Executive Engineer, PHED, PMC Dn. Makrana
Executive Engineer, PHED, PMC Dn. Makrana
Makrana
Behind Post Office, Manglana Road, Makrana-341505
e-mail: eepmc.nag.phed@rajasthan.gov.in
Sub: Package-04, CDS-01 Work for Construction of Cluster Distribution System for 110 villages & dhanies
(other habitations) of Parbatsar Tehsil under JICA assisted Rajasthan Rural Water Supply & Fluorosis
Mitigation Project (Nagaur) including village distribution system and IEC activities with 10 years
Operation & Maintenance on Turnkey basis. Submission of Pump Foundation (Pedestal) Drawing &
Design at Gular & Peelwa Pump House.
Ref: 1. CE, PMSC Nagaur Office Letter No. 3141 dated. 25.09.2017 (LoA)
2. Contract Agreement No. CEPMC-01/2017-18 dated 18.10.2017
3. M/s. Offshore Infrastructures Limited letter no. 341 dated 25-03-2019
4. PMSC Latter No. 279 dated 01-04-2019
Under the subject matter & reference above, kindly find enclosed here with
the Pump Foundation (Pedestal) Drawing & Design at Gular & Peelwa Pump House. For
Construction of package-4 (CDS-01) work, as submitted by M/s. OIL & recommemded for
approval by PMSC, Nagaur vide letter under reference 3 & 4 above, for further necessary action.
It is recommened for approval.
Encl. As above.
No. EE/PMC/Mak/D&D
Copy to following for information and necessary action please
1 CE, PHED, PMC, RRWS&FMP, Nagaur.
2 Project Manager, M/s. Offshore Infrastructures Limited Parbatsar.