Proposed Utilities Piping & Fittings of Soaps & Cometics Plant

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Sedibus Industrial and Facilities Management Corporation

ID Task Name Duration Start Finish Predec February 2019 March 2019 April 2019 May 2019 June 2019 Jul
19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 0
1 CONSTRUCTION PHASE 117 days Mon 21/01/19 Tue 02/07/19
2 Carbon Steel Pipes 43 days Mon 21/01/19 Wed 20/03/19
3 Prefabrication of Brackets for Steel 9 days Mon 21/01/19 Thu 31/01/19
4 Layouting of Carbon Steel Pipe 5 days Fri 01/02/19 Thu 07/02/19 3
5 Installation of Bracketing for Carbin Steel Pipe 9 days Fri 08/02/19 Wed 20/02/19 4
6 Installation of Carbon Steel Piping 15 days Thu 21/02/19 Wed 13/03/19 5
7 Sealing Carbon Steel 3 days Thu 14/03/19 Mon 18/03/19 6
8 Testing Carbon Steel 2 days Tue 19/03/19 Wed 20/03/19 7
9 Galvanized Carbon Steel 43 days Fri 01/02/19 Tue 02/04/19
10 Prefabrication of Brackets for Galvanized Pipe 9 days Fri 01/02/19 Wed 13/02/19 3
11 Layouting of Galvanized Steel Piping 5 days Thu 14/02/19 Wed 20/02/19 10
12 Installation of Bracketing for Galvanized Pipe 9 days Thu 21/02/19 Tue 05/03/19 11
13 Installation of Galvanized Piping 15 days Wed 06/03/19 Tue 26/03/19 12
14 Sealing of Galvanized Piping 3 days Wed 27/03/19 Fri 29/03/19 13
15 Testing Galvanized Steel Piping 2 days Mon 01/04/19 Tue 02/04/19 14
16 PVC Pipes 43 days Thu 14/02/19 Mon 15/04/19 10
17 Prefabrication of Brackets 9 days Thu 14/02/19 Tue 26/02/19 10
18 Layouting of PVC Pipes 5 days Wed 27/02/19 Tue 05/03/19 17
19 Installation of Bracketing for PVC Pipe 9 days Wed 06/03/19 Mon 18/03/19 18
20 Installation of PVC Piping 15 days Tue 19/03/19 Mon 08/04/19 19
21 Sealing of PVC Pipes 3 days Tue 09/04/19 Thu 11/04/19 20
22 Testing PVC Pipes 2 days Fri 12/04/19 Mon 15/04/19 21
23 Bolts and Gaskets 25 days Tue 16/04/19 Mon 20/05/19
24 Layouting of Bolts and Gaskets 6 days Tue 16/04/19 Tue 23/04/19 22
25 Installation of Bracket 5 days Wed 24/04/19 Tue 30/04/19 24
26 Installation of Bolts and Gaskets 9 days Wed 01/05/19 Mon 13/05/19 25
27 Commissioning 3 days Tue 14/05/19 Thu 16/05/19 26
28 Testing and Acceptance of Installation 2 days Fri 17/05/19 Mon 20/05/19 27
29 Piping Insulation 26 days Tue 21/05/19 Tue 25/06/19
30 Layouting of Insulation 3 days Tue 21/05/19 Thu 23/05/19 28
31 Installation of Piping Insulation 14 days Fri 24/05/19 Wed 12/06/19 30
32 Sealing of Insulation 7 days Thu 13/06/19 Fri 21/06/19 31
33 Testing of Insulation 2 days Mon 24/06/19 Tue 25/06/19 32
34 Piping Cladding 31 days Tue 21/05/19 Tue 02/07/19
35 Layouting of Cladding 5 days Tue 21/05/19 Mon 27/05/19 28
36 Installation of Cladding 14 days Tue 28/05/19 Fri 14/06/19 35
37 Sealing of Cladding 10 days Mon 17/06/19 Fri 28/06/19 36
38 Testing of Piping Cladding 2 days Mon 01/07/19 Tue 02/07/19 37

Task Summary Rolled Up Progress Project Summary


Project: Printer Room Prepared by:
Date: Wed 16/01/19 Progress Rolled Up Task Split Group By Summary
Jade C. Salac
Milestone Rolled Up Milestone External Tasks Deadline

PROPOSED UTILITIES PIPING Page 1 of 1
 & FITTINGS OF SOAPS & COMETICS PLANT