The
precaution is providing by a back-up generator. The back-up generator used must be able to
provide electricity needed for the whole plant. We assume that our plant having a black out for 1
days maximum. Our plant need around 146.088 kW and the generator need to fill 100% of our
needs which is 260.94 kW.
Fuel consumption for process Generator used is manufactured by Suter Power Diesel Generator
with 144 to 160 kW capacity, specifications: