Professional Documents
Culture Documents
Resumen01 ZambranoLuisa RamírezCarlos
Resumen01 ZambranoLuisa RamírezCarlos
Summary
- Verb-oriented WBS: Is a task-oriented WBS that defines the project work in terms of the
action that must be done to produce the deliverable. First word of an element: verb.
- Time-phased WBS: Breaks the project into major phases instead of task. A “rolling wave”
approach is adopted and only the near-term phase is planned in detail.
- The 100% Rule: States that the WBS includes 100% of the work defined by the project scope
and captures all deliverable in terms of the work to be completed, including project
management. The sum of the work at the “Child” level must equal 100% of the work
represented by the “partner” and the work represented by the project package must add up
100& of the work necessary to complete the work package.
- Planned Outcomes, Not Planned Actions: The best way to adhere to the 100% rule is to
define WBS elements in term of outcomes or results. WBS that subdivide work by project
phases must ensure that phases are separated by a deliverable.
- Level 2 is the Most Important: It determines how actual cost and schedule data are
grouped for future project cost and schedule estimating.
- How Far Down? An effective limit of WBS may be reached when it is no longer possible to
define planned outcomes and the only detail are actions.
- The 40-Hour Rule of Decomposition: There is no need to decompose further when a project
has been decomposed down to an element that has about 40 hours of allocated direct.
- The 4% Rule off Decomposition: A WBS is adequately decomposed when the lowest
element is about 4% of the total project.
REFERENCES: