Project Name

Company Today's Date:

Team Lead: Name


Start Date: 8/12/2013 Monday
[42]

Duration
(Days)
Task # of Hours
Task# Tasks Lead Required Start End
1 Task1 Name 8/12/13 8/23/13 10
1.1 Task1.1 - 8/12/13 8/13/13 2
1.2 Task1.2 - 8/14/13 8/16/13 3
1.2.1 Task1.3 - 8/19/13 8/20/13 2
1.2.2 Introductions - 8/21/13 8/23/13 3
2 Task 2 Name 8/26/13 10/4/13 40
2.1 2.00 8/26/13 8/26/13 1
2.2 5.00 8/26/13 8/26/13
2.3 0.50 8/26/13 8/26/13
2.4 1.00 8/27/13 8/27/13 1
2.5 4.00 8/27/13 8/27/13
2.6 1.00 8/27/13 8/27/13
2.7 0.50 8/27/13 8/27/13
2.8 0.50 8/27/13 8/27/13
2.9 8.00 8/28/13 8/28/13 1
2.10 2.00 8/29/13 8/29/13
2.11 2.00 8/29/13 8/29/13
2.12 2.00 8/29/13 8/29/13
2.13 3.00 8/29/13 8/29/13
2.14 3.00 8/30/13 8/30/13 1
2.15 - 9/2/13 9/27/13 20
2.16 2.00 9/3/13 9/3/13
2.17 2.00 9/4/13 9/4/13
2.18 3.00 9/5/13 9/5/13
2.19 3.00 9/6/13 9/6/13
2.2 3.00 9/9/13 9/9/13
2.21 3.00 9/10/13 9/10/13
2.22 3.00 9/11/13 9/11/13
2.23 3.00 9/12/13 9/12/13
2.24 3.00 9/13/13 9/13/13
2.25 2.00 9/18/13 9/18/13
3 Task 3 Name 9/16/13 10/4/13 15
3.1 1.30 9/17/13 9/17/13 1
3.2 1.30 9/17/13 9/17/13
3.3 1.00 9/17/13 9/17/13
3.4 0.30 9/20/13 9/20/13
3.5 10/1/13 10/1/13
3.6 10/1/13 10/1/13
3.7 10/1/13 10/1/13
3.8 10/1/13 10/1/13
3.9 10/1/13 10/1/13
3.10 10/1/13 10/1/13
3.11 10/1/13 10/1/13
3.12 1.30 9/19/13 9/19/13 1
3.13 1.30 9/19/13 9/19/13
3.14 2.30 9/19/13 9/19/13
3.15 0.00 9/19/13 9/19/13
3.16 2.30 9/17/13 9/17/13
3.17 0.30 9/20/13 9/20/13 1
3.18 1.30 9/20/13 9/20/13
3.19 1.30 9/20/13 9/20/13
3.20 1.30 9/20/13 9/20/13
3.21 9/16/13 10/4/13
4 Task 4 Name 9/23/13 10/18/13 26
4.1 2.30 9/23/13 9/23/13
4.2 6.00 9/24/13 9/24/13 1
4.3 6.00 9/25/13 9/25/13 1
4.4 6.00 9/26/13 9/26/13 1
4.5 9/27/13 10/18/13 16
Today's Date: 9/27/2013 Friday
(vertical red line)

Days Remaining
First Day of Week (Mon=2): ###
2###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

Days Complete
% Complete

02 - Sep - 13
09 - Sep - 13
16 - Sep - 13
23 - Sep - 13
30 - Sep - 13

04 - Nov - 13
12 - Aug - 13
19 - Aug - 13
26 - Aug - 13

07 - Oct - 13
14 - Oct - 13
21 - Oct - 13
28 - Oct - 13
Working
Days

100% 10 10 0
100% 2 2 0
100% 3 3 0
100% 2 2 0
100% 3 3 0
100% 30 40 0
100% 1 1 0
100% 1 0 0
100% 1 0 0
100% 1 1 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 1 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 1 0
25% 20 3 17
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
100% 1 0 0
0% 15 0 15
0% 1 0 1
0% 0 0
0% 0 0
0% 0 0

0% 0
0% 0
0% 0
0% 0
0% 0
0% 0
0% 1 0 1
0% 0
0% 0
0% 0
0% 0
0% 1 0 1
0% 0
0% 0
0% 0
0 15
0% 20 0 26

0% 1 0 1
0% 1 0 1
0% 1 0 1
0% 16 0 16
[42]

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
04 - Nov - 13

18 - Nov - 13
25 - Nov - 13
02 - Dec - 13
09 - Dec - 13
16 - Dec - 13
23 - Dec - 13
30 - Dec - 13

03 - Feb - 14
10 - Feb - 14
17 - Feb - 14
24 - Feb - 14
03 - Mar - 14
10 - Mar - 14
17 - Mar - 14
24 - Mar - 14
31 - Mar - 14
11 - Nov - 13

06 - Jan - 14
13 - Jan - 14
20 - Jan - 14
27 - Jan - 14