Reference No.: BatStateU-RA-RES-01
RISKS.
Process A: Submission of research proposal using incorrect forms
Effectivity Date: March 26, 2018
Revision No.: 00
No} Key Steps Risk Description Cause/s Action/s to Address the Risk Responsible | Target Date
1 [Receiving of Capsule [Submission of research [Unfamiliar with the ISO forms to = Provide correct ISO forms for research proposal Proponent, | February 2019
[Research Proposal proposal using be used + Provide downloadable ISO forms online Coordinator,
incorrect forms Director, Staff
[Submission of research|Not familiar on how to Provide sample standard template; Provide proper Proponent, | February 2019
Iproposal with wrong accomplished the ISO forms guidance and assistance Coordinator,
format of proposal Director, Staff
2 [Endorsement of [Lost of documents [Proposals were not submitted - Track documents on record books and verify the | Director, Asst. | March 2019
|Capsule Research directly to the responsible received copies rector, Staff
Proposal loffice/person }+ Ensure the implementation of document tracking
system
+ Scan all submitted proposals as back-up files
|. Ask for re-submission
|Voluminous proposals [Not evaluated at once due to other Setting of Quota VPRDES, | March 2019
for evaluation of the tasks assigned + Identification and creation of pool of experts Director, Asst.
assigned assistant + Partition of the remaining proposal to active status | Director, Staff
director land to be included in the next colloquium
3 [Presentation to [Unavailability of the | Urgent call for presentation |- Proper scheduling of research colloquium and strict| _ Proponent, May 2018
Research Colloquium. }researcher(s) to present|+ Delayed notice implementation of the schedule of the call for Coordinator,
|- Sudden lack of J+ Researchers have prior proposal. Co-proponents may be allowed to present | Director, Staff
interest lcommitment the research proposal
+ The presentation shall be re-scheduled on the next
research colloquium.
[Lack or unavailability | Source out external evaluators at least two months | _ External May 2018
lof external panel of + Late sending of invitation before the presentation Evaluator,
+ Increase the number of external experts being Director, Asst.
levaluators
| Has prior commitment
tapped
Director, Staff
Page 1 of 5Process Owner: Research Office
Presentation to
Research Council
[Unavai
lcommon time of the
research council
Effectivity Date: March 26, 2018
RISK/OPPORTUNITIES ASSESSMENT.
‘Short notice
+ Late sending of invitation
|+ Members have prior commitment
+ Doing other task that needs to be
addressed immediately
Provide the schedule to the Research Council
beforehand and confirm their attendance
J+ Re-scheduling of research council
‘VPRDES,
Directors,
Proponent, Staff
Revision No.: 00
‘Tune 2018
[implementation of
Research project
Delays in
implementation due to
jundelivered supplies
land equipment
|+ No contact for specific supplier
+ Lack specifications on the
requested item
+ Supplier does not conform with
the required specifications
+ Delayed posting for possible
+ Regular follow-up of request
+ Assist the Procurement Office in canvassing and
purchasing supplies and equipment
+ Conduct of pre-implementation booth camp
+ Grant/ endorse the request for the revisions of
limetable
Proponent,
Coordinator,
Staff
‘August 2018
'rerminal Report
lof terminal report
work plan
+ Delay in the conduct of research
{terminal reports
+ Tagging for clearance of faculty
+ Request letter of justification from the researcher
+ Endorse/grant the request for project extension
Directors,
Coordinators,
Faculty
Researchers
[Unmet project timerine| ty of the needed - Regular monitoring of the researchers regarding the| Director, Asst. | August 2018
and materials in the progress of his project, Directors,
implementation of the project J+ Request letter of justification from the researcher | Coordinators,
land grant/ endorse the request for the revisions of Faculty
timetable Researchers
[Delays in submission Researchers were unable to + Regular follow-up to the researcher to submit Director, Asst. | August 2018
lof quarter/progress conduct the research as to the |quarter reports
reports lapproved work plan + Tagging for clearance of faculty
+ Request letter of justification from the researcher Faculty
and grant/ endorse the request for the revisions of | Researchers
timetable
6 |Submission of [Delays in submission |* Did not comply with the project |- Regular follow-up to the researcher to submit Director, Asst. | December 2018
Page 20f5Reference No.: BatStateU-RA-RES-01
Process Owner: Research Office
[Unfinished projects
[Submission of research
proposal using
Receiving of Capsule
Research Proposal
[Project leader/staff no longer
[connected with the university
+ Researchers were hesitant to
|continue the research due to
difficulty in the procurement of
Imaterials and supplies for the full
[implementation of the project
Process B: Submission of Research Proposal to External Funding Agencies
[Unfamiliar with ISO forms to be
lused
Effectivity Date: March 26, 2018
‘A letter of non-compliance to the researcher
+ Request updates and progress of the project
+ Tagging for clearance of faculty
+ Endorse/grant the request for project extension
+ Provide sanctions to the researchers
+ Provide correct ISO forms for research proposal
| Provide downloadable ISO forms online
Director, Asst.
Directors,
Coordinators,
Faculty
Researchers
Proponent,
Coordinator,
Revision No.: 00
December 2018
February 2019
+ Doing other task that needs to be
laddressed immediately
incorrect forms Director, Staff
[Submission of research [Not familiar on how to - Provide sample standard template Proponent, | March 2019
lproposal with wrong accomplished the ISO forms + Provide proper guidance and assistance Coordinator,
format of proposal Director, Staff
2 [Endorsement of [Lost documents Proposals were not submitted J; Track documents on record books and verify the | Director, Asst. | April 2018
ICapsule Research directly to the responsible received copies Director, Staff
Proposal loffice/person + Ensure the implementation of document tracking
system
+ Scan all submitted proposals as back-up files
J+ Ask for re-submission
/Voluminous proposals |Not evaluated at once due to other - Setting of Quota VPRDES, ‘April 2018
for evaluation of the tasks assigned + Identification and creation of pool of experts Director, Asst.
lassigned assistant + Partition of the remaining proposal to active status | Director, Staff
director. land to be included in the next colloquium
3 [Presentation to [Unavailability of [+ Short notice + Provide the schedule to the Research Council VPRDES, May 2018
Research Council __fcommon time of the _|+ Late sending of invitation lbeforchand and confirm their attendance Directors,
research council + Members have prior commitment + Re-scheduling of research council Proponent, Staff