Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 11

Delay Notice

Letter No (1)

28/Mar/12

Subject: Additional Cost and Time notice for Local Authorities Permission

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated 3/25/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID Letter 1 - 1

Activity Name Authorities Permissions

The Impacted Existing Activity:

Activity ID SUBz100020

Activity Name Excavation Activity

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (2)

24/Mar/12

Subject: Additional Cost and Time notice for Site Handing Over

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.2 dated 3/20/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID Letter 2 - 1

Activity Name Site Delivery Delay

The Impacted Existing Activity:

Activity ID SUBZ100010

Activity Name Mobilization

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (3)

18/Apr/12

Subject: Additional Cost and Time notice for Pumps Submittal

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.2 dated 4/15/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID MAR-20-1

Activity Name New Pumps Submittal

The Impacted Existing Activity:

Activity ID 0801MW0011

Activity Name INSTALLATION OF WATER & FIRE PUMPS

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (4)

15/May/12

Subject: Additional Cost and Time notice for Lighting Fixture Type 2*26 w

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated 5/12/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID MAR 4-1

Activity Name Delay of MAR response

The Impacted Existing Activity:

Activity ID A2250

Activity Name LIGHTING FIXTURES& SWITCHS Procurement

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (5)

3/Jan/13

Subject: Additional Cost and Time notice for Item no.1 ( Utilities will be available on 1 July 2013 ).

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated 2/1/2013

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID MOM-13-1

Activity Name Delay of Utilities availability

The Impacted Existing Activity:

Activity ID A2450

Activity Name Elevators TESTING AND COMMISSIONING

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (6)

9/3/20162

Subject: Additional Cost and Time notice for Supplying Safe door

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.2 dated 9/1/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID MOM 9-1

Activity Name Safe Door Supplying Delay

The Impacted Existing Activity:

Activity ID Arch1070

Activity Name Wall Preparation for Painting

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (7)

1/Apr/12

Subject: Additional Cost and Time notice for Under Ground Water Level

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated 3/29/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID RFI No.3-1

Activity Name Response from Consultant

The Impacted Existing Activity:

Activity ID SUBZ100030

Activity Name COMPACTING WORKS UNDER THE P.C LAYER

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (8)

4/Feb/13

Subject: Additional Cost and Time notice for Clash between Lighting Unit and Diffuser

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated 2/1/2013

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID RFI-6- 1

Activity Name Remove Fixed Lighting Fixture

The Impacted Existing Activity:

Activity ID 0801EL0005

Activity Name LIGHTING FIXTURES& SWITCHS & OUTLETS

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (9)

10/May/12

Subject: Additional Cost and Time notice for Doors and Windows Shop Drawing

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated 5/7/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID SDF 2-1

Activity Name New Door Submittal

The Impacted Existing Activity:

Activity ID ARCH1150

Activity Name WOODEN DOORS INSTALLING

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (10)

5/Jun/12

Subject: Additional Cost and Time notice for Change Marble Fixation

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.1 dated 6/2/2012

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID SWI1_1

Activity Name Demolish all fixed marble

The Impacted Existing Activity:

Activity ID Arch1110

Activity Name MARBLE WORKS VIP SEC. WALL'S CLADDING


&FLOORING

The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice

Letter No (11)

19/Mar/13

Subject: Additional Cost and Time notice for Change Painting Color Code

Dear Employer,

Reference to the subject mentioned above and client Letter Ref.3 dated 3/15/2013

We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.

Following are the impacted activities due to Employer instruction:

The additional scope of work:

Activity ID SWI 2_1

Activity Name Submit new material for approved

The Impacted Existing Activity:

Activity ID A2290

Activity Name Painting Site delivery date

The additional cost and / or time impact analysis will be submitted in due course.

You might also like