PROJECT Improvement/Widening of Timawa Ave including RROW -K0003+(-620) - K0003+117; K0003+117 - K0003+470

CONTRACTOR JHJ CONSTRUCTION

CHRONOLOGY OF EVENTS
ACTION INCLUSIVE DATES REASON REMARKS

EFFECTIVITY OF CONTRACT April 03, 2018 - -

Variation Order No. 1 July, 2018 to suit actual site conditions Approved by Distric

W.S.O. No. 1 August 16, 2017 – September 14, 2017 due to pending removal of obstruction Approved by Distric

C.W.S.O. No. 1a September 15, 2017 – October 14, 2017 due to pending removal of obstruction Approved by Region

Time Extension No. 1 August 16, 2017 – September 14, 2017 in-lieu of W.S.O. No. 1 Approved by Distric

Work Resumption Order No. 1 October 15, 2017 obstruction settled Approved by Distric

Time Extension No. 2 September 15, 2017 – October 14, 2017 in-lieu of C.W.S.O. No. 1a Approved by Region

W.S.O. No. 2 December 1, 2017 – December 30, 2017 due to pending removal of obstruction Approved by ASEC. Bernardo

C.W.S.O. No. 2a December 31, 2017 – January 29, 2018 due to pending removal of obstruction Approved by USEC. Yabut

Time Extension No. 3 December 1, 2017 – December 30, 2017 in-lieu of W.S.O. No. 2 Approved by ASEC. Bernardo

Work Resumption Order No. 2 January 30, 2018 obstruction settled Approved by Distric

Time Extension No. 3 December 31, 2017 – January 29, 2018 in-lieu of C.W.S.O. No. 2a Approved by USEC. Bernard
REMARKS

Approved by District Engineer

Approved by District Engineer

Approved by Regional Director

Approved by District Engineer

Approved by District Engineer

Approved by Regional Director

proved by ASEC. Bernardo (D.O. 105 S2017)

pproved by USEC. Yabut (D.O. 105 S2017)

proved by ASEC. Bernardo (D.O. 105 S2017)

Approved by District Engineer

pproved by USEC. Bernardo (D.O. 12 S2018)