RE: 2014 Grant Application – City Park Projects


Budgetary Cost Summary

Date: November 8, 2014


______________________________________________________________________________

We understand that you are looking at reconstructing three restroom facilities and also doing some work
on the North Ogden Park Grandstands. The restrooms at Oak Lawn Park, Orton Park, and Lomond View
Park need to be replaced. The Oak Lawn Park restroom facility would include a storage room and a
concessions area. The Orton Park and Lomond View Park restroom facilities would include storage
rooms. Each building would be furnished complete with all fixtures and amenities. The old buildings at
each of these parks would need to be demolished. The grandstands at North Ogden Park need some
repair work and painting. A concessions area beneath the grandstands could also be reconstructed. This
would include hot water and sinks to allow additional food options. Attached to this letter are detailed
budgetary estimates for this work. A summary of the budgetary cost estimates is listed below.

Location Description Cost

Oak Lawn Park Demolish the existing structure. Construct 70’x25’ Atlas block $187,275
building complete with concessions area and storage room. Each
restroom contains 5 stalls and 2 sinks.
Orton Park Demolish the existing structure. Construct 52’x25’ Atlas block $139,480
building complete with storage room. Each restroom contains 5 stalls
and 2 sinks.
Lomond View Park Demolish the existing structure. Construct 52’x25’ Atlas block $139,480
building complete with storage room. Each restroom contains 5 stalls
and 2 sinks.
North Ogden Park Repair broken wood and paint the grandstands. Replace metal clad $65,110
wooden bench seats with aluminum seats. Replace railing and safety
fencing. Reconstruct concessions area below grandstands including
water and sewer service lines.

Total $531,345

We have also attached a site plan for each of the restroom facilities. Please let us know if you have any
questions.

 
1716 East 5600 South ● South Ogden, Utah 84403 ● (801) 476-9767 ● FAX (801) 476-6768
___________________________________________________________

North Ogden City Corporation


Oak Lawn Park Restroom Reconstruction Project
Budgetary Estimate
Location: 1200 E 2500 N, North Ogden, UT 84414
Date: November 5, 2013

Item Description Quantity Unit Unit Price Total Amount


1 Construct 70' x 24' restroom facility including a concessions 1 ls $120,000.00 $120,000.00
room and storage room complete with sewer, water and
electrical components. Includes temporary 6’ chain link safety
fence and all other appurtenances in accordance with the
drawings and specifications to render the construction of the
building complete.
2 Furnish and install plumpbing fixture & toilet accessories. 1 ls $25,000.00 $25,000.00
3 Furnish and Install Import fill material. 100 ton $18.00 $1,800.00

4 Demolish existing building; level out grading at restroom; cap 1 ls $4,000.00 $4,000.00
sprinklers; etc.
5 Construct new 1" culinary water service line to restroom. 30 lf $20.00 $600.00
Includes connection to existing service stub.
6 Construct new 30" concrete curb and gutter. Includes 4" thick 60 lf $20.00 $1,200.00
road base, sprikler repair, and landscape restoration. Also
includes clearing, grading and subgrade preparation.
7 Furnish and Install ADA hanicap ramp. 1 ea $800.00 $800.00

8 Furnish and Install 15" R.C.P. pipe. 100 lf $36.00 $3,600.00


9 Furnish and install standard 24"x24" catch basin w/ grate. 1 ea $2,200.00 $2,200.00

10 Furnish and install new 4" sewer lateral. Includes connection to 50 ea $50.00 $2,500.00
existing service stub.
11 Furnish and install sewer clean-out outside restroom building 2 ea $400.00 $800.00
complete with concrete collar to grade.
12 Furnish and install 4" thick concrete flatwork including 4" granular 1,300 sf $5.50 $7,150.00
base material (outside of building footprint). Interior concrete for
13 fl ill b install city
Furnish and d i standard
bid it 1"
1 culinary water service meter 1 ea $600.00 $600.00
station complete. City to provide meter.

PROJECT SUBTOTAL = $170,250.00


10% Contingency = $17,025.00
PROJECT TOTAL = $187,275.00

________________________________________ JONES AND ASSOCIATES CONSULTING ENGINEERS


___________________________________________________________

North Ogden City Corporation


Orton / Green Arces Park Restroom Reconstruction Project
Budgetary Estimate
Location: 2050 North 600 East North Ogden, UT 84414
Date: November 6, 2013

Item Description Quantity Unit Unit Price Total Amount


1 Construct 52'x25' restroom facility including storage room 1 ls $94,000.00 $94,000.00
complete with sewer, water and electrical connections,
landscape restoration and all appurtenances in accordance with
the drawings and specifications.
2 Furnish and install plumpbing fixture & toilet accessories. 1 ls $21,000.00 $21,000.00

3 Demolish existing building; level out grading at restroom; cap 1 ls $3,500.00 $3,500.00
sprinklers; etc.
4 Construct new 1" culinary water service line to restroom. 20 lf $20.00 $400.00
Includes connection to existing service stub.
5 Furnish and install new 4" sewer lateral. Includes connection to 20 lf $50.00 $1,000.00
existing service stub.
6 Furnish and install sewer clean-out outside restroom building 2 ea $400.00 $800.00
complete with concrete collar to grade.

7 Furnish and install 4" thick concrete flatwork including 4" granular 1,000 sf $5.50 $5,500.00
base material (outside of building footprint). Interior concrete for
8 fl ill b install city
Furnish and d i standard
bid i 1"
1 culinary water service meter 1 ea $600.00 $600.00
station complete. City to provide meter.
PROJECT SUBTOTAL = $126,800.00
10% Contingency = $12,680.00
PROJECT TOTAL = $139,480.00

________________________________________ JONES AND ASSOCIATES CONSULTING ENGINEERS


___________________________________________________________

North Ogden City Corporation


Lomond View Park Restroom Reconstruction Project
Budgetary Estimate
Location: 220 East Elberta Drive North Ogden, UT 84414
Date: November 6, 2013

Item Description Quantity Unit Unit Price Total Amount


1 Construct 52'x25' restroom facility including storage room 1 ls $94,000.00 $94,000.00
complete with sewer, water and electrical connections,
landscape restoration and all appurtenances in accordance with
the drawings and specifications.

2 Furnish and install plumpbing fixture & toilet accessories. 1 ls $21,000.00 $21,000.00

3 Demolish existing building; level out grading at restroom; cap 1 ls $3,500.00 $3,500.00
sprinklers; etc.
4 Construct new 1" culinary water service line to restroom. 20 lf $20.00 $400.00
Includes connection to existing service stub.
5 Furnish and install new 4" sewer lateral. Includes connection to 20 lf $50.00 $1,000.00
existing service stub.
6 Furnish and install sewer clean-out outside restroom building 2 ea $400.00 $800.00
complete with concrete collar to grade.
7 Furnish and install 4" thick concrete flatwork including 4" granular 1,000 sf $5.50 $5,500.00
base material (outside of building footprint). Interior concrete for
floors will be covered in bid item 1.

8 Furnish and install city standard 1" culinary water service meter 1 ea $600.00 $600.00
station complete. City to provide meter.

PROJECT SUBTOTAL = $126,800.00


10% Contingency = $12,680.00
PROJECT TOTAL = $139,480.00

________________________________________ JONES AND ASSOCIATES CONSULTING ENGINEERS


___________________________________________________________

  North Ogden City Corporation
   North Ogden Park Grandstand Improvement Project
    Budgetary Estimate
    Location:  500 E 2700 N, North Ogden, UT 84414
     Date: November 7, 2013

Item Description Quantity Unit Unit Price Total Amount


1 Paint the grandstand (100' long x 25' wide x 11 rows high). 1 L.S. $9,350.00 $9,350.00
2 Construct new 42" high safety fencing/railing along the back and  150 lf $65.00 $9,750.00
sides of bleachers with 3" max opening.
3 Replace broken stairs and foot boards 250 fbm $3.50 $875.00
4 Remove wood bench boards and replace with metal benches. 1,100 ft $6.50 $7,150.00
5 Construct concession area under bleacher complete with two  288 sf $72.00 $20,736.00
compartment sink and water heater.
6 Furnish and install 4" sewer service to grandstands including surface  184 lf $45.00 $8,280.00
restoration.
7 Furnish and install sewer cleanout. 2 ea $400.00 $800.00
8 Connect to existing sewer main. 1 ea $450.00 $450.00
9 Furnish and install 1" culinary water service to grandstands including  75 lf $20.00 $1,500.00
surface restoration.
10 Connect to existing water meter $1.00 ea $300.00 $300.00

PROJECT SUBTOTAL =  $59,191.00
10%  Contingency =  $5,919.10
PROJECT TOTAL =  $65,110.10