Job No. PECS2016001 Doc No.

PECS/201601/APPROACH JETTY/007
Rev. No. 0
Survey, Design, Construction, Supply, Erection & Commissioning
of Raw Water Intake Structure (Fixed type), Pump House on Intake structure
Project Title including Pumping Machineries with all related Accessories,
Raw Water Transmission Main for drawing 35 MGD Raw Water from The River Hooghly
and Delivering to Water Treatment Plant on EPC Turnkey Basis
Owner Superintending Engineer, Eastern Circle, Public Health
Engineering Dte., Govt. of WB

Design of Approach Jetty for Intake


WAPCOS LIMITED (A Govt. of India Undertaking)

Pump House (Habra Gaighata Intake


Owner's Consultant
Executing Agency Simplex Infrastructures Limited
Consultanct to EA Projectscape Engineering Consultancy Services Private Limited
Project)
Name of Unit Structural Analysis & Design of Approach Jetty (Calculation of
Scour Depth)
Drawing Ref.
Designed by: Shubhajit Barik Checked by: G
Chakraborty Approved by: G Chakraborty
Date: 9/6/2016
Reference
CALCULATIONS

CALCULATION OF MAXIMUM SCOUR DEPTH VIS-A-VIS SCOUR DEPTH CALCULATED BY


KoPT FOR HABRA-GAIGHATA INTAKE PROJECT :

CALCULATION OF SILT FACTOR ( Ksf ) :


Ksf = 1.76√dm ( As
per clause No. 703.2.2 of IRC:78-2014)

dm = weighted mean diameter of bed


material in millimetre
(The recommendation of KoPT as per letter
no: Hyd/ 12029/Jubilee bridge/PHED/862 on Dated: 02.08.2016
the value of dm along the region has been
considered as 0.119 mm for the purpose of scour depth calculation.)

dm = 0.119 mm
So, Ksf = 0.607

CALCULATION OF SCOUR DEPTH 40.0M FROM HIGH BANK LINE


W.R.T.HHWL (for 1000Ø Pile) High Bank
line has been considered

(Refer Sketch No. PECS/SIL/1601/003/SK-01


as wetted line where HHWL merges

with the River Bed profile near bank

Maxm Discharge Velocity, V = 1.50 m/sec


(Recommendation of KoPT as per Letter No.

Hyd/ 12029/Jubilee bridge/PHED/862)


Discharge per M width of
waterway (Db) =(A x V) = 3.76 cumecs
Depth of Water considered for unit discharge from HHWL = 2.508 m
(at centre of
farthest pile nearly 40.0 m away from High Bank Line, 4.67m - 2.162m)
So, Design Discharge per M
width of waterway = 4.89 cumecs
Increase of 30% over Design Discharge, as per

clause No. 703.1.1 of IRC:78-2014, Catchment

area less than 3000 km2

MEAN SCOUR DEPTH (dsm):

As per IRC: 78-2014 the mean scour Depth


below Hight Flood Level (HHWL) can be calculated theoritically from the
following equation:
dsm = 1.34
(Db /Ksf) 1/3

dsm= Mean depth of Scour


Db = The design discharge for foundation
per metre width of effective Waterway
Ksf = Silt factor for a representative
sample of bed material obtained uptothe level of anticipated deepest scour.

Here, Mean Scour Depth, dsm= 2.686


m (From HHWL)

Maxm Deoth of Scour from HHWL (2dsm) =


5.372 m ( As per clause No. 703.3.1.1 of IRC:78-2014)

1.a) Maxm Scour Depth From HHWL =


5.372 m (As calculated above)
1.b) Max Scour Depth From river Bed Level
=
m

2.180 m (The recommendation of KoPT as per Letter No.

Hyd/ 12029/Jubilee bridge/PHED/862 on Dated:


Calculated Maxm Scour Depth From HHWL (2.18+2.508) =
4.688 m 02.08.2016

So, for Design purpose we would


consider the Maximum Value = 5.372 m from HHWL
Page 1 of 2
Job No. PECS2016001 Doc No.
PECS/201601/APPROACH JETTY/007
Rev. No. 0
Survey, Design, Construction, Supply, Erection & Commissioning
of Raw Water Intake Structure (Fixed type), Pump House on Intake structure
Project Title including Pumping Machineries with all related Accessories,
Raw Water Transmission Main for drawing 35 MGD Raw Water from The River Hooghly
and Delivering to Water Treatment Plant on EPC Turnkey Basis
Owner Superintending Engineer, Eastern Circle, Public Health
Engineering Dte., Govt. of WB

Design of Approach Jetty for Intake


WAPCOS LIMITED (A Govt. of India Undertaking)

Pump House (Habra Gaighata Intake


Owner's Consultant
Executing Agency Simplex Infrastructures Limited
Consultanct to EA Projectscape Engineering Consultancy Services Private Limited
Project)
Name of Unit Structural Analysis & Design of Approach Jetty (Calculation of
Scour Depth)
Drawing Ref.
Designed by: Shubhajit Barik Checked by: G
Chakraborty Approved by: G Chakraborty
Date: 9/6/2016
Reference
CALCULATIONS

CALCULATION OF SCOUR DEPTH BEYOND 40.0M HIGH BANK LINE


W.R.T.HHWL (for1200Ø Pile) High Bank line
has been considered
(Refer Sketch No. PECS/SIL/1601/003/SK-01
as wetted line where HHWL merges

with the River Bed profile near bank

Max Discharge Velocity, V = 3.00 m/sec


m

( Recommendation of KoPT as per Letter No.

Hyd/ 12029/Jubilee bridge/PHED/1597)


Discharge per M width of
waterway (Db) =(A x V) = 15.41 cumecs
Depth of Water considered for unit discharge from HHWL = 5.138 m
(at centre of
farthest pile nearly 40.0 m away from High Bank Line, 4.67m + 0.468m)
So, Design Discharge per M
width of waterway = 20.04 cumecs
Increase of 30% over Design Discharge, as per

clause No. 703.1.1 of IRC:78-2014, Catchment

area less than 3000 km2


MEAN SCOUR DEPTH (dsm):

As per IRC: 78-2014 the mean scour Depth


below Hight Flood Level (HHWL) can be calculated theoritically from the
following equation:
dsm = 1.34 (Db
/Ksf) 1/3

dsm= Mean depth of Scour


Db = The design discharge for foundation
per metre width of effective Waterway
Ksf = Silt factor for a representative
sample of bed material obtained uptothe level of anticipated deepest scour.

Here, Mean Scour Depth, dsm= 4.298


m (From HHWL)

Maxm Deoth of Scour from HHWL (2dsm)=


8.597 m ( As per clause No. 703.3.1.1 of IRC:78-2014)

2.a) Maxm Scour Depth From HHWL=


8.597 m (As calculated above)

(The recommendation of KoPT as per Letter No.


2.b) Max Scour Depth From river Bed Level=
m

8.400 m

Hyd/ 12029/Jubilee bridge/PHED/1597 on Dated:


Calculated Maxm Scour Depth From HHWL (8.400+5.138)=
13.538 m 11.12.2015

So, for Design purpose we would consider


the Maximum Value = 13.538 m from HHWL

Page 2 of 2