Delay Notice Faz
Delay Notice Faz
Letter No (1)
28/Mar/12
Subject: Additional Cost and Time notice for Local Authorities Permission
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated 3/25/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID Letter 1 - 1
Activity ID SUBz100020
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (2)
24/Mar/12
Subject: Additional Cost and Time notice for Site Handing Over
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.2 dated 3/20/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID Letter 2 - 1
Activity ID SUBZ100010
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (3)
18/Apr/12
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.2 dated 4/15/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID MAR-20-1
Activity ID 0801MW0011
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (4)
15/May/12
Subject: Additional Cost and Time notice for Lighting Fixture Type 2*26 w
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated 5/12/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID A2250
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (5)
3/Jan/13
Subject: Additional Cost and Time notice for Item no.1 ( Utilities will be available on 1 July 2013 ).
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated 2/1/2013
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID MOM-13-1
Activity ID A2450
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (6)
9/3/20162
Subject: Additional Cost and Time notice for Supplying Safe door
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.2 dated 9/1/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID Arch1070
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (7)
1/Apr/12
Subject: Additional Cost and Time notice for Under Ground Water Level
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated 3/29/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID SUBZ100030
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (8)
4/Feb/13
Subject: Additional Cost and Time notice for Clash between Lighting Unit and Diffuser
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated 2/1/2013
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID RFI-6- 1
Activity ID 0801EL0005
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (9)
10/May/12
Subject: Additional Cost and Time notice for Doors and Windows Shop Drawing
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated 5/7/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID ARCH1150
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (10)
5/Jun/12
Subject: Additional Cost and Time notice for Change Marble Fixation
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.1 dated 6/2/2012
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID SWI1_1
Activity ID Arch1110
The additional cost and / or time impact analysis will be submitted in due course.
Delay Notice
Letter No (11)
19/Mar/13
Subject: Additional Cost and Time notice for Change Painting Color Code
Dear Employer,
Reference to the subject mentioned above and client Letter Ref.3 dated 3/15/2013
We hereby notify the client that there will be additional cost and / or time due to the client instructions
mentioned above.
Activity ID A2290
The additional cost and / or time impact analysis will be submitted in due course.