Professional Documents
Culture Documents
Chapter 2-ENG PDF
Chapter 2-ENG PDF
:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
CHAPTER 2
PIPELINE DESIGN
CONTENTS
Page No.
2.1 Codes and Standards 3
2.2 Design Stages 3
2.2.1 Front End Design 4
2.2.2 Conceptual Design 4
2.2.3 Detailed Design 5
2.3 Pipeline Routing Offshore 6
2.3.1 Preliminary Routing 6
2.3.2 Navigation 7
2.3.3 Shore Approaches 7
2.3.4 Existing Pipelines and Structures 8
2.3.5 Platform approaches and riser location 8
2.3.6 Topographical and Hydrographic Survey 10
2.3.7 Soil Data 10
2.3.8 Final offshore routing 10
2.4 Pipeline Routing Onshore 11
2.4.1 Considerations 11
2.4.2 Route Information 12
2.4.3 Permanent Right-of-Way 12
2.4.4 Block Valve Stations 12
2.4.5 Final Routing 12
2.5 Pipeline Routing Tolerance Requirements 12
2.6 Geotechnical Site Investigation 13
2.6.1 Planning 14
2.7 Materials 17
2.7.1 Carbon Steel 17
2.7.2 Glass Reinforced Plastic 18
2.7.3 Corrosion Resistant Alloys 19
2.7.4 Plastics 19
2.7.5 Flexibles 19
2.8 Leak Detection and Isolation Systems 19
2.9 Diameter Selection 20
2.9.1 Basics 20
2.9.2 General Considerations 20
2.9.3 Velocity Limitations 21
2.9.4 Recommended Standard Operating Pressures 22
2.9.5 Sizing Criteria for Liquid Lines 22
2.9.6 Sizing Criteria for Gas Lines 24
2.9.7 Sizing Criteria for Two-Phase Lines 24
2.9.8 Pressure Losses in Valves and Fittings 24
2.10 Wall Thickness Selection 25
2.10.1 Basics 25
2.10.2 General Considerations 25
2.10.3 Hoop Stress Sizing Criterion 26
2.10.4 Code Transition 27
2.10.5 Pipe Wall Thickness Tolerances 28
2.10.6 Minimum Nominal Pipe Wall Thickness 28
2.11 Standardisation of Linepipe 29
2.12 Environmental Data 29
2.12.1 Waves 29
2.12.2 Currents 31
2.12.3 Water Depth 32
2.12.4 Ambient Temperatures 32
2.12.5 Operating Temperatures 33
2.12.6 Marine Growth 33
Approved:2009 Page 1 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Approved:2009 Page 2 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
ASME B.31.4: Liquid transportation systems for hydrocarbons, liquid petroleum gas,
anhydrous ammonia, and alcohols
Design of offshore pipelines is usually carried out in three stages: conceptual engineering,
preliminary engineering, and detail engineering. During the conceptual engineering stage,
issues of technical feasibility and constraints on the system design and construction are
addressed. Potential difficulties are revealed and non-viable options are eliminated.
Required information for the forthcoming design and construction are identified. The
outcome of the conceptual engineering allows for scheduling of development and a rough
estimate of associated cost. The preliminary engineering defines system concept (pipeline
size and grade), prepares authority applications, and provides design details sufficient to
order pipeline. In the detail engineering phase, the design is completed in sufficient detail to
define the technical input for all procurement and construction tendering. A complete
pipeline design includes pipeline sizing (diameter and wall thickness) and material grade
selection based on analyses of stress, hydrodynamic stability, span, thermal insulation,
corrosion and stability coating, and riser specification. The following sections detail the
specific requirements for each design stage.
Approved:2009 Page 3 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
During the front-end design of a pipeline, the transport requirements are defined in terms of
product, throughput and pressure/temperature regimes. The Project Development Plan
usually documents the preliminary size, routing options and design philosophy and includes
basis for design parameters such as design life, fluid composition, environmental and
operating conditions.
The following activities are normally carried out during the conceptual design of an offshore
pipeline:
• Survey route,
• Select the pipeline route and prepare drawings, including riser location
• Perform a brief environmental impact assessment,
• Finalise the pipeline diameter,
• Select pipeline material and corrosion prevention methods,
• Select pipeline and riser wall thickness,
• Check pipeline in-situ stresses
• Select riser clamp positions, check riser stresses and prepare riser drawings,
• Determine concrete weight coating thickness and density,
• Prepare pipeline and riser installation feasibility report,
Approved:2009 Page 4 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The following activities are normally carried out during the conceptual design of an onshore
pipeline:
The following activities are normally carried out during the detailed design of an offshore
pipeline:
Approved:2009 Page 5 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The following activities are normally carried out during the detailed design of an onshore
pipeline:
• Detailed survey by XGM of the preliminary route,
• Select final route,
• Prepare alignment sheets,
• Select and peg the final pipeline route,
• Design cathodic protection system,
• Design major road and river crossings,
• Determine pipeline lowering into trench parameters,
• Prepare welding specifications,
• Prepare pre-commissioning procedure,
• Prepare operating, maintenance and inspection manual,
• Prepare final bill of materials,
• Prepare detailed design report
The minimum allowable horizontal curvature of a pipeline depends on various factors, such
as installation method, diameter, wall thickness and operating conditions. For submarine
pipelines, the minimum radius of curvature at bends in the route is governed by two factors:
As an approximation, soil friction enables a pipeline curve radius, R, if R is greater than the
term,
Approved:2009 Page 6 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
T
R=
fw
where:
Conservative values of T and f shall be adopted since the above equation ignores pipe
stiffness. Special consideration shall be given to route curvatures near pipeline 'free ends'
(e.g. start up/lay down).
The effect of route curvature on the equivalent stress in the pipe wall shall be checked on a
case by case basis. Generally, bending stresses of up to 10% of SMYS will have no
adverse effect. In the absence of suitable data, the following values may be used for
conceptual design purposes:
Pipe diameter Minimum radius (m)
Less than DN 250 1000
DN 250 DN 450 2000
Over DN 450 3000
Pipeline alignment sheet drawings shall be referenced to the system, and shall show all
pertinent route co-ordinates (e.g. start up/lay down, tangent points, intersection points,
centre points of curvature, kilometre posts).
2.3.2 Navigation
Marine traffic may constitute a hazard during and after construction. The primary risk of
damage is by dragging anchors or "sawing" anchor cables. Parts of waterways where
navigation is difficult, mooring and anchoring locations should be avoided as pipeline
crossing sites. To reduce the risks of damage by anchors, in such areas, burial of pipelines
may be advisable.
The pipeline shore approach location may be influenced by the existence of industrial,
commercial or residential installations on the shore or banks. Not only may such
installations prohibit the routing of the pipeline in the neighbourhood, but the availability of a
work area on the bank may prohibit the construction or eliminate certain construction
method as e.g. bottom pull. Obviously, a concentration of rocks, barge tie-up points, gravel
or sand pits, and residential, commercial or industrial installations has a negative effect on
the crossing site.
Approved:2009 Page 7 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Crossing of existing pipelines require special measures such as additional dredging, jetting
down existing line, sandbagging or installing saddles, to avoid over-stressing and cathodic
protection system interference. Selection of a route with fewer crossings could therefore be
financially attractive.
Offshore platforms normally are, or will be, concentration points for pipelines and shipping,
and also present navigational obstructions to construction equipment. The pipeline route
should, therefore, be chosen at a practical distance (say 100m) from those structures which
are unrelated to the pipeline. Pipelines close to offshore platforms should, as far as
possible, be arranged in corridors to facilitate the anchoring of vessels for support and
future construction activities at the platform.
The pipeline route shall be selected with due regard to safety of the public and personnel,
protection of the environment, and the probability of damage to the existing submarine
pipeline or other facilities such as electrical cables shall take into design consideration.
Line crossings near platforms should be prevented as they may jeopardise future riser
repairs or relocations. The design should ensure that crossings are sufficiently protected
both from a mechanical and cathodic protection point of view.
In deciding where to approach the platform and where to locate the riser, the following
factors should be considered:
Approved:2009 Page 8 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
In order to establish the number of risers which can be set at a given platform the average
spacing between adjacent risers and the seabed approach angles need to be considered.
The minimum approach angle to a platform face shall be 30° but for practical reasons the
approach angle should be as near as possible to 90°. The minimum angle between
adjacent riser approaches on the seabed should be 4°. The minimum spacing between
adjacent risers (measured from centrelines) on a given jacket face is dependent upon water
depth and shall be as follows:
When pipelines have to approach the jacket with angles greater than 30o from the central
axis the spacing between the risers should be increased by 0.3 m to allow more space
between the lines on the seabed.
If the direct approach of a pipeline is hampered by the future position of a jack-up rig,
doglegs can be laid consisting of:
• 90o bend with minimum radius of 5 times the outside diameter.
• section of 25 to 30 m
Doglegs should also be used in preference to tight curved approaches to jackets and
provide a means of allowing for thermal expansion in addition to that provided by riser
deflection below the bottom clamp.
Approved:2009 Page 9 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
A very important item for riser locations is the design of a complex layout. Several
platforms together form a complex, which should have a staggered layout along a straight
line (spine) in order to:
• free as much of the jacket faces as possible for risers,
• allow easy barge access,
• position different production functions along the spine, so that future extension of any
function is perpendicular to the spine,
• allow for new functions to be installed along the spine,
Often a dedicated riser platform is installed to supply additional riser capacity (with scraper
barrels and manifolds) and/or to reduce the overall risk levels.
For new developments and extensions of existing complexes a careful study of the new
layout should be made in conjunction with anchor patterns (especially the drilling rigs) and
pipeline approaches.
2.3.6 Topographical and Hydrographic Survey
To select the most satisfactory route for an underwater pipeline and to obtain environmental
data necessary for design, information concerning the history, geology, hydrology and
degree of marine activity should be gathered.
When a preliminary routing is chosen, after evaluation of alternatives, the following detail
surveys should be made:
• Side-scan sonar to detect existing lines, ship wrecks, debris etc.
• Pinger survey for sub-bottom profile.
• Bathymetric survey for water depth measurements.
Upon completion of the pipeline, it is normal practice to perform an "as-built" side scan and
bathymetric survey to determine its final location.
2.3.7 Soil Data
Soil data will indicate the necessity and difficulty of excavation and soil stability. If the data
is inconclusive, then sampling and boring with analysis by a qualified consultant may be
required.
If the seabed or river bed is unstable, as for example, in mud lump or mud slide areas
around river deltas, or there is coral or rock, the pipeline should, if possible, be routed
around these areas (refer section 2.6).
Based on the information gathered a final routing can be selected and drawn on alignment
sheets and platform approach drawings, for approval.
The alignment sheets usually have a horizontal scale of 1:5,000 and vertical scale of 1:100
and provide details on the pipeline. The platform approach drawing usually has a scale
1:100. For pipeline routing tolerance requirements see Section 2.5.
Approved:2009 Page 10 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
2.4.1 Considerations
The proximity of residential areas and major roads poses safety and environmental
limitations in the routing of pipelines. Where possible these areas should be avoided. Prime
drilling reserves should also be left clear. Obstructions to be avoided include:
• Buildings
• Hard-surfaced areas
• Roads (where possible)
• Wooded or jungle areas
• Other pipelines
• Rivers (where possible)
• Swampy or marshy areas
• Beach areas (erosion problems)
During the route selection process, consideration of the risk contours to residential areas
shall be made. The risk contours should consider all future developments and provide a risk
level. Refer to "DNV - Technical Guidelines".
Pipelines should never be routed directly above or below existing pipelines. Wherever
possible, pipelines shall be buried. Although this increases installation costs it reduces
external corrosion and future maintenance and does not restrict maintenance vehicle
access.
There are occasions where existing above ground pipe racks can be used but efforts shall
be employed to reduce these existing racks. After taking account of the above
considerations, pipe routings should be:
• as straight as possible (eases installation and reduces cost)
• follow natural or logical routes
• utilise existing rights of way (to minimise soil erosion)
River crossings should be straight rather than bowed or severely angled across the river.
Where a change of direction or a shift in line becomes inevitable it is good practice to
combine this with other requirements such as shutdown valves, connections to other
facilities, expansion legs and to do so at points where the line can run parallel to existing
pipeline(s).
After selecting the preliminary route, the government shall be consulted to determine any
future development plans along or close to the proposed route and to gain approval of the
route.
For all significant onshore pipeline projects, an Environmental Impact Assessment (EIA)
and Quantitative Risk Assessment (QRA) shall be carried-out before finalising the route.
Approved:2009 Page 11 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
To identify the areas described above, topographical background maps shall be used in
conjunction with drilling reserve maps. Aerial photographs are a good source of information
when choosing a preliminary route especially with regard to jungle or other natural
obstacles. When the preliminary routing drawings have been prepared a site survey shall
be carried out. There are no exceptions to this rule. Where thick jungle or undergrowth
prevents 'walking the line' consideration should be given to altering the route accordingly.
During the site visit actual construction dimensions shall be obtained from fixed points such
as well heads, fence lines, centrelines of roads, buildings or any other suitable 'hard' point.
All onshore pipelines should have sectionalising block valve stations at maximum intervals
as defined by the ASME B31.4 and B31.8 codes to allow isolation during an emergency. It
is generally good practice to install valves upstream and downstream of river crossings,
particularly for oil lines.
The final routing should be drawn on alignment sheets, which include pipeline details. The
alignment sheets shall be discussed and agreed upon with the project matrix. In addition
approval should be obtained from all relevant parties.
2.5.1 General
Pipeline routing should be addressed at the very beginning of any new pipeline project.
The route selection should always be progressed with open dialogue between marine
operations, XGM (topographical department) and the pipeline engineering group in order
that the relevant information and requirements of these functions are considered and
addressed.
Where a proposed route from an existing platform is in the general direction of any existing
line the route should follow close and parallel to such existing pipeline corridor for as long
as practically possible, as this will minimise the impact on marine operations, such as the
anchoring patterns at existing platforms.
Where pipelines are laid along existing pipeline corridors the offset limits between the new
pipeline and an existing pipeline, except at platform approaches, shall be as follows:
Approved:2009 Page 12 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The maximum deviation from alignment along the prescribed route shall be ±15m except
within 450m of the riser, where the maximum allowable deviation shall be as shown in
Section 2.5.2.
For pipelines installed by the Tow method, this deviation may be relaxed after consultation
between the Pipeline Engineering Department, Marine Operations and where relevant, the
installation contractor.
• From 450m of the riser to 150m from the riser : tapering from 15m to 3m
At the pipeline to riser interface the deviation shall be sufficiently small so as to allow
installation of the riser clamps without introducing bending stresses in the riser.
The objective of the site investigation for a marine pipeline is to obtain sufficient reliable
information to permit the safe and economic design of installation and permanent works.
The investigation shall be designed to verify and expand upon any information previously
collected.
The various stages relating to site survey and geotechnical investigation are illustrated in
Figure 3. At the initial stages of a project development, it is often adequate to assess
geotechnical aspects from desk study information.
As the project progresses, the level of detail required increases and additional costs are
incurred in acquiring this information. The important factor to appreciate is that at all times
expenditure on the site survey and geotechnical data should be commensurate with the
level of detail required.
Approved:2009 Page 13 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
2.6.1 Planning
At project conception, the data available shall be sufficient to demonstrate the feasibility
and suitability of the preferred pipeline design concepts and selected route corridors. This
can often be achieved by a desk study to collate published data and information from
previous investigations.
As the project progresses towards detailed design and construction, the data shall be
sufficiently detailed to provide input into pipeline design and to allow contractors to provide
optimised pricing for supply and installation works.
The site investigation programme for a marine pipeline development shall therefore be
undertaken in progressive stages. Planning for each stage shall be carried out based on the
results from previous findings in order to optimise the extent of investigation work.
Factors such as: vertical and horizontal uniformity of soil profiles, geological history and
pipeline system size and concept, shall be directly reflected in the extent of the site
investigation. A full appraisal of the various geological factors at a site shall be summarised
in a geo-hazard study.
It is recommended that all stages of the planning and performance of a survey are directed
by a suitably experienced person. The sequence of the site investigation programme shall
be as follows:
Approved:2009 Page 14 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Desk study
The desk study shall incorporate a review of all appropriate sources of information and the
collection and evaluation of all relevant available types of data for the area of interest. The
various factors that should be investigated include, but are not limited to:
• Geological databases
• Bathymetric information
• Geophysical data
• Geotechnical data
• Metocean data (tides, currents etc)
• Seismicity
• Performance of existing pipelines
• Human activities (eg location of pipelines, cables wrecks, munitions disposal site,
aggregate dredging
The performance of a desk study alone is not normally sufficient for detailed engineering
purposes. The desk study is the best way of obtaining some information, including location
of existing subsea infrastructure (e.g. pipelines and cables) which may be required for the
planning of both the survey and the construction works.
Geophysical survey
A geophysical survey will need to be performed along the proposed route of the marine
pipeline to collect information on:
• Seabed topography – by echo-sounding or swathe bathymetry. The latter is particularly
important in sand wave areas or other areas of generally uneven seabed.
• Seabed features and obstructions – by methods such as side scan sonar
• Profiling of uppermost 5m, or so, of seabed – usually by means of reflection seismic
techniques (sub bottom profiling). Recent developments in towed resistivity and seismic
refraction methods are providing useful complementary data. This is particularly the
case in very shallow water where seismic reflection is not practical.
• Detection of existing cables, pipelines and other metallic obstructions – by means of a
towed magnetometer, however, note is made that not all metallic objects may be
detected, in particular small fibre optic cables.
As a general rule, the width of the survey corridor is between 500m and 1000m, centred on
the proposed pipeline route. The actual width is influenced by factors such as water depth,
seabed features and the need to provide a degree of flexibility in routing.
Shore approach corridors are more likely to be around 500 metres wide, whereas areas in
deeper water incorporating seabed features such as pockmarks and iceberg scars may
warrant survey corridors in excess of 1000 metres to allow re-routing based on detailed
engineering, to minimise the number of potential free-spans. If the geotechnical survey is to
be performed as a separate exercise (see below) it is still advisable and practical to collect
Approved:2009 Page 15 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
some soil samples by grab or gravity core to aid the immediate interpretation of surface and
sub-bottom profiling data.
Survey tie-lines to nearby locations where soils information has previously been gathered
will also aid this process.
Using current satellite technology it is now feasible to transmit interpreted data between the
geotechnical and geophysical vessels to facilitate onboard interpretation and programme
modifications as appropriate. The performance of the geophysical survey alone, or in
addition to the desk study, is not normally sufficient for detailed engineering purposes,
unless site geotechnical data are already available.
GeoBAS survey
The term ‘geoBAS’ (Geophysical Burial Assessment Survey) describes survey operations
using geophysical methods operated from seabed sleds, and towed by the survey ship, to
provide continuous quantitative information for the first few metres of soil below seabed.
Available methods include seismic refraction and electrical resistivity systems. The use of
these methods is often justified if trenching is difficult or the properties of the seabed are
very variable. A more reliable continuous engineering assessment of the route can be made
if GeoBAS measurements are integrated with CPT and core sample data.
GeoBAS equipment is normally mounted on a sled, which is pulled by the survey vessel at
speeds of between 1 and 4knots. It is essential to have some knowledge of seabed
features and potential obstructions to reduce the risk of damage or loss of the equipment.
GeoBAS surveys may also be useful on the shore approach where deeper burial is required
and sometimes rock is present near the surface. Towed systems can be pulled through the
shallow water zone either towards or away from the beach. Technical issues relating to
shallow water and surf noise should be addressed in a project specific manner.
Geotechnical survey
Approved:2009 Page 16 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The suitability of each tool for use in the geotechnical survey shall be assessed. This
should be carried out in conjunction with knowledge of the engineering objectives of the
selected concept(s) and the results of the desk study and geophysical survey phases.
2.7 Materials
Linepipe for pipelines is ordered according to API Spec. 5L for material grades from B to
X70, supplemented by VIETSOVPETRO’s specification. High Strength Butt-Weld Fittings
for pipelines are ordered to MSS-SP-75 for material grades WPHY 42 to WPHY 70,
supplemented by VIETSOVPETRO’s specification. High Strength Flanges for pipelines are
ordered to ASTM A694 for material grades F42 to F70.
• Yield strength
• Ultimate tensile strength
• Elongation
Approved:2009 Page 17 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
• Reduction in area
• Fracture toughness
• Hardness of welded joints
• Hydrogen induced cracking resistance
Tests and acceptance criteria for these properties are covered in the above specifications.
The grade of the material is determined by the Specified Minimum Yield Strength (SMYS)
expressed in thousands of psi (X-42 = 42,000 psi). Metric values for SMYS are:
API Spec. 5L SMYS SMTS Equivalent Strength Materials
Grade for
Linepipe (MPa) (MPa) Butt-Weld Fittings Flanges
B 241 413 ASTM A234 WPB ASTM A105
X42 289 413 MSS-SP-75 WPHY 42 ASTM A694 F42
X52 358 455 MSS-SP-75 WPHY 52 ASTM A694 F52
X60 413 517 MSS-SP-75 WPHY 60 ASTM-A694 F60
X65 448 530 MSS-SP-75 WPHY 65 ASTM-A694 F65
X70 482 565 MSS-SP-75 WPHY 70 ASTM A694 F70
Offshore pipelines are usually constructed in material Grades X42 and X52. Many onshore
pipelines may be constructed from Grade B material. For new and future carbon steel
pipelines the material grade is set as follows:
Note that for pipelines (refer ASME B31.4 and B31.8) a weld joint factor of 1.0 may be
applied for ERW pipe, but for piping (refer ASME B31.3) a factor of less than 1.0 is applied.
For DN400 and greater SAW (Submerged Arc Welded) pipe may be used.
Glass Reinforced Plastic (GRP) pipelines usually have been used for flowlines, water mains
(onshore) and water piping (offshore).
GRP is advantageous for the transport of corrosive products. In addition the friction factor
for fluid flow can be substantially below steel and the life for GRP piping is usually
significantly longer than that experienced with steel.
Unlike steel, GRP pipe can come in a wide range of material specifications for different
applications. Careful selection is thus required.
Approved:2009 Page 18 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The means of connection of pipe joints is either mechanical or adhesive. The application of
GRP should be considered for all future pipelines transporting corrosive fluids on a
performance and life cycle cost basis.
For very corrosive service, the application of corrosion resistant alloys, such as stainless
steel or carbon steel with an internal cladding, shall be considered. Before designing a
corrosion resistant alloy, VIETSOVPETRO JV should be consulted.
2.7.4 Plastics
For the transport of domestic gas and water, pipes made from polymer compounds have
found world-wide acceptance. Some of the referred materials are:
For high pressure applications, Polyethylene (PE) lined steel pipe could be considered.
The PE liner provides the corrosion-resistant fluid barrier, whilst the steel carrier provides
the strength (Ref. 54).
2.7.5 Flexibles
Flexible pipelines have found use in many other parts of the world particularly in deeper
waters. Materials used in the carcass construction allow flexible pipelines to be corrosion
resistant (Ref. 53). Flexible pipelines are expensive and their application can usually only
be justified for repairs on damaged pipelines, risers, jumper hoses, or short pipeline runs.
Many of pipelines are equipped with a low pressure sensor on the inlet, for closing the inlet
valve. The low pressure sensor can usually only detect full bore ruptures, relatively close to
the inlet.
Some pipelines have a high flow sensor in addition to the low pressure sensor. This system
allows smaller than full bore ruptures to be detected along the whole line.
Pipelines must have an integrity monitoring system capable of detecting leak. A leak
detection system in itself has no effect on the leak expectancy of a pipeline and will only
make the operator aware of the occurrence of a leak, enabling him to take remedial actions
in order to limit the consequences of the release. The leak detection system requirements
will vary depending on the pipeline system in question (e.g. offshore or onshore, length etc.)
however, the following should be considered at the design stage and/or implemented during
operation.
Approved:2009 Page 19 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
2.9.1 Basics
Unless otherwise stated, pipe diameters refer to the outside pipe diameters. Nominal pipe
sizes (NPS) are quoted in inches. These are the actual outside diameters in sizes of NPS
14 and beyond. Up to NPS 12, the diameters are not exact. For example NPS 4 has an
outside diameter of 4.5 inches.
Nominal Diameters (DN) are quoted in mm. These are never the exact outside diameters
but a metric approximation to them. Standard diameters and wall thicknesses for steel
linepipe are listed in API-5L (Ref. 20).
It is generally good practice for short lines to choose the next standard pipe size above the
exact requirement.
Throughput
The forecast over the life of the pipeline should be as accurate as possible, with reasonable
allowances for unforeseen increases. To accommodate a high peak of relatively short
Approved:2009 Page 20 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
duration it might be more economical to increase the design pressure than to install a
pipeline designed for that peak throughput at a lower pressure.
In the case of a gradual increase in throughput over the life of the pipeline or a sudden
increase at a later date, the possibility of installing a second pipeline at some time during
the life of the first should be considered, as this may prove to be more economical and
operationally attractive.
Fluid properties
Main properties are specific gravity, operating temperatures, viscosity and / or composition.
Operating pressure
Capital investment and operating cost that are required for increasing the inlet pressure will
also influence the overall economics.
Depending on the conditions at the intended location such as weather conditions, current
velocity, wave heights, tidal effects, bottom conditions, water depth, etc., there may be a
preference for one of the possible construction methods which in turn could put certain
limitations on the selection of line sizes. The available or preferential construction method
also may limit the selection of pipe wall thickness and grade and the type of coating.
Future Use
The function of a pipeline may change over the years. Future uses should be anticipated in
the design phase, and incorporated in the design where possible.
When high water dropouts might be expected in oil lines it is advised to design for a
minimum velocity of 1.5 m/s.
Velocities in wet and two phase gas lines should be high enough avoid slugging problems,
typically more than 3 m/s.
Erosion of the pipeline wall due to impingement of high-velocity liquids or gases might
occur, particular in flowlines and at bends. The equation commonly used to assess the
potential for erosion is (Ref. 24):
⎛ 1 ⎞
Ve = 122 ⎜⎜ ⎟⎟
⎝ ρm ⎠
Approved:2009 Page 21 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
where:
This equation gives a lower bound to potential erosional problems. Velocities in excess of
Ve, may still be acceptable. In those cases VIETSOVPETRO JV should be consulted for
further analysis. Velocities below Ve are safe.
Related with the separation stages at the production facilities the following pressure classes
can be distinguished:
Maximum
Operating
ANSI Pressure
Nomenclature Pressure regime
class (below 38 °C)
(kPa) (kPa)
The ANSI classification is only relevant to any fittings (flanges, valves, etc.) which may be
included in a pipeline. These can be the "weak points" in a pipeline design. For the pipeline
it is good practice to determine a design pressure based on the anticipated maximum
operating pressure plus a 10 % margin.
2.9.5 Sizing Criteria for Liquid Lines
In single phase liquid pipelines the fluid properties remain essentially constant over the
entire length of the pipeline unless there is a significant temperature change.
The general equation for the pressure drop in a liquid pipeline is as follows:
Lv 2
Δ P = ρgΔz + ρf
2d
Approved:2009 Page 22 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
where:
The fluid velocity “v” may be determined from the volumetric flow rate by:
4Q
v=
where : πd 2
Q = volumetric flow rate (m3/s)
To determine the friction factor “f” the Reynolds number “Re” has to be calculated from:
vd
Re =
υ
where:
v = flow velocity [m/s]
υ = kinematic viscosity [m2/s]
The friction factor “f” can be read from the standard Moody diagram with a suitable value of
relative roughness ε/d. Typical values of pipe wall roughness ε are:
For the design of new or non corrosive pipelines, a roughness value of 0.045 mm is often
used. For detailed analysis it is recommended to use the PIPESIM correlations.
Approved:2009 Page 23 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
For level gas lines, containing no liquid, the AGA equation can be used for initial sizing.
Pi 2 − Po2 Q2
= CfzT ρ − 5
L d
where:
Pi = inlet pressure [MPa]
There are numerous correlations for pressure drop / flow / diameter / flow regime
determination for two-phase flow. None is easy to apply without computer assistance. It is
recommended that for all two-phase (and so-called three-phase) calculations the PIPESIM
correlations are used.
Pressure losses in valves and fittings are usually determined on the basis of an equivalent
length of pipe following the table below.
Approved:2009 Page 24 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
2.10.1 Basics
By attempts to restrict the range of wall thicknesses in any one size in order to limit the
material stocks provided the cost penalty is small.
Pipe schedules are a series of numbers which identify a range of standard pipe wall
thickness and are used for on-plot pipework, designed in accordance with ANSI/ASME
B31.3 only.
Definitions:
Design pressure is to be taken as the MOP or the pressure class of the connected piping
system, whichever is greater.
Maximum operating pressure is the highest pressure at which a piping system is operated
during a normal operating cycle, abbreviated as MOP. (Sometimes referred to as
maximum actual operating pressure.)
The wall thickness selection is primarily based on the hoop stress criteria, as specified in
the ASME B31.4 and B31.8 codes. The ASME B31.4 code basically applies to liquid lines
and the ASME B31.8 code to gas and two-phase lines. For details refer to the relevant
codes.
Approved:2009 Page 25 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
A corrosion allowance is only added to the minimum required wall, if the service conditions
are corrosive. Additional wall thickness may be required to:
The pipe wall thicknesses should provide an adequate allowable operating pressure under
the applicable codes and this Guideline.
The internal design pressure should not be less than the maximum steady state operating
pressure. If levels of pressure rise due to surges (and other variations from normal
operations) exceed the internal design pressure by more than 10%, protective equipment
should be provided.
The required wall thickness can be based on the following hoop stress criterion:
pD
t=
2σ y fET
where:
t = nominal wall thickness [m]
p = design pressure [MPa]
For offshore pipelines, the ASME B31.8 code specifies for the hoop stress design factors:
Approved:2009 Page 26 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The ASME B31.4 code (liquid lines) specifies for onshore lines a design factor of 0.72
throughout; however this has been modified for certain locations, for application here. The
ASME B31.8 code (gas/liquid lines) specifies for onshore lines according to zones. Refer to
Table 1 in Section 2.13.2.
Particularly for offshore pipelines and risers, a detailed stress analysis should be carried-out
taking into account all load conditions (thermal, environmental, bending) and all stress
components (axial, hoop, shear).
Pigging facilities (launchers and receivers) are designed in accordance with the pipeline
codes and are generally installed on the scraper deck of a platform. In view of pig / sphere
runs through pipelines, great differences of internal diameter (steps) cannot be tolerated.
The transition of code from pipeline (ASME B31.4/8) to piping (ASME B31.3) should
therefore be at the valves connected to the barrel and tee (see Figures 5 and 6).
There are numerous examples of scraper barrels and/or riser connecting pipework which
have been designed according to ASME B31.3 (specification break at the riser insulation
flange). This situation should be corrected on a maintenance opportunity basis, provided
the incremental costs are small.
Approved:2009 Page 27 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The steel wall thickness should not deviate from the nominal thickness by more than +10%
or -5% for all sizes of welded pipe. Furthermore, below a nominal wall thickness of 7 mm
the acceptable minus tolerance is -0.35 mm and above 10 mm wall thickness the maximum
acceptable minus tolerance is -0.5 mm.
For all sizes of seamless pipe, the wall thickness should not deviate from the nominal
thickness by more than +15% or -10%.
The wall thickness which will facilitate high quality welds, coating and construction, should
not be less than the following minima:
Approved:2009 Page 28 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
To rationalise the amount and variety of pipe held in stock and to simplify handling
provisions, VSP may standardise on one wall thickness and material grade per pipe
diameter for short lines. In addition some sizes of pipe may not be used.
The table below gives the recommended pipe sizes, wall thickness and grades of material.
Non-conformance of new pipelines with values in this list should only be considered if the
additional capital expenditure can be justified against the costs of stocking non-standard
pipeline joints for repair purposes.
2.12.1 Waves
As a minimum, the following wave data shall be available at suitable locations along the
route:
Approved:2009 Page 29 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
• Significant wave heights (Hs) and spectral peak periods (Tp) for 1 year and 100 year
return period storms.
• Maximum wave heights (Hmax) and associated periods (Tmax) for 1 year and 100 year
return period storms.
For overall pipeline stability assessment, the significant wave height and spectral peak
period shall-be used to calculate wave induced flow velocities. For-riser design, and for
localised pipeline sections such as spans and crossings, the maximum wave height and
associated period shall be used.
For each combination of water depth and wave parameters, a suitable wave theory for
predicting water particle motions shall be adopted.
At locations of relatively shallow water depth and near shore areas, shoaling and refraction
effects shall be evaluated including the effects of bottom friction on wave height, sediment
transport and other effects. If a shoaling and refraction analysis is not considered
necessary, suitable justification shall be provided
The design wave used for concept of the design of offshore jackets in which the most
probable is maximum wave in a period of 100 years which is replaced by a regular wave of
a suitable wave length, period and steepness.
To determine the wave-induced water particle velocity at any water depth VIETSOVPETRO
JV could be consulted. They will select a suitable wave theory and from user supplied data
will calculate:
• Wave length, wave celerity, depth of wave influence and wave profile.
As an approximate alternative, the linear wave theory may be applied. First the wavelength
needs to be estimated. The controlling equation is:
gT 2 ⎛ 2π d ⎞
L= tanh ⎜ ⎟
2π ⎝ L ⎠
where:
L = Wavelength [m]
g = Gravitational acceleration [m/s2]
T = wave period [s]
d = water depth [m]
Note that this equation is implicit in L and therefore requires an iterative solution. A good
starting point is to assume a deep water wavelength, i.e.:
Approved:2009 Page 30 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
gT 2
L=
2π
and substitute in the right hand side to find a new value of L. Repeat until convergence,
which is usually rapid.
For conditions in which d / L > 0.1 the maximum horizontal water particle velocity may be
determined from:
π H cosh⎛⎜ 2π
( d−y) / L ⎞
⎟
uw = ⎝ ⎠
T sinh(2π/L )
where:
uw = wave induced velocity at depth y, [m/s]
y=d−D
where:
d = water depth, [m]
D = total outside diameter of pipe (including coatings) [m]
For conditions in which d / L < 0.1, such as the foreshore area, linear wave theory is not
applicable. In this region solitary wave theory should be applied.
The design practice for on-bottom stability of pipelines is to consider the significant wave
height.
For riser design the maximum wave height data for a 100 year return period should be
used, which is the same approach as taken for all jacket tubular. For maintenance and
operational related assessment of risers the significant wave height data should be used,
with a 10 year return period and similarly for installation, a 1 year return period.
2.12.2 Currents
Design 'steady' current data will be provided in the form of directional for 1 year and 100
year return periods. As a minimum, a surface and near bottom velocity shall be provided,
including tidal, surge, and wind driven components.
If an accurate profile is not available, the design current at any depth shall be calculated
from the available data in accordance with the 1/7th power law:
Approved:2009 Page 31 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
1/ 7
⎛D⎞
uc =u s ⎜ ⎟
⎝d⎠
where:
uc = current velocity one pipe diameter above the seabed [m/s]
For a pipeline resting on the seabed boundary layer effects are significant and an 'effective"
(mean) current velocity acting on the pipeline shall be calculated. This may be taken as the
integral of the square of the velocity from the seabed to the top of the pipe. An alternative,
conservative approximation is to use the current velocity at the top of the pipe in
hydrodynamic force calculations.
At a given location, the most critical (either maximum or minimum) water depth should be
used as appropriate in each design analysis. For example, minimum water depth (LAT)
shall be used for pipeline on-bottom stability and in-situ stress analyses.
The relevant storm surge may, however, be added to the water depth in such cases.
Maximum water depth (HAT) shall be used for pipeline buckling, collapse and installation
stress analyses. For buckling and collapse analyses, surface wave heights shall also be
included.
For riser stress analyses, both maximum and minimum depths shall be considered, as
either may prove critical.
Approved:2009 Page 32 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The maximum product temperature from an oil well is unlikely to exceed 50°C but note that
material limitations are imposed at temperatures in excess of 38°C for certain components.
New wells, however, tend to have higher pressures and temperatures.
2.12.6 Marine Growth
In the absence of more accurate data, the marine growth thickness for the riser assembly
shall be assumed to be 90 mm at MSL. Marine growth decreases in thickness with
increasing water depth. This thickness shall be assumed to decrease by 1 mm for every
further 2 metres of water depth.
2.13.1 General
Pipelines and risers have to be designed against the following during all phases of
installation and operation.
• Yielding
• Buckling
• Fatigue
Loading which cause the generation of stresses in the pipe wall may be grouped as follows:
a. Functional Loads
- Pressure (including burial pressure)
- Self weight (or buoyancy)
- Thermal loads
b. Environmental Loads
- Wind
- Currents
- Waves
- Accidental loads (including anchors)
The loading generate combinations of hoop, bending and longitudinal (axial) stresses.
These stresses are usually combined using the von Mises criterion.
2.13.2 Stresses
The pipeline wall thickness selection is usually governed by the hoop stress criterion (see
section 2.10.3).
The hoop stress is directly related to the internal design pressure of the line:
PD
σh =
2t
Approved:2009 Page 33 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
where:
t = wall thickness [m]
P = internal pressure [MPa]
σh = hoop stress [MPa]
Hoop stresses and longitudinal stresses (including the maximum bending stresses) in pipe
material are combined using the von Mises criterion, as follows.
(
σ eq = σ h 2 +σ L 2 −σ hσ L +3τ 2 )
where:
σ eq = equivalent stress [MPa]
Note: the equivalent stress is maximised when one stress is compressive (typically the
longitudinal stress) and the other is tensile (typically the hoop stress). Tensile stresses are
generally assumed to be positive, compressive stresses negative.
The specified minimum yield stress (SMYS) is generally defined as the stress level at 0.5 %
strain, during a tensile test.
The stress calculations for the operational phase shall be carried out with the nominal wall
thickness excluding the corrosion allowance.
For pipelines operating above 60°C, consideration shall be given to switch from a stress
based design to a strain based design. In such cases, guidance and approval shall be
sought from the VIETSOVPETRO JV (see also 2.13.3).
Approved:2009 Page 35 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
NOTE
1. For the purpose of this Guide the definition of Zones shall be as follows:
For lines considered to be critical and for lines to or from manned facilities, Zone 2 shall extend 500m
outwards from the bottom bend of the riser at the seabed.
For lines considered to be non-critical and for lines to or from not normally manned facilities, Zone 2
shall extend 50m from the bottom bend of the riser at the seabed, and shall include the expansion
spool where present.
For landfall areas Zone 2 shall be taken as extending from LAT to 500m offshore.
Zone 1 shall be taken as all areas outside of Zone 2.
For short in-field lines (typically, less than 2km) it may be more economical to classify the entire line
under Zone 2.
2. The specified allowable stresses during installation are not applicable to installation methods where
yielding of the pipe wall is an integral part of the method (e.g. reeling, bending shoe, J-tube pull). For
such methods, refer to (2.13.3).
3. During installation, a factor of 0.85 may be applied to the bending stress in the equivalent stress
calculation in accordance with the DNV 1981 Rules, paragraph 4.3.2.6.
4. For the standard S-lay method of pipeline installation, the allowable equivalent stress in the overbend
(supported on the barge ramp/stinger) may be increased to 96% of SMYS under functional loading
conditions.
During pipeline construction where yielding of the pipe is an integral part of the method, it is
sometimes more appropriate to apply limitations to the maximum allowable strain of the
pipe wall rather than to a maximum allowable stress.
Examples are offshore pipeline installation by reeling, and riser installation by J-tube pull or
bending shoe.
When the pipeline is plastically deformed, it shall be demonstrated that, after straining, the
pipeline material still complies with the required specifications; this is particularly relevant to
toughness, hardness and yield to tensile ratio properties. In such cases, maximum
Approved:2009 Page 36 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
allowable strains shall be as defined in paragraphs of sec. 5 C600, sec. 6 A300 and sec. 9
E100 of the DNV 1996 Rules. (See Reference 4).
D
ε=
2R
where:
ε = bending strain in outer fibre
D = pipe outer diameter [m]
R = bending radius [m]
σ = Eε
where:
σ = Bending stress [MPa]
E = Young's Modulus of elasticity [MPa]
NOTE: During installation and operation the maximum allowable stresses shall be in
accordance with Table 2 of Section 2.13.2.
For cold bending of linepipe the bending strain shall not exceed 2 %. In addition, the pure
bending buckling criteria should be checked. This criterion defines the maximum allowable
elastic curvature. The corresponding minimum allowable elastic bend radius is given by:
1 D2
Rmin = −
=
t
where:
k
Rmin = Minimum bend radius [m]
−
The design of pipelines for service at elevated temperatures, the equivalent stress
requirements (2.13.2) may in some situations lead to very high wall thicknesses. Such
pipelines may hence also require a strain-based design approach to allow for efficient
design. This is particularly relevant to pipelines transporting hot products (typically above
80 °C).
Approved:2009 Page 37 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
For pipelines operating at temperatures above 100°C temperature de-rating factors should
also be taken into account. This is particularly relevant to the use of Corrosion Resistant
Alloy (CRA) materials.
When a line is laid, it is empty and the external water pressure creates a compressive hoop
stress, which could cause collapse of the pipe. An out-of-roundness in the pipe enhances
the risk of collapse. At the locations where the calculated external pressure which would
cause buckling is lower than the actual external pressure, the pipeline shall be fitted with
buckle arrestors (typically every ten joints).
For pipelines installed from a laybarge a minimum D/t (diameter to wall thickness) ratio of
60 should be used in order to avoid buckling during the laying procedure.
Hydrostatic collapse is generally not a concern, in view of its shallow waters. For projects
in deeper waters (typically > 100m) collapse may need to be taken into account.
In any case, buckling and collapse calculations shall be performed for both the installation
and operational conditions and the 'worst case' load conditions. Maximum water depth
(HAT), inclusive of surface wave heights, shall be used for pipeline buckling and collapse
analyses. The pipeline system shall have an adequate factor of safety against the following
modes of failure during all design conditions:
• Local buckling due to combined bending, external pressure and axial force
• Propagation buckling
Acceptance criteria for local buckling and 'bar' buckling modes shall be in accordance with
Appendix A of the DNV 1996 Rules, as follows:
2.064
⎛ t ⎞
Pbi = 0.02 E ⎜ ⎟
⎝D⎠
where:
E = Young's modulus of elasticity for steel
D = nominal outer diameter of pipe, [m]
t = minimum pipe wall thickness, [m]
Note:
t = nominal wall thickness minus the manufacturing tolerance
Approved:2009 Page 38 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Due to the economic consequences of a propagating buckle, a safety factor fb against the
initiation of a propagating buckle shall be used. A recommended value for fb is 1.5, although
other values may be agreed on a case by case basis. Buckle arrestors shall be installed
where the external pressure, Pext ≥ Pbi /fb. Alternatively, for short pipelines, it may be more
economical to increase the wall thickness to ensure that Pext ≥ Pbi /fb.
Buckle arrestor spacing shall be based on an assessment of installation and repair costs,
but should not exceed one every 10 pipe joints.
The external overpressure necessary for an initiated buckle to propagate along the pipeline
is less than Pbi and is given by:
2 .4
⎛ t ⎞
Pbp = 24 S y ⎜ ⎟
⎝D⎠
where:
Sy = SMYS of the pipe steel (as per API Specification 5L)
However, if buckle arrestors are installed where Pext ≥ Pbi /fb, there is no need to install such
arrestors where Pbp < Pext < Pbi /fb.
The acceptance criteria for pipe collapse due to external pressure shall be that Pext > Pc, the
critical collapse pressure. Pc shall be determined by the following equation:
g (r , d )Py Pe
Critical collapse pressure, Pc =
(P y
2
+ Pe
2
)
where:
⎛ t ⎞
Pure plastic collapse pressure, Py = 2 S y ⎜ ⎟
⎝D⎠
2 E (t D )
3
Pure elastic collapse pressure, Pe =
( )
1.4 1 − γ 2 (1 − t D )
2
With: r=
Py
Pe
and d =δ D ( t)
(Dmax − Dmin )
δ=
(Dmax + Dmin )
Sensitivity of the above calculation shall be checked with methods laid down in DNV 1996
Rules.
Approved:2009 Page 39 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
A pipeline resting on the seabed is subjected to forces resulting from steady currents and
waves. These forces are:
• Fd = drag force
• FL = lift force
• Fm = inertia force
In determining the maximum wave and current loads, the water particle velocities due to
current and waves are assumed to be additive thus :
u = uc + uw
The distributed loading on a pipe or riser due to relative particle motion is determined using
the Morison equation.
2
u
Fd = ρ D Cd
2
where: Fd = unit drag force acting normal to the pipe and in the plane
defined by the velocity vector and the pipe axis [N/m]
ρ
3
= mass density of surrounding liquid [kg/m ]
D = outer diameter of the pipe including coatings [m]
Cd = drag coefficient for flow normal to the pipe axis
The drag coefficient depends upon a number of parameters including Reynolds number,
the Keulegan-Carpenter number (for waves) and pipe roughness.
The lift force per unit length for a pipe in close proximity to a fixed boundary (seabed) is
calculated in similar fashion.
2
u
FL = ρ D CL
2
where F = unit lift force acting normal to the pipe and normal to the
L
velocity vector [N/m]
C = lift coefficient for flow normal to the pipe axis
L
Approved:2009 Page 40 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The inertia forces exerted by accelerating water particles (wave induced) is determined
from the following relationship.
π D
2
du
Fm = ρ Cm
4 dt
where F = unit inertia force acting normal to the pipe axis [N/m]
m
The following table taken gives recommended coefficients. See also DNV 1996 Pipeline
Rules.
Cm - 3.3 3.3
Note:
1) Uwi = wave-induced velocity; U = total velocity
2) These values for Cd and CL are in principle only valid for diameters below DN 300 (12 in.)
or for velocities above 2 m/s. For larger diameters or lower velocities Cd and CL vary with
the Keulegan-Carpenter number (Kc = Um T/D) and may be considerably higher. In that
case the advice of specialists is required, although the above values can give a sensitivity
check for calculation purposes.
2.13.6 Wind Forces
These forces are assumed to act normal to the pipe axis - in the plane defined by the pipe
axis and the wind direction.
The "static" wind force per unit length of a pipe may be determined by the following formula:
Fw = 0. 613 Cw v w Dt
2
Approved:2009 Page 41 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
where Fw = wind force per unit length, acting normal to pipe axis [N/m]
The drag coefficient should, strictly, depend on wind velocity, pipe diameter and surface
roughness. However, the following coefficients may be used for individual pipes.
Point loads can be introduced on pipelines for example by laybarge rollers and pipeline
supports. A detailed finite element analysis of the stresses induced is usually not warranted.
However, for checking purposes, one could use the analytical solution of a unit pipe
diameter long thin tube supported at the base and loaded by its own weight.
For buried pipelines the stresses induced due to soil cover and wheel loadings may be
calculated as follows:
wDt
σb = 6 3 3
1. 42 x 10 t + 2 .18 P D
Approved:2009 Page 42 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The induced bending stress in direct combination with the hoop stress should remain below
the allowable stress limit.
Thermal expansion loadings generally cause few problems both onshore and offshore
Brunei. This is due to low variations in ambient temperatures and small differences in
operating and surroundings temperatures. The thermal expansion of a long pipeline,
subject to axial soil friction and constant temperature loading is:
μW
δ = La
2
2EA
α E A ΔT
where: La =
μW
where: δ = expansion at the end of the pipeline [m]
α
-6
=
linear expansion coefficient [11.7 x 10 /°C]
Pipelines are regularly subjected to spanning caused by scouring and coral areas
respectively. Scouring takes place around many jackets leaving the riser, riser bend, and a
section of pipeline free of the seabed. A pipeline crossing another pipeline by means of
(sandbag) support at regular intervals, may also be subject to a multiple number of
unsupported spans.
The method of assessing maximum allowable span length considers three primary
conditions:
c. Loaded cyclically due to vortex shedding (which induces a cyclic bending stress)
Note that when a pipeline, which has already been installed, subsequently needs to be
supported, it should be lifted up to a neutral (level) position before the supports are placed
in order to ensure that there is no sagging left in the line. If this procedure is not followed
Approved:2009 Page 43 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
the remedial effect of providing supports is minimised as the line will remain in a stressed
condition.
The functional loads on a pipeline span are pressure and bending (due to pipeline weight
only). The pressure induces a hoop stress of β times the yield stress (σh = β σy) in the pipe
and an axial stress σa1 (due either to end-cap effect or Poisson effect).
PD
σh = = β σ y tensile (see section 2.13.2)
2t
The bending load induces an axial stress σa2 component (the bending stress) of α times the
yield stress such that:
σa2 = + α σy or - α σy
σa = σa1 + σa2
σ eq =σ y (α 2 +0.75β 2 )
Rearranging gives:
⎛ σ eq 2 ⎞
α = ⎜ 2 −0.75β 2 ⎟
⎜σ ⎟
⎝ y ⎠
The factor β is determined by the design pressure of the line. The ratio of equivalent to yield
stress is governed by the acceptance criteria. For the functional loads the limit is 72% and
for functional plus environmental loads, the limit is 96% as shown for Zone 1 in Table 2 of
Section 2.13.2. Substitution of these ratios provides one value for the ratio α and multiplied
by the yield stress the maximum allowable bending stress.
The bending stress induced by submerged weight of the pipeline, ws (uniform load) on the
pipeline span can be determined by modelling the pipeline as a beam, with an average
support condition between a simply supported and fixed end.
2
ws L
M=
10
Approved:2009 Page 44 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
σb = M D and
2I
I=
π
64
(D 4
−(D − 2t )
4
)
where M = induced bending moment [N m]
ws = uniform distributed load rate [N/m]
L = span length [m]
D = pipe outside diameter [m]
4
I = area moment of inertia [m ]
t = pipe wall thickness [m]
σ = bending stress [Pa]
b
The shear stress induced by the submerged weight [ws] (uniformly distributed load) on the
pipeline span may be similarly determined by modelling the pipeline as a beam, with an
average support condition between a simply supported and fixed end.
Fs
σs =
A
ws L
where Fs = = shear force
2
A = Cross section area of the pipe
π
=
4
(D − (D−2t ) )
2 2
The equivalent stress is calculated using von Mises criterion (see section 2.13.2). Note
from 2.13.2 that the equivalent stress is maximised when σb is negative, i.e. compressive.
Also, the equivalent stress shall not exceed α, where α is the limit value shown for Zone 1
in Table 2 of Section 2.13.2.
Therefore, the maximum allowable span length, [Lmax] occurs when σb is maximised such
that = σeq = α x SMYS. Substituting σb into the combined stress formula gives:
⎛σ h ⎛σ
2
2⎞ 2⎞
σ h 2 +⎜ −α Lmax ⎟ −σ h ⎜ h −α Lmax ⎟+ β Lmax =(%SMYS )
2 2
⎝ 2 ⎠ ⎝ 2 ⎠
3σ h
2
Approved:2009 Page 45 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
α = ws D
where : 20I
2
β = 3 w s2
2A
To determine the maximum allowable span length, under the functional plus environmental
conditions, the submerged weight should be combined with wave and current induced drag
lift and inertia forces, see section 2.13.5.
Therefore :- {
q = (W − FL ) + (FD + FM )
2 2
}
where: F = drag force due to 100 year return wave and current induced velocity (see
D
section 2.13.5)
FL = Lift force due to 100 year return wave and current conditions
FM = inertia force due to 100 year return wave and current conditions
The coefficients for drag, lift and inertia should be obtained from DNV Rules. Note, the
coefficient will be different than for an on-bottom pipeline due to the gap between bottom-of-
pipe and the seabed.
In accordance with Table 2 of Section 2.13.2, the equivalent stress shall not exceed 90% of
SMYS. Similar to the approach adopted for functional loads, Lmax can be solved:
3σ h
2
α = ws D
where : 20I
2
β =3ws
and 2A2
The third load condition to be analysed is fatigue, due to vortex induced vibrations. These
vibrations only occur within certain ranges of cross-flow velocities. In order to determine
these ranges the natural frequency of the span or riser first needs to be established. The
first mode of vibration of a span with the "average" support condition is:
2.56 ⎛ E I ⎞
Fn = ⎜ ⎟
L2 ⎝ M ⎠
-1
Where: F =
n natural frequency [s ]
5
E =
Young's Modulus of elasticity = 2.05 x 10 [MPa]
Approved:2009 Page 46 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
M = virtual mass per unit length i.e., mass per unit length of pipeline
including the coatings and contents plus the mass per unit length
of displaced water [kg/m]
For a steady state flow, the frequency of the vortex shedding Fv can be evaluated using the
formula below:
Su
Fv =
D
-1
Where: Fv =
vortex shedding frequency in water [s ]
S = Strouhal number
u = steady current velocity, excluding wave induced current, [m/s]
The Strouhal Number depends on the drag coefficient Cd which in turn depends or the
Reynolds Number Re of the current flow. The span is considered safe if the span natural
frequency is 1.3 times the vortex induced frequency. Thus the span length should be less
than:
1/ 4
⎛ EI D2 ⎞
L=3.15⎜⎜ 2
⎟⎟
⎝ MU ⎠
Where: U = Wave or current ratio
2.14.1 General
2.14.2 Analysis
The on-bottom stability limit is reached when the water particle induced forces on the
pipeline are equal to the lateral (frictional) resistance of the pipe:
Fd + Fi = μ ( W − FL )
Approved:2009 Page 47 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The wave and current induced drag, inertia and lift forces are detailed in section 2.13.5.
These forces are time dependent, due to the periodicity of the waves. As the maxima for
the drag, inertia and lift forces are out-of-phase, the phase angles have to be taken into
account, when evaluating the above limit.
For gas lines, the on-bottom stability should be ensured under 100 year return wave and
current conditions. Oil pipelines should also meet this criterion, but in addition should be
stable during installation. The submerged weight of an oil line during installation is lower
than during operation, since the pipe is filled with air rather than oil during laying. In the
latter case, the 1 year return wave and current conditions are applied, as the installation
duration is short.
The soil friction factor varies with the pipeline surface material and seabed surface
condition. The following values are recommended:
The hydrodynamic coefficients and safety factors are based on the simplified method
included in DNV's recommended practice. This method is nowadays applied in its entirety.
In some shallow water depths the DN100 and DN150 gas lines may need 25 mm or more
concrete if lying individually, for stability. If they are part of a bundle, attached to a flowline
or liquid filled line, it is usually not required. Also in soil conditions where the line will sink
wholly or partly the drag force and lift force will be reduced considerably. Initially however
the line is assumed to be laid on top of a well defined seabed.
3 3
The standard density for concrete coatings is 2243 kg/m (140 lb/ft ) but a more dense mix
3 3
of 3044 kg/m (190 lb/ft ) is also used where coating thickness has to be minimised. Water
absorption of upto 3% of the concrete weight is allowed but may not be applied when
designing the weight coating.
In deciding between a combination of concrete thickness and density, to give the required
submerged weight, the following points should be considered:
Approved:2009 Page 48 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
• The minimum practical thickness of concrete coating is 25 mm and for marginal cases
of instability without concrete coating, additional pipe wall thickness may be the most
economical solution.
• When sacrificial anodes are needed, it is desirable to have a concrete coating to give a
continuous external diameter.
• For laybarge installation, it is desirable to provide mechanical protection of the bitumen
corrosion coat by the application of a concrete coating.
Concrete coating and the field joint infill mode should follow the relevant VIETSOVPETRO
JV specification.
The submerged weight calculation routines should be included in the on-bottom stability
calculation. In case the steel wall thickness includes a corrosion allowance, the submerged
weight of the pipeline reduces with time. At the design stage, it may be assumed that, at
the end of the service life, 50 % of the corrosion allowance will still contribute to the
submerged weight, since the corrosion itself is usually not perfectly uniform.
Approved:2009 Page 49 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
2.15.1 Components
The riser is the vertical or near vertical section of a submarine pipeline which connects the
pipeline on the seabed with the facilities on an offshore platform or jacket.
The riser design factor is lower than the pipeline design factor (see section 2.10.3),
resulting in a thicker pipe or a higher grade material. The latter option has the advantage of
maintaining a constant internal bore for the complete pipeline system. Risers and
expansion spools shall be designed according to the requirements for Zone 2 areas as
shown in Table 2 of 2.13.2.
Risers typically are attached on the outside of the jacket and held in place by riser clamps
(guides). The riser is normally allowed to slide in the longitudinal direction within each
clamp (guide). The vertical loads are therefore normally taken up by the deck support.
Scouring underneath the riser bend and over a length of approximately 15 m underneath
the pipeline should be taken into account, resulting in the vertical support carrying
approximately 95% of the riser load, including the ESD and 7.5 m of pipeline length at the
seabed.
The riser clamps have in the past typically contained 6 mm polychloroprene ('neoprene')
rubber sheeting inside the clamp shell to isolate the riser from the cathodic protection
system of the jacket. Severe external corrosion is experienced underneath riser clamps in
the splashzone, probably because the clamps are fit tight to the riser, or disbondment
occurs giving rise to crevice type corrosion.
A more suitable material for clamp shells is composite thermoplastic sheeting (Ultra-high
Molecular Weight Polyethylene or UHMW-PE). This lining material consists of a double
layer sheet: a thermoplastic outer layer which is in contact with the riser and a natural
rubber inner layer which is glued to the clamp shell to aid installation. The thermoplastic
surface has a low friction coefficient which allows free sliding of the riser in contact with it
and is hence unlikely to cause frictional tearing of the paint coating.
The sheet is extended from the clamp shell over the flat flange faces as well and pre-drilled
holes in the sheet allow the clamp bolts to be passed through and tightened up over the
sheet thus locating it firmly inside the clamps.
To prevent boat impact on risers, a boat fender is normally provided. Alternatively, one
could consider locating the riser on the inside of the platform. The latter approach is,
however, not very practical from an installation and repair point of view.
Where the pipeline cathodic protection system is different from the system used for platform
cathodic protection, isolation of the two systems is required, in order to prevent any adverse
effects on the pipeline from stray current interference.
Whereas in the past insulation flanges have been used for this purpose, experience has
shown that these deteriorate in time and become ineffective. Hence monobloc insulation
joints shall be used instead where there is a requirement to isolate the pipeline from the
platform CP system. Many of the new risers are fitted with an ESD valve located at the
working height above the spider deck (about 3 m above mean sea level), where a perimeter
walkway is usually available. As a consequence, the insulation joint will be very close to
the ESD valve flange.
Approved:2009 Page 50 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Typically a jacket has a 1:10 batter, usually resulting in the need for a 5° bend. A mitre not
exceeding 3° should only be used during the construction hook-up of the riser to
accommodate misalignment.
A knee brace is only necessary for the installation of risers. After installation, the knee
brace shall be removed by divers, to minimise operational stress levels.
All riser bends shall have a minimum radius of 5 pipe diameters (R=5D) to facilitate pigging
operations. However where space is limited on existing facilities a 3D bend radius may be
considered, subject to approval by VIETSOVPETRO JV.
Approved:2009 Page 51 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
All passive fire protection systems proposed by Vendors, Consultants or Contractors shall
be supported by certification and / or approval by an internationally recognised
Classification Society such as Lloyd's Register, Det norske Veritas or Bureau Veritas.
The riser bottom bend angle depends on the jacket batter and the pipeline jacket approach
angle, as follows:
β = acos{cos(χ)sin(α)}
χ β
0° 84.3°
30° 85.1°
45° 86.0°
60° 87.2°
90° 90.0°
The bends are procured to the bending specification, which calls for a bend angle tolerance
of ±1 degree.
3EIδ
M = 2
L
Approved:2009 Page 52 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
σ b = M2 ID
The equivalent stress of the combined bending and hoop stress is not allowed to exceed
67% of the yield stress, i.e. the stress limit for risers when taking into account both the
functional and the environmental loads (see section 2.13.2).
From the formula, one can conclude that the first subsea clamp should be located as high
as possible, since the bending moment reduces quadratically with the distance L.
Additional bracing a few metres above sea bed should thus not be used. However, to avoid
vortex induced vibrations, the unsupported riser length should not exceed the following limit
(see section 2.13.9):
1
⎡ E Ig D 2 ⎤ 4
L=3.15⎢ 2 ⎥
⎣⎢ M U ⎦⎥
The above approach is not entirely conservative, as not all the environmental loads have
been taken into account; the wave and current induced drag forces have been neglected.
However, these forces are usually negligible. Nevertheless, for the design of large risers it
is recommended to perform a full finite element analysis, for example with the computer
program RISR or equivalent.
2.16 Corrosion
A pipeline is designed for a limited functional lifetime, typically 30 years for offshore lines.
The major factors which govern the potential lifetime duration of a carbon steel pipeline are
composition of transported medium and the environmental conditions. Alternative materials
to carbon steel are briefly discussed in section 2.7.
When pipelines are taken out of service they are either mothballed (preserved with inhibited
water to arrest internal corrosion) or abandoned. As such they should not be generally
considered fit for purpose at a future date. Mothballed lines may be considered for re-use
subject to proof of mechanical integrity (by intelligent pigging or hydrotest to a sufficiently
Approved:2009 Page 53 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
high pressure so as to prove integrity with regard to existing defects). Abandoned pipelines
are considered to have been left in a state such that they are not in any way preserved from
ongoing corrosion or deterioration to their physical condition. Abandoned pipelines should
therefore not be re-used for transport of any product as they are considered as having been
scrapped at the point of abandonment.
All internal corrosion problems which occur in oil field pipeline operations are due to the
presence of water.
Of the three dissolved gases mentioned, oxygen is by far the worst of the group. If present,
it can cause severe corrosion at very low concentrations (less than 1 ppm). It is a strong
and rapid oxidising agent in cathodic reactions.
When carbon dioxide dissolves in water, it forms carbonic acid, decreases the pH of the
water, and increases its corrosivity.
It is not as corrosive as oxygen, but usually results in pitting. Corrosion primarily caused by
dissolved carbon dioxide is commonly called "sweet" corrosion.
Hydrogen sulphide is very soluble in water, and when dissolved, behaves as a weak acid
and usually causes pitting. Attack due to the presence of dissolved hydrogen sulphide is
referred to as "sour" corrosion and normally takes the form of stress corrosion cracking or
hydrogen induced cracking. Sulphate Reducing Bacteria (SRBs) may occur in, or have
been introduced to, the formation water.
Onshore pipelines below-ground are generally only protected by external coatings although
at present sacrificial (magnesium) anodes or impressed current systems are being installed
on all new lines. The resistivity of the soil controls the corrosion of below-ground pipelines.
In general the higher the resistance of the soil the less likely is corrosion and the less effect
any cathodic protection measures may be. Typically, lower resistance soils are found in the
areas of rivers, ditches, and close to the shore.
Pipelines above-ground and on racks can only be protected by external coatings. These
coatings have to be resistant to sunlight and usually consist of polyurethane paints.
Surface laid pipelines are heavily prone to corrosive attack. The upper areas of coating are
degraded in the sun and the lower areas are kept continually moist. Many surface laid
pipelines are being removed.
Approved:2009 Page 54 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Where the internal corrosion of carbon steel pipelines is expected to be high or bacterial
action is expected, chemical injection may be applied.
The effectiveness of inhibitors generally depends upon the flow regime existing in pipeline
and the level of wall-wetting.
In general if annular dispersed, slug, or bubbly type flow exists in a pipeline then continuous
inhibitor may be applied. If stratified flow conditions exist then batch inhibitor may be
considered. The computer program PIPESIM may be used for flow regime prediction.
The corrosion coating system to be used on marine pipelines to provide protection against
external corrosion will depend upon the pipeline installation method, the method selected
for obtaining adequate specific gravity, time required for applying of coating, and cost. In
general, Polyethylene (PE) is used for small diameter pipelines not requiring any concrete
weight coatings. For the large diameter pipelines, asphalt enamel and wrap is applied, in
combination with a concrete coating. For the riser protection see section 2.15.3.
For onshore, below-ground pipelines are normally PE coated. For the field joints, the
application of heat shrink sleeves are preferred, but tapes might be acceptable. All above-
ground pipelines are painted in accordance with the painting specification. Air/ground
interfaces are taped following the tape specification.
Service temperature limits for external corrosion coatings are tabulated below:
The pipelines have been normally protected by an impressed current system. A sacrificial
anode system was only applied if:
Approved:2009 Page 55 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
• it was not possible to install an impressed current system, because of lack of power
supply,
• an impressed current system induces stray current effects,
• the pipeline was in excess of 35 km in length.
The use of sacrificial anodes on all subsea pipelines are based upon the following reasons:
1. Elimination of monitoring and maintenance requirement (impressed current system)
2. Self-regulating nature of sacrificial anode system
3. No operator intervention for correct functioning
4. No risk from incorrect connection
Most of pipelines are electrically isolated from the upstream and downstream facilities by
insulating flanges. For the design of new offshore subsea pipelines the use of insulation
flanges is no longer sanctioned, for reasons already stated in Section 2.15.1.
Monobloc insulation joints shall therefore be used instead, which provide more reliable long
term electrical isolation between the subsea pipeline and the platform structure.
When internal or external corrosion has been found, a pipeline may still be operated
although in some cases this may require reduction of the maximum allowable operating
pressure, MAOP, or derating.
In determining the derating required, step one is to check the corrosion allowance designed
into the pipeline. The minimum steel wall thickness tm is equal to the nominal thickness
minus the corrosion allowance. If the remaining wall thickness exceeds the minimum
thickness, no derating is required. If the remaining thickness is less than the minimum, then
a derating equation is applied. The most common de-rating equation is contained in
Appendix L of the B31.8 code. Billiton Research Arnhem (BRA) has slightly modified the
formulae.
The BRA method is now used in preference to the B31.8 method. The MOP of the derated
pipeline shall be checked and confirmed to be below the derated MAOP.
A riser installation stress analysis shall be performed to ensure that the riser and adjacent
sections of pipeline are not overstressed at any stage. Stress limits are defined in Section
2.13.2.
If a large thermal offset is not required, the 'stalk on' method of installation shall be
considered as the base case. The analysis shall simulate all lifting and hold-hack lines,
supplemental buoyancy, and any other applied loads. Unless alternative data is available,
the following barge characteristics shall be assumed for davit lift of the pipeline end
Approved:2009 Page 56 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
If necessary, alternative installation methods such as J-tube pull, bending shoe, subsea
flanged tie-in, hyperbaric welding, etc. may be considered. Lift analyses of expansion
spools and risers shall be performed where relevant.
A dynamic load factor of 2.0 shall be applied to all static lift forces in accordance with API
RP 2A.
Gauging pigs are used to ascertain the dimensional condition of the pipe internal diameter.
Such a pig is fitted with a thin aluminium plate with a diameter smaller than the pipe internal
diameter. If the gauging plate passes the line without any damage, the internal dimensional
condition is acceptable. It is important that the plate diameter selection is based on the
narrowest bore section (i.e. usually the thickest pipe wall) and will pass all the bends,
flanges and fittings.
D p =0.97{Do − 2(1.15t )} − 5
If the gauging plate is damaged, it is difficult to trace the location of the dent or debris along
the pipeline. Under those circumstances, it is recommended to run a geometry inspection
pig. This pig measures the internal diameter over the entire length of the line, but is more
expensive.
Cleaning pigs are used to maintain the pipeline throughput efficiency and to minimise
internal corrosion. Batching pigs are used to separate one fluid from the other, for example
to de-water a pipeline using gas.
Approved:2009 Page 57 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
In a natural gas transmission line, compressor oil overflow can combine with dust, distillate,
and minute droplets of water in the gas stream and coat the inside of the pipe. Wax and
sand deposition in crude lines and liquid hold-up in 2-phase flowlines both increase
resistance to flow which in turn decreases pipeline efficiency and increases cost of
transmission.
Internal corrosion is intensified and corrosion control is made more difficult by the
accumulation of silt, sand, mud, completion fluids, stagnant water and bacterial deposits.
The majority of the chemicals used for corrosion inhibition are metal-surface active and are
adversely affected by the presence of these accumulations. For example in the case of
bacterial corrosion, deposits give shelter to bacteria permitting their population expansion.
Periodic cleaning of a pipeline will help considerably to control many of these corrosion
factors. Routine operational pigging for cleaning purposes should form part of the overall
plan for the maintenance of pipelines, and should be defined in the context of the Pipeline
Integrity Management System (PIMS).
It should be remembered that the cleaning operation can be carried out without seriously
affecting the operation of the pipeline or its throughput.
The frequency of cleaning pipelines can best be decided after an initial programme has
been carried out. During this period, careful records should be kept as to the amount and
nature of contaminating material removed. Frequency once established, can be changed
when operating conditions change (e.g. the introduction water injection). The high capital
cost of installing pipelines, together with their strategic value once they are operating, make
it imperative that corrosion is controlled as much as possible. Pipeline pigging, as outlined
above, has a significant role to play in extending pipeline life in exchange for a small
increase in operating costs.
PIMS recommends that pigging requirement and frequency are determined by the criticality
rating of each line which is based upon the risk and consequence of a line failure.
A wide range of cleaning and batching pigs are available such as a cup type, foam type and
sphere type.
Inflatable polyurethane spheres are commonly used. They can be sized to any pipe bore
within the same nominal pipe size. They are very useful in cases where an undersized
sphere is required. Correct inflation of these spheres is critical to the sphere's performance
and the inflating medium should be water. Before inflating the sphere, the sphere pump
and connections should have all air bled out and the sphere should not contain any air after
inflation. For cleaning operations spheres should be sized exactly on the pipe internal
diameter. For batching operations the sphere should be inflated some 3% greater than the
internal diameter of the pipe in which it will run and this should be checked with callipers.
Spheres may get stuck or hang at large branch tees, i.e., where branch diameter is similar
to run diameter. In these instances “sphere” tees are preferred.
In general, mandrel pigs such as cup pigs or bi-directional pigs are more efficient than
sphere pigs and where practicable these should be used in preference to the above.
It is essential to check the by-pass ports on pigs prior to insertion. For wax removal service
it may be desirable to secure a degree of by-pass flow to prevent wax scrapings combining
to seize the pig's transit.
On new pipelines it is recommended that a brush pig is run, with the aim of 'polishing' the
internal bore in order to obtain optimal pipeline efficiency and reduce scale accumulations.
Approved:2009 Page 58 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Note, based on previous experience, the use of spring mounted brushes is not effective in
removing scale (do not provide enough pressure). Fixed brush pigs have been proven more
effective.
Pinger pigs are used to locate a pipeline obstruction. By tracking the signal emitted from a
pinger mounted on the pig, the pig can be located when it becomes blocked at the
obstruction. The acoustic pingers usually used have a signal life of either 10 or 30 days.
They only emit an acoustic signal when they are wet and can therefore only be used for
liquid (hydrotest water) filled pipeline. The pinger can be installed inside a perforated
protection cage, usually mounted at the rear end of the pig in line with the pig body. For
bigger pipelines the pinger cage will be incorporated in the pig body.
• Check with manufacturer on tolerance of pig for internal diameter, dents, and bends for
the pipe size in question.
• Specify all fitting (flanges, tees) to have the nominal pipe inside diameter.
• Specify all tees to have guide bars following the standard drawing.
• Specify all valves to be full bore, in accordance with API 6D and with the nominal pipe
ID. If gate valves are selected the through conduit type should be specified. Wedge
type gate valves have cavities in which by-pass across the pig can occur causing the
pig to stop. This is particularly true when spheres are used.
Approved:2009 Page 59 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
• Fittings should never be located close together. A space of at least 3 pipe diameters of
straight pipe should be left between fittings.
Four pig launcher/receiver standard mechanical drawings are available, these are:-
i) Scraper Launcher/Receiver facilities (with double block and bleed)
ii) Scraper Launcher/Receiver Facilities (without double block and bleed)
iii) Intelligent Pig Launcher/Receiver Facilities (without double block and bleed)
iv) Intelligent Pig Launcher/Receiver Facilities (with double block and bleed)
In general, double block and bleed isolation is only required in high pressure, toxic or
critical service. For specific requirements refer to the EP safety manual. For operating
launchers/receivers refer to the relevant Operating Bulletins.
In line with operational experience, vertical launchers should not be used for the following
reasons:
• where intelligent pigs are used, these may 'flop' under considerable weight and damage
cups
• vertical door opening mechanisms have proved problematic
• traps cannot be fully drained and residue on valve balls can promote corrosion
• debris may become lodged in seats causing valve failure
• pig handling is generally not geared for vertical handling operations
Approved:2009 Page 60 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
On many onshore flowlines, ITAG launcher and receiver valve systems have been installed,
for cleaning and/or well fluid separation purposes only. The system basically consists of
one ball valve with an inlet, outlet and a pig insert/retrieve opening. The unit is relatively
easy to operate and is far less expensive than a conventional launcher/receiver unit. They
are not provided with isolation valves and bypasses to allow maintenance work without
shutting down the system.
2.19.1 General
Standard requisition sheets shall be developed as of VIETSOVPETRO format, for onshore
and offshore pipeline long lead materials. These sheets are included in Request for
Engineering Documents (RED) sheets do not need to be prepared, since these
requirements are already covered by the referenced standards and/or buyer descriptions.
Approved:2009 Page 61 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
2.19.3 Flanges
Flanges shall be forged in accordance with ASTM A694.
To avoid differences in internal diameter of the pipeline versus the flange bore, the flange
material grade has to be equivalent to the linepipe material grade. In addition, the nominal
internal bore (or pipe wall thickness) should also be indicated on the requisition sheet.
The butt-weld fittings for pipelines shall be manufactured in accordance with MSS-SP-75.
To avoid differences in internal diameter of the pipeline versus fitting bore, the fitting
material grade shall be equivalent to the linepipe material grade. The required wall
thickness shall be specified on the requisition sheet.
Barred tees shall be constructed from a material grade equivalent to the linepipe material
grade. Furthermore, bars need to be welded into the tee.
For all new pipelines a unique 4-digit Pipeline Identification (PID) number shall be obtained
from and allocated by the custodian of the Corporate Pipeline Database (CPD).
The pipeline engineer shall notify the custodian concerned of the new pipeline in writing,
who in turn shall inform the project and design consultants of the same. The PID shall be
shown on all drawings, charts and schematics, and in all design documentation as
appropriate.
2.20.2 Pipeline Data Sheets
Pipeline data sheets summarise the pipeline design, by listing the key parameters. They
are usually developed at the end of conceptual design.
A typical offshore pipeline data sheets is shown below:
General
a. Field location
b. Service
c. Facility From and To
d. Nominal Diameter (DN)
e. Length (including risers)
Approved:2009 Page 62 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Pipeline Data
a. Pipeline outside diameter (steel)
b. Pipeline steel wall thickness
c. Length (riser base to riser base)
d. Line pipe material and grade
e. Specified minimum yield strength (SMYS)
f. Anti-Corrosion Coating Type
g. Anti-Corrosion Coating Thickness
h. Density of corrosion coating
i. Weight Coating Thickness
j. Concrete density
k. Pipeline empty weight in air
l. Pipeline submerged weight (empty)
m. Pipeline submerged weight (product)
Riser data
a. Riser outside diameter (steel)
b. Riser Wall Thickness
c. Riser Material and Grade
d. Specified minimum yield strength (SMYS)
e. Riser Min Bend Radius
f. Riser bend angle-1 and 2
Approved:2009 Page 63 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
g. Flange rating
Installation data
a. Pipeline installation method
b. Riser setting method
c. Gauging plate size
d. Hydrostatic test pressure
e. Hydrostatic test duration
Hydrostatic pressure testing is the accepted method of demonstrating the structural integrity of
pipelines after the completion of construction. Prior to commencing the hydrostatic test the pipeline
should have been adequately cleaned of construction debris and have successfully passed a
gauging plate (preferably aluminium) of 95 percent minimum internal diameter undamaged through
the section to be tested.
Approved:2009 Page 64 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
In some instances valves are used to segment a completed pipeline for testing purposes. In such
cases it is necessary to ensure that the differential pressure across the valve is within its design
allowance and that special provisions are made to monitor possible leakage across the valve.
Scraper trap facilities included in any test section are to be tested to the same design code as the
pipeline. Depending on the quality of the water to be used for hydrostatic testing and/or the length
of time it is likely to remain in the pipeline after testing consideration should be given to protecting
the pipeline by the addition of inhibitors, biocides and oxygen scavengers. Water analysis should
be carried out to determine these requirements.
Legend:
PI = pressure gauge, range 1½ times test pressure
PR = pressure recorder, range 1½ times test pressure recording time 24 hrs. min.
DWT = dead weight tester, accuracy 0.01 bar, with current calibration certificate
Tl1 = pipeskin temperature probes, sensitivity 0.1ºC
Tl2 = intermediate pipeskin temperature probes (onshore pipelines only)
Tl3 = ambient temperature measurement, sensitivity 0.5 ºC
M = volumetric measurement device during pipeline pressurizing i.e. flowmeter or pump
stroke counter
Approved:2009 Page 65 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
The method for calculating the residual air volume is demonstrated in Figure 8.0.
Method:
The air content shall be determined by constructing a pressure/volume plot from atmospheric
pressure up to the linear section of the pressure volume plot curve and extrapolating back to the
axis. The volume of the air shall then be read directly from the horizontal axis and compared with
the total volume of the section.
The maximum residual air contained in the system when filled with water shall not exceed 0.5% of
the calculated volume of the system. If the air content is found to exceed this volume the section of
pipeline shall be refilled.
In special circumstances where the availability of water is very limited and it is not practical to refill
the pipeline it is possible to proceed with the leak test. However due allowance for the presence of
residual air should be included in the evaluation method and where necessary the leak test
duration extended accordingly.
Approved:2009 Page 66 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Where:
DV = incremental volume, m³
Dp = incremental pressure, bar
DT = incremental temperature, °C
V = pipeline fill volume, m³
D = pipeline outside diameter, m
E = Young’s elastic modulus of steel, bar
t = pipe wall thickness, m
n = Poisson ratio, -
B = bulk modulus of water, bar
G = volumetric expansion of water, °C-1
a = linear expansion of steels, °C-1
By comparison of the incremental volume changes due to pressure and temperature fluctuations
over the leak test hold period, the acceptability of the test can be established.
In the event of there being any doubt after evaluation of the hold period, the test should be
extended until such time as the acceptability is adequately demonstrated or alternatively the
presence of a leak is confirmed. In the latter event the leak has to be located and removed from
the pipeline prior to retesting.
For reference values of the bulk modulus and volumetric expansion of both fresh water and sea
water are given in Figures 9 to 12.
Approved:2009 Page 67 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Approved:2009 Page 68 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
Approved:2009 Page 69 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
(1) All liquid transportation piping systems within the scope of this Code, regardless of
stress, shall be tested after construction. Carbon dioxide systems shall be
hydrostatically tested.
(2) Systems to be operated at a hoop stress of more than 20% of the specified
minimum yield strength of the pipe shall be hydrostatically tested.
(3) Systems to be operated at a hoop stress of 20% or less of specified minimum yield
strength of the pipe may be subjected to a leak test in lieu of the hydrostatic test.
Approved:2009 Page 70 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
(4) When testing piping, in no case shall the test pressure exceed that stipulated in the
standards of material specifications (except pipe) incorporated.
(5) Equipment not to be subjected to test pressure shall be disconnected from the
piping or otherwise isolated. Valves may be used if valve, including closing
mechanism, is suitable for the test pressure.
(b) Testing Tie-h. Because it is sometimes necessary to divide a pipeline into test sections
and install test heads, connecting piping, and other necessary appurtenances for testing, or
to install a pre-tested replacement section, it is not required that tie-in welds be tested;
however, tie-in welds and girth welds joining lengths of pre-tested pipe shall be inspected
by radiographic or other accepted nondestructive methods if system is not pressure tested
after tie-in. After such inspection, the joint shall be coated and inspected before backfilling.
(c) Testing Controls and Protective Equipment. All controls and protective equipment,
including pressure limiting devices, regulators, controllers, relief valves, and other
safety devices, shall be tested to determine that they are in good mechanical condition; of
adequate capacity, effectiveness, and reliability of operation for the service in which
they are employed; functioning at the correct pressure; and properly installed and
protected from foreign materials or other conditions that might prevent proper operation.
(1) Those portions of piping systems where all of the pressured components are
visually inspected during the proof test determine that here is no leakage require no
further test. This can include lengths of pipe that are pre-tested for user’s
replacement sections.
(2) On those portions of piping systems not visually inspected while under test, the
proof test shall be followed by a reduced pressure leak test equivalent to not less
than 1.1 times the internal design pressure for not less than 4 hr.
(b) API RP 11 10 may be used for guidance for the hydrostatic test.
(c) The hydrostatic test shall be conducted with water, except liquid petroleum that does not
vaporize rapidly may be used provided:
(1) The pipeline section under test is not offshore and is outside of cities and other
populated areas, and each building within 300 ft (90 m) of the test section is
unoccupied while the test pressure is equal to or greater than a pressure which
produces a hoop stress of 50% of the specific minimum yield strength of the pipe;
(2) The test section is kept under surveillance by regular patrols during test; and
Approved:2009 Page 71 of 72
RULES FOR OPERATION, INSPECTION AND Doc. No.:
JV MAINTENANCE OF OFFSHORE PROCESS PIPING AND VSP-SR-16
VIETSOVPETRO UNDERWATER PIPELINES
Chapter 2: Pipeline Design Revision: 00
(d) If the testing medium in the system will be subject to thermal expansion during the test,
provisions shall be made for relief of excess pressure. Effects of temperature changes shall
be taken into account when interpretations are made of recorded test pressures.
(e) After completion of the hydrostatic test, it is important in cold weather that the lines, valves,
and fittings be drained completely of any water to avoid damage due to freezing.
(f) Carbon dioxide pipelines, valves, and fittings shall be dewatered and dried prior to placing
in service to prevent the possibility of forming a corrosive compound from carbon dioxide
and water.
Approved:2009 Page 72 of 72