HITUNGAN KOEFISIEN

PEKERJAAN PERSIAPAN
Item Pekerjaan Volume Koefisien Durasi Waktu Hasil
Pembersihan Lapangan 336.00
Pekerja 0.100 33.60 4 8 32 1.05000000
Mandor 0.050 16.80 4 8 32 0.52500000
Pemasangan Bouplank 74.00
Pekerja 0.100 7.40 3 8 24 0.30833333
Tukang Kayu 0.100 7.40 3 8 24 0.30833333
Kepala Tukang 0.010 0.74 3 8 24 0.03083333
Mandor 0.005 0.37 3 8 24 0.01541667
Kayu 5/7 0.001 0.07 0.07400000
Paku Biasa 2"-5" 0.020 1.48 1.48000000
Kayu papan 3/20 0.004 0.30 0.29600000
Direksi Keet 4.00
Kayu 5/7 0.001 0.0040 0.00400000
Paku Biasa 2"-5" 0.020 0.0800 0.08000000
Kayu papan 3/20 0.004 0.0160 0.01600000
Tukang Kayu 0.100 0.4000 6 8 48 0.00833333
Pekerja 0.100 0.4000 6 8 48 0.00833333
Kepala Tukang 0.010 0.0400 6 8 48 0.00083333
Mandor 0.005 0.0200 6 8 48 0.00041667
Los Kerja 12.00
Kayu 5/7 0.001 0.0120 0.01200000
Paku Biasa 2"-5" 0.020 0.2400 0.24000000
Kayu papan 3/20 0.004 0.0480 0.04800000
Tukang Kayu 0.100 1.2000 4 8 32 0.03750000
Pekerja 0.100 1.2000 4 8 32 0.03750000
Kepala Tukang 0.010 0.1200 4 8 32 0.00375000
Mandor 0.005 0.0600 4 8 32 0.00187500
PEKERJAAN TANAH DAN PASIR
Pek. Galian Tanah Pondasi 101.43
Pekerja 0.750 76.0725 3 8 24 3.16968750
Mandor 0.025 2.5358 3 8 24 0.10565625
Pek. Urugan tanah kembali 25.36
Pekerja 0.192 4.8691 1 8 8 0.60864000
Mandor 0.019 0.4818 1 8 8 0.06023000
Pek. Timbunan Tanah Bawah Lantai 26.80
Pekerja 0.192 5.1456 1 8 8 0.64320000
Mandor 0.010 0.2680 1 8 8 0.03350000
Tanah Urugan 1.200 32.1600 32.16000000
Pek. Urugan Pasir Bawah Lantai 20.10
Pekerja 0.300 6.0300 1 8 8 0.75375000
Mandor 0.010 0.2010 1 8 8 0.02512500
Pasir Urug 1.100 22.1100 22.11000000
Pek. Urugan Pasir Bawah Pondasi 5.07
Pekerja 0.300 1.5210 1 8 8 0.19012500
Mandor 0.010 0.0507 1 8 8 0.00633750
Pasir Urug 1.100 5.5770 5.57700000
PEKERJAAN BETON
Pas. Pondasi Batu Gunung 43.70
Pekerja 3.000 131.1000 4 8 32 4.09687500
Tukang Batu 1.000 43.7000 4 8 32 1.36562500
Kepala Tukang 0.050 2.1850 4 8 32 0.06828125
Mandor 0.030 1.3110 4 8 32 0.04096875
Batu Gunung 1.100 48.0700 48.07000000
Semen Portland 104.000 4,544.8000 4,544.80000000
Pasir Pasangan 0.520 22.7240 22.72400000
Pas. Pondasi Batu Kosong 12.81
Pekerja 0.780 9.9918 4 8 32 0.31224375
Tukang Batu 0.390 4.9959 4 8 32 0.15612188
Kepala Tukang 0.039 0.4996 4 8 32 0.01561219
Mandor 0.039 0.4996 4 8 32 0.01561219
Batu Gunung 15/20 cm 1.200 15.3720 15.37200000
Pasir Urug 0.300 3.8430 3.84300000
SLOEF 3.16
Beton Bertulang 1.000 3.1600 3.16000000
Pembesian Beton 145.000 458.2000 458.20000000
Bekisting 8.000 25.2800 25.28000000
Kuda-Kuda Beton 0.79
Beton Bertulang 1.000 0.7900 0.79000000
Pembesian Beton 145.000 114.5500 114.55000000
Bekisting 8.000 6.3200 6.32000000
Kolom 2.84
Beton Bertulang 1.000 2.8400 2.84000000
Pembesian Beton 145.000 411.8000 411.80000000
Bekisting 8.000 22.7200 22.72000000
Ring Balk 3.16
Beton Bertulang 1.000 3.1600 3.16000000
Pembesian Beton 145.000 458.2000 458.20000000
Bekisting 8.000 25.2800 25.28000000
Rabat Beton Bawah Lantai 8.04
Pekerja 1.650 13.2660 1 8 8 1.65825000
Tukang Batu 0.250 2.0100 1 8 8 0.25125000
Kepala Tukang 0.025 0.2010 1 8 8 0.02512500
Mandor 0.080 0.6432 1 8 8 0.08040000
Semen Portland 197.000 1,583.8800 1,583.88000000
Pasir Beton 0.470 3.7788 3.77880000
Koral Beton 0.940 7.5576 7.55760000
Air 180.000 1,447.2000 1,447.20000000
Rabat Beton Carport 0.72
Pekerja 1.650 1.1880 1 8 8 0.14850000
Tukang Batu 0.250 0.1800 1 8 8 0.02250000
Kepala Tukang 0.025 0.0180 1 8 8 0.00225000
Mandor 0.080 0.0576 1 8 8 0.00720000
Semen Portland 197.000 141.8400 141.84000000
Pasir Beton 0.470 0.3384 0.33840000
Koral Beton 0.940 0.6768 0.67680000
Air 180.000 129.6000 129.60000000
PEKERJAAN DINDING DAN LANTAI
Pek. Dinding 1:5 22.22
Pekerja 0.320 7.1104 6 8 48 0.14813333
Tukang Batu 0.100 2.2220 6 8 48 0.04629167
Kepala Tukang 0.010 0.2222 6 8 48 0.00462917
Mandor 0.015 0.3333 6 8 48 0.00694375
Bata Merah 5x11x22 70.000 1,555.4000 1,555.40000000
Semen Portland 9.680 215.0896 215.08960000
Pasir Pasangan 0.045 0.9999 0.99990000
Pek. Plesteran 1:3 39.83
Pekerja 0.250 9.9575 3 8 24 0.41489583
Tukang Batu 0.200 7.9660 3 8 24 0.33191667
Kepala Tukang 0.020 0.7966 3 8 24 0.03319167
Mandor 0.013 0.4979 3 8 24 0.02074479
Semen Portland 10.800 430.1640 430.16400000
Pasir Pasangan 0.026 1.0356 1.03558000
Pek. Plesteran 1:5 380.63
Pekerja 0.250 95.1575 7 8 56 1.69924107
Tukang Batu 0.200 76.1260 7 8 56 1.35939286
Kepala Tukang 0.020 7.6126 7 8 56 0.13593929
Mandor 0.013 4.7579 7 8 56 0.08496205
Semen Portland 7.290 2,774.7927 2,774.79270000
Pasir Pasangan 0.028 10.6576 10.65764000
Pek. Acian 420.46
Pekerja 1.000 420.4600 4 8 32 13.13937500
Tukang Batu 1.000 420.4600 4 8 32 13.13937500
Kepala Tukang 0.100 42.0460 4 8 32 1.31393750
Mandor 0.050 21.0230 4 8 32 0.65696875
Semen Portland 5.000 2,102.3000 2,102.30000000
Kapur Pasangan 0.030 12.6138 12.61380000
Pas. Dinding Keramik wc 20x20 22.45
Pekerja 0.600 13.4700 2 8 16 0.84187500
Tukang Batu 0.450 10.1025 2 8 16 0.63140625
Kepala Tukang 0.045 1.0103 2 8 16 0.06314063
Mandor 0.030 0.6735 2 8 16 0.04209375
Keramik 20x20 1.000 22.4500 22.45000000
Semen Portland 9.300 208.7850 208.78500000
Pasir Pasangan 0.018 0.4041 0.40410000
Semen Warna 1.500 33.6750 33.67500000
Pas. Keramik 40x40 48.38
Pekerja 0.620 29.9956 3 8 24 1.24981667
Tukang Batu 0.350 16.9330 3 8 24 0.70554167
Kepala Tukang 0.035 1.6933 3 8 24 0.07055417
Mandor 0.030 1.4514 3 8 24 0.06047500
Keramik 40x40 1.000 48.3800 48.38000000
Semen Portland 11.380 550.5644 550.56440000
Pasir Pasangan 0.042 2.0320 2.03196000
Semen Warna 1.500 72.5700 72.57000000
Pas. Keramik 20x20 2.03
Pekerja 0.620 1.2586 1 8 8 0.15732500
Tukang Batu 0.350 0.7105 1 8 8 0.08881250
Kepala Tukang 0.035 0.0711 1 8 8 0.00888125
Mandor 0.030 0.0609 1 8 8 0.00761250
Keramik 20x20 1.000 2.0300 2.03000000
Semen Portland 11.380 23.1014 23.10140000
Pasir Pasangan 0.042 0.0853 0.08526000
Semen Warna 1.500 3.0450 3.04500000
Pas. Trasram 9.32
Pekerja 0.650 6.0580 4 8 32 0.18931250
Tukang Batu 0.200 1.8640 4 8 32 0.05825000
Kepala Tukang 0.020 0.1864 4 8 32 0.00582500
Mandor 0.030 0.2796 4 8 32 0.00873750
Bata Merah 5x11x22 140.000 1,304.8000 1,304.80000000
Semen Portland 43.500 405.4200 405.42000000
Pasir Pasangan 0.080 0.7456 0.74560000
PEKERJAAN PINTU DAN JENDELA
Pek. Kusen Pintu dan Jendela Kelas I 0.49
Pekerja 6.000 2.9400 3 8 24 0.12250000
Tukang Kayu 20.000 9.8000 3 8 24 0.40833333
Kepala Tukang 2.000 0.9800 3 8 24 0.04083333
Mandor 0.300 0.1470 3 8 24 0.00612500
Balok Kayu Klas I 1.100 0.5390 0.53900000
Pek. Daun Pintu kelas I 10.76
Pekerja 1.544 16.6134 1 8 8 2.07668000
Tukang Kayu 4.633 49.8511 1 8 8 6.23138500
Kepala Tukang 0.463 4.9819 1 8 8 0.62273500
Mandor 0.463 4.9819 1 8 8 0.62273500
Papan Kayu Klas I (kayu bangkirei) 0.040 0.4304 0.43040000
Pas. Kaca Mati 4.71
Pekerja 0.150 0.7065 1 8 8 0.08831250
Tukang Kayu 0.500 2.3550 1 8 8 0.29437500
Kepala Tukang 0.050 0.2355 1 8 8 0.02943750
Mandor 0.010 0.0471 1 8 8 0.00588750
Kaca Bening 5 mm 1.000 4.7100 4.71000000
Kayu Les Klas II 0.005 0.0236 0.02355000
Pas. Jendela Jungkit 2.88
Pekerja 0.800 2.3040 1 8 8 0.28800000
Tukang Kayu 2.000 5.7600 1 8 8 0.72000000
Kepala Tukang 0.200 0.5760 1 8 8 0.07200000
Mandor 0.040 0.1152 1 8 8 0.01440000
Papan Kayu Klas I (kayu bangkirei) 0.035 0.1008 0.10080000
Kaca Bening 5 mm 1.100 3.1680 3.16800000
Pas. Kunci Tanam 10.00
Pekerja 0.010 0.1000 2 8 16 0.00625000
Tukang Kayu 0.500 5.0000 2 8 16 0.31250000
Kepala Tukang 0.010 0.1000 2 8 16 0.00625000
Mandor 0.005 0.0500 2 8 16 0.00312500
Kunci Tanam 2 x Putar 1.000 10.0000 10.00000000
Pas. Engsel Pintu 33.00
Pekerja 0.015 0.4950 2 8 16 0.03093750
Tukang Kayu 0.150 4.9500 2 8 16 0.30937500
Kepala Tukang 0.015 0.4950 2 8 16 0.03093750
Mandor 0.001 0.0248 2 8 16 0.00154688
Engsel Pintu Kuningan 1.000 33.0000 33.00000000
Pas. Grendel Pintu 10.00
Pekerja 0.010 0.1000 2 8 16 0.00625000
Tukang Kayu 0.100 1.0000 2 8 16 0.06250000
Kepala Tukang 0.010 0.1000 2 8 16 0.00625000
Mandor 0.005 0.0500 2 8 16 0.00312500
Grendel Pintu 1.000 10.0000 10.00000000
Pas. Engsel Jendela 32.00
Pekerja 0.020 0.6400 2 8 16 0.04000000
Tukang Kayu 0.200 6.4000 2 8 16 0.40000000
Kepala Tukang 0.020 0.6400 2 8 16 0.04000000
Mandor 0.010 0.3200 2 8 16 0.02000000
Engsel Jendela Kuningan 1.000 32.0000 32.00000000
Pas. Grendel Jendela 16.00
Pekerja 0.012 0.1920 2 8 16 0.01200000
Tukang Kayu 0.120 1.9200 2 8 16 0.12000000
Kepala Tukang 0.012 0.1920 2 8 16 0.01200000
Mandor 0.006 0.0960 2 8 16 0.00600000
Grendel Jendela 1.000 16.0000 16.00000000
Pas. Hak angin 2.00
Pekerja 0.012 0.0240 2 8 16 0.00150000
Tukang Kayu 0.120 0.2400 2 8 16 0.01500000
Kepala Tukang 0.012 0.0240 2 8 16 0.00150000
Mandor 0.006 0.0120 2 8 16 0.00075000
Kair Angin 1.000 2.0000 2.00000000
PEKERJAAN ATAP DAN PLAFOND
Pek. Kuda-Kuda 0.58
Pekerja 4.000 2.3200 2 8 16 0.14500000
Tukang Kayu 12.000 6.9600 2 8 16 0.43500000
Kepala Tukang 1.200 0.6960 2 8 16 0.04350000
Mandor 0.200 0.1160 2 8 16 0.00725000
Balok Kayu Klas II 1.100 0.6380 0.63800000
Besi Strip 15.000 8.7000 8.70000000
Paku Biasa 2" - 5" 0.800 0.4640 0.46400000
Pek. Balok Nok 0.10
Pekerja 4.000 0.4000 2 8 16 0.02500000
Tukang Kayu 12.000 1.2000 2 8 16 0.07500000
Kepala Tukang 1.200 0.1200 2 8 16 0.00750000
Mandor 0.200 0.0200 2 8 16 0.00125000
Balok Kayu Klas II 1.100 0.1100 0.11000000
Besi Strip 15.000 1.5000 1.50000000
Paku Biasa 2" - 5" 0.800 0.0800 0.08000000
Pek. Skor Angin 0.27
Pekerja 4.000 1.0800 1 8 8 0.13500000
Tukang Kayu 12.000 3.2400 1 8 8 0.40500000
Kepala Tukang 1.200 0.3240 1 8 8 0.04050000
Mandor 0.200 0.0540 1 8 8 0.00675000
Balok Kayu Klas II 1.100 0.2970 0.29700000
Besi Strip 15.000 4.0500 4.05000000
Paku Biasa 2" - 5" 0.800 0.2160 0.21600000
Pek. Kaso+ Reng 0.34
Pekerja 0.100 0.0340 2 8 16 0.00212500
Tukang Kayu 0.100 0.0340 2 8 16 0.00212500
Kepala Tukang 0.010 0.0034 2 8 16 0.00021250
Mandor 0.005 0.0017 2 8 16 0.00010625
Balok Kayu Klas II 0.012 0.0041 0.00408000
Paku Biasa 2" - 5" 0.150 0.0510 0.05100000
Pek. Atap Genteng 87.16
Pekerja 0.200 17.4320 3 8 24 0.72633333
Tukang Kayu 0.100 8.7160 3 8 24 0.36316667
Kepala Tukang 0.010 0.8716 3 8 24 0.03631667
Mandor 0.010 0.8716 3 8 24 0.03631667
Genteng metal 11.0000 958.7600 958.76000000
Paku Biasa 2" - 5" 0.030 2.6148 2.61480000
Pek. Nok Atap Genteng 10.63
Pekerja 0.150 1.5945 1 8 8 0.19931250
Tukang Kayu 0.075 0.7973 1 8 8 0.09965625
Kepala Tukang 0.008 0.0797 1 8 8 0.00996563
Mandor 0.008 0.0797 1 8 8 0.00996563
Nok Genteng Beton 3.000 31.8900 31.89000000
Semen Portland 5.000 53.1500 53.15000000
Pasir Pasangan 0.020 0.2126 0.21260000
Pek. Rangka Plafond 0.30
Pekerja 0.600 0.1800 2 8 16 0.01125000
Tukang Kayu 1.800 0.5400 2 8 16 0.03375000
Kepala Tukang 0.180 0.0540 2 8 16 0.00337500
Mandor 0.030 0.0090 2 8 16 0.00056250
Balok Kayu Klas II 0.012 0.0036 0.00360000
Paku Biasa 2" - 5" 2.000 0.6000 0.60000000
Pek. Plafond 53.14
Pekerja 0.300 15.9420 2 8 16 0.99637500
Tukang Kayu 0.500 26.5700 2 8 16 1.66062500
Kepala Tukang 0.050 2.6570 2 8 16 0.16606250
Mandor 0.020 1.0628 2 8 16 0.06642500
Etermit 1.000 53.1400 53.14000000
Tripleks 0.390 20.7246 20.72460000
Paku 0.020 1.0628 1.06280000
Pek. Les Pinggir Plafond 104.10
Pekerja 0.050 5.2050 2 8 16 0.32531250
Tukang Kayu 0.050 5.2050 2 8 16 0.32531250
Kepala Tukang 0.005 0.5205 2 8 16 0.03253125
Mandor 0.003 0.3123 2 8 16 0.01951875
Kayu Profil 1.100 114.5100 114.51000000
Pek. Listplank 4.18
Pekerja 0.110 0.4598 2 8 16 0.02873750
Tukang Kayu 0.220 0.9196 2 8 16 0.05747500
Kepala Tukang 0.022 0.0920 2 8 16 0.00574750
Mandor 0.005 0.0209 2 8 16 0.00130625
Balok Kayu Klas II 0.011 0.0460 0.04598000
Paku Biasa 2" - 5" 0.050 0.2090 0.20900000
PEKERJAAN PENGECATAN
Pek. Pengecatan Tembok 210.23
Pekerja 0.200 42.0460 4 8 32 1.31393750
Tukang Kayu 0.100 21.0230 4 8 32 0.65696875
Kepala Tukang 0.009 1.8921 4 8 32 0.05912719
Mandor 0.030 6.3069 4 8 32 0.19709063
Plamir 1 x 0.100 21.0230 21.02300000
Cat Dasar 1 x 0.100 21.0230 21.02300000
Cat Penutup 2 x 0.200 42.0460 42.04600000
Pek. Cat Kusen, Pintu, dan Jendela 20.30
Pekerja 0.070 1.4210 2 8 16 0.08881250
Tukang Kayu 0.105 2.1315 2 8 16 0.13321875
Kepala Tukang 0.004 0.0812 2 8 16 0.00507500
Mandor 0.003 0.0508 2 8 16 0.00317188
Cat Meni 0.200 4.0600 4.06000000
Plamir 1 x 0.150 3.0450 3.04500000
Cat Dasar 1 x 0.170 3.4510 3.45100000
Cat Penutup 2 x 0.350 7.1050 7.10500000
Pek. Pengecatan Plafond 53.14
Pekerja 0.200 10.6280 1 8 8 1.32850000
Tukang Kayu 0.100 5.3140 1 8 8 0.66425000
Kepala Tukang 0.009 0.4783 1 8 8 0.05978250
Mandor 0.030 1.5942 1 8 8 0.19927500
Plamir 1 x 0.100 5.3140 5.31400000
Cat Dasar 1 x 0.100 5.3140 5.31400000
Cat Penutup 2 x 0.200 10.6280 10.62800000
Pek. Pengecatan Listplank 4.18
Pekerja 0.070 0.2926 1 8 8 0.03657500
Tukang Kayu 0.105 0.4389 1 8 8 0.05486250
Kepala Tukang 0.004 0.0167 1 8 8 0.00209000
Mandor 0.003 0.0105 1 8 8 0.00130625
Cat Meni 0.200 0.8360 0.83600000
Plamir 1 x 0.150 0.6270 0.62700000
Cat Dasar 1 x 0.170 0.7106 0.71060000
Cat Penutup 2 x 0.350 1.4630 1.46300000
PEKERJAAN INSTALASI LISTRIK
Pas. Instalasi Listrik Dalam 63.00
Kabel NYA 1 x 2,5 mm 15.000 945.0000 3 8 24 39.37500000
Pas. Saklar Ganda 2.00
Saklar ganda 1.000 2.0000 1 8 8 0.25000000
Pas. Saklar Tunggal 6.00
Saklar tunggal 1.000 6.0000 1 8 8 0.75000000
Pas. Stop Kontak 7.00
Stop Kontak 1.000 7.0000 1 8 8 0.87500000
Pas. Lampu Kapsul Susu 5.00
Lampu Kapsul 40 Watt Philips 1.000 5.0000 1 8 8 0.62500000
Pas. Lampu TL 1 x 40 Watt 2.00
Lampu TL 1 x 40 Watt ( TKI ) 1.000 2.0000 1 8 8 0.25000000
Pas. Lampu TL 2 x 40 Watt 3.00
Lampu TL 2 x 40 Watt ( RM ) 1.000 3.0000 1 8 8 0.37500000
PEKERJAAN SANITASI
Pek. Stop Kran 4.00
Kran 1.000 4.0000 1 8 8 0.50000000
Pek. Pipa 3/4" 4.00
galvanis diameter 0,75 " 1.000 4.0000 1 8 8 0.50000000
Pek. Pipa PVC 4" 7.00
PVC 4 m diameter 4" 1.000 7.0000 1 8 8 0.87500000
Pas. Kloset Duduk 2.00
Pekerja 3.300 6.6000 1 8 8 0.82500000
Tukang Kayu 1.100 2.2000 1 8 8 0.27500000
Kepala Tukang 0.001 0.0020 1 8 8 0.00025000
Mandor 0.160 0.3200 1 8 8 0.04000000
Kloset Duduk Lengkap 1.000 2.0000 2.00000000
Pek. Bak Cuci Piring 1.00
Bak Cuci Piring 1.000 1.0000 1 8 8 0.12500000
Bak Air Fiber 2.00
Bak mandi lps porselin/ keramik 1.000 2.0000 1 8 8 0.25000000
Floor Drain 3.00
Floordrain 1.000 3.0000 1 8 8 0.37500000
Pek. Septictank 1.00
Septictank & peresapan 1.000 1.0000 2 8 16 0.06250000

You might also like