
12.28 Brass Cleanout 4" x 4" pc 12.00 350.00 105.00 4,200.00 1,260.00 5,460.00
12.11 uPVC Elbow 90o x 2"Ø pc 60.00 25.00 7.50 1,500.00 450.00 1,950.00
12.07 uPVC Sanitary Pipe 2"Ø pc 60.00 210.00 63.00 12,600.00 3,780.00 16,380.00
12.22 uPVC Wye 2" x 2" pc 24.00 38.00 11.40 912.00 273.60 1,185.60

3Sty15CL Schoolbuilding 104 of 179


Three-Storey Fifteen (15) Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor
12.17 uPVC Tee 2" x 2" pc 24.00 36.00 10.80 864.00 259.20 1,123.20
12.30 uPVC P-Trap 2" pc 12.00 66.00 19.80 792.00 237.60 1,029.60
12.08 uPVC Sanitary Pipe 3"Ø pc 120.00 420.00 126.00 50,400.00 15,120.00 65,520.00
12.12 uPVC Elbow 90o x 3"Ø pc 90.00 53.00 15.90 4,770.00 1,431.00 6,201.00
12.33 PVC Cement can 27.00 150.00 45.00 4,050.00 1,215.00 5,265.00
Sub-total 363,165.90
13.00 Painting Works
Concrete surfaces sq.m 7,889.55
13.18 Neutralizer gal 99.00 132.00 39.60 13,068.00 3,920.40 16,988.40
13.01 Latex, Flat gal 395.00 424.00 127.20 167,480.00 50,244.00 217,724.00
13.14 Masonry Putty gal 395.00 319.00 95.70 126,005.00 37,801.50 163,806.50
13.02 Latex, Semi Gloss gal 395.00 492.50 147.75 194,537.50 58,361.25 252,898.75
13.20 Acri Color qrt 99.00 165.00 49.50 16,335.00 4,900.50 21,235.50
Wood surfaces sq.m 1,185.04
13.04 Enamel, Flatwall gal 60.00 483.00 144.90 28,980.00 8,694.00 37,674.00
13.15 Glazing Putty gal 60.00 492.00 147.60 29,520.00 8,856.00 38,376.00
13.05 Enamel, Semi Gloss gal 60.00 497.00 149.10 29,820.00 8,946.00 38,766.00
13.16 Paint Thinner gal 45.00 260.00 78.00 11,700.00 3,510.00 15,210.00
Sub-total 802,679.15
14.00 Tile Works
Wall sq.m 209.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 5,382.00 14.00 4.20 75,348.00 22,604.40 97,952.40
14.16 Tile Adhesive 25 kg/bag bag 38.00 224.10 67.23 8,515.80 2,554.74 11,070.54
14.13 Tile Trim 6mm pc 16.00 97.75 29.33 1,564.00 469.20 2,033.20
14.15 Tile Grout 5 kg/bag bag 16.00 150.00 45.00 2,400.00 720.00 3,120.00
14.15 Flooring sq.m 62.42
14.01 Unglazed Floor Tiles 20cm x 20cm pc 1,608.00 12.00 3.60 19,296.00 5,788.80 25,084.80
14.16 Tile Adhesive 25 kg/bag bag 12.00 224.10 67.23 2,689.20 806.76 3,495.96
14.15 Tile Grout 5 kg/bag bag 5.00 150.00 45.00 750.00 225.00 975.00
Sub-total 143,731.90

I. DIRECT COST 14,873,717.86


II. INDIRECT COST 19% of (I) 2,826,006.39
III. TAX 12% of (I+II) 2,123,966.91
IV. TOTAL CONSTRUCTION COST (I+II+III) 19,823,691.16
V. ENGINEERING OVERHEAD 1% of (IV) 198,236.91
VI. TOTAL PROJECT COST 0.4 PhP20,021,928.07
PhP20,022,000.00

Prepared by: Checked: Approved:

3Sty15CL Schoolbuilding 105 of 179


FourStorey Sixteen (16) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED FOUR-STOREY EIGHT-CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 59,714.81 43,652.20 59,714.81 43,652.20
Billboard
Safety and Health lot 1.00 59,714.81 0.00 59,714.81 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 213.75 0.00 20.00 0.00 4,275.00
1.02 Structural Excavation cu.m 368.37 0.00 200.00 0.00 73,674.00
1.03 Backfilling and Compaction cu.m 352.77 0.00 45.00 0.00 15,874.55
1.06 Select Fill cu.m 304.59 150.00 45.00 45,689.06 13,706.72
1.04 Gravel Bedding G-1 cu.m 48.17 980.00 180.00 47,210.52 8,671.32
1.05 Soil Poisoning sq.m 235.13 15.00 4.50 3,526.88 1,058.06
Sub-total
2.00 Concreting Works
Lean Concrete cu.m 11.53
2.01 Portland Cement bag 70.00 218.00 42.50 15,260.00 2,975.00
2.05 Crushed Gravel 1" cu.m 11.75 980.00 150.00 11,515.00 1,762.50
2.03 Washed Sand cu.m 6.00 900.00 150.00 5,400.00 900.00
Column Footing cu.m 142.54
2.01 Portland Cement bag 1,711.00 218.00 42.50 372,998.00 72,717.50
2.05 Crushed Gravel 1" cu.m 142.75 980.00 150.00 139,895.00 21,412.50
2.03 Washed Sand cu.m 71.50 900.00 150.00 64,350.00 10,725.00
Tie beams cu.m 19.24
2.01 Portland Cement bag 231.00 218.00 42.50 50,358.00 9,817.50
2.02 Crushed Gravel 3/4" cu.m 19.25 980.00 175.00 18,865.00 3,368.75
2.03 Washed Sand cu.m 9.75 900.00 150.00 8,775.00 1,462.50
Wall Footing cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 42.50 3,924.00 765.00
2.05 Crushed Gravel 1" cu.m 2.00 980.00 150.00 1,960.00 300.00
2.03 Washed Sand cu.m 1.00 900.00 150.00 900.00 150.00
Columns cu.m 68.40
2.01 Portland Cement bag 821.00 218.00 42.50 178,978.00 34,892.50
2.02 Crushed Gravel 3/4" cu.m 68.50 980.00 175.00 67,130.00 11,987.50
2.03 Washed Sand cu.m 34.25 900.00 150.00 30,825.00 5,137.50
Beams and Girders cu.m 69.37
2.01 Portland Cement bag 833.00 218.00 42.50 181,594.00 35,402.50
2.02 Crushed Gravel 3/4" cu.m 69.50 980.00 175.00 68,110.00 12,162.50
2.03 Washed Sand cu.m 34.75 900.00 150.00 31,275.00 5,212.50
Suspended Slab cu.m 62.43
2.01 Portland Cement bag 750.00 218.00 42.50 163,500.00 31,875.00
2.02 Crushed Gravel 3/4" cu.m 62.50 980.00 175.00 61,250.00 10,937.50
2.03 Washed Sand cu.m 31.25 900.00 150.00 28,125.00 4,687.50

4Sty16CL Schoolbuilding 106 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Roof Beams cu.m 13.36
2.01 Portland Cement bag 161.00 218.00 42.50 35,098.00 6,842.50
2.02 Crushed Gravel 3/4" cu.m 13.50 980.00 175.00 13,230.00 2,362.50
2.03 Washed Sand cu.m 6.75 900.00 150.00 6,075.00 1,012.50
Stairs cu.m 14.58
2.01 Portland Cement bag 175.00 218.00 42.50 38,150.00 7,437.50
2.02 Crushed Gravel 3/4" cu.m 14.75 980.00 175.00 14,455.00 2,581.25
2.03 Washed Sand cu.m 7.50 900.00 150.00 6,750.00 1,125.00
Slab on Grade cu.m 21.38
2.01 Portland Cement bag 193.00 218.00 42.50 42,074.00 8,202.50
2.05 Crushed Gravel 1" cu.m 21.50 980.00 150.00 21,070.00 3,225.00
2.03 Washed Sand cu.m 10.75 900.00 150.00 9,675.00 1,612.50
Ramp on Fill cu.m 1.00
2.01 Portland Cement bag 9.00 218.00 42.50 1,962.00 382.50
2.05 Crushed Gravel 1" cu.m 1.00 980.00 150.00 980.00 150.00
2.03 Washed Sand cu.m 0.50 900.00 150.00 450.00 75.00
Media Agua cu.m 4.50
2.01 Portland Cement bag 54.00 218.00 42.50 11,772.00 2,295.00
2.02 Crushed Gravel 3/4" cu.m 4.50 980.00 175.00 4,410.00 787.50
2.03 Washed Sand cu.m 2.25 900.00 150.00 2,025.00 337.50
Sub-total
3.00 Rebar Works
3.01 Column Footing kg 14,592.56 43.10 8.62 628,939.12 125,787.82
3.01 Tie beams kg
Main Bars - Grade 60 kg 2,707.67 43.10 8.62 116,700.49 23,340.10
3.01 Stirrups - Grade 40 kg 1,554.44 40.10 8.02 62,333.20 12,466.64
3.01 Wall Footing - Grade 40 kg 59.14 40.10 8.02 2,371.51 474.30
3.01 Columns kg
Main Bars - Grade 60 kg 12,525.26 43.10 8.62 539,838.88 107,967.78
3.01 Ties - Grade 40 kg 9,661.00 40.10 8.02 387,405.94 77,481.19
3.01 Beams and Girders
Main Bars - Grade 60 kg 10,698.14 43.10 8.62 461,089.75 92,217.95
3.01 Stirrups - Grade 40 kg 5,806.19 40.10 8.02 232,828.14 46,565.63
3.01 Suspended Slab - Grade 40 kg 7,933.98 40.10 8.02 318,152.68 63,630.54
3.01 Roof Beams
Main Bars - Grade 60 kg 1,011.35 43.10 8.62 43,589.16 8,717.83
3.01 Stirrups - Grade 40 kg 599.68 40.10 8.02 24,047.01 4,809.40
3.01 Suspended Slab - Grade 40 kg 7,933.98 40.10 8.02 318,152.68 63,630.54
3.01 Stairs - Grade 60 kg 829.92 43.10 8.62 35,769.55 7,153.91
3.01 Slab on Grade - Grade 40 kg 902.33 40.10 8.02 36,183.61 7,236.72
3.01 Ramp on Fill - Grade 40 kg 21.04 40.10 8.02 843.81 168.76
3.01 Media Agua - Grade 40 kg 332.70 40.10 8.02 13,341.27 2,668.25
3.01 Deformed Round Bars kg 77,169.38
3.02 G.I. Tie Wire kg 1,544.00 60.00 9.00 92,640.00 13,896.00
Sub-total
4.00 Formworks
Tie beams sq.m 249.00
4.01 Coco Lumber bd.ft 2,739.00 16.00 4.80 43,824.00 13,147.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 64.00 580.00 162.00 37,120.00 10,368.00
4.04 CWN, Assorted kg 39.00 60.00 18.00 2,340.00 702.00
Columns sq.m 534.11
4.01 Coco Lumber bd.ft 9,080.00 16.00 4.80 145,280.00 43,584.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 138.00 580.00 162.00 80,040.00 22,356.00
4.04 CWN, Assorted kg 128.00 60.00 18.00 7,680.00 2,304.00
Beams and Girders sq.m 565.20
4.01 Coco Lumber bd.ft 9,609.00 16.00 4.80 153,744.00 46,123.20

4Sty16CL Schoolbuilding 107 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 146.00 580.00 162.00 84,680.00 23,652.00
4.04 CWN, Assorted kg 135.00 60.00 18.00 8,100.00 2,430.00
Suspended Slab sq.m 624.33
4.01 Coco Lumber bd.ft 10,614.00 16.00 4.80 169,824.00 50,947.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 161.00 580.00 162.00 93,380.00 26,082.00
4.04 CWN, Assorted kg 149.00 60.00 18.00 8,940.00 2,682.00
Roof Beams sq.m 134.93
4.01 Coco Lumber bd.ft 2,294.00 16.00 4.80 36,704.00 11,011.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 35.00 580.00 162.00 20,300.00 5,670.00
4.04 CWN, Assorted kg 33.00 60.00 18.00 1,980.00 594.00
Stairs sq.m 42.90
4.01 Coco Lumber bd.ft 730.00 16.00 4.80 11,680.00 3,504.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 15.00 580.00 162.00 8,700.00 2,430.00
4.04 CWN, Assorted kg 11.00 60.00 18.00 660.00 198.00
Media Agua sq.m 40.50
4.01 Coco Lumber bd.ft 517.00 16.00 4.80 8,272.00 2,481.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 14.00 580.00 162.00 8,120.00 2,268.00
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00
Sub-total
5.00 Masonry Works
Masonry Wall sq.m 1,053.87
5.05 CHB 6" thk pc 13,174.00 12.00 3.00 158,088.00 39,522.00
5.02 Portland Cement bag 1,067.36 218.00 51.00 232,683.93 54,435.23
5.03 Washed Sand cu.m 88.92 900.00 180.00 80,032.05 16,006.41
5.06 10mm x 6m RSB kg 2,778.51 40.10 9.03 111,418.14 25,089.92
5.07 G.I. Tie Wire kg 56.00 60.00 15.00 3,360.00 840.00
Plastering sq.m 2,107.74
5.02 Portland Cement bag 696.00 218.00 51.00 151,728.00 35,496.00
5.03 Washed Sand cu.m 70.00 900.00 180.00 63,000.00 12,600.00
Floor Topping sq.m 641.25
5.02 Portland Cement bag 424.00 218.00 51.00 92,432.00 21,624.00
5.03 Washed Sand cu.m 43.00 900.00 180.00 38,700.00 7,740.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 16.00 7,317.50 887.63 117,080.00 14,202.00
(lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 7.00 4,167.50 529.13 29,172.50 3,703.88
(lever type door knob)

D-3 Flush Door 0.70m x 2.10m on 150mm


6.05 set 2.00 3,567.50 517.13 7,135.00 1,034.25
Wooden Jamb complete with Accessories

D-4 Cubicle Door 0.60m x 1.20m on


6.06 150mm Wooden Jamb complete with set 11.00 3,408.75 443.81 37,496.25 4,881.94
Accessories

W - 1, ( 2.4 x 1.5 m) Steel Casement


Window with Grilles, Semi French Type
6.51 set 16.00 5,750.00 2,012.50 92,000.00 32,200.00
with 1/4 thk Clear Glass Panes complete
with Accessories

4Sty16CL Schoolbuilding 108 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type
6.08 Silver Colored Frame and Fixed Clear set 16.00 4,672.00 570.00 74,752.00 9,120.00
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 3, ( 2.0 x 0.6 m) Steel Awning Window


6.09 with Grilles with 1/4 thk Clear Glass Panes set 4.00 4,248.00 525.00 16,992.00 2,100.00
complete with Accessories

W - 4, ( 0.95 x 0.6 m) Steel Awning Window


6.54 with Grilles with 1/4 thk Clear Glass Panes set 4.00 750.00 262.50 3,000.00 1,050.00
complete with Accessories

6.25 Security Grilles -2.30 X 1.30m set 4.00 4,020.95 1,809.43 16,083.81 7,237.71
6.26 Security Grilles -4.30 X 1.30m set 10.00 5,412.55 2,435.65 54,125.51 24,356.48
6.26 Security Grilles -1.50 X 1.60m set 16.00 2,323.81 1,045.72 37,181.03 16,731.46
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,302.91 32.00 9.60 41,693.18 12,507.96
7.14 L 50 x 50 x 6mm kg 1,544.83 32.00 9.60 49,434.62 14,830.39
7.07 LC 150 x 65 x 20 x 2.0mm kg 2,274.29 43.00 12.90 97,794.47 29,338.34
7.18 Plain Round Bar 10mmØ x 6m pc 10.00 107.00 32.10 1,070.00 321.00
7.19 Plain Round Bar 12mmØ x 6m pc 12.00 185.00 55.50 2,220.00 666.00
7.30 Turn Buckle 12 mmØ pc 12.00 60.00 18.00 720.00 216.00
Anchor Bolt with Nuts and Washer, 12mmØ
7.34 pc 72.00 27.00 8.10 1,944.00 583.20
x 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ
7.35 pc 72.00 12.00 3.60 864.00 259.20
x 50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 1.50 9,300.00 2,790.00 13,950.00 4,185.00
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 3.00 5,390.00 1,617.00 16,170.00 4,851.00
7.45 G.I. Pipe 2"Ø Sch.40 pc 39.00 1,781.00 534.30 69,459.00 20,837.70
7.23 Square Bar 19mm□ x 6m pc 30.00 620.00 186.00 18,600.00 5,580.00
7.46 Welding Rod kg 103.00 67.00 20.10 6,901.00 2,070.30
13.12 Primer, Zinc Chromate gal 6.00 537.00 161.10 3,222.00 966.60
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-
8.16 m 340.20 380.00 76.00 129,276.00 25,855.20
Painted, 1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.610m x
8.22 pc 22.00 415.00 0.00 9,130.00 0.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x
8.19 pc 12.00 560.00 0.00 6,720.00 0.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m
8.17 pc 11.00 560.00 0.00 6,160.00 0.00
x 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 2,477.00 1.80 0.00 4,458.60 0.00
8.36 Roof Sealant L 4.00 299.75 0.00 1,199.00 0.00
8.37 Blind Rivets pc 450.00 1.35 0.00 607.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 213.75
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 1,372.00 38.00 11.40 52,136.00 15,640.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 75.00 350.00 105.00 26,250.00 7,875.00
9.22 Finishing Nails kg 5.00 70.00 21.00 350.00 105.00

4Sty16CL Schoolbuilding 109 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
9.23 Common Wire Nails kg 25.00 50.00 15.00 1,250.00 375.00
9.24 Concrete Nails kg 5.00 70.00 21.00 350.00 105.00
9.42 Wood Preservative, Brown L 7.00 900.00 270.00 6,300.00 1,890.00
Exterior ceiling sq.m 60.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 386.00 38.00 11.40 14,668.00 4,400.40
9.06 Plywood, Marine 1/4" x 4' x 8' pc 21.00 360.00 108.00 7,560.00 2,268.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 7.00 50.00 15.00 350.00 105.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 10.00 245.00 73.50 2,450.00 735.00
9.16 Fascia Board, Wooden bd.ft 250.92 36.00 10.80 9,033.12 2,709.94
Blackboards sq.m 46.08
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 293.00 38.00 11.40 11,134.00 3,340.20
9.43 Lawanit, 1/4" thk pc 16.00 280.00 84.00 4,480.00 1,344.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00
9.23 Common Wire Nails kg 6.00 50.00 15.00 300.00 90.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 205.00 50.00 15.00 10,250.00 3,075.00
10.08 RSC 32mmØ pc 1.00 339.00 101.70 339.00 101.70
10.35 Entrance Cap 32mm dia. pc 1.00 75.00 11.25 75.00 11.25
10.16 Junction Box, 4" x 4" G.I. pc 60.00 15.00 4.50 900.00 270.00
10.17 Utility Box, 2" x 4" G.I. pc 56.00 30.00 4.28 1,680.00 239.40
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 1,845.00 33.00 7.02 60,885.00 12,951.90
10.13 8.0 mm2 THW Wire, Stranded m 64.00 79.00 16.38 5,056.00 1,048.32
10.11 60.0 mm2 THW Wire, Stranded m 30.00 33.00 7.02 990.00 210.60
10.28 Duplex C.O. with Plate pc 24.00 263.80 21.00 6,331.20 504.00
10.23 Single Switch with Plate pc 8.00 97.68 13.46 781.44 107.70
10.24 2-Gang Switch with Plate pc 8.00 153.00 21.53 1,224.00 172.20
10.25 3-Gang Switch with Plate pc 4.00 208.00 29.59 832.00 118.35
10.20 FL 2 x 40W Industrial Type set 44.00 840.00 126.00 36,960.00 5,544.00
10.53 Incandescent Bulb 50W set 12.00 35.00 5.25 420.00 63.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 12.00 25.00 3.75 300.00 45.00
10.32 Telephone Outlet with Plate pc 5.00 251.00 37.65 1,255.00 188.25
10.23 Single Switch with Plate pc 24.00 97.68 13.46 2,344.32 323.10
10.25 3-Gang Switch with Plate pc 4.00 208.00 29.59 832.00 118.35
10.26 Circuit Breaker, 150A 2P pc 1.00 251.00 37.65 251.00 37.65
10.58 Electrical Tape pc 12.00 37.50 5.63 450.00 67.50
10.54 Vibrating Bell 8" set 4.00 1,500.00 225.00 6,000.00 900.00
10.55 Fire Alarm Bell, Vibrating Type set 4.00 2,000.00 300.00 8,000.00 1,200.00

10.56 Fire Alarm Station, Manual Single Action set 4.00 1,750.00 262.50 7,000.00 1,050.00

10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 12.00 5,500.00 825.00 66,000.00 9,900.00
11.64 Concrete Counter Sink Type, with Lever Ty set 1.00 3,150.00 472.50 3,150.00 472.50
11.19a G.I. Tee, 3/4" x 1/2"Ø pc 16.00 41.25 12.38 660.00 198.00
11.61 Water Closet Flange set 12.00 262.50 39.38 3,150.00 472.50
11.67 Tissue Holder pc 1.00 250.00 37.50 250.00 37.50

4Sty16CL Schoolbuilding 110 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
11.04 PP-R Pipe 1"Ø pc 14.00 558.00 167.40 7,812.00 2,343.60
11.10 PP-R Coupling, 1"Ø pc 16.00 25.00 7.50 400.00 120.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 11.00 3.30 22.00 6.60
11.05 PP-R Pipe 3/4"Ø pc 24.00 345.00 103.50 8,280.00 2,484.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 16.00 23.00 6.90 368.00 110.40
11.09 PP-R Coupling, 3/4"Ø pc 16.00 15.00 4.50 240.00 72.00
11.16 PP-R Tee, 3/4"Ø pc 16.00 31.00 9.30 496.00 148.80
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 29.00 84.97 25.49 2,464.13 739.24
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 4.00 250.00 75.00 1,000.00 300.00
11.65 S.S.Floor Drain 4' x 4" pc 12.00 97.50 14.63 1,170.00 175.50
11.68 S.S. Grab Rail 1-1/2"Ø set 1.00 5,000.00 435.00 5,000.00 435.00
11.66 Teflon Tape roll 12.00 12.00 1.80 144.00 21.60
11.69 Mirror sq.ft 96.00 100.00 15.00 9,600.00 1,440.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 8.00 1,500.00 450.00 12,000.00 3,600.00
12.02 Concrete Pipe 150mmØ pc 65.00 200.00 60.00 13,000.00 3,900.00
12.32 Three Chamber Septic Vault unit 1.00 42,878.52 14,039.42 42,878.52 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 16.00 560.00 168.00 8,960.00 2,688.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 4.00 82.50 24.75 330.00 99.00
12.13 uPVC Elbow 90o x 4"Ø pc 16.00 96.00 28.80 1,536.00 460.80
12.27 uPVC Wye 4" x 4" pc 12.00 165.00 49.50 1,980.00 594.00
12.21 uPVC Tee 4" x 4" pc 12.00 138.00 41.40 1,656.00 496.80
12.25 uPVC Wye 4" x 2" pc 16.00 97.00 29.10 1,552.00 465.60
12.29 Brass Cleanout 6" x 6" pc 2.00 675.00 202.50 1,350.00 405.00
12.28 Brass Cleanout 4" x 4" pc 6.00 350.00 105.00 2,100.00 630.00
12.11 uPVC Elbow 90o x 2"Ø pc 12.00 25.00 7.50 300.00 90.00
12.07 uPVC Sanitary Pipe 2"Ø pc 18.00 210.00 63.00 3,780.00 1,134.00
12.22 uPVC Wye 2" x 2" pc 12.00 38.00 11.40 456.00 136.80
12.17 uPVC Tee 2" x 2" pc 12.00 36.00 10.80 432.00 129.60
12.30 uPVC P-Trap 2" pc 16.00 66.00 19.80 1,056.00 316.80
12.08 uPVC Sanitary Pipe 3"Ø pc 45.00 420.00 126.00 18,900.00 5,670.00
12.12 uPVC Elbow 90o x 3"Ø pc 16.00 53.00 15.90 848.00 254.40
12.33 PVC Cement can 14.00 150.00 45.00 2,100.00 630.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 3,782.66
13.18 Neutralizer gal 48.00 132.00 39.60 6,336.00 1,900.80
13.01 Latex, Flat gal 190.00 424.00 127.20 80,560.00 24,168.00
13.14 Masonry Putty gal 190.00 319.00 95.70 60,610.00 18,183.00
13.02 Latex, Semi Gloss gal 190.00 492.50 147.75 93,575.00 28,072.50
13.20 Acri Color qrt 48.00 165.00 49.50 7,920.00 2,376.00
Wood surfaces sq.m 597.07
13.04 Enamel, Flatwall gal 30.00 0.40 144.90 12.00 4,347.00
13.15 Glazing Putty gal 30.00 492.00 147.60 14,760.00 4,428.00
13.05 Enamel, Semi Gloss gal 30.00 497.00 149.10 14,910.00 4,473.00
13.16 Paint Thinner gal 23.00 260.00 78.00 5,980.00 1,794.00
Sub-total
14.00 Tile Works
Wall sq.m 152.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 4,180.00 14.00 4.20 58,520.00 17,556.00
14.16 Tile Adhesive 25 kg/bag bag 28.00 224.10 67.23 6,274.80 1,882.44
14.13 Tile Trim 6mm pc 16.00 97.75 29.33 1,564.00 469.20
14.15 Tile Grout 5 kg/bag bag 12.00 150.00 45.00 1,800.00 540.00

4Sty16CL Schoolbuilding 111 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
14.15 Flooring sq.m 56.70
14.01 Unglazed Floor Tiles 20cm x 20cm pc 1,560.00 12.00 3.60 18,720.00 5,616.00
14.16 Tile Adhesive 25 kg/bag bag 11.00 224.10 67.23 2,465.10 739.53
14.15 Tile Grout 5 kg/bag bag 5.00 150.00 45.00 750.00 225.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNAND
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

4Sty16CL Schoolbuilding 112 of 179


FourStorey Sixteen (16) Classroom

Republic of the Philippines


RTMENT OF EDUCATION
S AND SCHOOLS ENGINEERING DIVISION
Pasig City

IGHT-CLASSROOM

GRAND TOTAL

103,367.02

59,714.81
163,081.83

4,275.00
73,674.00
15,874.55
59,395.78
55,881.84
4,584.94
213,686.11

18,235.00
13,277.50
6,300.00

445,715.50
161,307.50
75,075.00

60,175.50
22,233.75
10,237.50

4,689.00
2,260.00
1,050.00

213,870.50
79,117.50
35,962.50

216,996.50
80,272.50
36,487.50

195,375.00
72,187.50
32,812.50

4Sty16CL Schoolbuilding 113 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

41,940.50
15,592.50
7,087.50

45,587.50
17,036.25
7,875.00

50,276.50
24,295.00
11,287.50

2,344.50
1,130.00
525.00

14,067.00
5,197.50
2,362.50
2,030,243.00

754,726.94

140,040.59
74,799.85
2,845.82

647,806.65
464,887.13

553,307.70
279,393.77
381,783.22

52,307.00
28,856.41
381,783.22
42,923.46
43,420.34
1,012.57
16,009.52

106,536.00
3,972,440.17

56,971.20
47,488.00
3,042.00

188,864.00
102,396.00
9,984.00

199,867.20

4Sty16CL Schoolbuilding 114 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

108,332.00
10,530.00

220,771.20
119,462.00
11,622.00

47,715.20
25,970.00
2,574.00

15,184.00
11,130.00
858.00

10,753.60
10,388.00
624.00
1,204,526.40

197,610.00
287,119.16
96,038.46
136,508.06
4,200.00

187,224.00
75,600.00

114,056.00
46,440.00
1,144,795.68

131,282.00

32,876.38

8,169.25

42,378.19

124,200.00

4Sty16CL Schoolbuilding 115 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

83,872.00

19,092.00

4,050.00

23,321.52
78,481.99
53,912.49
601,635.82

54,201.14
64,265.01
127,132.81
1,391.00
2,886.00
936.00

2,527.20

1,123.20

18,135.00
21,021.00
90,296.70
24,180.00
8,971.30
4,188.60
421,254.96

155,131.20

9,130.00

6,720.00

6,160.00

4,458.60
1,199.00
607.50
183,406.30

67,776.80
34,125.00
455.00

4Sty16CL Schoolbuilding 116 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

1,625.00
455.00
8,190.00

19,068.40
9,828.00
182.00
455.00
182.00
2,340.00
3,185.00
11,743.06

14,474.20
5,824.00
91.00
390.00
91.00
180,480.46

13,325.00
440.70
86.25
1,170.00
1,919.40
172.50

73,836.90
6,104.32
1,200.60
6,835.20
889.14
1,396.20
950.35
42,504.00
483.00
345.00
1,443.25
2,667.42
950.35
288.65
517.50
6,900.00
9,200.00

8,050.00

6,325.00
188,000.73

75,900.00
3,622.50
858.00
3,622.50
287.50

4Sty16CL Schoolbuilding 117 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

10,155.60
520.00
28.60
10,764.00
478.40
312.00
644.80
3,203.37
416.00
1,300.00
1,345.50
5,435.00
165.60
11,040.00
130,099.37

15,600.00
16,900.00
56,917.93
11,648.00
429.00
1,996.80
2,574.00
2,152.80
2,017.60
1,755.00
2,730.00
390.00
4,914.00
592.80
561.60
1,372.80
24,570.00
1,102.40
2,730.00
150,954.73

8,236.80
104,728.00
78,793.00
121,647.50
10,296.00

4,359.00
19,188.00
19,383.00
7,774.00
374,405.30

76,076.00
8,157.24
2,033.20
2,340.00

4Sty16CL Schoolbuilding 118 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

24,336.00
3,204.63
975.00
117,122.07

11,076,132.92
2,104,465.25
1,581,671.78
14,762,269.96
147,622.70
PhP14,909,892.66
PhP14,910,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

4Sty16CL Schoolbuilding 119 of 179


FourStorey Sixteen (16) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED FOUR-STOREY TWELVE-CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 110,220.63 73,480.42 110,220.63 73,480.42
Billboard
Safety and Health lot 1.00 110,220.63 0.00 110,220.63 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 342.00 0.00 20.00 0.00 6,840.00
1.02 Structural Excavation cu.m 657.05 0.00 200.00 0.00 131,409.00
1.03 Backfilling and Compaction cu.m 568.06 0.00 45.00 0.00 25,562.59
1.06 Select Fill cu.m 487.35 150.00 45.00 73,102.50 21,930.75
1.04 Gravel Bedding G-1 cu.m 80.71 980.00 180.00 79,093.35 14,527.35
1.05 Soil Poisoning sq.m 376.20 15.00 4.50 5,643.00 1,692.90
Sub-total
2.00 Concreting Works
Lean Concrete cu.m 11.70
2.01 Portland Cement bag 71.00 218.00 42.50 15,478.00 3,017.50
2.05 Crushed Gravel 1" cu.m 11.75 980.00 150.00 11,515.00 1,762.50
2.03 Washed Sand cu.m 6.00 900.00 150.00 5,400.00 900.00
Column Footing cu.m 233.60
2.01 Portland Cement bag 2,804.00 218.00 42.50 611,272.00 119,170.00
2.05 Crushed Gravel 1" cu.m 233.75 980.00 150.00 229,075.00 35,062.50
2.03 Washed Sand cu.m 117.00 900.00 150.00 105,300.00 17,550.00
Tie beams cu.m 44.84
2.01 Portland Cement bag 539.00 218.00 42.50 117,502.00 22,907.50
2.02 Crushed Gravel 3/4" cu.m 45.00 980.00 175.00 44,100.00 7,875.00
2.03 Washed Sand cu.m 22.50 900.00 150.00 20,250.00 3,375.00
Wall Footing cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 42.50 3,924.00 765.00
2.05 Crushed Gravel 1" cu.m 2.00 980.00 150.00 1,960.00 300.00
2.03 Washed Sand cu.m 1.00 900.00 150.00 900.00 150.00
Columns cu.m 128.29
2.01 Portland Cement bag 1,540.00 218.00 42.50 335,720.00 65,450.00
2.02 Crushed Gravel 3/4" cu.m 128.50 980.00 175.00 125,930.00 22,487.50
2.03 Washed Sand cu.m 64.25 900.00 150.00 57,825.00 9,637.50
Beams and Girders cu.m 135.56
2.01 Portland Cement bag 1,627.00 218.00 42.50 354,686.00 69,147.50
2.02 Crushed Gravel 3/4" cu.m 135.75 980.00 175.00 133,035.00 23,756.25
2.03 Washed Sand cu.m 68.00 900.00 150.00 61,200.00 10,200.00
Suspended Slab cu.m 98.45
2.01 Portland Cement bag 1,182.00 218.00 42.50 257,676.00 50,235.00
2.02 Crushed Gravel 3/4" cu.m 98.50 980.00 175.00 96,530.00 17,237.50
2.03 Washed Sand cu.m 49.25 900.00 150.00 44,325.00 7,387.50

4Sty16CL Schoolbuilding 120 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Roof Beams cu.m 24.18
2.01 Portland Cement bag 291.00 218.00 42.50 63,438.00 12,367.50
2.02 Crushed Gravel 3/4" cu.m 24.25 980.00 175.00 23,765.00 4,243.75
2.03 Washed Sand cu.m 12.25 900.00 150.00 11,025.00 1,837.50
Stairs cu.m 29.16
2.01 Portland Cement bag 350.00 218.00 42.50 76,300.00 14,875.00
2.02 Crushed Gravel 3/4" cu.m 29.25 980.00 175.00 28,665.00 5,118.75
2.03 Washed Sand cu.m 14.75 900.00 150.00 13,275.00 2,212.50
Slab on Grade cu.m 34.20
2.01 Portland Cement bag 308.00 218.00 42.50 67,144.00 13,090.00
2.05 Crushed Gravel 1" cu.m 34.25 980.00 150.00 33,565.00 5,137.50
2.03 Washed Sand cu.m 17.25 900.00 150.00 15,525.00 2,587.50
Ramp on Fill cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 42.50 3,924.00 765.00
2.05 Crushed Gravel 1" cu.m 2.00 980.00 150.00 1,960.00 300.00
2.03 Washed Sand cu.m 1.00 900.00 150.00 900.00 150.00
Media Agua cu.m 5.40
2.01 Portland Cement bag 65.00 218.00 42.50 14,170.00 2,762.50
2.02 Crushed Gravel 3/4" cu.m 5.50 980.00 175.00 5,390.00 962.50
2.03 Washed Sand cu.m 2.75 900.00 150.00 2,475.00 412.50
Sub-total
3.00 Rebar Works
3.01 Column Footing kg 28,826.69 43.10 8.62 1,242,430.45 248,486.09
3.01 Tie beams kg
Main Bars - Grade 60 kg 8,498.07 43.10 8.62 366,266.82 73,253.36
3.01 Stirrups - Grade 40 kg 3,633.70 40.10 8.02 145,711.21 29,142.24
3.01 Wall Footing - Grade 40 kg 118.28 40.10 8.02 4,743.03 948.61
3.01 Columns kg
Main Bars - Grade 60 kg 17,911.69 43.10 8.62 771,993.93 154,398.79
3.01 Ties - Grade 40 kg 19,337.98 40.10 8.02 775,452.84 155,090.57
3.01 Beams and Girders
Main Bars - Grade 60 kg 19,872.76 43.10 8.62 856,515.78 171,303.16
3.01 Stirrups - Grade 40 kg 8,262.53 40.10 8.02 331,327.37 66,265.47
3.01 Suspended Slab - Grade 40 kg 11,770.11 40.10 8.02 471,981.47 94,396.29
3.01 Roof Beams
Main Bars - Grade 60 kg 17,067.19 43.10 8.62 735,595.72 147,119.14
3.01 Stirrups - Grade 40 kg 3,633.70 40.10 8.02 145,711.21 29,142.24
3.01 Stairs - Grade 60 kg 1,659.84 43.10 8.62 71,539.10 14,307.82
3.01 Slab on Grade - Grade 40 kg 1,443.74 40.10 8.02 57,893.78 11,578.76
3.01 Ramp on Fill - Grade 40 kg 42.09 40.10 8.02 1,687.61 337.52
3.01 Media Agua - Grade 40 kg 399.24 40.10 8.02 16,009.52 3,201.90
3.01 Deformed Round Bars kg 142,477.58
3.02 G.I. Tie Wire kg 2,850.00 60.00 9.00 171,000.00 25,650.00
Sub-total
4.00 Formworks
Tie beams sq.m 193.50
4.01 Coco Lumber bd.ft 2,129.00 16.00 4.80 34,064.00 10,219.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 34.00 580.00 162.00 19,720.00 5,508.00
4.04 CWN, Assorted kg 30.00 60.00 18.00 1,800.00 540.00
Columns sq.m 897.12
4.01 Coco Lumber bd.ft 15,252.00 16.00 4.80 244,032.00 73,209.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 154.00 580.00 162.00 89,320.00 24,948.00
4.04 CWN, Assorted kg 214.00 60.00 18.00 12,840.00 3,852.00
Beams and Girders sq.m 1,081.80
4.01 Coco Lumber bd.ft 18,391.00 16.00 4.80 294,256.00 88,276.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 186.00 580.00 162.00 107,880.00 30,132.00

4Sty16CL Schoolbuilding 121 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
4.04 CWN, Assorted kg 258.00 60.00 18.00 15,480.00 4,644.00
Suspended Slab sq.m 984.47
4.01 Coco Lumber bd.ft 16,737.00 16.00 4.80 267,792.00 80,337.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 169.00 580.00 162.00 98,020.00 27,378.00
4.04 CWN, Assorted kg 235.00 60.00 18.00 14,100.00 4,230.00
Roof Beams sq.m 215.40
4.01 Coco Lumber bd.ft 3,662.00 16.00 4.80 58,592.00 17,577.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 37.00 580.00 162.00 21,460.00 5,994.00
4.04 CWN, Assorted kg 52.00 60.00 18.00 3,120.00 936.00
Stairs sq.m 42.90
4.01 Coco Lumber bd.ft 730.00 16.00 4.80 11,680.00 3,504.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 15.00 580.00 162.00 8,700.00 2,430.00
4.04 CWN, Assorted kg 11.00 60.00 18.00 660.00 198.00
Media Agua sq.m 48.60
4.01 Coco Lumber bd.ft 620.00 16.00 4.80 9,920.00 2,976.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 17.00 580.00 162.00 9,860.00 2,754.00
4.04 CWN, Assorted kg 9.00 60.00 18.00 540.00 162.00
Sub-total
5.00 Masonry Works
Masonry Wall sq.m 1,617.55
5.05 CHB 6" thk pc 20,220.00 12.00 3.00 242,640.00 60,660.00
5.02 Portland Cement bag 1,638.22 218.00 51.00 357,132.92 83,549.44
5.03 Washed Sand cu.m 136.49 900.00 180.00 122,836.50 24,567.30
5.06 10mm x 6m RSB kg 4,264.64 40.10 9.03 171,011.99 38,509.68
5.07 G.I. Tie Wire kg 86.00 60.00 15.00 5,160.00 1,290.00
Plastering sq.m 3,235.10
5.02 Portland Cement bag 1,068.00 218.00 51.00 232,824.00 54,468.00
5.03 Washed Sand cu.m 107.00 900.00 180.00 96,300.00 19,260.00
Floor Topping sq.m 1,026.00
5.02 Portland Cement bag 678.00 218.00 51.00 147,804.00 34,578.00
5.03 Washed Sand cu.m 68.00 900.00 180.00 61,200.00 12,240.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 24.00 7,317.50 887.63 175,620.00 21,303.00
(lever type door knob)

D-2 Flush Door 0.80m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 8.00 3,704.44 470.34 29,635.56 3,762.70
(lever type door knob)

D-3 Flush Door 0.90m x 2.10m on 150mm


6.05 set 5.00 4,167.50 529.13 20,837.50 2,645.63
Wooden Jamb complete with Accessories

D-3a Louver Door 0.80m x 2.10m on 150mm


Wooden Jamb complete with Accessories set 2.00 3,704.44 470.34 7,408.89 940.68
(lever type door knob)

D-4 Cubicle Door 0.60m x 1.20m on 150mm


6.06 set 18.00 3,408.75 443.81 61,357.50 7,988.63
Wooden Jamb complete with Accessories

W - 1, ( 4.0 x 1.5 m) Steel Casement Window


6.51 with Grilles, Semi French Type with 1/4 thk set 24.00 5,750.00 2,012.50 138,000.00 48,300.00
Clear Glass Panes complete with Accessories

4Sty16CL Schoolbuilding 122 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type Silver
6.08 Colored Frame and Fixed Clear Glass set 24.00 4,672.00 570.00 112,128.00 13,680.00
Transom on 50 x 150 mm Wooden Jamb
complete with Accessories

W - 3, ( 2.0 x 0.6 m) Steel Awning Window with


6.09 Grilles with 1/4 thk Clear Glass Panes set 8.00 4,248.00 525.00 33,984.00 4,200.00
complete with Accessories

W - 4, ( 0.95 x 0.6 m) Steel Awning Window


6.54 with Grilles with 1/4 thk Clear Glass Panes set 5.00 750.00 262.50 3,750.00 1,312.50
complete with Accessories

Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 1,954.37 32.00 9.60 62,539.78 18,761.93
7.14 L 50 x 50 x 6mm kg 2,317.25 32.00 9.60 74,151.94 22,245.58
7.07 LC 150 x 65 x 20 x 2.0mm kg 3,569.77 43.00 12.90 153,500.18 46,050.05
7.18 Plain Round Bar 10mmØ x 6m pc 16.00 107.00 32.10 1,712.00 513.60
7.19 Plain Round Bar 12mmØ x 6m pc 16.00 185.00 55.50 2,960.00 888.00
7.30 Turn Buckle 12 mmØ pc 16.00 60.00 18.00 960.00 288.00
Anchor Bolt with Nuts and Washer, 12mmØ x
7.34 pc 108.00 27.00 8.10 2,916.00 874.80
50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
7.35 pc 108.00 12.00 3.60 1,296.00 388.80
50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 2.25 9,300.00 2,790.00 20,925.00 6,277.50
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 4.50 5,390.00 1,617.00 24,255.00 7,276.50
7.45 G.I. Pipe 2"Ø Sch.40 pc 88.00 1,781.00 534.30 156,728.00 47,018.40
7.23 Square Bar 19mm□ x 6m pc 57.00 620.00 186.00 35,340.00 10,602.00
7.46 Welding Rod kg 157.00 67.00 20.10 10,519.00 3,155.70
13.12 Primer, Zinc Chromate gal 9.00 537.00 161.10 4,833.00 1,449.90
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted,
8.16 m 516.60 380.00 76.00 196,308.00 39,261.60
1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.610m x
8.22 pc 34.00 415.00 0.00 14,110.00 0.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x
8.19 pc 12.00 560.00 0.00 6,720.00 0.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x
8.17 pc 17.00 560.00 0.00 9,520.00 0.00
2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 3,761.00 1.80 0.00 6,769.80 0.00
8.36 Roof Sealant L 8.00 299.75 0.00 2,398.00 0.00
8.37 Blind Rivets pc 630.00 1.35 0.00 850.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 342.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 2,195.00 38.00 11.40 83,410.00 25,023.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 119.00 350.00 105.00 41,650.00 12,495.00
9.22 Finishing Nails kg 7.00 70.00 21.00 490.00 147.00
9.23 Common Wire Nails kg 40.00 50.00 15.00 2,000.00 600.00
9.24 Concrete Nails kg 7.00 70.00 21.00 490.00 147.00
9.42 Wood Preservative, Brown L 11.00 900.00 270.00 9,900.00 2,970.00

4Sty16CL Schoolbuilding 123 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Exterior ceiling sq.m 87.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 560.00 38.00 11.40 21,280.00 6,384.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 31.00 360.00 108.00 11,160.00 3,348.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 11.00 50.00 15.00 550.00 165.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 10.00 245.00 73.50 2,450.00 735.00
9.16 Fascia Board, Wooden bd.ft 339.48 36.00 10.80 12,221.28 3,666.38
Blackboards sq.m 69.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 439.00 38.00 11.40 16,682.00 5,004.60
9.43 Lawanit, 1/4" thk pc 24.00 280.00 84.00 6,720.00 2,016.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 8.00 50.00 15.00 400.00 120.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.02 Electrical Conduit uPVC, 20mmØ pc 312.00 69.75 20.93 21,762.00 6,528.60
10.03 Electrical Conduit uPVC, 32mmØ pc 24.00 137.50 41.25 3,300.00 990.00
RSC 40mmØ pc 1.00 460.00 138.00 460.00 138.00
Entrance Cap 40mm dia. pc 1.00 102.00 30.60 102.00 30.60
10.16 Junction Box, 4" x 4" G.I. pc 96.00 15.00 4.50 1,440.00 432.00
10.17 Utility Box, 2" x 4" G.I. pc 91.00 30.00 4.28 2,730.00 389.03
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 2,772.00 33.00 7.02 91,476.00 19,459.44
10.13 8.0 mm2 THW Wire, Stranded m 71.00 79.00 16.38 5,609.00 1,162.98
10.10 60.0 mm2 THW Wire, Stranded m 54.00 180.00 54.00 9,720.00 2,916.00
10.28 Duplex C.O. with Plate pc 32.00 263.80 21.00 8,441.60 672.00
10.23 Single Switch with Plate pc 24.00 97.68 13.46 2,344.32 323.10
10.24 2-Gang Switch with Plate pc 24.00 153.00 21.53 3,672.00 516.60
10.25 3-Gang Switch with Plate pc 4.00 208.00 29.59 832.00 118.35
10.20 FL 2 x 40W Industrial Type set 48.00 840.00 126.00 40,320.00 6,048.00
10.21 FL 1 x 40W Industrial Type set 28.00 490.00 73.50 13,720.00 2,058.00
Compact Fluorescent Lamp, 18 watts pc 28.00 165.00 33.00 4,620.00 924.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 28.00 25.00 3.75 700.00 105.00
Panel Box, Bolt-on type, 6 Branches with
set 4.00 4,697.50 964.61 18,790.00 3,858.45
60AT/100AF Main (Lugs)
Panel Box, Bolt-on type, 4 Branches with
set 1.00 4,452.75 667.91 4,452.75 667.91
100AT/100AF Main
10.58 Electrical Tape pc 15.00 37.50 5.63 562.50 84.38
10.54 Vibrating Bell 8" set 4.00 1,500.00 225.00 6,000.00 900.00
10.55 Fire Alarm Bell, Vibrating Type set 4.00 2,000.00 300.00 8,000.00 1,200.00
10.56 Fire Alarm Station, Manual Single Action set 4.00 1,750.00 262.50 7,000.00 1,050.00
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 20.00 5,500.00 825.00 110,000.00 16,500.00
Wall hung lavatory w/accessories set 2.00 2,100.00 315.00 4,200.00 630.00
11.64 Concrete Counter Sink Type, with Lever Type set 8.00 3,150.00 472.50 25,200.00 3,780.00
11.19a G.I. Tee, 3/4" x 1/2"Ø pc 32.00 41.25 12.38 1,320.00 396.00
11.61 Water Closet Flange set 20.00 262.50 39.38 5,250.00 787.50
11.67 Tissue Holder pc 2.00 250.00 37.50 500.00 75.00
11.04 PP-R Pipe 1"Ø pc 28.00 558.00 167.40 15,624.00 4,687.20
11.10 PP-R Coupling, 1"Ø pc 32.00 25.00 7.50 800.00 240.00

4Sty16CL Schoolbuilding 124 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 4.00 11.00 3.30 44.00 13.20
11.05 PP-R Pipe 3/4"Ø pc 48.00 345.00 103.50 16,560.00 4,968.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 32.00 23.00 6.90 736.00 220.80
11.09 PP-R Coupling, 3/4"Ø pc 32.00 15.00 4.50 480.00 144.00
11.16 PP-R Tee, 3/4"Ø pc 32.00 31.00 9.30 992.00 297.60
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 60.00 84.97 25.49 5,098.20 1,529.46
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 8.00 250.00 75.00 2,000.00 600.00
11.65 S.S.Floor Drain 4' x 4" pc 24.00 97.50 14.63 2,340.00 351.00
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00 870.00
11.66 Teflon Tape roll 24.00 12.00 1.80 288.00 43.20
11.69 Mirror sq.ft 192.00 100.00 15.00 19,200.00 2,880.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 10.00 1,500.00 450.00 15,000.00 4,500.00
12.02 Concrete Pipe 150mmØ pc 92.00 200.00 60.00 18,400.00 5,520.00
12.32 Three Chamber Septic Vault unit 1.00 42,878.52 14,039.42 42,878.52 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 32.00 560.00 168.00 17,920.00 5,376.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 8.00 82.50 24.75 660.00 198.00
12.13 uPVC Elbow 90o x 4"Ø pc 32.00 96.00 28.80 3,072.00 921.60
12.27 uPVC Wye 4" x 4" pc 24.00 165.00 49.50 3,960.00 1,188.00
12.21 uPVC Tee 4" x 4" pc 24.00 138.00 41.40 3,312.00 993.60
12.25 uPVC Wye 4" x 2" pc 32.00 97.00 29.10 3,104.00 931.20
12.29 Brass Cleanout 6" x 6" pc 4.00 675.00 202.50 2,700.00 810.00
12.28 Brass Cleanout 4" x 4" pc 12.00 350.00 105.00 4,200.00 1,260.00
12.11 uPVC Elbow 90o x 2"Ø pc 24.00 25.00 7.50 600.00 180.00
12.07 uPVC Sanitary Pipe 2"Ø pc 36.00 210.00 63.00 7,560.00 2,268.00
12.22 uPVC Wye 2" x 2" pc 24.00 38.00 11.40 912.00 273.60
12.17 uPVC Tee 2" x 2" pc 24.00 36.00 10.80 864.00 259.20
12.30 uPVC P-Trap 2" pc 32.00 66.00 19.80 2,112.00 633.60
12.08 uPVC Sanitary Pipe 3"Ø pc 56.00 420.00 126.00 23,520.00 7,056.00
12.12 uPVC Elbow 90o x 3"Ø pc 20.00 53.00 15.90 1,060.00 318.00
12.33 PVC Cement can 37.00 150.00 45.00 5,550.00 1,665.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 6,056.84
13.18 Neutralizer gal 76.00 132.00 39.60 10,032.00 3,009.60
13.01 Latex, Flat gal 303.00 424.00 127.20 128,472.00 38,541.60
13.14 Masonry Putty gal 303.00 319.00 95.70 96,657.00 28,997.10
13.02 Latex, Semi Gloss gal 303.00 492.50 147.75 149,227.50 44,768.25
13.20 Acri Color qrt 76.00 165.00 49.50 12,540.00 3,762.00
Wood surfaces sq.m 913.92
13.04 Enamel, Flatwall gal 46.00 483.00 144.90 22,218.00 6,665.40
13.15 Glazing Putty gal 46.00 492.00 147.60 22,632.00 6,789.60
13.05 Enamel, Semi Gloss gal 46.00 497.00 149.10 22,862.00 6,858.60
13.16 Paint Thinner gal 35.00 260.00 78.00 9,100.00 2,730.00
Sub-total
14.00 Tile Works
Wall sq.m 304.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 8,360.00 14.00 4.20 117,040.00 35,112.00
14.16 Tile Adhesive 25 kg/bag bag 55.00 224.10 67.23 12,325.50 3,697.65
14.13 Tile Trim 6mm pc 64.00 97.75 29.33 6,256.00 1,876.80
14.15 Tile Grout 5 kg/bag bag 23.00 150.00 45.00 3,450.00 1,035.00
14.15 Flooring sq.m 113.40
14.01 Unglazed Floor Tiles 20cm x 20cm pc 3,119.00 12.00 3.60 37,428.00 11,228.40

4Sty16CL Schoolbuilding 125 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
14.16 Tile Adhesive 25 kg/bag bag 21.00 224.10 67.23 4,706.10 1,411.83
14.15 Tile Grout 5 kg/bag bag 9.00 150.00 45.00 1,350.00 405.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNAN
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

4Sty16CL Schoolbuilding 126 of 179


FourStorey Sixteen (16) Classroom

public of the Philippines


TMENT OF EDUCATION
AND SCHOOLS ENGINEERING DIVISION
Pasig City

LVE-CLASSROOM

GRAND TOTAL

183,701.05

110,220.63
293,921.69

6,840.00
131,409.00
25,562.59
95,033.25
93,620.70
7,335.90
359,801.44

18,495.50
13,277.50
6,300.00

730,442.00
264,137.50
122,850.00

140,409.50
51,975.00
23,625.00

4,689.00
2,260.00
1,050.00

401,170.00
148,417.50
67,462.50

423,833.50
156,791.25
71,400.00

307,911.00
113,767.50
51,712.50

4Sty16CL Schoolbuilding 127 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

75,805.50
28,008.75
12,862.50

91,175.00
33,783.75
15,487.50

80,234.00
38,702.50
18,112.50

4,689.00
2,260.00
1,050.00

16,932.50
6,352.50
2,887.50
3,550,320.25

1,490,916.54

439,520.18
174,853.45
5,691.63

926,392.71
930,543.41

1,027,818.94
397,592.85
566,377.77

882,714.86
174,853.45
85,846.92
69,472.54
2,025.14
19,211.43

196,650.00
7,390,481.81

44,283.20
25,228.00
2,340.00

317,241.60
114,268.00
16,692.00

382,532.80
138,012.00

4Sty16CL Schoolbuilding 128 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

20,124.00

348,129.60
125,398.00
18,330.00

76,169.60
27,454.00
4,056.00

15,184.00
11,130.00
858.00

12,896.00
12,614.00
702.00
1,713,642.80

303,300.00
440,682.36
147,403.80
209,521.68
6,450.00

287,292.00
115,560.00

182,382.00
73,440.00
1,766,031.84

196,923.00

33,398.26

23,483.13

8,349.56

69,346.13

186,300.00

4Sty16CL Schoolbuilding 129 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

125,808.00

38,184.00

5,062.50

686,854.57

81,301.71
96,397.52
199,550.23
2,225.60
3,848.00
1,248.00

3,790.80

1,684.80

27,202.50
31,531.50
203,746.40
45,942.00
13,674.70
6,282.90
718,426.65

235,569.60

14,110.00

6,720.00

9,520.00

6,769.80
2,398.00
850.50
275,937.90

108,433.00
54,145.00
637.00
2,600.00
637.00
12,870.00

4Sty16CL Schoolbuilding 130 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

27,664.00
14,508.00
182.00
715.00
182.00
3,510.00
3,185.00
15,887.66

21,686.60
8,736.00
182.00
520.00
182.00
276,462.26

28,290.60
4,290.00
598.00
132.60
1,872.00
3,119.03
172.50

110,935.44
6,771.98
12,636.00
9,113.60
2,667.42
4,188.60
950.35
46,368.00
15,778.00
5,544.00
805.00

22,648.45

5,120.66

646.88
6,900.00
9,200.00
8,050.00
6,325.00
313,124.10

126,500.00
4,830.00
28,980.00
1,716.00
6,037.50
575.00
20,311.20
1,040.00

4Sty16CL Schoolbuilding 131 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

57.20
21,528.00
956.80
624.00
1,289.60
6,627.66
416.00
2,600.00
2,691.00
10,870.00
331.20
22,080.00
260,061.16

19,500.00
23,920.00
56,917.93
23,296.00
858.00
3,993.60
5,148.00
4,305.60
4,035.20
3,510.00
5,460.00
780.00
9,828.00
1,185.60
1,123.20
2,745.60
30,576.00
1,378.00
7,215.00
205,775.73

13,041.60
167,013.60
125,654.10
193,995.75
16,302.00

28,883.40
29,421.60
29,720.60
11,830.00
615,862.65

152,152.00
16,023.15
8,132.80
4,485.00

48,656.40

4Sty16CL Schoolbuilding 132 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

6,117.93
1,755.00
237,322.28

18,664,027.14
3,546,165.16
2,665,223.08
24,875,415.37
248,754.15
PhP25,124,169.53
PhP25,125,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

4Sty16CL Schoolbuilding 133 of 179


FourStorey Sixteen (16) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED FOUR-STOREY EIGHT-CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 107,324.96 78,723.28 107,324.96 78,723.28
Billboard
Safety and Health lot 1.00 107,324.96 0.00 107,324.96 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 427.50 0.00 20.00 0.00 8,550.00
1.02 Structural Excavation cu.m 677.37 0.00 200.00 0.00 135,474.00
1.03 Backfilling and Compaction cu.m 701.41 0.00 45.00 0.00 31,563.29
1.06 Select Fill cu.m 609.19 150.00 45.00 91,378.13 27,413.44
1.04 Gravel Bedding G-1 cu.m 92.22 980.00 180.00 90,374.62 16,599.42
1.05 Soil Poisoning sq.m 470.25 15.00 4.50 7,053.75 2,116.13
Sub-total
2.00 Concreting Works
Lean Concrete cu.m 21.14
2.01 Portland Cement bag 127.00 218.00 42.50 27,686.00 5,397.50
2.05 Crushed Gravel 1" cu.m 21.25 980.00 150.00 20,825.00 3,187.50
2.03 Washed Sand cu.m 10.75 900.00 150.00 9,675.00 1,612.50
Column Footing cu.m 261.32
2.01 Portland Cement bag 3,136.00 218.00 42.50 683,648.00 133,280.00
2.05 Crushed Gravel 1" cu.m 261.50 980.00 150.00 256,270.00 39,225.00
2.03 Washed Sand cu.m 130.75 900.00 150.00 117,675.00 19,612.50
Tie beams cu.m 37.00
2.01 Portland Cement bag 445.00 218.00 42.50 97,010.00 18,912.50
2.02 Crushed Gravel 3/4" cu.m 37.25 980.00 175.00 36,505.00 6,518.75
2.03 Washed Sand cu.m 18.75 900.00 150.00 16,875.00 2,812.50
Wall Footing cu.m 4.00
2.01 Portland Cement bag 36.00 218.00 42.50 7,848.00 1,530.00
2.05 Crushed Gravel 1" cu.m 4.00 980.00 150.00 3,920.00 600.00
2.03 Washed Sand cu.m 2.00 900.00 150.00 1,800.00 300.00
Columns cu.m 125.54
2.01 Portland Cement bag 1,507.00 218.00 42.50 328,526.00 64,047.50
2.02 Crushed Gravel 3/4" cu.m 125.75 980.00 175.00 123,235.00 22,006.25
2.03 Washed Sand cu.m 63.00 900.00 150.00 56,700.00 9,450.00
Beams and Girders cu.m 126.64
2.01 Portland Cement bag 1,520.00 218.00 42.50 331,360.00 64,600.00
2.02 Crushed Gravel 3/4" cu.m 126.75 980.00 175.00 124,215.00 22,181.25
2.03 Washed Sand cu.m 63.50 900.00 150.00 57,150.00 9,525.00
Suspended Slab cu.m 124.87
2.01 Portland Cement bag 1,499.00 218.00 42.50 326,782.00 63,707.50
2.02 Crushed Gravel 3/4" cu.m 125.00 980.00 175.00 122,500.00 21,875.00
2.03 Washed Sand cu.m 62.50 900.00 150.00 56,250.00 9,375.00

4Sty16CL Schoolbuilding 134 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Roof Beams cu.m 25.66
2.01 Portland Cement bag 308.00 218.00 42.50 67,144.00 13,090.00
2.02 Crushed Gravel 3/4" cu.m 25.75 980.00 175.00 25,235.00 4,506.25
2.03 Washed Sand cu.m 13.00 900.00 150.00 11,700.00 1,950.00
Stairs cu.m 29.16
2.01 Portland Cement bag 350.00 218.00 42.50 76,300.00 14,875.00
2.02 Crushed Gravel 3/4" cu.m 29.25 980.00 175.00 28,665.00 5,118.75
2.03 Washed Sand cu.m 14.75 900.00 150.00 13,275.00 2,212.50
Slab on Grade cu.m 42.75
2.01 Portland Cement bag 385.00 218.00 42.50 83,930.00 16,362.50
2.05 Crushed Gravel 1" cu.m 42.75 980.00 150.00 41,895.00 6,412.50
2.03 Washed Sand cu.m 21.50 900.00 150.00 19,350.00 3,225.00
Ramp on Fill cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 42.50 3,924.00 765.00
2.05 Crushed Gravel 1" cu.m 2.00 980.00 150.00 1,960.00 300.00
2.03 Washed Sand cu.m 1.00 900.00 150.00 900.00 150.00
Media Agua cu.m 9.00
2.01 Portland Cement bag 108.00 218.00 42.50 23,544.00 4,590.00
2.02 Crushed Gravel 3/4" cu.m 9.00 980.00 175.00 8,820.00 1,575.00
2.03 Washed Sand cu.m 4.50 900.00 150.00 4,050.00 675.00
Sub-total
3.00 Rebar Works
3.01 Column Footing kg 26,765.96 43.10 8.62 1,153,613.05 230,722.61
3.01 Tie beams kg
Main Bars - Grade 60 kg 5,071.33 43.10 8.62 218,574.28 43,714.86
3.01 Stirrups - Grade 40 kg 2,994.34 40.10 8.02 120,072.87 24,014.57
3.01 Wall Footing - Grade 40 kg 118.28 40.10 8.02 4,743.03 948.61
3.01 Columns kg
Main Bars - Grade 60 kg 22,962.98 43.10 8.62 989,704.61 197,940.92
3.01 Ties - Grade 40 kg 17,630.35 40.10 8.02 706,977.12 141,395.42
3.01 Beams and Girders
Main Bars - Grade 60 kg 20,113.81 43.10 8.62 866,905.30 173,381.06
3.01 Stirrups - Grade 40 kg 10,477.51 40.10 8.02 420,148.23 84,029.65
3.01 Suspended Slab - Grade 40 kg 15,867.96 40.10 8.02 636,305.36 127,261.07
3.01 Roof Beams
Main Bars - Grade 60 kg 1,963.49 43.10 8.62 84,626.27 16,925.25
3.01 Stirrups - Grade 40 kg 1,074.61 40.10 8.02 43,091.94 8,618.39
3.01 Stairs - Grade 60 kg 1,659.84 43.10 8.62 71,539.10 14,307.82
3.01 Slab on Grade - Grade 40 kg 1,804.67 40.10 8.02 72,367.23 14,473.45
3.01 Ramp on Fill - Grade 40 kg 42.09 40.10 8.02 1,687.61 337.52
3.01 Media Agua - Grade 40 kg 665.40 40.10 8.02 26,682.54 5,336.51
3.01 Deformed Round Bars kg 129,212.63
3.02 G.I. Tie Wire kg 2,585.00 60.00 9.00 155,100.00 23,265.00
Sub-total
4.00 Formworks
Tie beams sq.m 239.50
4.01 Coco Lumber bd.ft 2,635.00 16.00 4.80 42,160.00 12,648.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 62.00 580.00 162.00 35,960.00 10,044.00
4.04 CWN, Assorted kg 37.00 60.00 18.00 2,220.00 666.00
Columns sq.m 981.77
4.01 Coco Lumber bd.ft 16,691.00 16.00 4.80 267,056.00 80,116.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 253.00 580.00 162.00 146,740.00 40,986.00
4.04 CWN, Assorted kg 234.00 60.00 18.00 14,040.00 4,212.00
Beams and Girders sq.m 1,031.25
4.01 Coco Lumber bd.ft 17,532.00 16.00 4.80 280,512.00 84,153.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 265.00 580.00 162.00 153,700.00 42,930.00

4Sty16CL Schoolbuilding 135 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
4.04 CWN, Assorted kg 246.00 60.00 18.00 14,760.00 4,428.00
Suspended Slab sq.m 1,248.67
4.01 Coco Lumber bd.ft 21,228.00 16.00 4.80 339,648.00 101,894.40
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 321.00 580.00 162.00 186,180.00 52,002.00
4.04 CWN, Assorted kg 298.00 60.00 18.00 17,880.00 5,364.00
Roof Beams sq.m 259.18
4.01 Coco Lumber bd.ft 4,406.00 16.00 4.80 70,496.00 21,148.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 67.00 580.00 162.00 38,860.00 10,854.00
4.04 CWN, Assorted kg 62.00 60.00 18.00 3,720.00 1,116.00
Stairs sq.m 85.80
4.01 Coco Lumber bd.ft 1,459.00 16.00 4.80 23,344.00 7,003.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 30.00 580.00 162.00 17,400.00 4,860.00
4.04 CWN, Assorted kg 21.00 60.00 18.00 1,260.00 378.00
Media Agua sq.m 81.00
4.01 Coco Lumber bd.ft 1,033.00 16.00 4.80 16,528.00 4,958.40
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 28.00 580.00 162.00 16,240.00 4,536.00
4.04 CWN, Assorted kg 15.00 60.00 18.00 900.00 270.00
Sub-total
5.00 Masonry Works
Masonry Wall sq.m 1,959.89
5.05 CHB 6" thk pc 24,499.00 12.00 3.00 293,988.00 73,497.00
5.02 Portland Cement bag 1,984.91 218.00 51.00 432,710.16 101,230.36
5.03 Washed Sand cu.m 165.37 900.00 180.00 148,831.43 29,766.29
5.06 10mm x 6m RSB kg 5,167.21 40.10 9.03 207,205.15 46,659.91
5.07 G.I. Tie Wire kg 104.00 60.00 15.00 6,240.00 1,560.00
Plastering sq.m 3,919.78
5.02 Portland Cement bag 1,294.00 218.00 51.00 282,092.00 65,994.00
5.03 Washed Sand cu.m 130.00 900.00 180.00 117,000.00 23,400.00
Floor Topping sq.m 1,282.50
5.02 Portland Cement bag 847.00 218.00 51.00 184,646.00 43,197.00
5.03 Washed Sand cu.m 85.00 900.00 180.00 76,500.00 15,300.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 32.00 7,317.50 887.63 234,160.00 28,404.00
(lever type door knob)

D-2 Flush Door 0.80m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 8.00 3,704.44 470.34 29,635.56 3,762.70
(lever type door knob)

D-3 Flush Door 0.90m x 2.10m on 150mm


6.05 set 5.00 4,167.50 529.13 20,837.50 2,645.63
Wooden Jamb complete with Accessories

D-3a Louver Door 0.80m x 2.10m on


150mm Wooden Jamb complete with set 2.00 3,704.44 470.34 7,408.89 940.68
Accessories (lever type door knob)

D-4 Cubicle Door 0.60m x 1.20m on


6.06 150mm Wooden Jamb complete with set 18.00 3,408.75 443.81 61,357.50 7,988.63
Accessories

W - 1, ( 4.0 x 1.5 m) Steel Casement


Window with Grilles, Semi French Type
6.51 set 32.00 5,750.00 2,012.50 184,000.00 64,400.00
with 1/4 thk Clear Glass Panes complete
with Accessories

4Sty16CL Schoolbuilding 136 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type
6.08 Silver Colored Frame and Fixed Clear set 32.00 4,672.00 570.00 149,504.00 18,240.00
Glass Transom on 50 x 150 mm Wooden
Jamb complete with Accessories

W - 3, ( 2.0 x 0.6 m) Steel Awning Window


6.09 with Grilles with 1/4 thk Clear Glass Panes set 8.00 4,248.00 525.00 33,984.00 4,200.00
complete with Accessories

W - 4, ( 0.95 x 0.6 m) Steel Awning Window


6.54 with Grilles with 1/4 thk Clear Glass Panes set 5.00 750.00 262.50 3,750.00 1,312.50
complete with Accessories

6.25 Security Grilles -2.30 X 1.30m set 6.00 4,020.95 1,809.43 24,125.71 10,856.57
6.26 Security Grilles -4.30 X 1.30m set 30.00 5,412.55 2,435.65 162,376.53 73,069.44
6.26 Security Grilles -1.50 X 1.60m set 32.00 2,323.81 1,045.72 74,362.06 33,462.93
Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 2,388.67 32.00 9.60 76,437.50 22,931.25
7.14 L 50 x 50 x 6mm kg 2,832.19 32.00 9.60 90,630.14 27,189.04
7.07 LC 150 x 65 x 20 x 2.0mm kg 4,433.43 43.00 12.90 190,637.31 57,191.19
7.18 Plain Round Bar 10mmØ x 6m pc 20.00 107.00 32.10 2,140.00 642.00
7.19 Plain Round Bar 12mmØ x 6m pc 24.00 185.00 55.50 4,440.00 1,332.00
7.30 Turn Buckle 12 mmØ pc 24.00 60.00 18.00 1,440.00 432.00
Anchor Bolt with Nuts and Washer, 12mmØ
7.34 pc 132.00 27.00 8.10 3,564.00 1,069.20
x 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ
7.35 pc 132.00 12.00 3.60 1,584.00 475.20
x 50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 2.75 9,300.00 2,790.00 25,575.00 7,672.50
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 5.50 5,390.00 1,617.00 29,645.00 8,893.50
7.45 G.I. Pipe 2"Ø Sch.40 pc 45.00 1,781.00 534.30 80,145.00 24,043.50
7.23 Square Bar 19mm□ x 6m pc 60.00 620.00 186.00 37,200.00 11,160.00
7.46 Welding Rod kg 194.00 67.00 20.10 12,998.00 3,899.40
13.12 Primer, Zinc Chromate gal 11.00 537.00 161.10 5,907.00 1,772.10
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-
8.16 m 642.60 380.00 76.00 244,188.00 48,837.60
Painted, 1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.610m x
8.22 pc 42.00 415.00 0.00 17,430.00 0.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x
8.19 pc 12.00 560.00 0.00 6,720.00 0.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m
8.17 pc 21.00 560.00 0.00 11,760.00 0.00
x 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 4,679.00 1.80 0.00 8,422.20 0.00
8.36 Roof Sealant L 8.00 299.75 0.00 2,398.00 0.00
8.37 Blind Rivets pc 750.00 1.35 0.00 1,012.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 427.50
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 2,744.00 38.00 11.40 104,272.00 31,281.60
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 149.00 350.00 105.00 52,150.00 15,645.00
9.22 Finishing Nails kg 9.00 70.00 21.00 630.00 189.00

4Sty16CL Schoolbuilding 137 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
9.23 Common Wire Nails kg 50.00 50.00 15.00 2,500.00 750.00
9.24 Concrete Nails kg 9.00 70.00 21.00 630.00 189.00
9.42 Wood Preservative, Brown L 14.00 900.00 270.00 12,600.00 3,780.00
Exterior ceiling sq.m 105.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 675.00 38.00 11.40 25,650.00 7,695.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 37.00 360.00 108.00 13,320.00 3,996.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00
9.23 Common Wire Nails kg 13.00 50.00 15.00 650.00 195.00
9.24 Concrete Nails kg 3.00 70.00 21.00 210.00 63.00
9.42 Wood Preservative, Brown L 4.00 900.00 270.00 3,600.00 1,080.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 10.00 245.00 73.50 2,450.00 735.00
9.16 Fascia Board, Wooden bd.ft 398.52 36.00 10.80 14,346.72 4,304.02
Blackboards sq.m 92.16
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 586.00 38.00 11.40 22,268.00 6,680.40
9.43 Lawanit, 1/4" thk pc 32.00 280.00 84.00 8,960.00 2,688.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00
9.23 Common Wire Nails kg 11.00 50.00 15.00 550.00 165.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.02 Electrical Conduit uPVC, 20mmØ pc 384.00 69.75 20.93 26,784.00 8,035.20
10.03 Electrical Conduit uPVC, 32mmØ pc 24.00 137.50 41.25 3,300.00 990.00
RSC 40mmØ pc 1.00 540.00 162.00 540.00 162.00
Entrance Cap 40mm dia. pc 1.00 90.00 18.00 90.00 18.00
10.16 Junction Box, 4" x 4" G.I. pc 117.00 15.00 4.50 1,755.00 526.50
10.17 Utility Box, 2" x 4" G.I. pc 112.00 30.00 4.28 3,360.00 478.80
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 3,456.00 33.00 7.02 114,048.00 24,261.12
10.13 8.0 mm2 THW Wire, Stranded m 79.00 79.00 16.38 6,241.00 1,294.02
10.10 30.0 mm2 THW Wire, Stranded m 54.00 180.00 54.00 9,720.00 2,916.00
10.28 Duplex C.O. with Plate pc 45.00 263.80 21.00 11,871.00 945.00
10.23 Single Switch with Plate pc 22.00 97.68 13.46 2,148.96 296.18
10.24 2-Gang Switch with Plate pc 28.00 153.00 21.53 4,284.00 602.70
10.25 3-Gang Switch with Plate pc 4.00 208.00 29.59 832.00 118.35
10.20 FL 2 x 40W Industrial Type set 64.00 840.00 126.00 53,760.00 8,064.00
Compact Fluorescent Lamp, 18 watts pc 28.00 165.00 33.00 4,620.00 924.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 28.00 25.00 3.75 700.00 105.00
Panel Box, Bolt-on type, 8 Branches with
set 1.00 4,074.75 611.21 4,074.75 611.21
60AT/100AF Main (Lugs)
Panel Box, Bolt-on type, 6 Branches with
set 3.00 3,804.75 2,092.76 11,414.25 6,278.29
60AT/100AF Main (Lugs)
Panel Box, Bolt-on type, 4 Branches with
set 1.00 8,130.75 1,219.61 8,130.75 1,219.61
125AT/225AF Main
10.58 Electrical Tape pc 18.00 37.50 5.63 675.00 101.25
10.54 Vibrating Bell 8" set 4.00 1,500.00 225.00 6,000.00 900.00
10.55 Fire Alarm Bell, Vibrating Type set 4.00 2,000.00 300.00 8,000.00 1,200.00

10.56 Fire Alarm Station, Manual Single Action set 4.00 1,750.00 262.50 7,000.00 1,050.00

10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 20.00 5,500.00 825.00 110,000.00 16,500.00
Wall hung lavatory w/accessories set 2.00 2,100.00 315.00 4,200.00 630.00
11.64 Concrete Counter Sink Type, with Lever Ty set 8.00 3,150.00 472.50 25,200.00 3,780.00

4Sty16CL Schoolbuilding 138 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
11.19a G.I. Tee, 3/4" x 1/2"Ø pc 32.00 41.25 12.38 1,320.00 396.00
11.61 Water Closet Flange set 20.00 262.50 39.38 5,250.00 787.50
11.67 Tissue Holder pc 2.00 250.00 37.50 500.00 75.00
11.04 PP-R Pipe 1"Ø pc 28.00 558.00 167.40 15,624.00 4,687.20
11.10 PP-R Coupling, 1"Ø pc 32.00 25.00 7.50 800.00 240.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 4.00 11.00 3.30 44.00 13.20
11.05 PP-R Pipe 3/4"Ø pc 48.00 345.00 103.50 16,560.00 4,968.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 32.00 23.00 6.90 736.00 220.80
11.09 PP-R Coupling, 3/4"Ø pc 32.00 15.00 4.50 480.00 144.00
11.16 PP-R Tee, 3/4"Ø pc 32.00 31.00 9.30 992.00 297.60
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 60.00 84.97 25.49 5,098.20 1,529.46
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 8.00 250.00 75.00 2,000.00 600.00
11.65 S.S.Floor Drain 4' x 4" pc 24.00 97.50 14.63 2,340.00 351.00
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00 870.00
11.66 Teflon Tape roll 24.00 12.00 1.80 288.00 43.20
11.69 Mirror sq.ft 192.00 100.00 15.00 19,200.00 2,880.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 16.00 1,500.00 450.00 24,000.00 7,200.00
12.02 Concrete Pipe 150mmØ pc 130.00 200.00 60.00 26,000.00 7,800.00
12.32 Three Chamber Septic Vault unit 1.00 42,878.52 14,039.42 42,878.52 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 32.00 560.00 168.00 17,920.00 5,376.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 8.00 82.50 24.75 660.00 198.00
12.13 uPVC Elbow 90o x 4"Ø pc 32.00 96.00 28.80 3,072.00 921.60
12.27 uPVC Wye 4" x 4" pc 24.00 165.00 49.50 3,960.00 1,188.00
12.21 uPVC Tee 4" x 4" pc 24.00 138.00 41.40 3,312.00 993.60
12.25 uPVC Wye 4" x 2" pc 32.00 97.00 29.10 3,104.00 931.20
12.29 Brass Cleanout 6" x 6" pc 4.00 675.00 202.50 2,700.00 810.00
12.28 Brass Cleanout 4" x 4" pc 12.00 350.00 105.00 4,200.00 1,260.00
12.11 uPVC Elbow 90o x 2"Ø pc 24.00 25.00 7.50 600.00 180.00
12.07 uPVC Sanitary Pipe 2"Ø pc 36.00 210.00 63.00 7,560.00 2,268.00
12.22 uPVC Wye 2" x 2" pc 24.00 38.00 11.40 912.00 273.60
12.17 uPVC Tee 2" x 2" pc 24.00 36.00 10.80 864.00 259.20
12.30 uPVC P-Trap 2" pc 32.00 66.00 19.80 2,112.00 633.60
12.08 uPVC Sanitary Pipe 3"Ø pc 68.00 420.00 126.00 28,560.00 8,568.00
12.12 uPVC Elbow 90o x 3"Ø pc 24.00 53.00 15.90 1,272.00 381.60
12.33 PVC Cement can 32.00 150.00 45.00 4,800.00 1,440.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 7,116.56
13.18 Neutralizer gal 89.00 132.00 39.60 11,748.00 3,524.40
13.01 Latex, Flat gal 356.00 424.00 127.20 150,944.00 45,283.20
13.14 Masonry Putty gal 356.00 319.00 95.70 113,564.00 34,069.20
13.02 Latex, Semi Gloss gal 356.00 492.50 147.75 175,330.00 52,599.00
13.20 Acri Color qrt 89.00 165.00 49.50 14,685.00 4,405.50
Wood surfaces sq.m 1,179.02
13.04 Enamel, Flatwall gal 59.00 0.40 144.90 23.60 8,549.10
13.15 Glazing Putty gal 59.00 492.00 147.60 29,028.00 8,708.40
13.05 Enamel, Semi Gloss gal 59.00 497.00 149.10 29,323.00 8,796.90
13.16 Paint Thinner gal 45.00 260.00 78.00 11,700.00 3,510.00
Sub-total
14.00 Tile Works
Wall sq.m 304.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 8,360.00 14.00 4.20 117,040.00 35,112.00

4Sty16CL Schoolbuilding 139 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
14.16 Tile Adhesive 25 kg/bag bag 55.00 224.10 67.23 12,325.50 3,697.65
14.13 Tile Trim 6mm pc 64.00 97.75 29.33 6,256.00 1,876.80
14.15 Tile Grout 5 kg/bag bag 23.00 150.00 45.00 3,450.00 1,035.00
14.15 Flooring sq.m 113.40
14.01 Unglazed Floor Tiles 20cm x 20cm pc 3,119.00 12.00 3.60 37,428.00 11,228.40
14.16 Tile Adhesive 25 kg/bag bag 21.00 224.10 67.23 4,706.10 1,411.83
14.15 Tile Grout 5 kg/bag bag 9.00 150.00 45.00 1,350.00 405.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNAN
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

4Sty16CL Schoolbuilding 140 of 179


FourStorey Sixteen (16) Classroom

public of the Philippines


TMENT OF EDUCATION
AND SCHOOLS ENGINEERING DIVISION
Pasig City

HT-CLASSROOM

GRAND TOTAL

186,048.25

107,324.96
293,373.21

8,550.00
135,474.00
31,563.29
118,791.56
106,974.04
9,169.88
410,522.77

33,083.50
24,012.50
11,287.50

816,928.00
295,495.00
137,287.50

115,922.50
43,023.75
19,687.50

9,378.00
4,520.00
2,100.00

392,573.50
145,241.25
66,150.00

395,960.00
146,396.25
66,675.00

390,489.50
144,375.00
65,625.00

4Sty16CL Schoolbuilding 141 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

80,234.00
29,741.25
13,650.00

91,175.00
33,783.75
15,487.50

100,292.50
48,307.50
22,575.00

4,689.00
2,260.00
1,050.00

28,134.00
10,395.00
4,725.00
3,812,710.75

1,384,335.66

262,289.14
144,087.45
5,691.63

1,187,645.53
848,372.54

1,040,286.36
504,177.88
763,566.43

101,551.52
51,710.33
85,846.92
86,840.67
2,025.14
32,019.05

178,365.00
6,678,811.25

54,808.00
46,004.00
2,886.00

347,172.80
187,726.00
18,252.00

364,665.60
196,630.00

4Sty16CL Schoolbuilding 142 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

19,188.00

441,542.40
238,182.00
23,244.00

91,644.80
49,714.00
4,836.00

30,347.20
22,260.00
1,638.00

21,486.40
20,776.00
1,170.00
2,184,173.20

367,485.00
533,940.52
178,597.71
253,865.07
7,800.00

348,086.00
140,400.00

227,843.00
91,800.00
2,149,817.29

262,564.00

33,398.26

23,483.13

8,349.56

69,346.13

248,400.00

4Sty16CL Schoolbuilding 143 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

167,744.00

38,184.00

5,062.50

34,982.28
235,445.97
107,824.99
1,234,784.81

99,368.76
117,819.19
247,828.51
2,782.00
5,772.00
1,872.00

4,633.20

2,059.20

33,247.50
38,538.50
104,188.50
48,360.00
16,897.40
7,679.10
731,045.85

293,025.60

17,430.00

6,720.00

11,760.00

8,422.20
2,398.00
1,012.50
340,768.30

135,553.60
67,795.00
819.00

4Sty16CL Schoolbuilding 144 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

3,250.00
819.00
16,380.00

33,345.00
17,316.00
273.00
845.00
273.00
4,680.00
3,185.00
18,650.74

28,948.40
11,648.00
182.00
715.00
182.00
344,859.74

34,819.20
4,290.00
702.00
108.00
2,281.50
3,838.80
172.50

138,309.12
7,535.02
12,636.00
12,816.00
2,445.14
4,886.70
950.35
61,824.00
5,544.00
805.00

4,685.96

17,692.54

9,350.36

776.25
6,900.00
9,200.00

8,050.00

6,325.00
356,943.44

126,500.00
4,830.00
28,980.00

4Sty16CL Schoolbuilding 145 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

1,716.00
6,037.50
575.00
20,311.20
1,040.00
57.20
21,528.00
956.80
624.00
1,289.60
6,627.66
416.00
2,600.00
2,691.00
10,870.00
331.20
22,080.00
260,061.16

31,200.00
33,800.00
56,917.93
23,296.00
858.00
3,993.60
5,148.00
4,305.60
4,035.20
3,510.00
5,460.00
780.00
9,828.00
1,185.60
1,123.20
2,745.60
37,128.00
1,653.60
6,240.00
233,208.33

15,272.40
196,227.20
147,633.20
227,929.00
19,090.50

8,572.70
37,736.40
38,119.90
15,210.00
705,791.30

152,152.00

4Sty16CL Schoolbuilding 146 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

16,023.15
8,132.80
4,485.00

48,656.40
6,117.93
1,755.00
237,322.28

19,974,193.68
3,795,096.80
2,852,314.86
26,621,605.33
266,216.05
PhP26,887,821.39
PhP26,888,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

4Sty16CL Schoolbuilding 147 of 179


FourStorey Sixteen (16) Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED FOUR-STOREY TWENTY-CLASSROOM


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 166,242.26 110,828.17 166,242.26 110,828.17
Billboard
Safety and Health lot 1.00 166,242.26 0.00 166,242.26 0.00
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 513.00 0.00 20.00 0.00 10,260.00
1.02 Structural Excavation cu.m 983.48 0.00 200.00 0.00 196,696.60
1.03 Backfilling and Compaction cu.m 852.08 0.00 45.00 0.00 38,343.40
1.06 Select Fill cu.m 731.03 150.00 45.00 109,653.75 32,896.13
1.04 Gravel Bedding G-1 cu.m 121.05 980.00 180.00 118,629.49 21,789.09
1.05 Soil Poisoning sq.m 564.30 15.00 4.50 8,464.50 2,539.35
Sub-total
2.00 Concreting Works
Lean Concrete cu.m 28.25
2.01 Portland Cement bag 170.00 218.00 42.50 37,060.00 7,225.00
2.05 Crushed Gravel 1" cu.m 28.25 980.00 150.00 27,685.00 4,237.50
2.03 Washed Sand cu.m 14.25 900.00 150.00 12,825.00 2,137.50
Column Footing cu.m 349.16
2.01 Portland Cement bag 4,190.00 218.00 42.50 913,420.00 178,075.00
2.05 Crushed Gravel 1" cu.m 349.25 980.00 150.00 342,265.00 52,387.50
2.03 Washed Sand cu.m 174.75 900.00 150.00 157,275.00 26,212.50
Tie beams cu.m 68.25
2.01 Portland Cement bag 820.00 218.00 42.50 178,760.00 34,850.00
2.02 Crushed Gravel 3/4" cu.m 68.50 980.00 175.00 67,130.00 11,987.50
2.03 Washed Sand cu.m 34.25 900.00 150.00 30,825.00 5,137.50
Wall Footing cu.m 2.00
2.01 Portland Cement bag 18.00 218.00 42.50 3,924.00 765.00
2.05 Crushed Gravel 1" cu.m 2.00 980.00 150.00 1,960.00 300.00
2.03 Washed Sand cu.m 1.00 900.00 150.00 900.00 150.00
Columns cu.m 185.06
2.01 Portland Cement bag 2,221.00 218.00 42.50 484,178.00 94,392.50
2.02 Crushed Gravel 3/4" cu.m 185.25 980.00 175.00 181,545.00 32,418.75
2.03 Washed Sand cu.m 92.75 900.00 150.00 83,475.00 13,912.50
Beams and Girders cu.m 184.50
2.01 Portland Cement bag 2,215.00 218.00 42.50 482,870.00 94,137.50
2.02 Crushed Gravel 3/4" cu.m 184.75 980.00 175.00 181,055.00 32,331.25
2.03 Washed Sand cu.m 92.50 900.00 150.00 83,250.00 13,875.00
Suspended Slab cu.m 146.98
2.01 Portland Cement bag 1,764.00 218.00 42.50 384,552.00 74,970.00
2.02 Crushed Gravel 3/4" cu.m 147.00 980.00 175.00 144,060.00 25,725.00
2.03 Washed Sand cu.m 73.50 900.00 150.00 66,150.00 11,025.00

4Sty16CL Schoolbuilding 148 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Roof Beams cu.m 34.67
2.01 Portland Cement bag 417.00 218.00 42.50 90,906.00 17,722.50
2.02 Crushed Gravel 3/4" cu.m 34.75 980.00 175.00 34,055.00 6,081.25
2.03 Washed Sand cu.m 17.50 900.00 150.00 15,750.00 2,625.00
Stairs cu.m 14.58
2.01 Portland Cement bag 175.00 218.00 42.50 38,150.00 7,437.50
2.02 Crushed Gravel 3/4" cu.m 14.75 980.00 175.00 14,455.00 2,581.25
2.03 Washed Sand cu.m 7.50 900.00 150.00 6,750.00 1,125.00
Slab on Grade cu.m 51.30
2.01 Portland Cement bag 462.00 218.00 42.50 100,716.00 19,635.00
2.05 Crushed Gravel 1" cu.m 51.50 980.00 150.00 50,470.00 7,725.00
2.03 Washed Sand cu.m 25.75 900.00 150.00 23,175.00 3,862.50
Ramp on Fill cu.m 1.00
2.01 Portland Cement bag 9.00 218.00 42.50 1,962.00 382.50
2.05 Crushed Gravel 1" cu.m 1.00 980.00 150.00 980.00 150.00
2.03 Washed Sand cu.m 0.50 900.00 150.00 450.00 75.00
Media Agua cu.m 4.50
2.01 Portland Cement bag 54.00 218.00 42.50 11,772.00 2,295.00
2.02 Crushed Gravel 3/4" cu.m 4.50 980.00 175.00 4,410.00 787.50
2.03 Washed Sand cu.m 2.25 900.00 150.00 2,025.00 337.50
Sub-total
3.00 Rebar Works
3.01 Column Footing kg 57,483.50 43.10 8.62 2,477,538.63 495,507.73
3.01 Tie beams kg
Main Bars - Grade 60 kg 15,042.16 43.10 8.62 648,317.18 129,663.44
3.01 Stirrups - Grade 40 kg 6,609.38 40.10 8.02 265,036.30 53,007.26
3.01 Wall Footing - Grade 40 kg 118.28 40.10 8.02 4,743.03 948.61
3.01 Columns kg
Main Bars - Grade 60 kg 32,162.21 43.10 8.62 1,386,191.16 277,238.23
3.01 Ties - Grade 40 kg 29,274.70 40.10 8.02 1,173,915.31 234,783.06
3.01 Beams and Girders
Main Bars - Grade 60 kg 27,355.45 43.10 8.62 1,179,019.85 235,803.97
3.01 Stirrups - Grade 40 kg 13,312.04 40.10 8.02 533,812.96 106,762.59
3.01 Suspended Slab - Grade 40 kg 22,196.01 40.10 8.02 890,060.15 178,012.03
3.01 Roof Beams
Main Bars - Grade 60 kg 24,921.36 43.10 8.62 1,074,110.49 214,822.10
3.01 Stirrups - Grade 40 kg 3,042.29 40.10 8.02 121,995.75 24,399.15
3.01 Stairs - Grade 60 kg 1,659.84 43.10 8.62 71,539.10 14,307.82
3.01 Slab on Grade - Grade 40 kg 2,165.60 40.10 8.02 86,840.67 17,368.13
3.01 Ramp on Fill - Grade 40 kg 21.04 40.10 8.02 843.81 168.76
3.01 Media Agua - Grade 40 kg 665.40 40.10 8.02 26,682.54 5,336.51
3.01 Deformed Round Bars kg 236,029.26
3.02 G.I. Tie Wire kg 4,721.00 60.00 9.00 283,260.00 42,489.00
Sub-total
4.00 Formworks
Tie beams sq.m 589.00
4.01 Coco Lumber bd.ft 6,479.00 16.00 4.80 103,664.00 31,099.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 101.00 580.00 162.00 58,580.00 16,362.00
4.04 CWN, Assorted kg 91.00 60.00 18.00 5,460.00 1,638.00
Columns sq.m 1,284.09
4.01 Coco Lumber bd.ft 21,830.00 16.00 4.80 349,280.00 104,784.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 220.00 580.00 162.00 127,600.00 35,640.00
4.04 CWN, Assorted kg 306.00 60.00 18.00 18,360.00 5,508.00
Beams and Girders sq.m 1,449.60
4.01 Coco Lumber bd.ft 24,644.00 16.00 4.80 394,304.00 118,291.20
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 249.00 580.00 162.00 144,420.00 40,338.00

4Sty16CL Schoolbuilding 149 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
4.04 CWN, Assorted kg 346.00 60.00 18.00 20,760.00 6,228.00
Suspended Slab sq.m 1,469.76
4.01 Coco Lumber bd.ft 24,986.00 16.00 4.80 399,776.00 119,932.80
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 252.00 580.00 162.00 146,160.00 40,824.00
4.04 CWN, Assorted kg 350.00 60.00 18.00 21,000.00 6,300.00
Roof Beams sq.m 340.68
4.01 Coco Lumber bd.ft 5,792.00 16.00 4.80 92,672.00 27,801.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 59.00 580.00 162.00 34,220.00 9,558.00
4.04 CWN, Assorted kg 82.00 60.00 18.00 4,920.00 1,476.00
Stairs sq.m 42.90
4.01 Coco Lumber bd.ft 730.00 16.00 4.80 11,680.00 3,504.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 15.00 580.00 162.00 8,700.00 2,430.00
4.04 CWN, Assorted kg 11.00 60.00 18.00 660.00 198.00
Media Agua sq.m 40.50
4.01 Coco Lumber bd.ft 517.00 16.00 4.80 8,272.00 2,481.60
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 14.00 580.00 162.00 8,120.00 2,268.00
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00
Sub-total
5.00 Masonry Works
Masonry Wall sq.m 2,151.69
5.05 CHB 6" thk pc 26,897.00 12.00 3.00 322,764.00 80,691.00
5.02 Portland Cement bag 2,179.19 218.00 51.00 475,064.50 111,138.94
5.03 Washed Sand cu.m 181.55 900.00 180.00 163,399.28 32,679.86
5.06 10mm x 6m RSB kg 5,672.89 40.10 9.03 227,482.79 51,226.18
5.07 G.I. Tie Wire kg 114.00 60.00 15.00 6,840.00 1,710.00
Plastering sq.m 4,303.38
5.02 Portland Cement bag 1,421.00 218.00 51.00 309,778.00 72,471.00
5.03 Washed Sand cu.m 143.00 900.00 180.00 128,700.00 25,740.00
Floor Topping sq.m 1,539.00
5.02 Portland Cement bag 1,016.00 218.00 51.00 221,488.00 51,816.00
5.03 Washed Sand cu.m 102.00 900.00 180.00 91,800.00 18,360.00
Sub-total
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


6.03 Wooden Jamb complete with Accessories set 40.00 7,317.50 887.63 292,700.00 35,505.00
(lever type door knob)

D-2 Flush Door 0.80m x 2.10m on 150mm


6.04 Wooden Jamb complete with Accessories set 8.00 3,704.44 470.34 29,635.56 3,762.70
(lever type door knob)

D-3 Flush Door 0.90m x 2.10m on 150mm


6.05 set 5.00 4,167.50 529.13 20,837.50 2,645.63
Wooden Jamb complete with Accessories

D-3a Louver Door 0.80m x 2.10m on 150mm


Wooden Jamb complete with Accessories set 2.00 3,704.44 470.34 7,408.89 940.68
(lever type door knob)

D-4 Cubicle Door 0.60m x 1.20m on 150mm


6.06 set 18.00 3,408.75 443.81 61,357.50 7,988.63
Wooden Jamb complete with Accessories

W - 1, ( 4.0 x 1.5 m) Steel Casement Window


6.51 with Grilles, Semi French Type with 1/4 thk set 40.00 5,750.00 2,012.50 230,000.00 80,500.00
Clear Glass Panes complete with Accessories

4Sty16CL Schoolbuilding 150 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR

W - 2, ( 1.5 x 1.6 m) Jalousie Window with


Clear Glass Blades on JalouPlus Type Silver
6.08 Colored Frame and Fixed Clear Glass set 40.00 4,672.00 570.00 186,880.00 22,800.00
Transom on 50 x 150 mm Wooden Jamb
complete with Accessories

W - 3, ( 2.0 x 0.6 m) Steel Awning Window with


6.09 Grilles with 1/4 thk Clear Glass Panes set 8.00 4,248.00 525.00 33,984.00 4,200.00
complete with Accessories

W - 4, ( 0.95 x 0.6 m) Steel Awning Window


6.54 with Grilles with 1/4 thk Clear Glass Panes set 5.00 750.00 262.50 3,750.00 1,312.50
complete with Accessories

Sub-total
7.00 Steel Works
7.13 L 50 x 50 x 5mm kg 2,822.98 32.00 9.60 90,335.23 27,100.57
7.14 L 50 x 50 x 6mm kg 3,347.14 32.00 9.60 107,108.35 32,132.51
7.07 LC 150 x 65 x 20 x 2.0mm kg 5,297.08 43.00 12.90 227,774.45 68,332.34
7.18 Plain Round Bar 10mmØ x 6m pc 24.00 107.00 32.10 2,568.00 770.40
7.19 Plain Round Bar 12mmØ x 6m pc 30.00 185.00 55.50 5,550.00 1,665.00
7.30 Turn Buckle 12 mmØ pc 20.00 60.00 18.00 1,200.00 360.00
Anchor Bolt with Nuts and Washer, 12mmØ x
7.34 pc 156.00 27.00 8.10 4,212.00 1,263.60
50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
7.35 pc 156.00 12.00 3.60 1,872.00 561.60
50mm x 200mm
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 3.25 9,300.00 2,790.00 30,225.00 9,067.50
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 6.50 5,390.00 1,617.00 35,035.00 10,510.50
7.45 G.I. Pipe 2"Ø Sch.40 pc 124.00 1,781.00 534.30 220,844.00 66,253.20
7.23 Square Bar 19mm□ x 6m pc 57.00 620.00 186.00 35,340.00 10,602.00
7.46 Welding Rod kg 230.00 67.00 20.10 15,410.00 4,623.00
13.12 Primer, Zinc Chromate gal 13.00 537.00 161.10 6,981.00 2,094.30
Sub-total
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted,
8.16 m 768.60 380.00 76.00 292,068.00 58,413.60
1220mm x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.610m x
8.22 pc 50.00 415.00 0.00 20,750.00 0.00
2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x
8.19 pc 12.00 560.00 0.00 6,720.00 0.00
2.440m x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x
8.17 pc 25.00 560.00 0.00 14,000.00 0.00
2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 5,596.00 1.80 0.00 10,072.80 0.00
8.36 Roof Sealant L 10.00 299.75 0.00 2,997.50 0.00
8.37 Blind Rivets pc 870.00 1.35 0.00 1,174.50 0.00
Sub-total
9.00 Carpentry Works
Interior ceiling sq.m 513.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 3,292.00 38.00 11.40 125,096.00 37,528.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 179.00 350.00 105.00 62,650.00 18,795.00
9.22 Finishing Nails kg 10.00 70.00 21.00 700.00 210.00
9.23 Common Wire Nails kg 60.00 50.00 15.00 3,000.00 900.00
9.24 Concrete Nails kg 10.00 70.00 21.00 700.00 210.00
9.42 Wood Preservative, Brown L 17.00 900.00 270.00 15,300.00 4,590.00

4Sty16CL Schoolbuilding 151 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
Exterior ceiling sq.m 123.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 791.00 38.00 11.40 30,058.00 9,017.40
9.06 Plywood, Marine 1/4" x 4' x 8' pc 43.00 360.00 108.00 15,480.00 4,644.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00
9.23 Common Wire Nails kg 15.00 50.00 15.00 750.00 225.00
9.24 Concrete Nails kg 3.00 70.00 21.00 210.00 63.00
9.42 Wood Preservative, Brown L 4.00 900.00 270.00 3,600.00 1,080.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 10.00 245.00 73.50 2,450.00 735.00
9.16 Fascia Board, Wooden bd.ft 457.56 36.00 10.80 16,472.16 4,941.65
Blackboards sq.m 115.20
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 732.00 38.00 11.40 27,816.00 8,344.80
9.43 Lawanit, 1/4" thk pc 39.00 280.00 84.00 10,920.00 3,276.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00
9.23 Common Wire Nails kg 14.00 50.00 15.00 700.00 210.00
9.24 Concrete Nails kg 3.00 70.00 21.00 210.00 63.00
Sub-total
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 520.00 50.00 15.00 26,000.00 7,800.00
10.03 Electrical Conduit uPVC, 32mmØ pc 24.00 137.50 41.25 3,300.00 990.00
RSC 40mmØ pc 1.00 460.00 138.00 460.00 138.00
Entrance Cap 40mm dia. pc 1.00 102.00 30.60 102.00 30.60
10.16 Junction Box, 4" x 4" G.I. pc 160.00 15.00 4.50 2,400.00 720.00
10.17 Utility Box, 2" x 4" G.I. pc 155.00 30.00 4.28 4,650.00 662.63
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 4,620.00 33.00 7.02 152,460.00 32,432.40
10.13 8.0 mm2 THW Wire, Stranded m 83.00 79.00 16.38 6,557.00 1,359.54
10.10 60.0 mm2 THW Wire, Stranded m 54.00 180.00 54.00 9,720.00 2,916.00
10.28 Duplex C.O. with Plate pc 56.00 263.80 21.00 14,772.80 1,176.00
10.23 Single Switch with Plate pc 22.00 97.68 13.46 2,148.96 296.18
10.24 2-Gang Switch with Plate pc 32.00 153.00 21.53 4,896.00 688.80
10.25 3-Gang Switch with Plate pc 8.00 208.00 29.59 1,664.00 236.70
10.20 FL 2 x 40W Industrial Type set 80.00 840.00 126.00 67,200.00 10,080.00
10.21 FL 1 x 40W Industrial Type set 34.00 490.00 73.50 16,660.00 2,499.00
Compact Fluorescent Lamp, 18 watts pc 36.00 165.00 33.00 5,940.00 1,188.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 36.00 25.00 3.75 900.00 135.00
Panel Box, Bolt-on type, 8 Branches with
set 1.00 4,877.50 731.63 4,877.50 731.63
60AT/100AF Main (Lugs)
Panel Box, Bolt-on type, 6 Branches with
set 3.00 4,697.50 964.61 14,092.50 2,893.84
60AT/100AF Main (Lugs)
Panel Box, Bolt-on type, 4 Branches with
set 1.00 6,802.75 1,020.41 6,802.75 1,020.41
125AT/225AF Main
10.58 Electrical Tape pc 21.00 37.50 5.63 787.50 118.13
10.54 Vibrating Bell 8" set 4.00 1,500.00 225.00 6,000.00 900.00
10.55 Fire Alarm Bell, Vibrating Type set 4.00 2,000.00 300.00 8,000.00 1,200.00
10.56 Fire Alarm Station, Manual Single Action set 4.00 1,750.00 262.50 7,000.00 1,050.00
10.57 Fire Alarm Control Panel, One Zone set 1.00 5,500.00 825.00 5,500.00 825.00
Sub-total
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 20.00 5,500.00 825.00 110,000.00 16,500.00
Wall hung lavatory w/accessories set 2.00 2,100.00 315.00 4,200.00 630.00
11.64 Concrete Counter Sink Type, with Lever Type set 8.00 3,150.00 472.50 25,200.00 3,780.00
11.19a G.I. Tee, 3/4" x 1/2"Ø pc 32.00 41.25 12.38 1,320.00 396.00
11.61 Water Closet Flange set 20.00 262.50 39.38 5,250.00 787.50
11.67 Tissue Holder pc 2.00 250.00 37.50 500.00 75.00

4Sty16CL Schoolbuilding 152 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
11.04 PP-R Pipe 1"Ø pc 28.00 558.00 167.40 15,624.00 4,687.20
11.10 PP-R Coupling, 1"Ø pc 32.00 25.00 7.50 800.00 240.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 4.00 11.00 3.30 44.00 13.20
11.05 PP-R Pipe 3/4"Ø pc 48.00 345.00 103.50 16,560.00 4,968.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 32.00 23.00 6.90 736.00 220.80
11.09 PP-R Coupling, 3/4"Ø pc 32.00 15.00 4.50 480.00 144.00
11.16 PP-R Tee, 3/4"Ø pc 32.00 31.00 9.30 992.00 297.60
11.77 PP-R Adaptor Female Thread 1/2"Ø pc 60.00 84.97 25.49 5,098.20 1,529.46
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00
11.44 Gate Valve, 1/2"Ø pc 8.00 250.00 75.00 2,000.00 600.00
11.65 S.S.Floor Drain 4' x 4" pc 24.00 97.50 14.63 2,340.00 351.00
11.68 S.S. Grab Rail 1-1/2"Ø set 2.00 5,000.00 435.00 10,000.00 870.00
11.66 Teflon Tape roll 24.00 12.00 1.80 288.00 43.20
11.69 Mirror sq.ft 192.00 100.00 15.00 19,200.00 2,880.00
Sub-total
12.00 Sanitary Works
12.01 Catch Basin unit 16.00 1,500.00 450.00 24,000.00 7,200.00
12.02 Concrete Pipe 150mmØ pc 130.00 200.00 60.00 26,000.00 7,800.00
12.32 Three Chamber Septic Vault unit 1.00 42,878.52 14,039.42 42,878.52 14,039.42
12.09 uPVC Sanitary Pipe 4"Ø pc 32.00 560.00 168.00 17,920.00 5,376.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 8.00 82.50 24.75 660.00 198.00
12.13 uPVC Elbow 90o x 4"Ø pc 32.00 96.00 28.80 3,072.00 921.60
12.27 uPVC Wye 4" x 4" pc 24.00 165.00 49.50 3,960.00 1,188.00
12.21 uPVC Tee 4" x 4" pc 24.00 138.00 41.40 3,312.00 993.60
12.25 uPVC Wye 4" x 2" pc 32.00 97.00 29.10 3,104.00 931.20
12.29 Brass Cleanout 6" x 6" pc 4.00 675.00 202.50 2,700.00 810.00
12.28 Brass Cleanout 4" x 4" pc 12.00 350.00 105.00 4,200.00 1,260.00
12.11 uPVC Elbow 90o x 2"Ø pc 24.00 25.00 7.50 600.00 180.00
12.07 uPVC Sanitary Pipe 2"Ø pc 36.00 210.00 63.00 7,560.00 2,268.00
12.22 uPVC Wye 2" x 2" pc 24.00 38.00 11.40 912.00 273.60
12.17 uPVC Tee 2" x 2" pc 24.00 36.00 10.80 864.00 259.20
12.30 uPVC P-Trap 2" pc 32.00 66.00 19.80 2,112.00 633.60
12.08 uPVC Sanitary Pipe 3"Ø pc 118.00 420.00 126.00 49,560.00 14,868.00
12.12 uPVC Elbow 90o x 3"Ø pc 42.00 53.00 15.90 2,226.00 667.80
12.33 PVC Cement can 37.00 150.00 45.00 5,550.00 1,665.00
Sub-total
13.00 Painting Works
Concrete surfaces sq.m 8,288.86
13.18 Neutralizer gal 104.00 132.00 39.60 13,728.00 4,118.40
13.01 Latex, Flat gal 415.00 424.00 127.20 175,960.00 52,788.00
13.14 Masonry Putty gal 415.00 319.00 95.70 132,385.00 39,715.50
13.02 Latex, Semi Gloss gal 415.00 492.50 147.75 204,387.50 61,316.25
13.20 Acri Color qrt 104.00 165.00 49.50 17,160.00 5,148.00
Wood surfaces sq.m 1,444.12
13.04 Enamel, Flatwall gal 73.00 483.00 144.90 35,259.00 10,577.70
13.15 Glazing Putty gal 73.00 492.00 147.60 35,916.00 10,774.80
13.05 Enamel, Semi Gloss gal 73.00 497.00 149.10 36,281.00 10,884.30
13.16 Paint Thinner gal 55.00 260.00 78.00 14,300.00 4,290.00
Sub-total
14.00 Tile Works
Wall sq.m 304.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 8,360.00 14.00 4.20 117,040.00 35,112.00
14.16 Tile Adhesive 25 kg/bag bag 55.00 224.10 67.23 12,325.50 3,697.65
14.13 Tile Trim 6mm pc 64.00 97.75 29.33 6,256.00 1,876.80
14.15 Tile Grout 5 kg/bag bag 23.00 150.00 45.00 3,450.00 1,035.00

4Sty16CL Schoolbuilding 153 of 179


FourStorey Sixteen (16) Classroom

UNIT COST TOTAL COST


I.D. NO DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
14.15 Flooring sq.m 113.40
14.01 Unglazed Floor Tiles 20cm x 20cm pc 3,119.00 12.00 3.60 37,428.00 11,228.40
14.16 Tile Adhesive 25 kg/bag bag 21.00 224.10 67.23 4,706.10 1,411.83
14.15 Tile Grout 5 kg/bag bag 9.00 150.00 45.00 1,350.00 405.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

Prepared by: Checked: Approved:

OLIVER R. HERNAN
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

4Sty16CL Schoolbuilding 154 of 179


FourStorey Sixteen (16) Classroom

epublic of the Philippines


TMENT OF EDUCATION
AND SCHOOLS ENGINEERING DIVISION
Pasig City

ENTY-CLASSROOM

GRAND TOTAL

277,070.43

166,242.26
443,312.68

10,260.00
196,696.60
38,343.40
142,549.88
140,418.58
11,003.85
539,272.30

44,285.00
31,922.50
14,962.50

1,091,495.00
394,652.50
183,487.50

213,610.00
79,117.50
35,962.50

4,689.00
2,260.00
1,050.00

578,570.50
213,963.75
97,387.50

577,007.50
213,386.25
97,125.00

459,522.00
169,785.00
77,175.00

4Sty16CL Schoolbuilding 155 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

108,628.50
40,136.25
18,375.00

45,587.50
17,036.25
7,875.00

120,351.00
58,195.00
27,037.50

2,344.50
1,130.00
525.00

14,067.00
5,197.50
2,362.50
5,050,265.00

2,973,046.36

777,980.62
318,043.56
5,691.63

1,663,429.40
1,408,698.37

1,414,823.82
640,575.56
1,068,072.19

1,288,932.58
146,394.90
85,846.92
104,208.81
1,012.57
32,019.05

325,749.00
12,254,525.34

134,763.20
74,942.00
7,098.00

454,064.00
163,240.00
23,868.00

512,595.20
184,758.00

4Sty16CL Schoolbuilding 156 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

26,988.00

519,708.80
186,984.00
27,300.00

120,473.60
43,778.00
6,396.00

15,184.00
11,130.00
858.00

10,753.60
10,388.00
624.00
2,535,894.40

403,455.00
586,203.44
196,079.13
278,708.97
8,550.00

382,249.00
154,440.00

273,304.00
110,160.00
2,393,149.54

328,205.00

33,398.26

23,483.13

8,349.56

69,346.13

310,500.00

4Sty16CL Schoolbuilding 157 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

209,680.00

38,184.00

5,062.50

1,026,208.57

117,435.80
139,240.86
296,106.79
3,338.40
7,215.00
1,560.00

5,475.60

2,433.60

39,292.50
45,545.50
287,097.20
45,942.00
20,033.00
9,075.30
1,019,791.55

350,481.60

20,750.00

6,720.00

14,000.00

10,072.80
2,997.50
1,174.50
406,196.40

162,624.80
81,445.00
910.00
3,900.00
910.00
19,890.00

4Sty16CL Schoolbuilding 158 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

39,075.40
20,124.00
273.00
975.00
273.00
4,680.00
3,185.00
21,413.81

36,160.80
14,196.00
273.00
910.00
273.00
411,491.81

33,800.00
4,290.00
598.00
132.60
3,120.00
5,312.63
172.50

184,892.40
7,916.54
12,636.00
15,948.80
2,445.14
5,584.80
1,900.70
77,280.00
19,159.00
7,128.00
1,035.00

5,609.13

16,986.34

7,823.16

905.63
6,900.00
9,200.00
8,050.00
6,325.00
445,151.35

126,500.00
4,830.00
28,980.00
1,716.00
6,037.50
575.00

4Sty16CL Schoolbuilding 159 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

20,311.20
1,040.00
57.20
21,528.00
956.80
624.00
1,289.60
6,627.66
416.00
2,600.00
2,691.00
10,870.00
331.20
22,080.00
260,061.16

31,200.00
33,800.00
56,917.93
23,296.00
858.00
3,993.60
5,148.00
4,305.60
4,035.20
3,510.00
5,460.00
780.00
9,828.00
1,185.60
1,123.20
2,745.60
64,428.00
2,893.80
7,215.00
262,723.53

17,846.40
228,748.00
172,100.50
265,703.75
22,308.00

45,836.70
46,690.80
47,165.30
18,590.00
864,989.45

152,152.00
16,023.15
8,132.80
4,485.00

4Sty16CL Schoolbuilding 160 of 179


FourStorey Sixteen (16) Classroom

GRAND TOTAL

48,656.40
6,117.93
1,755.00
237,322.28

28,150,355.36
5,348,567.52
4,019,870.75
37,518,793.63
375,187.94
PhP37,893,981.56
PhP37,894,000.00

OLIVER R. HERNANDEZ
Chief, PFSED

4Sty16CL Schoolbuilding 161 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
1.00 Earthworks
1.01 Clearing and Grubbing sq.m -
1.02 Structural Excavation cu.m -
1.03 Backfilling and Compaction cu.m -
1.04 Gravel Bedding G-1 cu.m 980.00
1.05 Soil Poisoning sq.m 15.00
1.06 Select Fill cu.m 150.00
2.00 Concreting Works -
2.01 Portland Cement bag 218.00
2.02 Crushed Gravel 3/4" cu.m 980.00
2.03 Washed Sand cu.m 900.00
2.04 Demolition of reinforced concrete cu.m -
2.05 Crushed Gravel 1" cu.m 980.00
3.00 Rebar Works -
3.01 Deformed Round Bars, Grade 40 kg 40.10
3.02 G.I. Tie Wire kg 60.00
3.03 G.I. Tie Wire roll 1,750.00
4.00 Formworks -
4.01 Coco Lumber bd.ft 16.00
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 350.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 580.00
4.04 CWN, Assorted kg 60.00
5.00 Masonry Works -
5.01 Demolition of Masonry Wall sq.m -
5.02 Portland Cement bag 218.00
5.03 Washed Sand cu.m 900.00
5.04 CHB 4" thk pc 9.50
5.05 CHB 6" thk pc 12.00
5.06 10mm x 6m RSB kg 40.10
5.07 G.I. Tie Wire kg 60.00
5.08 Concrete Louver Blocks pc 30.00
5.09 Plaster Moulding lm 125.00
6.00 Doors and Windows -
6.01 Removal of Door with Jamb set -
6.02 Removal of Window with Jamb sq.m -
D-1, Panel Door 0.90m x 2.10m on 150mm Wooden Jamb complete with
6.03 set 7,317.50
Accessories (lever type door knob)

D-2 Flush Door 0.90m x 2.10m on 150mm Wooden Jamb complete with
6.04 set 4,167.50
Accessories (lever type door knob)

6.05 D-3 Flush Door 0.70m x 2.10m on 150mm Wooden Jamb complete with Accessories set 3,567.50

6.06 D-4 Cubicle Door 0.60m x 1.20m on 150mm Wooden Jamb complete with Accessories set 3,408.75

W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.07 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 8,444.00
Jamb complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.08 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 4,672.00
Jamb complete with Accessories

Page 162 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
W - 3, ( 0.7 x 2.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.09 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 4,248.00
Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.07a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 6,700.00
complete with Accessories

W - 2, ( 1.5 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.08a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 3,800.00
complete with Accessories

W - 3, ( 0.7 x 2.6 m) Jalousie Window with Clear Glass Blades on Standard


6.09a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 3,500.00
complete with Accessories
6.10 Panel Door 0.90m x 2.10m pc 5,753.50
6.11 Panel Door 0.80m x 2.10m pc 4,400.00
6.12 Panel Door 0.70m x 2.10m pc 3,600.00
6.13 Panel Door 0.60m x 2.10m pc 3,600.00
6.14 Flush Door 0.90m x 2.10m pc 1,740.00
6.15 Flush Door 0.80m x 2.10m pc 1,500.00
6.16 Flush Door 0.70m x 2.10m pc 1,400.00
6.17 Flush Door 0.60m x 2.10m pc 1,400.00
6.18 Steel Door 0.70m x 2.10m pc 4,375.00
6.19 Steel Door 0.80m x 2.10m pc 4,500.00
6.20 Steel Door 0.90m x 2.10m pc 4,600.00
6.21 PVC Door 0.60m x 2.10m pc 1,550.00
6.22 Door Jamb 45mm x 100mm set 1,050.00
6.23 Door Jamb 45mm x 125mm set 1,450.00
6.24 Door Jamb 45mm x 150mm set 1,550.00
6.25 Steel Encased Clear Glass Window with Grilles sq.ft 125.00
6.26 Security Grilles sq.ft 90.00
6.27 Entrance, Lockset Standard set 467.50
6.28 Entrance, Handleset set 7,760.00
6.29 Entrance, Cylindrical Lockset set 1,640.00
6.30 Entrance, Lever Lockset set 2,820.00
6.31 Bathroom, Lockset Keyless set 1,080.00
6.32 Hinges, Standard 3-1/2" x 3-1/2" pa 75.00
6.33 Hinges, Ball Bearing 3-1/2" x 3-1/2" pa 680.00
D-1, Flush Door 0.90m x 2.10m on 100mm Wooden Jamb complete with
6.34 set 3,667.50
Accessories (lever type door knob)

W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.35 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 100 mm Wooden set 8,400.00
Jamb complete with Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.36 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 100 mm Wooden set 4,200.00
Jamb complete with Accessories

W - 1, ( 3.6 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.37 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 11,832.00
Jamb complete with Accessories

W - 2, ( 3.6 x 1.2 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.38 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 8,968.00
Jamb complete with Accessories

W - 3, ( 1.8 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.39 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 5,480.00
Jamb complete with Accessories

Page 163 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost

W - 4, ( 0.6 x 0.95 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.39 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 1,099.00
complete with Accessories

W - 4, ( 0.6 x 0.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.40 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 763.00
Jamb complete with Accessories

W - 1, ( 4.0 x 1.8 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.41 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 14,572.00
Jamb complete with Accessories

W - 2, ( 2.1 x 1.8 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.42 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 7,792.00
Jamb complete with Accessories

W - 3, ( 1.3 x 1.8 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.43 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 4,616.00
Jamb complete with Accessories

W - 4, ( 1.2 x 0.7 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.44 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 1,718.00
Jamb complete with Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on JalouPlus Type
6.45 Silver Colored Frame and Fixed Clear Glass Transom on 50 x 150 mm Wooden set 4,200.00
Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.35a Aluminum Casing and Fixed Clear Glass Transom on 50 x 100 mm Wooden Jamb set 6,656.00
complete with Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.36a Aluminum Casing and Fixed Clear Glass Transom on 50 x 100 mm Wooden Jamb set 3,328.00
complete with Accessories

W - 1, ( 3.6 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.37a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 9,216.00
complete with Accessories

W - 2, ( 3.6 x 1.2 m) Jalousie Window with Clear Glass Blades on Standard


6.38a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 6,912.00
complete with Accessories

W - 3, ( 1.8 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.39b Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 4,608.00
complete with Accessories

W - 4, ( 0.6 x 0.95 m) Jalousie Window with Clear Glass Blades on Standard Aluminum
6.39a Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb complete with set 912.00
Accessories

W - 4, ( 0.6 x 0.6 m) Jalousie Window with Clear Glass Blades on Standard


6.40a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 576.00
complete with Accessories

W - 1, ( 4.0 x 1.8 m) Jalousie Window with Clear Glass Blades on Standard


6.41a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 11,520.00
complete with Accessories

W - 2, ( 2.1 x 1.8 m) Jalousie Window with Clear Glass Blades on Standard


6.42a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 6,048.00
complete with Accessories

W - 3, ( 1.3 x 1.8 m) Jalousie Window with Clear Glass Blades on Standard


6.43a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 3,744.00
complete with Accessories

W - 4, ( 1.2 x 0.7 m) Jalousie Window with Clear Glass Blades on Standard


6.44a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 1,344.00
complete with Accessories

Page 164 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost

W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on Standard


6.45a Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 mm Wooden Jamb set 3,328.00
complete with Accessories

6.46 D-3 Flush Door 0.60m x 2.10m on 150mm Wooden Jamb complete with Accessories set 3,367.50

D-1, (0.90 x 2.10) Steel Door and Jamb with Fixed Glass Transom complete with
6.47 set 6,000.00
Accessories
D-2, (0.80 x 2.10) Steel Door and Jamb with Fixed Glass Transom complete with
6.48 set 5,800.00
Accessories
D-3, (0.90 x 2.10) Steel Door and Jamb with Steel Grilles Transom and Stainless Kick
6.49 set 6,500.00
Plate complete with Accessories

D-4, (0.70 x 2.10) Steel Door and Jamb with Fixed Glass Transom complete with
6.50 set 5,500.00
Accessories

W - 1, ( 2.4 x 1.5 m) Steel Casement Window with Grilles, Semi French Type with 1/4
6.51 set 5,750.00
thk Clear Glass Panes complete with Accessories

W - 2, ( 1.8 x 1.5 m) Steel Casement Window with Grilles, Semi French Type with 1/4
6.52 set 4,350.00
thk Clear Glass Panes complete with Accessories

W - 3, ( 1.8 x 1.2 m) Steel Casement Window with Grilles, Semi French Type with 1/4
6.53 set 3,500.00
thk Clear Glass Panes complete with Accessories

W - 4, ( 0.6 x 0.6 m) Steel Awning Window with Grilles with 1/4 thk Clear Glass Panes
6.54 set 750.00
complete with Accessories
7.00 Steel Works -
7.01 C 6 x 10.5 kg 65.36
7.02 C 6 x 8.2 kg 65.36
7.03 LC 75 x 38 x 15 x 2.0mm kg 43.00
7.04 LC 100 x 50 x 15 x 1.5mm kg 43.00
7.05 LC 100 x 50 x 15 x 2.0mm kg 43.00
7.06 LC 100 x 50 x 15 x 3.0mm kg 43.00
7.07 LC 150 x 65 x 20 x 2.0mm kg 43.00
7.08 LC 150 x 65 x 20 x 3.0mm kg 43.00
7.09 LC 120 x 50 x 20 x 2.0mm kg 43.00
7.10 LC 120 x 50 x 20 x 3.0mm kg 43.00
7.11 L 25 x 25 x 3mm kg 32.00
7.12 L 30 x 30 x 6mm kg 32.00
7.13 L 50 x 50 x 5mm kg 32.00
7.14 L 50 x 50 x 6mm kg 32.00
7.15 Flat Bar 1" x 1/8" kg 32.00
7.16 Flat Bar 1" x 3/16" kg 32.00
7.17 Flat Bar 1" x 1/4" kg 32.00
7.18 Plain Round Bar 10mmØ x 6m pc 107.00
7.19 Plain Round Bar 12mmØ x 6m pc 185.00
7.20 Plain Round Bar 16mmØ x 6m pc 286.00
7.21 Square Bar 12mm□ x 6m pc 141.00
7.22 Square Bar 16mm□ x 6m pc 218.00
7.23 Square Bar 19mm□ x 6m pc 620.00
7.24 Steel Plate 1.20m x 2.40m x 12mm pc 10,500.00
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 9,300.00
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 8,635.00
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 5,390.00
7.28 Tubular 50mm x 150mm x 2.0mm pc 2,640.00
7.29 Tubular 50mm x 100mm x 1.5mm pc 1,085.00

Page 165 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
7.30 Turn Buckle 12 mmØ pc 60.00
7.31 Turn Buckle 16 mmØ pc 80.00
7.32 Anchor Bolt with Nuts and Washer, 20mmØ x 50mm x 300mm pc 65.00
7.33 Anchor Bolt with Nuts and Washer, 16mmØ x 50mm x 300mm pc 45.00
7.34 Anchor Bolt with Nuts and Washer, 12mmØ x 50mm x 300mm pc 27.00
7.35 Anchor Bolt with Nuts and Washer, 10mmØ x 50mm x 200mm pc 12.00
7.36 B.I. Pipe 100mmØ Sch.40 pc 2,262.00
7.37 B.I. Pipe 75mmØ Sch.40 pc 1,658.00
7.38 B.I. Pipe 50mmØ Sch.40 pc 880.00
7.39 B.I. Pipe 38mmØ Sch.40 pc 632.00
7.40 B.I. Pipe 32mmØ Sch.40 pc 537.00
7.41 B.I. Pipe 50mmØ Sch.20 pc 691.00
7.42 B.I. Pipe 38mmØ Sch.20 pc 499.00
7.43 B.I. Pipe 32mmØ Sch.20 pc 435.00
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 1,069.00
7.45 G.I. Pipe 2"Ø Sch.40 pc 1,781.00
7.46 Welding Rod kg 67.00
8.00 Roofing Works -
8.01 Removal of Roofing Sheets sq.m -
8.02 Removal of Ridge Roll pc -
8.03 Removal of Flashing pc -
8.04 Removal of Gutter pc -
8.05 Removal of Fascia Board pc -
8.06 Corrugated G.I. Sheet Ga.26, 36" x 8' pc 310.00
8.07 Corrugated G.I. Sheet Ga.26, 36" x 9' pc 348.75
8.08 Corrugated G.I. Sheet Ga.26, 36" x 10' pc 387.50
8.09 Corrugated G.I. Sheet Ga.26, 36" x 12' pc 465.00
8.10 Plain G.I. Sheet Ga.26, 4' x 8' pc 400.00
8.11 Plain G.I. Sheet Ga.26, 3' x 8' pc 350.00
8.12 Gutter Ga.26, 24" x 8' pc 300.00
8.13 Flashing Ga.26, 24"x 8' pc 270.00
8.14 Ridge Roll Ga.26, 24"x 8' pc 270.00
8.15 Long-Span Roofing, Rib-Type, Pre-Painted, 1220mm x 0.4mm thk m 360.00
8.16 Long-Span Roofing, Corrugated, Pre-Painted, 1220mm x 0.4mm thk m 380.00
8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 560.00
8.18 Ridge Roll, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 605.00
8.19 Flashing, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 560.00
8.20 Flashing, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 605.00
8.21 Flashing, Pre-Painted, Spanish, 0.610m x 2.440m x 0.4mm thk pc 600.00
8.22 Gutter, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 415.00
8.23 Gutter, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 605.00
8.24 Gutter, Stainless, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 1,525.00
8.25 Gutter, Pre-Painted, Spanish, 0.610m x 2.440m x 0.4mm thk m 600.00
8.26 Polyethylene Foam with One Side Aluminum 10mm thk m 105.00
8.27 Polyethylene Foam with One Side Aluminum 15mm thk m 142.00
8.28 Polyethylene Foam with One Side Aluminum 20mm thk m 179.50
8.29 Polyethylene Foam with One Side Aluminum 25mm thk m 216.50
8.30 Polyethylene Foam with Two Side Aluminum 5mm thk m 103.50
8.31 Polyethylene Foam with Two Side Aluminum 10mm thk m 141.00

Page 166 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
8.32 Polyethylene Foam with Two Side Aluminum 15mm thk m 178.00
8.33 Polyethylene Foam with Two Side Aluminum 20mm thk m 215.00
8.34 Polyethylene Foam with Two Side Aluminum 25mm thk m 252.00
8.35 Teckscrew 2-1/2" pc 1.80
8.36 Roof Sealant L 299.75
8.37 Blind Rivets pc 1.35
8.38 Umbrella Nails kg 60.00
9.00 Carpentry Works -
9.01 Removal of Ceiling sq.m -
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 350.00
9.03 Plywood, Ordinary 3/8" x 4' x 8' pc 520.00
9.04 Plywood, Ordinary 1/2" x 4' x 8' pc 580.00
9.05 Plywood, Ordinary 3/4" x 4' x 8' pc 850.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 360.00
9.07 Plywood, Marine 1/2" x 4' x 8' pc 650.00
9.08 Plywood, Marine 3/4" x 4' x 8' pc 1,050.00
9.09 Fiber Cement Board, 1/4" x 4' x 8' pc 540.00
9.10 Fiber Cement Board, 3/16" x 4' x 8' pc 390.00
9.11 Rough Lumber, Sun Dried, Yakal bd.ft 120.00
9.12 Rough Lumber, Sun Dried, Guijo bd.ft 120.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 38.00
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 60.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 245.00
9.16 Fascia Board, Wooden bd.ft 36.00
9.17 Fascia Board, Fiber Cement 10" x 8' pc 279.00
9.18 Fascia Board, Fiber Cement 12" x 8' pc 325.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 352.50
9.20 Fascia Board, Fiber Cement 12" x 12' pc 405.00
9.21 Ficem Board Nails kg 90.00
9.22 Finishing Nails kg 70.00
9.23 Common Wire Nails kg 50.00
9.24 Concrete Nails kg 70.00
9.25 Removal of T&G bd.ft -
9.26 T&G 3/4" x 4" ft 20.00
9.27 T&G 3/4" x 6" ft 32.50
9.28 Wood Glue L 120.00
9.29 Acoustic Board 2' x 4' pc 320.00
9.30 Main Tee Runner 1" x 1" x 10' pc 98.85
9.31 Cross Tee 1" x 1" x 10' pc 90.00
9.32 Wall Angle 1" x 1" x 10' pc 90.00
9.33 Suspension Rod #8 kg 145.00
9.34 Removal of Wooden Truss bd.ft -
9.35 Removal of Purlins bd.ft -
9.36 Removal of Partition sq.m -
9.37 Machine Bolts with Std. Nuts and Washers, 5/8" x 7" pc 18.00
9.38 Machine Bolts with Std. Nuts and Washers, 5/8" x 8" pc 20.00
9.39 Machine Bolts with Std. Nuts and Washers, 5/8" x 10" pc 25.00
9.40 Machine Bolts with Std. Nuts and Washers, 1/2" x 7" pc 12.00
9.41 Machine Bolts with Std. Nuts and Washers, 1/2" x 8" pc 15.00

Page 167 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
9.42 Wood Preservative, Brown L 900.00
9.43 Lawanit, 1/4" thk pc 280.00
9.44 Concealed Hinges pc 30.00
9.45 S.S. Cabinet Handle pc 90.00
9.46 6mm thk Clear Glass sq.ft 60.00
9.47 S.S. Tube 3/4"Ø m 420.00
9.48 S.S. Flange 3/4"Ø pa 75.00
9.49 Drawer Guide, Metal 20" Full Extension set 420.00
9.50 Folding Door, Full Louver 450 x 1830mm set 1,435.00
9.51 Heavy Duty Steel Track with Roller m 1,650.00
10.00 Electrical Works -
10.01 Electrical Conduit uPVC, 15mmØ pc 50.00
10.02 Electrical Conduit uPVC, 20mmØ pc 69.75
10.03 Electrical Conduit uPVC, 32mmØ pc 137.50
10.04 Electrical Conduit uPVC, 40mmØ pc 192.50
10.05 Electrical Conduit uPVC, 50mmØ pc 214.75
10.06 RSC 20mmØ pc 112.50
10.07 RSC 25mmØ pc 175.00
10.08 RSC 32mmØ pc 339.00
10.09 RSC 38mmØ pc 430.50
10.10 30.0 mm2 THW Wire, Stranded m 180.00
10.11 3.5 mm THW Wire, Stranded
2
m 33.00
10.12 5.5 mm2 THW Wire, Stranded m 50.50
10.13 8.0 mm THW Wire, Stranded
2
m 79.00
10.14 14.0 mm2 THW Wire, Stranded m 84.50
10.15 22.0 mm THW Wire, Stranded
2
m 133.90
10.16 Junction Box, 4" x 4" G.I. pc 15.00
10.17 Utility Box, 2" x 4" G.I. pc 30.00
10.18 FL 2 x 40W Recessed Type with Luminare 24" x 48" set 2,600.00
10.19 FL 1 x 40W Recessed Type with Luminare 6" x 48" set 1,184.50
10.20 FL 2 x 40W Industrial Type set 840.00
10.21 FL 1 x 40W Industrial Type set 490.00
10.22 FL 1 x 20W Industrial Type set 440.00
10.23 Single Switch with Plate pc 97.68
10.24 2-Gang Switch with Plate pc 153.00
10.25 3-Gang Switch with Plate pc 208.00
10.26 3-Way Switch with Plate pc 251.00
10.27 Single C.O. with Plate pc 88.00
10.28 Duplex C.O. with Plate pc 263.80
10.29 Duplex C.O. Weatherproof pc 756.50
10.30 Aircon Outlet with Plate pc 282.75
10.31 TV Terminal Outlet with Plate pc 322.50
10.32 Telephone Outlet with Plate pc 251.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 25.00
10.34 Entrance Cap 20mm dia. pc 50.00
10.35 Entrance Cap 32mm dia. pc 75.00
10.36 Entrance Cap 25mm dia. pc 70.00
10.37 Grounding Rod, 2.4m x 16mm dia. pc 150.00
10.38 Circuit Breaker, 20A 2P set 313.00

Page 168 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
10.39 Circuit Breaker, 30A 2P set 313.00
10.40 Circuit Breaker, 40A 2P set 441.25
10.41 Circuit Breaker, 50A 2P set 441.25
10.42 Circuit Breaker, 60A 2P set 441.25
10.43 Circuit Breaker, 100A 2P set 650.00
10.44 Circuit Breaker, 175A 2P set -
10.45 Safety Switch 100A 2P set 2,224.75
10.46 Safety Switch 30A 2P set 603.25
10.47 Panel Box, Flush Type, 6 Branches set 1,400.00
10.48 Panel Box, Flush Type, 4 Branches set 1,202.75
10.49 Panel Box, Flush Type, 8 Branches set 1,580.00
10.50 Panel Box, Flush Type, 12 Branches set 2,530.75
10.51 Panel Box, Flush Type, 10 Branches set 1,850.00
10.52 Flourescent Tube 40W set -
10.53 Incandescent Bulb 50W set 35.00
10.54 Vibrating Bell 8" set 1,500.00
10.55 Fire Alarm Bell, Vibrating Type set 2,000.00
10.56 Fire Alarm Station, Manual Single Action set 1,750.00
10.57 Fire Alarm Control Panel, One Zone set 5,500.00
10.58 Electrical Tape pc 37.50
10.59 Rubber Tape roll 100.00
11.00 Plumbing Works -
11.01 uPVC Water Line 1/2"Ø pc 55.00
11.02 uPVC Water Line 3/4"Ø pc 85.00
11.03 uPVC Water Line 1"Ø pc 112.00
11.04 PP-R Pipe 1"Ø pc 558.00
11.05 PP-R Pipe 3/4"Ø pc 345.00
11.06 PP-R Pipe 1/2"Ø pc 217.00
11.04a G.I. Pipe 1"Ø Sch.40 pc 460.00
11.05a G.I. Pipe 3/4"Ø Sch.40 pc 360.00
11.06a G.I. Pipe 1/2"Ø Sch.40 pc 260.00
11.07 G.I. Coupling, 3/8"Ø pc 11.00
11.08 PP-R Coupling, 1/2"Ø pc 9.00
11.09 PP-R Coupling, 3/4"Ø pc 15.00
11.10 PP-R Coupling, 1"Ø pc 25.00
11.11 PP-R Coupling, 1-1/2"Ø pc 17.00
11.12 PP-R Coupling, 2"Ø pc 143.00
11.13 PP-R Coupling, 3"Ø pc 447.00
11.08a G.I. Coupling, 1/2"Ø pc 10.75
11.09a G.I. Coupling, 3/4"Ø pc 14.75
11.10a G.I. Coupling, 1"Ø pc 23.75
11.11a G.I. Coupling, 1-1/2"Ø pc 35.00
11.12a G.I. Coupling, 2"Ø pc 45.00
11.13a G.I. Coupling, 3"Ø pc 150.00
11.14 G.I. Tee, 3/8"Ø pc 19.75
11.15 PP-R Tee, 1/2"Ø pc 17.00
11.16 PP-R Tee, 3/4"Ø pc 31.00
11.17 PP-R Tee, 1"Ø pc 50.00
11.15a G.I. Tee, 1/2"Ø pc 17.75

Page 169 of 179


database.xls

Unit Cost of Labor & Materials

Item Material
Item Description Unit
No. Unit Cost
11.16a G.I. Tee, 3/4"Ø pc 21.25
11.17a G.I. Tee, 1"Ø pc 42.75
11.18 G.I. Tee, 3/8" x 1/2"Ø pc 23.75
11.19 PP-R Tee, 3/4" x 1/2"Ø pc 25.00
11.20 PP-R Tee, 1" x 1/2"Ø pc 44.00
11.21 PP-R Elbow 90o x 1/2"Ø pc 14.00
11.22 PP-R Elbow 90o x 3/4"Ø pc 23.00
11.23 PP-R Elbow 90o x 1"Ø pc 37.00
11.24 PP-R Coupling Reducer, 1/2" x 3/4"Ø pc 11.00
11.25 PP-R Coupling Reducer, 1-1/2" x 1/2"Ø pc 62.00
11.26 PP-R Coupling Reducer, 2" x 1"Ø pc 114.00
11.27 PP-R Plug, 1/2"Ø pc 8.00
11.28 PP-R Plug, 3/4"Ø pc 12.00
11.29 PP-R Plug, 1"Ø pc 19.00
11.30 PP-R Plug, 1-1/2"Ø pc 54.00
11.31 PP-R Plug, 2"Ø pc 116.00
11.19a G.I. Tee, 3/4" x 1/2"Ø pc 41.25
11.20a G.I. Tee, 1" x 1/2"Ø pc 41.25
11.21a G.I. Elbow 90o x 1/2"Ø pc 11.00
11.22a G.I. Elbow 90 x 3/4"Ø
o
pc 20.75
11.23a G.I. Elbow 90o x 1"Ø pc 33.75
11.24a G.I. Coupling Reducer, 1/2" x 3/4"Ø pc 40.00
11.25a G.I. Coupling Reducer, 1-1/2" x 1/2"Ø pc 40.00
11.26a G.I. Coupling Reducer, 2" x 1"Ø pc 58.25
11.27a G.I. Plug, 1/2"Ø pc 9.75
11.28a G.I. Plug, 3/4"Ø pc 12.50
11.29a G.I. Plug, 1"Ø pc 20.50
11.30a G.I. Plug, 1-1/2"Ø pc 30.75
11.31a G.I. Plug, 2"Ø pc 42.50
11.32 S.S. Elbow 90 x 1/2"Ø
o
pc 90.00
11.33 S.S. Elbow 90 x 3/4"Ø
o
pc 146.00
11.34 S.S. Elbow 90o x 1"Ø pc 230.00
11.35 S.S. Coupling, 3/4"Ø pc 130.00
11.36 S.S. Coupling, 1"Ø pc 200.00
11.37 S.S. Tee, 1/2"Ø pc 130.00
11.38 S.S. Tee, 3/4"Ø pc 200.00
11.39 S.S. Tee, 1"Ø pc 330.00
11.40 S.S. Union Patente, 1/2"Ø pc 300.00
11.41 S.S. Union Patente, 3/4"Ø pc 400.00
11.42 S.S. Bushing, 3/4"Ø pc 60.00

Page 170 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
e
###
e
20.00 l
m
200.00
a
45.00 n
/
180.00 T
4.50 i
n
45.00 s
- m
i
42.50 t
h
175.00
150.00
500.00
150.00
-
8.02
9.00
262.50
-
4.80
90.00
162.00
18.00
-
360.00
51.00
180.00
2.25
3.00
9.03
15.00
9.00
62.50
-
88.76
24.16

887.63
###

529.13

517.13

443.81

1,005.00
###

570.00
###

Page 171 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
e
e
525.00 l
m
a
n
1,005.00
/
T
i
n
570.00
s
m
i
525.00 t
h

675.00
660.00
540.00
540.00
225.00
225.00
210.00
210.00
656.25
675.00
690.00
232.50
157.50
217.50
232.50
56.25
40.50
46.75
776.00
164.00
282.00
108.00
7.50
68.00

302.75
###

550.00
###

275.00
###

1,387.50
###

1,042.50
###

690.00
###

Page 172 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
e
e
182.40 l
m
a
n
105.00
### /
T
i
n
### s
1,728.00
m
i
t
### h
907.20

561.60
###

201.60
###

502.50
###

550.00

275.00

1,387.50

1,042.50

690.00

182.40

105.00

1,728.00

907.20

561.60

201.60

Page 173 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
e
e
502.50 l
m
a
487.13 n
/
T
1,800.00 i
n
1,740.00 s
m
i
1,800.00 t
h

1,650.00

2,012.50
###

1,522.50
###

1,225.00
###

262.50
###

-
19.61
19.61
12.90
12.90
12.90
12.90
12.90
12.90
12.90
12.90
9.60
9.60
9.60
9.60
9.60
9.60
9.60
32.10
55.50
85.80
42.30
65.40
186.00
3,150.00
2,790.00
2,590.50
1,617.00
792.00
325.50

Page 174 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
18.00 e
e
24.00 l
m
19.50
a
13.50 n
/
8.10 T
3.60 i
n
678.60 s
m
497.40
i
264.00 t
h
189.60
161.10
207.30
149.70
130.50
320.70
534.30
20.10
-
7.50
15.00
15.00
15.00
23.50
62.00
69.75
77.50
93.00
80.00
70.00
60.00
54.00
54.00
72.00
76.00
112.00
121.00
112.00
121.00
120.00
83.00
121.00
305.00
120.00
21.00
28.40
35.90
43.30
20.70
28.20

Page 175 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
35.60 e
e
43.00 l
m
50.40
a
0.36 n
/
59.95 T
0.27 i
n
12.00 s
m
-
i
8.00 t
h
105.00
156.00
174.00
255.00
108.00
195.00
315.00
162.00
117.00
36.00
36.00
11.40
18.00
73.50
10.80
83.70
97.50
105.75
121.50
27.00
21.00
15.00
21.00
5.00
6.00
9.75
36.00
96.00
29.66
27.00
27.00
43.50
4.00
4.00
8.00
5.40
6.00
7.50
3.60
4.50

Page 176 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
270.00 e
e
84.00 l
m
9.00
a
27.00 n
/
18.00 T
126.00 i
n
22.50 s
m
126.00
i
430.50 t
h
495.00
-
15.00
20.93
41.25
57.75
64.43
33.75
52.50
101.70
129.15
54.00
7.02
10.14
16.38
25.35
40.17
4.50
4.28
390.00
177.68
126.00
73.50
66.00
13.46
21.53
29.59
37.65
13.20
21.00
76.50
42.41
48.38
37.65
3.75
7.50
11.25
10.50
22.50
46.95

Page 177 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
46.95 e
e
66.19 l
m
66.19
a
66.19 n
/
97.50 T
- i
n
333.71 s
m
90.49
i
210.00 t
h
180.41
237.00
379.61
277.50
-
5.25
225.00
300.00
262.50
825.00
5.63
15.00
-
16.50
25.50
33.60
167.40
103.50
65.10
138.00
108.00
78.00
3.30
2.70
4.50
7.50
5.10
42.90
134.10
3.23
4.43
7.13
10.50
13.50
45.00
5.93
5.10
9.30
15.00
5.33

Page 178 of 179


e
r
/
database.xls M
a
nit Cost of Labor & Materials s
o
n
Labor /
S
Unit Cost t
6.38 e
e
12.83 l
m
7.13
a
7.50 n
/
13.20 T
4.20 i
n
6.90 s
m
11.10
i
3.30 t
h
18.60
34.20
2.40
3.60
5.70
16.20
34.80
12.38
12.38
3.30
6.23
10.13
12.00
12.00
17.48
2.93
3.75
6.15
9.23
12.75
27.00
43.80
69.00
39.00
60.00
39.00
60.00
99.00
90.00
120.00
18.00

Page 179 of 179

You might also like