Memorandum: Consulting Engineers
Memorandum: Consulting Engineers
Memorandum: Consulting Engineers
CONSULTING ENGINEERS
MEMORANDUM
We understand that you are looking at reconstructing three restroom facilities and also doing some work
on the North Ogden Park Grandstands. The restrooms at Oak Lawn Park, Orton Park, and Lomond View
Park need to be replaced. The Oak Lawn Park restroom facility would include a storage room and a
concessions area. The Orton Park and Lomond View Park restroom facilities would include storage
rooms. Each building would be furnished complete with all fixtures and amenities. The old buildings at
each of these parks would need to be demolished. The grandstands at North Ogden Park need some
repair work and painting. A concessions area beneath the grandstands could also be reconstructed. This
would include hot water and sinks to allow additional food options. Attached to this letter are detailed
budgetary estimates for this work. A summary of the budgetary cost estimates is listed below.
Oak Lawn Park Demolish the existing structure. Construct 70’x25’ Atlas block $187,275
building complete with concessions area and storage room. Each
restroom contains 5 stalls and 2 sinks.
Orton Park Demolish the existing structure. Construct 52’x25’ Atlas block $139,480
building complete with storage room. Each restroom contains 5 stalls
and 2 sinks.
Lomond View Park Demolish the existing structure. Construct 52’x25’ Atlas block $139,480
building complete with storage room. Each restroom contains 5 stalls
and 2 sinks.
North Ogden Park Repair broken wood and paint the grandstands. Replace metal clad $65,110
wooden bench seats with aluminum seats. Replace railing and safety
fencing. Reconstruct concessions area below grandstands including
water and sewer service lines.
Total $531,345
We have also attached a site plan for each of the restroom facilities. Please let us know if you have any
questions.
1716 East 5600 South ● South Ogden, Utah 84403 ● (801) 476-9767 ● FAX (801) 476-6768
___________________________________________________________
4 Demolish existing building; level out grading at restroom; cap 1 ls $4,000.00 $4,000.00
sprinklers; etc.
5 Construct new 1" culinary water service line to restroom. 30 lf $20.00 $600.00
Includes connection to existing service stub.
6 Construct new 30" concrete curb and gutter. Includes 4" thick 60 lf $20.00 $1,200.00
road base, sprikler repair, and landscape restoration. Also
includes clearing, grading and subgrade preparation.
7 Furnish and Install ADA hanicap ramp. 1 ea $800.00 $800.00
10 Furnish and install new 4" sewer lateral. Includes connection to 50 ea $50.00 $2,500.00
existing service stub.
11 Furnish and install sewer clean-out outside restroom building 2 ea $400.00 $800.00
complete with concrete collar to grade.
12 Furnish and install 4" thick concrete flatwork including 4" granular 1,300 sf $5.50 $7,150.00
base material (outside of building footprint). Interior concrete for
13 fl ill b install city
Furnish and d i standard
bid it 1"
1 culinary water service meter 1 ea $600.00 $600.00
station complete. City to provide meter.
3 Demolish existing building; level out grading at restroom; cap 1 ls $3,500.00 $3,500.00
sprinklers; etc.
4 Construct new 1" culinary water service line to restroom. 20 lf $20.00 $400.00
Includes connection to existing service stub.
5 Furnish and install new 4" sewer lateral. Includes connection to 20 lf $50.00 $1,000.00
existing service stub.
6 Furnish and install sewer clean-out outside restroom building 2 ea $400.00 $800.00
complete with concrete collar to grade.
7 Furnish and install 4" thick concrete flatwork including 4" granular 1,000 sf $5.50 $5,500.00
base material (outside of building footprint). Interior concrete for
8 fl ill b install city
Furnish and d i standard
bid i 1"
1 culinary water service meter 1 ea $600.00 $600.00
station complete. City to provide meter.
PROJECT SUBTOTAL = $126,800.00
10% Contingency = $12,680.00
PROJECT TOTAL = $139,480.00
2 Furnish and install plumpbing fixture & toilet accessories. 1 ls $21,000.00 $21,000.00
3 Demolish existing building; level out grading at restroom; cap 1 ls $3,500.00 $3,500.00
sprinklers; etc.
4 Construct new 1" culinary water service line to restroom. 20 lf $20.00 $400.00
Includes connection to existing service stub.
5 Furnish and install new 4" sewer lateral. Includes connection to 20 lf $50.00 $1,000.00
existing service stub.
6 Furnish and install sewer clean-out outside restroom building 2 ea $400.00 $800.00
complete with concrete collar to grade.
7 Furnish and install 4" thick concrete flatwork including 4" granular 1,000 sf $5.50 $5,500.00
base material (outside of building footprint). Interior concrete for
floors will be covered in bid item 1.
8 Furnish and install city standard 1" culinary water service meter 1 ea $600.00 $600.00
station complete. City to provide meter.
North Ogden City Corporation
North Ogden Park Grandstand Improvement Project
Budgetary Estimate
Location: 500 E 2700 N, North Ogden, UT 84414
Date: November 7, 2013
PROJECT SUBTOTAL = $59,191.00
10% Contingency = $5,919.10
PROJECT TOTAL = $65,110.10