Created by: Matej Vidić

Tue 9.4.19

ID Task PRINTING
DN Task Name Duration Finish May 2019 June 2019
Mode 18 19 20 21 22 23 24 25 26
27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
455 Y xxx DNxxx - STL - 02 33,73 days Mon 24.6.19

456 Y Tehnološka razrada 1,5 days Fri 26.4.19 Odjel tehnologije[1,67]

457 Y Nabava 1,5 days Tue 30.4.19 Nabava[0,17]

458 Y Plazma rezanje 3,9 days Mon 6.5.19 Razrez[1,25]

459 Y Strojna obrada 2,93 days Tue 7.5.19 Strojna obrada[3,33]

460 Y Bravarska priprema 3,25 days Fri 10.5.19 Br. Priprema[4,38]

461 Y 2D montaža 3,75 days Mon 20.5.19 2D grupa[1,67]

462 Y 3D montaža kotla 1,88 days Wed 22.5.19 3D grupa[1,5]

463 Y Zavarivanje kotla 2,51 days Mon 27.5.19 Zavarivanje[6,25]

464 Y Opremanje 3,13 days Fri 31.5.19 Opremanje[3,5]

465 Y Montaza konzervatora 3,33 days Wed 29.5.19 ADG[1,88]

466 Y Montaža komponenti 3,33 days Wed 29.5.19 Dome I Komponente[2,34]

467 Y Montaža pokrova 3,31 days Thu 30.5.19 Pokrov[1,89]

468 Y Probna montaža 3,33 days Mon 10.6.19 Probna montaža[2,81]

469 Y Vanjska kontrola 2 days Thu 13.6.19

470 Y Pjeskarenje I popravke 2,57 days Tue 18.6.19 Popravke I pjekarenje[8,5]

471 Y Lakiranje I otprema 6 days Mon 24.6.19 Lakiranje I otp

472 Y Isporuka 0 days Mon 24.6.19 24.6

20190409_Preis Usora_planning_rev06 Page 1