2014-002 Offplot
2014-002 Offplot
From: TS – Inspection
Re: Visual Inspection of the off plot piping supports and FO Day Tank T-8111
Findings :
a. The filling and circulation line of T-703B from the header to the tank aren’t resting on the pipe support #1
and sleeper #1 on the bund wall (see pic. #1 and piping plan layout for location )
b. The circulation line of T-703AB ; the pipe shoe isn’t resting on the sleeper #2.
Location : north of H-8301 (see pic. #2 and piping plan layout for location )
c. The pipes running on the sleepers #3 & #4, east of T-703 AB ( see pic. #3 ).
d. P-703 Discharge Piping isn’t resting on the adjustable support (see pic. #5) .
e. FW line running on the sleeper between the MCC and 700 pump area isn’t sitting on all the sleepers (see pic.
#6)
f. MS steam header on north-south pipe rack , east of unit 100 ; the pipe shoe has somehow been twisted and
now the pipe isn’t being supported before the expansion loop .(see pic. #7)
g. T-8111 - Insulation is totally soaked with FO due to overfilling of the tank (see pic. #8).
h. T-8111 – P&V looks plugged and not working properly (see pic. #9).
Initiated by : Approved by :
SLEEPER #1
ON TOP BUNDWALL , EAST OF T-703AB
PIC. #1
SLEEPER #2
EAST OF T-703AB ; NORTH OF H-8301
PIC. #2
SLEEPER #3
SLEEPERS , EAST OF T-703AB
PIC. #3
SLEEPER #3
SLEEPERS , EAST OF T-703AB
SLEEPER #4
SLEEPER , EAST OF T-703AB
PIC. #4
GAP ; ADJUST SUPPORT
DISCHARGE LINE OF P-703
PIC. #5
SLEEPER #5 & #6
BETWEEN MCC 700 & PUMP AREA 700
PIC. #6
PIPE SHOE OF MS STEAM HEADER
ON N-S PIPERACK ; EAST OF UNIT 100
PIC. #7
PIC. #9