April 3, 2019
EA - Project Sequencing
Short Term Improvements
• Emergency culvert repairs – relining of 3 existing
CSP culverts
$20M
$15M
$10M
$5M
Table #2 – Alternative Project Sequencing
$20M
$15M
$10M
$5M
Projection of Costs
Summary
Regulatory Approvals
- DFO approvals pending
Risk
Alternative Project Sequencing
Infrastructure Improvements
- Rock fill widening and stabilization – deferred to 2039
- Pavement & maintenance repairs – 2019
- Road enhancements – deferred to 2039
- Chemong Bridge rehabilitation - 2022
Regulatory Approvals
- DFO approvals may be not required to complete maintenance and
enhancements.
- DFO approvals would eventually be needed for any in-water work (2039).
Recommendation
Be it resolved that County Council receives the James A Gifford
Causeway Widening Cost Savings Opportunities report; and
That County Council endorse proceeding with the Causeway
Improvement Plan as being the lowest cost solution and as
previously approved by Council in the 10 year capital forecast.