EVENTS & SHIFT SUMMARY OF GIS

SHIFT DETAILS EVENTS AND SHIFT SUMMARY


SHIFT SHIFT INCHARGE EMP. CODE S.No.
1 Partial discharge test is going on inside GIS.
A KAVITA SONI 14729 2 Wiring of ABT Meter in 400kv LINE-2 and CRP Panel is under process.

1 Partial discharge test is going on inside GIS.


2 As informed by NTPC (due to maintenance work in their side ) LINE-1 charging has been delayed till 24.02.2012
B BINOY ACHARYA 14707

1 All parameters of GIS normal.


C ABHISHEK KUMAR SINGH 14696 2
3
CHECK POINTS
OIL LEVEL INDICATION

S.No. Location Check Points Oil Level in OLI


A shift B shift C shift
400 KV LINE-1 11:00am 06:00pm
1 400 KV CVT R Phase 50% 50% 50%
2 400 KV CVT Y Phase 60% 60% 60%
3 400 KV CVT B Phase 60% 60% 60%
400/220 KV ICT-3
1 400 KV Bushing R Phase 70% 70% 70%
2 400 KV Bushing Y Phase 45% 45% 45%
3 400 KV Bushing B Phase 75% 75% 75%
4 220 KV Bushing R Phase 50% 50% 50%
5 220 KV Bushing Y Phase 60% 60% 60%
6 220 KV Bushing B Phase 60% 60% 60%
7 Conservator(Main) 40% 45% 45%
8 Conservator(OLTC) 50% 50% 50%

LA LEAKAGE CURRENT & COUNTER READINGS

S.No. Location Check Points IL(mA) Counter Reading IL(mA) Counter Reading IL(mA) Counter Reading
A Shift B Shift C Shift
400 KV Line-1 11:00am 06:00pm
1 400 KV R Phase 0 29 0 29 0 29
2 400 KV Y phase 0 27 0 27 0 27
3 400 KV B Phase 0 27 0 27 0 27
400 KV ICT#3 side
1 400 KV R Phase 0 5 0 5 0 5
2 400 KV Y phase 0 6 0 6 0 6
3 400 KV B Phase 0 5 0 5 0 5
220 KV ICT#3 side
1 220 KV R Phase 0 6 0 6 0 6
2 220 KV Y phase 0 6 0 6 0 6
3 220 KV B Phase 0 6 0 6 0 6

MISCELLANEOUS

A SHIFT B SHIFT C SHIFT


S.NO. Check points
OK / Not OK OK / Not OK OK / Not OK
1 Check ON/OFF Indication OK OK OK
2 Check Semaphore Indication NOT OK NOT OK NOT OK
3 Any Alarm in LCC NO NO NO
4 Any Alarm in RCC NO NO NO
5 220 V Battery charger OK OK OK
6 48 V Battery charger OK OK OK
7 UPS for SCADA OK OK OK
8 PLCC OK OK OK
9 ACDB OK OK OK
10 DCDB OK OK OK
11 PLCC HOTLINE PHONE OK OK OK
12 P&T PHONE OK OK OK
13 FAX MACHINE OK OK OK
14 PRINTER OK OK OK
15 INDOOR GIS LIGHTING OK OK OK
16 OUTDOOR GIS LIGHTING OK OK OK
S.NO Compartment Name Normal Range A Shift B Shift C shift
400KV Line-1(C 401)
1 400kv breaker compartment R-Phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
2 400kv breaker compartment Y-Phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
3 400kv breaker compartment B-Phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
4 SF6 Gas compartment-1 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
5 SF6 Gas compartment-1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
6 SF6 Gas compartment-1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
7 SF6 Gas compartment-2 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
8 SF6 Gas compartment-2 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
9 SF6 Gas compartment-2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
10 SF6 Gas compartment-3 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
11 SF6 Gas compartment-3 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
12 SF6 Gas compartment-3 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
13 SF6 Gas compartment-4 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
14 SF6 Gas compartment-4 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
15 SF6 Gas compartment-4 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
16 SF6 Gas compartment-5 R phase 0.60 to 0.65 mpa 0.65/green 0.63/green
17 SF6 Gas compartment-5 Y phase 0.60 to 0.65 mpa 0.65/green 0.64/green
18 SF6 Gas compartment-5 B phase 0.60 to 0.65 mpa 0.65/green 0.64/green
19 400kv CT R Phase(Outdoor) green green
20 400kv CT Y Phase(Outdoor) green green
21 400kv CT B Phase(Outdoor) green green
400 KV LINE -2 (C-403)
1 400kv breaker compartment R-Phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
2 400kv breaker compartment Y-Phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
3 400kv breaker compartment B-Phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
4 SF6 Gas compartment-1 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
5 SF6 Gas compartment-1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
6 SF6 Gas compartment-1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
7 SF6 Gas compartment-2 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
8 SF6 Gas compartment-2 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
9 SF6 Gas compartment-2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
10 SF6 Gas compartment-3 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
11 SF6 Gas compartment-3 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
12 SF6 Gas compartment-3 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
13 SF6 Gas compartment-4 R phase 0.60 to 0.65 mpa 0.00/Red 0.00/Red
14 SF6 Gas compartment-4 Y phase 0.60 to 0.65 mpa 0.00/Red 0.00/Red
15 SF6 Gas compartment-4 B phase 0.60 to 0.65 mpa 0.00/Red 0.00/Red
16 SF6 Gas compartment-5 R phase 0.60 to 0.65 mpa 0.66/green 0.64/green
17 SF6 Gas compartment-5 Y phase 0.60 to 0.65 mpa 0.66/green 0.64/green
18 SF6 Gas compartment-5 B phase 0.60 to 0.65 mpa 0.65/green 0.64/green
19 400kv CT R Phase(Outdoor) green green
20 400kv CT Y Phase(Outdoor) green green
21 400kv CT B Phase(Outdoor) green green

SHIFT INCHARGE NAME KAVITA SONI BINOY ABHISHEK(14696)


S NO. Compartment Name Normal Range A Shift B Shift C Shift
400KV ICT 1(C 402)
1 400 kv Breaker compartment R phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
2 400 kv Breaker compartment Y phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
3 400 kv Breaker compartment B phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
4 SF6 gas compartment 1 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
5 SF6 gas compartment 1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
6 SF6 gas compartment 1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
7 SF6 gas compartment 2 R phase 0.60 to 0.65 mpa 0.65/green 0.66/green
8 SF6 gas compartment 2 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
9 SF6 gas compartment 2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
10 SF6 gas compartment 3 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
11 SF6 gas compartment 3 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
12 SF6 gas compartment 3 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
13 SF6 gas compartment 4 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
14 SF6 gas compartment 4 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
15 SF6 gas compartment 4 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
16 SF6 gas compartment 5 R phase 0.60 to 0.65 mpa 0.67/green 0.66/green
17 SF6 gas compartment 5 Y phase 0.60 to 0.65 mpa 0.67/green 0.64/green
18 SF6 gas compartment 5 B phase 0.60 to 0.65 mpa 0.67/green 0.64/green
400KV ICT 2 (C 404)
1 400 kv Breaker compartment R phase(0) 0.65 to 0.7 mpa 0.70/green 0.71/green
2 400 kv Breaker compartment Y phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
3 400 kv Breaker compartment B phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
4 SF6 gas compartment 1 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
5 SF6 gas compartment 1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
6 SF6 gas compartment 1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
7 SF6 gas compartment 2 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
8 SF6 gas compartment 2 Y phase 0.60 to 0.65 mpa 0.66/green 0.66/green
9 SF6 gas compartment 2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
10 SF6 gas compartment 3 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
11 SF6 gas compartment 3 Y phase 0.60 to 0.65 mpa 0.65/green 0.66/green
12 SF6 gas compartment 3 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
13 SF6 gas compartment 4 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
14 SF6 gas compartment 4 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
15 SF6 gas compartment 4 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
16 SF6 gas compartment 5 R phase 0.60 to 0.65 mpa 0.66/green 0.64/green
17 SF6 gas compartment 5 Y phase 0.60 to 0.65 mpa 0.66/green 0.64/green
18 SF6 gas compartment 5 B phase 0.60 to 0.65 mpa 0.66/green 0.64/green
400KV ICT 3 (C-406)
1 400 kv Breaker compartment R phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
2 400 kv Breaker compartment Y phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
3 400 kv Breaker compartment B phase(0) 0.65 to 0.7 mpa 0.70/green 0.71/green
4 SF6 gas compartment 1 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
5 SF6 gas compartment 1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
6 SF6 gas compartment 1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
7 SF6 gas compartment 2 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
8 SF6 gas compartment 2 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
9 SF6 gas compartment 2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
10 SF6 gas compartment 3 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
11 SF6 gas compartment 3 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
12 SF6 gas compartment 3 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
13 SF6 gas compartment 4 R phase 0.60 to 0.65 mpa 0.65/green 0.66/green
14 SF6 gas compartment 4 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
15 SF6 gas compartment 4 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
16 SF6 gas compartment 5 R phase 0.60 to 0.65 mpa 0.66/green 0.64/green
17 SF6 gas compartment 5 Y phase 0.60 to 0.65 mpa 0.65/green 0.63/green
18 SF6 gas compartment 5 B phase 0.60 to 0.65 mpa 0.65/green 0.63/green

SHIFT INCHARGE NAME KAVITA SONI BINOY ABHISHEK(14696)


S NO. Compartment Name Normal Range A shift B Shift C Shift
400KV Bus coupler and VT( C-405)
1 400kv Breaker compartment R- phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
2 400kv Breaker compartment Y- phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
3 400kv Breaker compartment B- phase(0) 0.65 to 0.7 mpa 0.70/green 0.70/green
4 SF 6 Gas compartment-1 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
5 SF 6 Gas compartment-1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
6 SF 6 Gas compartment-1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
7 SF 6 Gas compartment-2 R phase 0.60 to 0.65 mpa 0.65/green 0.65/green
8 SF 6 Gas compartment-2 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
9 SF 6 Gas compartment-2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
10 SF6 Gas compartment -3VT MB-1 R phase0.60 to 0.65 mpa 0.65/green 0.65/green
11 SF6 Gas compartment -3VT MB-1 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
12 SF6 Gas compartment -3VT MB-1 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green
13 SF6 Gas compartment -3VT MB-2 R phase0.60 to 0.65 mpa 0.65/green 0.65/green
14 SF6 Gas compartment -3VT MB-2 Y phase 0.60 to 0.65 mpa 0.65/green 0.65/green
15 SF6 Gas compartment -3VT MB-2 B phase 0.60 to 0.65 mpa 0.65/green 0.65/green

SHIFT INCHARGE NAME KAVITA SONI BINOY ABHISHEK(14696)


PERMITS ISSUED FOR VARIOUS WORKS

Permit No. Permit TypePermit Issue Shift Permit Prepared By Permit Issued By Permit Issued for Status of Work Remarks
116 SAFETY A VISHNU PATAL ABHISHEK (14698) CRB (Shuttering,reinforcement ) Completed
110 SAFETY A Atul shrma Kavita soni Disconnection and connection of conductor from CT to SF6 bushing Completed
118 SAFETY A Abhishek marwari Kavita soni PD and HV Testing of GIS,SF6 jumper disconnection from SF6 Air bushing In complete