Professional Documents
Culture Documents
CAIRN TSG Q GUI 0005 B1 Guideline For Material Inspection Requirements
CAIRN TSG Q GUI 0005 B1 Guideline For Material Inspection Requirements
REVISION RECORD
Revision Philosophy
All revisions for review will be issued at A1, with subsequent A2, A3, etc as required.
All revisions approved for issue or implementation will be issued at B1, with subsequent B2, B3, etc as
required.
All revisions approved for issue or design and construction will be issued at C1, with subsequent C2, C3,
etc as required.
Narrative sections revised from previous approve issues are to be noted in the table below and/or
highlighted using the appropriate revision status thus: | A2
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas
and by the use of a triangle containing the revision status.
Revision History
CONTENTS
1.0 SCOPE 4
2.0 PURPOSE 5
1.0 SCOPE
The scope of this guideline covers the primary manufacture, inspection and testing of base
material components for use in CIL facilities and applies to the following materials of construction:
• Ferritic steels
The scope shall not be construed as covering all materials of construction that may be necessary
as a mitigation measure resulting from the corrosion risk assessment required by material
selection & corrosion control. Where the corrosion risk assessment identifies that alternative
materials of construction are necessary, the requirements for these shall be identified in
accordance with the principles in this guideline and submitted for CIL Engineering review and
agreement prior to their use.
a) For new ‘green field’ or ‘brown field incremental’ construction, the requirements shall be met in
full.
• That implementing the requirements is incompatible with the existing facility’s materials of
construction and would negatively impact the mechanical integrity as a result
• That the intended replacement materials have properties no worse than those already
installed
• That the existing materials show no sign of degradation as a result of non- compliance
with this guideline as demonstrated from appropriate in-service inspection.
The guideline embeds feedback and lessons learned from CIL facilities and external industry
experience and international standard development works.
The guideline supplements the requirements in the relevant and appropriate industry codes and
component material specifications pertaining to the scope of supply and shall be read in
conjunction with these. Where reference is made in the guideline to specific industry codes and
component material specifications, this shall be taken as meaning the latest published version,
including any amendments etc. current at the time of purchase order placement. Alternatives to
these referenced documents may be acceptable providing the alternative can be shown to
provide an equivalent or better level of quality, safety and design integrity.
2.0 PURPOSE
The purpose of this guideline is to define the minimum requirements for the manufacture,
inspection and testing of the most common metallic and non-metallic materials of construction
used in CIL facilities and to develop a consistent CIL approach to the specification of ‘base
material’ components to facilitate - wide procurement policies for the materials and components
referenced herein.
Vendor : Primary manufacturer of base material components. The definition shall also apply to
any third party contracted to provide manufacturing, inspection or testing services to the Vendor
Intermediary : An organisation which is supplied with components by the Vendor and which then
in turn supplies them without further processing or after processing without changing the
properties specified in the purchase order and referenced product specification e.g. machining
only
Base material component : Components such as plates, forgings, castings, seamless and
longitudinally welded pipes (including induction bends), tubes and fittings (including instrument
tubing and compression fittings), fibre reinforced composite tubular products and structural
components, thermoplastic tubular components, elastomeric and thermoplastic seals, metallic
and non-metallic gaskets.
Ferritic steel : Steels with a nominal alloy content of less than 11% (refer to ASTM A941 for
specific definitions):
• Alloy steels (AISI 4xxx & AISI 8xxx series, 1¼Cr-½Mo & 2¼Cr-1Mo)
Corrosion resistant alloy : Alloys with a nominal alloy content of 11% and above e.g.
• Nickel-based alloys
Sour environments : Sour Environments are defined as fluids containing water as a liquid and
hydrogen sulfide exceeding the limits defined. These environments may cause sulfide stress
cracking (SSC) of susceptible materials.
Non-sour environments : All other process and utility environments e.g. elevated temperature,
high pressure & cyclic fatigue environments or hazardous, extreme hazardous & cryogenic
environments. For the purposes of this guideline, the definition also applies to structural steel
components for fixed jacket structures, jetties, trestles, pipe racks, equipment and pipe support
etc.
Special forging or casting : Forging or casting manufactured for a specific application (i.e. not
standard’ piping or pressure vessel components). This will include:
• Forged or cast valve or rotating machinery casings for service in high pressure
environments (all materials);
Lot : Components from the same heat and subject to the same heat treatment (metallic
materials) or components from the same manufacturing batch (non-metallic materials).
Alternative sampling in accordance with ISO 2859-1 may be considered if referenced in a specific
design code or as agreed with CIL.
4.0 REFERENCES
International Standards Organisation (ISO)
ISO 10684 Fasteners – Hot Dip Galvanised Coatings
A333 Standard Specification for Seamless and Welded Steel Pipes for
Low Temperature Service
A370 Standard Test Methods and Definitions for Mechanical Testing
of Steel Products
A388 Standard Practice for Ultrasonic Examination of Steel Forgings
A403 Standard Specification for Wrought Austenitic Stainless Steel
Piping Fittings
A420 Standard Specification for Pipe Fittings of Wrought Carbon Steel
and Alloy Steel for Low Temperature Service
A435 Standard Specification for Straight-Beam Ultrasonic
Examination of Steel Plates
A578 Standard Specification for Straight-Beam Ultrasonic Examination
of Plain and Clad Steel Plates for Special Applications
A745 Standard Practice for Ultrasonic Examination of Austenitic
Steel Forgings
A770 Standard Specification for Through-Thickness Tension Testing
of Steel Plates for Special Applications
A961 Common Requirements for Steel Flanges, Forged Fittings,
Valves, and Parts for Piping Applications
A962 Common Requirements for Bolting Intended for Use at Any
Temperature from Cryogenic to the Creep Range
A991 Standard Test Method for Conducting Temperature Uniformity
Surveys of Furnaces Used to Heat Treat Steel Products
E112 Standard Test Method for Determining Average Grain Size
E1268 Standard Practice for Assessing the Degree of Banding or
Orientation of Microstructures
E280 Standard Test Method for Conducting Drop-weight Tests to
Determine Nil-Ductility Transition Temperature of Ferritic Steels
E407 Micro-etching Metals and Alloys
E562 Determining Volume Fraction by Systematic Manual Point
Count
F788 Surface Discontinuities of Bolts, Screws and Studs
F812 Surface Discontinuities of Nuts
G48 Standard Test Methods for Pitting and Crevice Corrosion
Resistance of Stainless Steels and Related Alloys by Use of
Ferric Chloride Solution
NACE International Standards
NACE MR0175/ISO 15156 Petroleum and Natural Gas Industries - Materials for use in
Testing
ACCP ASNT Central Certification Program
He shall ensure that the requirements of this Inspection requirement are properly implemented
through the project. He also provides professional advice on all Company QA arrangements, Co-
ordinates with the contractors in the resolution of quality issues.
QUALITY CONTROL TEAM
Quality Control team shall ensure that the requirements of this Inspection requirement are
properly implemented through the project.
The Team has responsibilities and authorities that include:
• Review and approve Suppliers and EPC contractors’ Quality Plans, Procedures as per
this inspection requirements.
• Ensure relevant QA and QC training for all site personnel and ensure all personnel
understand and effectively deliver their QA and QC responsibilities as per Quality Plan
and this Procedures.
6.0 GENERAL REQUIREMENT
6.1 General Manufacturing and HSSEQ Requirements
6.1.1 All components manufactured in accordance with this guideline shall meet the requirements of:
• Any applicable statutory regulations, including referenced codes or standards, of the
country where the components will be installed;
• The applicable design code and component material specifications;
• Other CIL Standards as applicable to the scope of supply.
6.1.2 All components for new construction shall be unused and less than 24 months old for metallic
components and 6 months old for non-metallic components (defined as the period from the date
of manufacture to the date of purchase on behalf of CIL).
6.1.3 In specific circumstances for in-service modifications to,or refurbishment/replacement of,
existing components, the re-use of existing components may be considered but shall be
subject to a continued fitness-for- service evaluation and detailed inspection regimes, using
methodologies and techniques approved by the CIL Engineering & Quality Authorities.
6.1.4 CRA components (with the exception of martensitic and 300-series stainless steels) shall
be procured from Vendors holding a current CIL qualification criteria relevant to their
scope of their supply, or CIL approved equivalent qualification programme . If these CRA
components are supplied from an intermediary, the intermediary shall demonstrate to the
satisfaction of CIL that the components have been procured from a Vendor holding an
appropriate qualification certificate current at the time of their manufacture, or CIL approved
equivalent qualification programme (as demonstrated above).
6.1.5 Fasteners shall be procured from Vendors operating a Quality Management System (QMS)
in accordance with the requirements of ASME B18.18 and this CIL Guideline. If the components
are supplied from an intermediary, the intermediary shall demonstrate to the satisfaction of CIL
that the fasteners have been procured from a source that operates in accordance with the above
requirements. Unless otherwise agreed with CIL, fasteners shall be assigned the following
categories for inspection:
Environment/Application Category
Non-sour process and utility environments 3
Structural steel application (including fixed jacket
structures) On-land buried applications
6.1.6 Where components are offered from an intermediary and do not comply with the requirements of
this guidline, acceptance of the components shall be subject to the approval of CIL Engineering
and Quality Authorities, based on the following principles:
a) All non-compliances shall be detailed for review by CIL Engineering and Quality
Authorities.
b) Where the data required by this guideline is missing or is not provided by the
intermediary, the components shall be rejected in the first instance.
c) Further to b) above, and subject to the approval of CIL Quality Authority, one component
in 25 from each lot shall be randomly selected by CIL for testing in accordance with this
guideline – if the tests meet the requirements of this guideline, the remaining
components of that lot may be accepted; if the tests fail to meet the requirements, the
components shall be rejected in accordance with Section 6.2.11.
d) Where the data required by this guideline is provided but the results do not meet the
requirements of this guideline, acceptance shall be based on either:
responsible for each stage - in all cases a column shall be included for the involvement of CIL or
its nominated representative.
6.2.5 For components supplied by an intermediary, an inspection and test plan is not required unless
the scope of supply includes further manufacturing, processing or inspection activities.
6.2.6 Components shall be supplied with the following Material test Report (MTR) type in accordance
with EN 10204:
6.2.8 For components referenced in Section 7.1.3, the original MTR from the raw material source
(e.g. cast billet) shall be supplied with the finished component in addition to the MTR for the
finished component.
6.2.9 For components supplied by an intermediary, the MTR shall comply with the following:
a) The intermediary shall submit either:
• An original MTR in accordance with Section 6.2.6;
• A copy of the original MTR certified by the intermediary as a ‘true copy of the original’;
• An intermediary-generated MTR complying with the requirements of Section 6.2.6 and
certified by the intermediary as a ‘true copy of the original’.
b) For components covered by Section 6.2.8, the original MTR or a copy of the original
MTR certified by the intermediary as a ‘true copy of the original’ shall be submitted.
C) For any component supplied with either a ‘true copy’ MTR or an intermediary- generated
MTR that is dated more than 18 months from the original test date, the original MTR for
the component shall be made available for CIL review. CIL reserves the right to require
additional testing of a representative component per lot to verify the stated properties.
6.2.10 Where an electronic certification scheme for the issue and control of MTRs is utilised, the
Vendor’s or intermediary’s QMS shall ensure that the scheme complies with the requirements
of EN 10204 and that full traceability is maintained between the electronic version of the MTR
and the component.
6.2.11 Any component identified as not complying with the requirements of this guideline shall be
quarantined and subject to an appropriate disposition as agreed with CIL, or removed and
replaced by a component complying fully with this guideline.
6.3 Marking and Identification
6.3.1 All acceptable components shall be clearly identified, and traceable back to the appropriate
MTR.The identification shall be retained until all inspection is complete and documentation
accepted by CIL
6.3.2 Identification of metallic components shall be by hard stamping using low stress, dot or U-type
stamps, engraving or non-deleterious indelible ink or paint. Hard stamping is not permitted for
thin-wall components (T<6.4mm).
6.3.3 Identification of non-metallic components shall be by non-deleterious indelible ink or paint.
6.3.4 Marking and identification for specific components shall comply with the following:
Spiral wound and jacketed metal gasket Each component shall be clearly and durably
identified and color coded in accordance with
ASME B16.20
Non-metallic gaskets Each component shall be clearly and durably
identified with the Vendor’s identification and
material type/grade in accordance with ASME
B16.21
FRP components Each component shall be clearly and durably
identified in accordance with the Vendor’s
identification and material type/grade
Thermoplastic pipe and fittings for use in gas Each component shall be clearly and durably
service identified and color coded
Thermoplastic pipe and fittings for use in utility Each component shall be clearly and durably
service marked in accordance with the Vendor’s
identification and material type/grade
Elastomeric and thermoplastic seals Traceability shall be maintained with the MTR in
accordance with the Vendor’s standard QA/QC
procedures
The shelf life of each type of component
shall be clearly identified on the packaging
and this shall be maintained during
subsequent storage
permanent coating system that is suitable for direct exposure to a marine environment,
and all openings shall be protected with end caps or other appropriate closure.
e) Components shall not be stored or stacked in direct contact with the ground. Where such
storage is necessary, a barrier layer shall be installed between the component and the
ground.
f) In addition to e) above, CRA components shall be protected from exposure to marine
atmospheres and shall have all open ends protected with end caps or other appropriate
closure.
g) Material shall be protected, stored and preserved in accordance with procedure “New
Material and Equipment Preservation-(CAIRN-TSG-J-PRO-0011)” in ordered to assertain
fit for purpose condition of material.
h) Fibre reinforced composite and thermoplastic components shall be stored under
cover unless they are manufactured to withstand ultra violet (UV) exposure in
accordance with Section 8.2 or Section 8.3 under cover to prevent unnecessary
exposure to UV light.
i) Elastomeric and thermoplastic seals and non-metallic gaskets shall be transported
and stored in waterproof crates or containers to prevent exposure to UV light and
humidity and shall be packed to ensure that no force likely to induce permanent
deformation (‘set’), is placed on the components.
6.4.2 Where components are supplied in containers, crates or bags, these shall be inspected prior to
shipment and further on receipt to confirm that these are unopened and that no damage has
occurred that would affect the integrity of the contents. In the case where any damage has
occurred, the components shall be rejected in accordance with Section 6.2.11.
6.4.3 Where components are supplied with temporary protective coatings, these shall be selected to
ensure that they can be removed easily prior to further processing. Where permanent protective
coatings are specified as part of the component supply, these protective coatings shall meet the
requirements of CAIRN-TSG-L-SP-0005.
7.0 METALLIC MATERIALS
7.1 General Manufacturing Requirements
7.1.1 Where Unified Numbering System (UNS) wrought designations, the requirements shall apply to
the appropriate UNS cast designations unless otherwise specified.
7.1.2 The following specific manufacturing requirements are applicable for all ferritic steel and CRA
materials:
Component Manufacturing requirements
Pipe 1. Seamless and welded line pipe shall meet the requirements of API 5L/ISO
3183 (carbon steel, high strength low alloy (HSLA) & micro alloyed steels) or API
5LC (CRA materials) or Piping Material Specification or CIL Specification
whichever is stringent.
2. Electric welded (EW) pipe/tube shall only be supplied from mills that utilise the
following manufacturing controls:
● high frequency (greater than 100kHz) welding processes
● on-line feedback systems for controlling heat input and roll pressure
● in-line capability for automatic weld seam tracking control, full weld volume
ultrasonic inspection and induction heat treatment capability
3. Skelp end welds shall be cut out of the finished pipe
Metallurgically bonded
(clad) components 1. Metallurgically bonded (clad) components shall comply with the following
requirements:
6. Metallurgically bonded (clad) line pipe shall meet the requirements of API 5LD
Weld overlaid Weld overlaid components shall meet the requirements of CIL Fabrication
components Specification
CRA-lined pipe 1. Mechanically-lined line pipe shall meet the requirements of API 5LD or
Pipeline Specification or CIL Specification whichever is stringent.
2. The liner shall have a minimum thickness of 2.5mm, consistent with obtaining
an acceptable interference fit and weld end preparation
3. The pipe ends shall be weld overlaid for a minimum distance of 50mm from the
(3)
edge
Notes:
1. The principles within ISO 15590-1 or ASME B16.49 shall be followed in developing appropriate
manufacturing procedure specifications for CRA induction bends
2. Minor cosmetic weld repairs are permitted after heat treatment provided the repair depth does not
encroach on the base material and the relevant welding procedure is qualified to demonstrate that the
hardness level below the repair area does not exceed the values stated in relevant standard
3. A greater length may be required subject to the final selection of the automated ultrasonic testing
methodology for the girth welds and results of any fatigue analysis
7.1.3 A procedure qualification test programme shall be undertaken for the following components to
demonstrate that the proposed manufacturing route and production parameters results in
components meeting the requirements of this guideline and further, that the proposed production
test sampling will give results which are representative of the actual component properties:
• HSLA or microalloyed line pipe with specified minimum yield strength (SMYS) ≥320MPa
(with reference to API 5L/ISO 3183);
• All special castings and standard castings for high pressure service (with reference to the
requirements of API 20A) or fixed jacket structures (with reference to Norsok M122);
• All special forgings and standard forgings for high pressure service (with reference
to the requirements of API 20C) or fixed jacket structures (with reference to Norsok
M123);
• HSLA or microalloyed steel plate, rolled product or hollow section from a new Vendor,
location or process route that does not possess relevant manufacturing and qualification
data to demonstrate compliance with the requirements of this guideline;
• Newly developed ferritic steels or ones that have not previously been supplied and for
which manufacturing and qualification data, or extensive fabrication experience, is not
available to demonstrate compliance with the requirements of this guideline;
• Integrally clad, mechanically lined pipe (with reference to API 5LD) or weld overlaid CRA
pipe and fittings.
7.1.4 For components referenced in Section 7.1.3:
a) A manufacturing procedure specification shall be developed to define all
necessarymanufacturing steps and essential variables for component
qualification. Re-qualification is required when the essential variables defined during the
qualification stage change.
b) A qualification test coupon shall be taken subject to the relevant requirements of the
component material specification.
7.1.5 Unacceptable surface or embedded flaws/imperfections shall be rectified or repaired as
follows:
c) Items shall be loaded in the furnace in a manner that allows free movement of air or
water and ensures all surfaces are heated or cooled evenly.
d) For bulk piping components, temperature monitoring by the furnace thermocouples
is acceptable providing the thermocouple measures temperatures within the
calibrated working zone. For special forgings or castings, a thermocouple shall be
attached to the surface of the heaviest cross section of the largest item in the heat
treatment load.
e) The hold time at temperature shall not commence until all the thermocouples reach the
specified hold temperature.
f) The rise, hold and fall times and temperatures shall be recorded on a hard copy chart in
addition to any computer readout and a certified copy of this chart shall accompany the
MTR.
g) The test coupon shall be included in the furnace load based on a minimum of one test
coupon per heat and heat treatment load.
h) When a furnace is repaired or rebuilt, a new temperature survey shall be carried out
before the furnace is used for heat treatment, unless it can be demonstrated that the
repairs do not affect the temperature tolerance of the furnace.
7.3.2 Where subsequent liquid quenching is required, the following requirements shall be met:
a) Quenching facilities shall be located in the immediate vicinity of the heat treatment
furnace to ensure that the time between removing the component(s) from the furnace
and quenching is less than 60 seconds from the time the furnace door is fully open or the
roof removed. An elapsed time greater than 60 seconds shall be subject to specific
qualification and shall be limited to components within the qualified range.
b) The quench tank shall be designed to completely immerse the components and the
medium agitated to ensure that all surfaces of the items are in contact with the circulating
medium.
c) The temperature of the medium during quenching shall be continuously monitored to
ensure the temperature does not exceed approximately 50°C at the end of quenching.
Measuring and recording instruments shall possess an accuracy of ±5°C of their full
scale range and shall be calibrated at least once every three months.
d) The quench medium shall be selected to ensure that the final specified properties
are met whilst minimising the likelihood of distortion or quench cracking. Any change in
the selected medium from that used during qualification will require re-qualification.
7.3.3 The tempering heat treatment temperature shall be at least 20°C higher than the upper limit of
the temperature range specified for any specified or anticipated heat treatment required during
subsequent fabrication e.g. hot forming, post weld heat treatment (PWHT).
7.3.4 A detailed procedure shall be developed to control the heat treatment and subsequent
cooling operations. All critical steps shall be included in the inspection and test plan in
accordance with Section 6.2.4.
7.4 Fasteners
7.4.1 Unless otherwise specified in the design code, fasteners shall be manufactured in accordance
with ASTM A962 and the follow
Non-sour
environments &
below ground Submerged applications
Requirements Sour environments
applications (including water-air interface)
(including soil-air
interface)
Steelmaking process:
Deoxidation Steel shall be fully killed & fine grained
Manufacturing process:
All grades
(with
exceptions ≤35HRC
as noted
below):
ASTM
A194Gr.2HM
≥200HB
(2)
& Gr.7M
nuts:
7.5.2 Ring-joint gaskets shall meet the surface finish and maximum hardness limits specified in ASME
B16.20 and shall be at least 30HRB points lower than the flange seating surface.
7.5.3 The strength and hardness of seal rings shall be selected to ensure that the completed joint
meets the integrity requirements of Flange Joint Management, Cleaning & Pressure Testing
according to CIL Specification.
7.5.4 In addition to the requirements of ASME B16.20 spiral wound gaskets shall meet the following
requirements:
a) The filler shall not contain asbestos.
b) Each gasket shall be supplied with a centring ring irrespective of the service
environment.
c) Each gasket shall be supplied with a solid metal inner ring when installed in the following:
• High pressure environments;
• Hazardous & extreme hazardous environments;
• Elevated & cryogenic temperature environments;
• Vacuum service;
• Cyclic fatigue service;
• Erosive service;
• Suction side of rotating machinery.
7.5.5 Gaskets and seal rings shall be identified in accordance with the requirements of Section 6.3
5. Where possible, full size specimens (10mmx10mm) shall be removed for testing.
Where full size specimens cannot be taken due to component thickness, size or
orientation constraints, sub-size specimens shall be removed. Unless otherwise
specified in the relevant design code, the impact energy shall be adjusted as follows:
Width of subsize specimen
Energy value for full size specimen × ------------------------------------------------------------
Width of full size specimen
6. The minimum impact energy values specified within this Standard are applicable
irrespective of sample orientation. Some design codes may require higher values for
specimens orientated in the longitudinal (axial) direction
7. The impact energy values as specified in CIL material specifications
8. Lateral expansion values shall be reported where required by the component material
specification, design code, or CIL Material Specifications
Fracture toughness 1. Testing shall be performed in accordance with the requirements of BS 7448-1, ISO
test 15653 or BS 7448-4 as appropriate
2. The number of test specimens will depend on the design basis and assessment level
used during the fitness-for-service evaluation and shall be agreed with the CIL
Engineering prior to Commencing testing. As a minimum, the following requirements
shall be met:
a) For a Level 1 and Level 2 deterministic assessment in accordance with BS 7910, or
as specified in the basis of design, a minimum of three valid test results are required to
represent each location (base metal, weld metal and HAZ as applicable)
b) The values obtained from these three specimens shall meet the requirements of
BS7910 with respect to scatter. Where the results do not meet these requirements an
additional number of test specimens shall be taken and the values from all the
specimens shall be included (not just the re-test values) in determining the acceptable
degree of scatter and where the results still do not comply with BS 7910 requirements
the test shall be considered invalid and the component rejected in accordance with
Section 6.2.11
c) For a Level 3 tearing instability assessment, a valid resistance curve representative
of each location (base metal, weld metal and HAZ as applicable) shall be determined.
The validity limits of these curves shall be determined in accordance with the
requirements of BS 7448-4
d) For wrought base components, specimens shall be through-thickness notched, taken
transverse to the direction of principal deformation (major rolling/forging direction)
e) For cast or hot isotactic pressed (HIP) base components, specimens shall be taken
transverse to the direction of maximum stress
f) For weld metals and HAZ, specimens shall be through-thickness notched, “NP” type
in accordance with ISO 15653
g) Test results in which ‘pop-in’ behavior is observed shall be subject to post-test
metallography to determine its significance
3. Where a repair weld is permitted, the following areas shall be tested as noted above:
● The repair weld metal
● The HAZ of the base material component and repair weld metal
● The HAZ of the original weld metal and repair weld metal
4. The test temperature shall be the lower of:
b) The test environment shall be selected to ensure that it is no less severe than the
predicted environment or the environment as measured during operations or from well
testing
c) The test solution shall be de-aerated to a maximum of 50ppb oxygen prior to starting
the test and maintained throughout
d) The pH shall be checked before and after testing to ensure that initial and final pH
values have been met within ±0.2 pH units
2. Specimens from welded components shall be taken transverse to the weld centerline
and tested in the as-welded condition with the weld root face in tension
3. Each specimen shall be strain gauged using a bi-axial strain gauge centered on the
loading surface for base material samples or on either side of the weld for welded
samples
4. For components subject to straining, the test coupon shall be subject to the same
requirements noted above for strain ageing
5. On completion of testing, the samples shall be cleaned and subject to surface NDE
and visually examined at x10 and x40 magnification to evaluate for any surface cracking
or localised corrosion
6. In certain applications, a full pipe ring test may be specified by CIL. When applicable,
the details shall be agreed with the CIL Quality Authority prior to commencing testing
7. A detailed procedure/methodology statement shall be supplied for CIL review
SCC/SSC test – CRAs 1. Testing shall be performed in accordance with Annex B of NACE MR0175/ISO15156-
3 and the following:
a) Four point bend specimens under constant displacement loading shall be used
b) The test environment shall be selected to ensure that it is no less severe than the
predicted environment or the environment as measured during operations or from well
testing
c) The test solution shall be de-aerated to a maximum of 10ppb oxygen prior to starting
the test and maintained throughout
d) The test shall be undertaken at 23°C±3°C and at the maximum design temperature.
For duplex shall be
e) The pH shall be checked before and after testing to ensure that initial and final pH
values have been met within ±0.1 pH units
2. Specimens from welded components shall be taken transverse to the weld centerline
and tested in the as-welded condition with the weld root face in tension. For materials
that exhibit ‘cold creep’ (e.g. duplex stainless steel), the specimen may be machined if
this can be demonstrated to avoid strain relaxation
3. Each specimen shall be strain gauged using a bi-axial strain gauge centered on the
loading surface for base material samples or on either side of the weld for welded
samples
4. For components subject to straining, the test coupon shall be subject to the same
requirements noted above for strain ageing
5. On completion of testing, the samples shall be cleaned and subject to surface NDE
and visually examined at x10 and x40 magnification to evaluate for any surface cracking
or localised corrosion
6. In certain applications alternative test samples and loads may be specified by CIL
When applicable, the details shall be agreed with the CIL Quality Authority prior to
commencing testing
8. Any evidence of pitting above the specified limit on the non-test surfaces shall
invalidate that test specimen and an additional specimen shall be prepared and tested
9. A detailed procedure/methodology statement shall be supplied for CIL review
Weldability testing 1. The test coupon shall be selected from the same grade and heat treatment condition
as the as-delivered component and shall be of sufficient length to provide all required
test specimens
2. The thickness of the test piece shall be the maximum thickness supplied (but need not
exceed 75mm) to provide similar heat conductive paths as will be experienced in
fabrication
3. The weld preparation shall be similar to that proposed during fabrication (unless a
square- edged test piece is required for fracture toughness testing of the HAZ)
4. The same welding process and consumables shall be used as proposed during
fabrication with the exception that SMAW and gas shielded flux cored arc welding
(FCAW-GS) may be interchanged providing the same heat input is used and the
essential and supplementary essential variables of the design code for each process are
met
5. The same preheat and PWHT (if applicable) conditions shall be used as proposed
during fabrication
6. The Crack Tip Opening Displacement (CTOD) method uses fatigue pre- cracked
specimens. The tests are carried out in displacement control with monotonic loading and
at a constant rate of increase in stress intensity factor within the range 0.5 – 3 MPa Ѵm
s-1 during the initial elastic deformation. The specimens are loaded to the maximum
force associated with plastic collapse. The method is especially appropriate to materials
that exhibit a change from ductile to brittle behavior with decreasing temperature. No
other influences of environment are covered. This test shall be conducted in line with
British Standard, BS 7448. Part 1-1991: Amendment 1: August 1999.Standards.
Notes:
1. HSLA line pipe steels may suffer strain ageing during coating with FBE – to demonstrate that there is no
deterioration in properties the test coupon shall be subject to the same heating cycle as proposed during coating
but without any imposed strain
2. Specific requirements will need to be developed on a case-by-case basis depending on the actual reeling cycle
and whether the load case is stress or strain based as this will affect the upper or lower bound tensile properties
and hence the result of a fracture assessment. These requirements shall be subject to agreement with CIL.
E. The requirements for the pitting corrosion test are based on the results of a sponsored project in which CIL took
part in and these have been summarised in a recommended practice document that is available from CIL
7.6.3 Components shall be tested during the manufacturing production in accordance with the design
code, component material specification and the following:
Forging & HIP products 1. One test coupon shall be prepared from either: One set of tests for each lot to
a) a representative sacrificial forging represent a maximum lot of
b) a prolongation 2000kg for components with
c) a separately forged test blank from the same an as-forged weight ≤50kg or
heat, and of the same nominal thickness reduced 5000kg for components with
by forging in the same manner and by the same an as-forged weight >50kg
amount of working and number of reductions, as
the production forging (not permitted for special
forgings or where the finished section thickness
T>100mm)
d) an integrated test block (HIP products)
2. A sacrificial forging or integral prolongation shall
be used for die forged or ring rolled components
and for tees
3. The test coupon shall not be removed until after
the final heat treatment.
4. Unless otherwise specified in the design code,
test specimens shall be taken from the T/2xT
location for forgings with a maximum section
thickness T≤50mm and T/4xT for forgings with
section thickness T>50mm. Additional test
specimens in accordance with the above shall be
taken from the crotch region of special forged tees
for a second full set of tests
5. For special forgings, sketches shall be
established showing type, size and location of test
specimens
Casting 1. One test coupon shall be prepared from either: One set of tests for each lot to
a) a representative sacrificial casting represent a maximum lot of
b) a test block integrally cast or gated onto the 2000kg
casting
2. The test coupon shall not be removed from the
casting until after the final heat treatment
3. Unless otherwise specified test specimens shall
be taken from the T/4 x T/2 location
4. For special castings sketches shall be
established showing type, size and location of test
specimens
Fittings, pipe, tube One test coupon shall be prepared from a One set of tests for each lot
representative sacrificial component
(1)
Induction bends One test coupon shall be prepared from a test One set of tests per bend
bend manufactured to the smallest radius for each
NPS
Metallurgically bonded One test coupon shall be prepared from each plate One set of tests as for
(clad) components or forging as specified above plates/forgings as above
CRA-lined pipe One test coupon shall be prepared from a One set of tests for each lot
representative sacrificial pipe
Weld overlaid component One test coupon shall be prepared from a One set of tests for each lot
representative sacrificial component
Notes: 1. If the results of mechanical testing from the test bend are considered acceptable then no further
destructive testing of the production bends will be required providing all the essential variables have been met
during production
7.6.4 Test coupons shall be sized to represent the thermal response of the component and large
enough to enable all required test samples to be obtained from a single coupon.
7.6.5 The method of removing a test coupon shall not influence the material properties i.e. if the test
coupon is removed by flame cutting, sufficient material shall be discarded to remove any heat
affected zone that would influence the final properties (such as strain ageing).
7.6.6 All test coupons shall be clearly identified and traceable back to the test lot/component.
7.6.7 Where further heat treatment is required or anticipated during subsequent fabrication, the
test coupon shall be subjected to a simulated heat treatment cycle (or cycles as appropriate) to
represent the maximum anticipated heat treatment applied during the fabrication to the following
materials:
• Conventional carbon steels with T>50mm;
• HSLA steels – all thickness’;
• Low alloy & nickel alloy steels with T>13mm.
7.6.8 Where tests from a sample fail to meet the acceptance criteria specified in the design code,
component material specification or, an additional two sets of test specimens shall be tested
unless otherwise noted in this guideline. If these additional specimens meet the acceptance
criteria, the representative lot shall be accepted; where they fail to meet the acceptance criteria
the representative lot shall be considered unacceptable and rejected in accordance with
Section 6.2.11.
7.7 Inspection Requirements
7.7.1 Components shall be inspected during manufacturing production in accordance with the design
code, component material specification and the following:
9 Hydrostatic testing
(6)
10 Positive material identification (PMI)
Notes:
1. Where the weld or HAZ oxidation is darker than light straw, chemical treatment is not permitted and in such
cases the weld shall be removed and the component re-welded
2. The thickness of the calibration block shall be within ±10% of the forging or casting reference thickness and
shall be made of the same material as the component or with similar acoustic attenuation properties
3. An angle beam probe shall be used where the forging or casting configuration makes interpretation of
ultrasound signals from a straight beam probe difficult, or where specified by the code
4. Where magnetic particle testing is specified, the wet contrast method shall be used with electromagnetic yolk or
permanent magnet
5. Where liquid penetrant testing (PT) is specified, penetrant materials shall meet the requirements of
Paragraph T-625 of ASME V for sulphur and halogen content regardless of the type of material to be examined
6. All CRA components shall be subject to selective PMI programme at the source of supply or on component
receipt, unless a criticality risk assessment in accordance with CIL Guideline to demonstrates that the risk of
incorrect components supply is low
7.7.2 For components subject to procedure qualification testing in accordance with Section 7.1.2, all
NDE operators shall be certified in accordance with a scheme meeting the requirements of ISO
9712. For Vendors with NDE operators certified in accordance with ASNT SNT-TC-1A, only
schemes under the supervision of an ASNT Certified NDE Level III or ASNT ACCP Professional
Level III operator are acceptable in meeting the intent of ISO 9712.F
7.7.3 For components other than those in Section 7.1.2, NDE operators shall be certified in
accordance with SNT TC 1 A or alternatively with an ASNT SNT-ST-1A scheme under the
supervision of a Vendor certified Level III operator.
8.0 NON METALLIC MATERIALS
8.1 General Manufacturing Requirements
8.1.1 All components shall be new (less than one year from the date of manufacture).
The re-use of existing components for modifications or refurbishment of existing facilities is not
permitted.
8.1.2 Components shall be supplied from a single Vendor to ensure the design basis is consistent and
there is compatibility of components during subsequent fabrication. The selection of components
from different Vendors will require CIL Quality Authority approval.
8.2 Fibre Reinforced Composite Materials
8.2.1 For tubular components, fittings and flanges, a procedure qualification test programme in
accordance with ISO 14692 shall be undertaken as follows to demonstrate that the proposed raw
materials, manufacturing method and production parameters results in components meeting the
requirements of this guideline:
a) The manufacturer’s pressure rating (MPR) and threshold envelope for alternative sizes
and pressure ratings shall be determined;
b) All tests involving the use of internal pressure shall be conducted on components with
unrestrained ends (i.e. no axial load shall be applied to the ends).
c) The fluid used for the qualification programme shall be potable water. Previous Vendor
data using other water environments may be accepted providing the chloride content
does not exceed 35g/L;
d) Unless otherwise agreed with CIL, the qualification programme shall be based on a
design life of 20 years.
8.2.2 For load-bearing structural members, decks, gratings and stairs, a procedure qualification test
programme shall be undertaken to demonstrate that the load carrying capacity meets the
minimum design requirements and that the proposed raw materials, manufacturing method and
production parameters results in components meeting the requirements of this guideline.
8.2.3 Components that are to be used in fire hazardous areas shall be qualified to demonstrate
acceptable performance as specified in the basis of design under the following service and
operating conditions:
a) Fire type (e.g. jet fire, hydrocarbon pool or impinging fire);
b) Process fluid (e.g. water, hydrocarbon gas or liquid);
c) Service flow condition (e.g. flowing, stagnant, dry or empty, dry or empty followed by
flowing conditions);
d) Integrity and endurance limits;
e) Surface spread of flame and heat release;
f) Smoke obscuration and toxicity;
8.2.4 Re-qualification is required when the essential variables noted below change:
a) Manufacturing method, winding angle greater than ±5°;
b) Generic resin/adhesive system or respective manufacturers;
c) Curing system chemistry, catalyst or respective manufacturers;
d) Curing time and/or temperature by more than ±20%;
e) Structural reinforcement material type or composition, finish or manufacturer;
f) Addition or deletion of additives, fillers or coatings specifically intended to enhance the
performance (e.g. conductivity, fire performance);
g) Geometry and dimensions outside of qualified threshold envelope.
8.2.5 The following specific manufacturing requirements are applicable for tubular components:
8.2.6 The following specific manufacturing requirements are applicable for all load- bearing
structural components, including gratings, stairs, handrails and cable trays:
8.2.7 Components shall be tested during manufacturing in accordance with the design code,
component material specification and the following:
≤3.0mm dia. x
0.5mm deep &
Pinholes less than 1 pit per
100cm²
(1)
Degree of 1% of each Measured Tg ±5% of Vendor’s baseline data
cure production lot or
once every 24 hours Barcol hardness greater than or equal to
(whichever is Vendor’s baseline data with no single reading
(2)
greatest) less than 90% of this baseline data
Notes:
1. Degree of cure shall be determined using either differential scanning calorimetry (DSC), modulated
differential scanning calorimetry (MDSC) or dynamic mechanical thermal analysis (DTMA) with the same
method as used during qualification used during production
2. For polyester and vinyl ester resin systems, Barcol hardness testing may be substituted for DSC,
MDSC or DTMA providing a minimum of ten readings are taken with the two highest and two lowest
reading discarded and the remaining six readings used to calculate an average reading. If Vendor
proposes this method, the hardness testing methodology shall be undertaken as part of the qualification
programme
8.2.8 Repairs are limited as follows and shall be subject to CIL. approval:
a) Not permitted to the CRL of tubular products nor structural layer of all components;
b) Grinding or cleaning and application of resin/hardener or CSM, is permitted for repair of
the surface layer;
c) Where permitted, an approved repair procedure, as recommended by the Vendor, shall
be used;
d) All repaired areas shall be recorded and re-inspected for compliance, and the inspection
reports included on the MTR or in final hand-over documentation.
8.2.9 The use of FRP components with inner/outer thermoplastic liners or steel strip laminate
components shall be subject to review and agreement by CIL Advance.
8.3 Thermoplastic Materials
8.3.1 A procedure qualification test programme shall be undertaken as follows to demonstrate
that the proposed raw materials, manufacturing method and production parameters results in
components meeting the requirements of this guideline:
Notes:
1. Where the component w ill be exposed to production chemicals (such as corrosion or w ax inhibitors, glycols etc.) or w ell stimulation fluids, these shall be
included in the test environment
2. Only required for pipe w ith T≥15m. Where the Vendor has previous data from full scale testing in accordance w ith ISO 13478, small scale testing is acceptable in
accordance w ith ISO 13477
8.3.2 Re-qualification is required when any of the following essential variables change or once every
five years (whichever occurs first):
8.3.3 The following specific manufacturing requirements are applicable for tubular components
and seals:
8.3.4 Components shall be inspected in accordance with the Vendor’s internal QA/QC requirements
and the following:
8.4.1 A procedure qualification test programme shall be undertaken in accordance with ISO 23936-2 to
demonstrate that the proposed raw materials, manufacturing method and production
parameters results in components meeting the requirements of this guideline.
8.4.2 In addition to the requirements of ISO 23936-2, the qualification programme shall also meet the
following requirements:
a) Where the component will be exposed to production chemicals (such as corrosion, scale
or wax inhibitors, glycols etc.) or drilling or well stimulation fluids, these shall also be
included in the test environment.
b) For flexible joints, where the component will potentially be exposed simultaneously to
production fluids/chemicals and seawater/air, and to cyclic fatigue, the qualification
programme shall be agreed with CIL
8.4.3 For RGD testing, the following additional requirements to those in ISO 23936-2 shall apply:
a) Where the standard test environment in ISO 23936-2 is less severe than the actual
service environment, the test environment shall be set at the maximum temperature,
pressure and rate of depressurisation expected in service;
b) A chemically aged specimen shall be included in the rapid gas decompression (RGD)
testing programme to demonstrate that the latter is not adversely affected by service
(unless the vendor has previous documented test data at the service conditions);
c) Where no previous documented data exists, samples shall be removed after the first and
third or fifth cycle of RGD testing to establish whether any damage is occurring;
8.4.4 Re-qualification is required when any of the following essential variables change or once every
five years (whichever occurs first):
8.4.5 Components shall be inspected in accordance with the Vendor’s internal QA/QC requirements
and the following:
8.5.1 All gaskets and seals shall be compatible with the process fluid and flange material.
8.5.2 In addition to the requirements of ASME B16.21 reinforcement or filler material for gaskets shall
not contain asbestos.